CONTENTS  INTRODUCTION
 PLANT LAYOUT
 WORKING PRINCIPLE
 COAL HANDELING PLANT
 BOILER
 ECONOMISER
 TURBINE
 GENERATOR
 COOLING TOWER
 ASH HANDELING PLANT
 CONTROL PANEL
 SWITCH YARD
INTRODUCTION
KALISINDH SUPER THERMAL POWER STATION(KATPP) is
located in Jhalawar district , Rajasthan.
KATPP has installed capacity of 1200MW.
The first unit is commissioned in 2014 March with an
installed capacity of 600 Megawatt. Similarly the
second unit is commissioned in 2014 June.
Source of water for the plant is from Kalisindh Dam.
Primary Coal source for the plant will be from Paras
east and Kanta Basin coal blocks in Chhatisgarh State.
Revised cost of the project is Rs 9479.51 Crores.
WORKING PRINCIPLE OF THERMAL POWER
PLANT
1. Water is pumped into the boiler
at high pressure.
2. Water is converted into steam at
constant pressure.
3. Expansion of steam into steam
turbine.
4. Rejection of heat into the
condenser.
PLANT LAYOUT
COAL HANDELING PLANT
 It consist of three parts
• Wagon unloading system
• Conveying system
• Crushing system
 8700 tons of coal required per day for each unit.
 Coal is supplied from Parsa and Kanta mines from Chhattisgarh.
OVERVIEW OF COAL
HANDELING PLANT RAW COAL
WAGON
TRIPPLER
HOOPPERS
BUNKERS
RAW COAL
FEEDERS
COAL
MILLS
BOILER
FURNANCE
BOI
LER
A Boiler or Steam generator is a closed vessel to which
water under pressure, is converted into steam.
It is one of a major component of a thermal power
plant
Always designed to absorb maximum amount of heat
released in the process of combustion
Types of boilers
•Water tube boiler
•Fire tube boiler
FD fan – To supply air for combustion of fuel in
furnace.
ID fan – For sucking out gases and discharge to
atmosphere.
ECONOMIS
ER It is a heat exchanger device that
heats up the fluid or recover residual
heat from the combustion product
It improves the efficiency of plant 10-
12%
Temperature : 315 C
STEAM TURBINE
A steam turbine is a mechanical device that extracts thermal energy from
pressurized steam , and converts it into mechanical energy.
In a thermal power plant generally three turbine are used to increase the efficiency.
High pressure turbine (HPT) : The superheated steam is directly fed to this
turbine to rotate it.
Intermediate pressure turbine(IPT) : The output from the HPT is reheated in a
reheater and used to rotate IPT.
Low pressure turbine (LPT) : The exhausted steam from IPT is directly fed to rotate
the shaft of LPT.
All the turbines are connected to a single shaft which is connected to the generator.
STEAM FLOW
IN TURBINE
TURBINE SPECIFICATION
No. of casings
Two Casings (HP/IP Turbine - LP
Turbine)
Three Casings (HP/IP Turbine - LP
Turbine ×2)
Three Casings (HP Turbine - IP Turbine
- LP Turbine)
Four Casings (HP Turbine - IP Turbine -
LP Turbine×2)
Five Casings (HP Turbine - IP Turbine -
LP Turbine×3)
Output Up to 1,200 MW
Main steam conditions Up to 28.0 MPa / Up to 600°C
Reheat steam conditions Up to 630°C
Revolutions per minute
3,000 min-1
(50 Hz) / 3,600 min-1
(60
Hz)
GENERATOR
 Generator has a magnetic field, it has a stator and a rotor. When steam turbine rotates the
generator shaft, it creates a magnetic field and produce electricity from electro-
mechanical energy conversion.
 The generator is driven by directly coupled steam turbine at a speed of 3000 rpm.
 The generated voltage will generally from 11KV to 33KV max.
 The generated voltage is stepped up by connecting Step up transformer and is also used for
auxiliary purpose.
ELECTROSTATIC PRECIPITATOR(ESP)
 An electrostatic precipitator (ESP) is another very important to filtrate the air. Due to
combustion of fuel, flue gas consist of ash particles ,dust, smoke , foreign particles which need
to be removed to reduce air pollution.
 It create a strong electric field to remove all unwanted particles from the flue gas.
Cooling Towers
 The two cooling towers of the facility are 202 meters tall and the tallest in the world.
 The circulating water picks up the heat from turbine exhaust and becomes heated. Hence this
heated cooling water needs to be cooled to complete the cycle.
 The water is cooled in cooling tower through circulating pump.
 Heat in circulating water is rejected in cooling tower.
 There will be around 2% evaporation loss happens in the cooling tower.
 There are circulating pumps are used to transfer the water in a closed cycle, from the
condenser to the cooling tower.
ASH HANDELING PLANT
 Electrostatic precipitator is used in ash handling plant to remove fly ash.
 Use of ash :-
• Manufacturing of building material.
• Making of concrete.
• Manufacturing of cement.
• Road construction etc.
TRANSFORMER
 It is a device that transfers electrical energy from one alternating current circuit to one or more
other circuits. Either increasing( stepping up) or decreasing ( stepping down) the voltage.
 Various Transformers at KATPP.
I. Generating transformer.
II. Unit auxiliary transformer.
III. Station Transformer.
SWITCHYARD  Switchyard is the interconnector between generation
and transmission and the same voltage is maintained in
switchyard.
 Switch consists of the following instruments:-
 Lightening Arresters
 Current Transformers
 Capacitive voltage transformers
 Bus bar
 Isolator
 Insulator
 Circuit breakers
 Protective relays
CONTROL PANEL
All the Basic parameter like temperature of steam and air, flow
of water and air, pressure, electricity generation etc. are
controlled in control panel.
Control panel 1 :- Fan control desk.
Control panel 2:- Fuel Control desk.
Control panel 3:- Steam & Water control desk.
Control panel 4:- Turbine Control desk.
Control panel 5:- Generator control desk.
CONCLUSION
Coal fired power plant are backbone
of the electricity supply system in
India, generating more than 70 % of
the electric power.
Even if more natural gas -
fueled combined cycle power plants
and more renewable power generation
facilities will be built, a major portion
of electric power will still be
provided by coal - fired power plants.
THANK YOU

