SlideShare a Scribd company logo
POWER PLANT ECONOMICS
KEY CONCEPTS IN POWER GENERATION
Electricity demand is commonly viewed in terms of base load vs.
peak load
Base load is the minimum level of electricity demand required
over a period of 24 hours; it is the load below which the
demand never falls and therefore must be supplied 100 percent
of the time.
Base load plants run continuously over extended periods of
time, and power from these plants is used to cater the base
demand of the grid (e.g. coal power plants, nuclear power
plants, hydroelectric plants, geothermal plants, solar thermal
KEY CONCEPTS IN POWER GENERATION
Peak load is time of high demand often occurring for shorter
durations; it is the difference between base demand and the
highest demand.
Peak load plants generally cater to demand peaks; they are
started up whenever there is a spike in demand and stopped when
the demand recedes (e.g. gas plants, solar power plants, wind
turbines, diesel generators).
CHARACTERISTICS INFLUENCING POWER PLANT
OPERATIONS
Flexibility of the generation source is determined by the minimum run time
and ramp times.
Minimum run time:
the shortest amount of time a plant can operate once it is turned on
 Ramp rate:
influences how quickly the plant can increase or decrease power output
 Ramp time:
the amount of time it takes from the moment a generator is turned on to the
moment it can start providing energy to the grid at its lower operating limit
CHARACTERISTICS INFLUENCING POWER PLANT
OPERATIONS
Less flexible plants (longer minimum run times and slower ramp times)
 generally better suited to provide base load energy
More flexible plants (shorter minimum run times and quicker ramp
times)  generally better suited to fill peak demand.
CHARACTERISTICS INFLUENCING POWER PLANT
OPERATIONS
Relative comparison of operating cost and operational flexibility for different power plan
technologies (this excludes most renewables since their operational flexibility is partially
dependent on prevailing weather conditions such as irradiance and wind speed/direction)
ECONOMICS OF POWER GENERATION
The art of determining the per unit (i.e., one kWh) cost of production of
electrical energy is known as economics of power generation. The
economics of power generation has assumed a great importance in this fast
developing power plant engineering. A consumer will use electric power
only if it is supplied at reasonable rate.
Therefore, power engineers have to find convenient methods to produce
electric power as cheap as possible so that consumers are tempted to use
electrical methods. Before passing on to the subject further, it is desirable
that the readers get themselves acquainted with the following terms much
used in the economics of power generation :
ECONOMICS OF POWER GENERATION
(i) Interest:
The cost of use of money is known as interest.
A power station is constructed by investing a huge capital. This money
is generally borrowed from banks or other financial institutions and the
supply company has to pay the annual interest on this amount. Even if
company has spent out of its reserve funds, the interest must be still
allowed for, since this amount could have earned interest if deposited in
a bank. Therefore, while calculating the cost of production of electrical
energy, the interest payable on the capital investment must be included.
ECONOMICS OF POWER GENERATION
(ii) Depreciation:
The decrease in the value of the power plant equipment and
building due to constant use is known as depreciation.
Cost of Electrical Energy
The total cost of electrical energy generated can be divided into
three parts, namely ;
(i) Fixed cost ;
(ii) Semi-fixed cost ;
(iii) Running or operating cost.
COST OF ELECTRICAL ENERGY
(i) Fixed cost.
It is the cost which is independent of maximum demand and units
generated. The fixed cost is due to the annual cost of central
organization, interest on capital cost of land and salaries of high
officials.(ii) Semi-fixed cost.
It is the cost which depends upon maximum demand but is
independent of units generated. The semi-fixed cost is directly
proportional to the maximum demand on power station and is on
account of annual interest and depreciation on capital investment of
building and equipment, taxes, salaries of management and clerical
staff. The maximum demand on the power station determines its size
and cost of installation. The greater the maximum demand on a power
station, the greater is its size and cost of installation.
COST OF ELECTRICAL ENERGY
(iii) Running cost.
It is the cost which depends only upon the number of units
generated. The running cost is on account of annual cost of
fuel, lubricating oil, maintenance, repairs and salaries of
operating staff. Since these charges depend upon the energy
output, the running cost is directly proportional to the
number of units generated by the station. In other words, if
the power station generates more units, it will have higher
running cost and vice-versa.
METHODS OF DETERMINING DEPRECIATION
There is reduction in the value of the equipment and other
property of the plant every year due to depreciation.
Therefore, a suitable amount (known