More Related Content

Similar to Presentation 1 (2).pptx

V.T ppt
V.T pptV.T ppt
V.T ppt
Aditi Tiwari
 
presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
rajam575648
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPT
parmod saharan
 
Industrial training at NTPC
Industrial training at NTPCIndustrial training at NTPC
Industrial training at NTPC
Priyanshu Singh
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
Aditya Empire
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
Prashant kumar
 
Presentation1
Presentation1Presentation1
Presentation1
Bhanu Pratap
 
Paras ppt
Paras pptParas ppt
kstps training report
kstps training reportkstps training report
kstps training report
Omprakash Choudhary
 
POWER PLANT.pdf
POWER PLANT.pdfPOWER PLANT.pdf
POWER PLANT.pdf
MishraAnup1
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
Sourabh Chourasiya
 
KTPS
KTPSKTPS
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
sagnikchoudhury
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview report
ASHOKKUMARPAL1
 
Dev
DevDev
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
sourabhgnit
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
Báppådìtÿâ Màîtÿ
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
Shivam Sharma
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
Prakash Jarotia
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Nirbhaya Vikas
 

Similar to Presentation 1 (2).pptx (20)

V.T ppt
V.T pptV.T ppt
V.T ppt
 
presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPT
 
Industrial training at NTPC
Industrial training at NTPCIndustrial training at NTPC
Industrial training at NTPC
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
 
Presentation1
Presentation1Presentation1
Presentation1
 
Paras ppt
Paras pptParas ppt
Paras ppt
 
kstps training report
kstps training reportkstps training report
kstps training report
 
POWER PLANT.pdf
POWER PLANT.pdfPOWER PLANT.pdf
POWER PLANT.pdf
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
 
KTPS
KTPSKTPS
KTPS
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview report
 
Dev
DevDev
Dev
 
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 

Recently uploaded

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 

Recently uploaded (20)

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 

Presentation 1 (2).pptx

  • 1. SWAMI KESHVANAND INSTITUTE OF TECHNOLOGY MANAGEMENT AND GRAMOTHAN, JAIPUR KALI SINDH SUPER THERMAL POWER PLANT (KATPP) JHALAWAR. SUBMITTED TO :- Mr. Ajay Bharadwaj SUBMITTED BY :- Naveen Jarwal
  • 2. CONTENTS  INTRODUCTION  PLANT LAYOUT  WORKING PRINCIPLE  COAL HANDELING PLANT  BOILER  ECONOMISER  TURBINE  GENERATOR  COOLING TOWER  ASH HANDELING PLANT  CONTROL PANEL  SWITCH YARD
  • 3. INTRODUCTION KALISINDH SUPER THERMAL POWER STATION(KATPP) is located in Jhalawar district , Rajasthan. KATPP has installed capacity of 1200MW. The first unit is commissioned in 2014 March with an installed capacity of 600 Megawatt. Similarly the second unit is commissioned in 2014 June. Source of water for the plant is from Kalisindh Dam. Primary Coal source for the plant will be from Paras east and Kanta Basin coal blocks in Chhatisgarh State. Revised cost of the project is Rs 9479.51 Crores.
  • 4. WORKING PRINCIPLE OF THERMAL POWER PLANT 1. Water is pumped into the boiler at high pressure. 2. Water is converted into steam at constant pressure. 3. Expansion of steam into steam turbine. 4. Rejection of heat into the condenser.
  • 6. COAL HANDELING PLANT  It consist of three parts • Wagon unloading system • Conveying system • Crushing system  8700 tons of coal required per day for each unit.  Coal is supplied from Parsa and Kanta mines from Chhattisgarh.
  • 7. OVERVIEW OF COAL HANDELING PLANT RAW COAL WAGON TRIPPLER HOOPPERS BUNKERS RAW COAL FEEDERS COAL MILLS BOILER FURNANCE
  • 8. BOI LER A Boiler or Steam generator is a closed vessel to which water under pressure, is converted into steam. It is one of a major component of a thermal power plant Always designed to absorb maximum amount of heat released in the process of combustion Types of boilers •Water tube boiler •Fire tube boiler FD fan – To supply air for combustion of fuel in furnace. ID fan – For sucking out gases and discharge to atmosphere.
  • 9. ECONOMIS ER It is a heat exchanger device that heats up the fluid or recover residual heat from the combustion product It improves the efficiency of plant 10- 12% Temperature : 315 C
  • 10. STEAM TURBINE A steam turbine is a mechanical device that extracts thermal energy from pressurized steam , and converts it into mechanical energy. In a thermal power plant generally three turbine are used to increase the efficiency. High pressure turbine (HPT) : The superheated steam is directly fed to this turbine to rotate it. Intermediate pressure turbine(IPT) : The output from the HPT is reheated in a reheater and used to rotate IPT. Low pressure turbine (LPT) : The exhausted steam from IPT is directly fed to rotate the shaft of LPT. All the turbines are connected to a single shaft which is connected to the generator.
  • 12. TURBINE SPECIFICATION No. of casings Two Casings (HP/IP Turbine - LP Turbine) Three Casings (HP/IP Turbine - LP Turbine ×2) Three Casings (HP Turbine - IP Turbine - LP Turbine) Four Casings (HP Turbine - IP Turbine - LP Turbine×2) Five Casings (HP Turbine - IP Turbine - LP Turbine×3) Output Up to 1,200 MW Main steam conditions Up to 28.0 MPa / Up to 600°C Reheat steam conditions Up to 630°C Revolutions per minute 3,000 min-1 (50 Hz) / 3,600 min-1 (60 Hz)
  • 13. GENERATOR  Generator has a magnetic field, it has a stator and a rotor. When steam turbine rotates the generator shaft, it creates a magnetic field and produce electricity from electro- mechanical energy conversion.  The generator is driven by directly coupled steam turbine at a speed of 3000 rpm.  The generated voltage will generally from 11KV to 33KV max.  The generated voltage is stepped up by connecting Step up transformer and is also used for auxiliary purpose.
  • 14. ELECTROSTATIC PRECIPITATOR(ESP)  An electrostatic precipitator (ESP) is another very important to filtrate the air. Due to combustion of fuel, flue gas consist of ash particles ,dust, smoke , foreign particles which need to be removed to reduce air pollution.  It create a strong electric field to remove all unwanted particles from the flue gas.
  • 15. Cooling Towers  The two cooling towers of the facility are 202 meters tall and the tallest in the world.  The circulating water picks up the heat from turbine exhaust and becomes heated. Hence this heated cooling water needs to be cooled to complete the cycle.  The water is cooled in cooling tower through circulating pump.  Heat in circulating water is rejected in cooling tower.  There will be around 2% evaporation loss happens in the cooling tower.  There are circulating pumps are used to transfer the water in a closed cycle, from the condenser to the cooling tower.
  • 16. ASH HANDELING PLANT  Electrostatic precipitator is used in ash handling plant to remove fly ash.  Use of ash :- • Manufacturing of building material. • Making of concrete. • Manufacturing of cement. • Road construction etc.
  • 17. TRANSFORMER  It is a device that transfers electrical energy from one alternating current circuit to one or more other circuits. Either increasing( stepping up) or decreasing ( stepping down) the voltage.  Various Transformers at KATPP. I. Generating transformer. II. Unit auxiliary transformer. III. Station Transformer.
  • 18. SWITCHYARD  Switchyard is the interconnector between generation and transmission and the same voltage is maintained in switchyard.  Switch consists of the following instruments:-  Lightening Arresters  Current Transformers  Capacitive voltage transformers  Bus bar  Isolator  Insulator  Circuit breakers  Protective relays
  • 19. CONTROL PANEL All the Basic parameter like temperature of steam and air, flow of water and air, pressure, electricity generation etc. are controlled in control panel. Control panel 1 :- Fan control desk. Control panel 2:- Fuel Control desk. Control panel 3:- Steam & Water control desk. Control panel 4:- Turbine Control desk. Control panel 5:- Generator control desk.
  • 20. CONCLUSION Coal fired power plant are backbone of the electricity supply system in India, generating more than 70 % of the electric power. Even if more natural gas - fueled combined cycle power plants and more renewable power generation facilities will be built, a major portion of electric power will still be provided by coal - fired power plants.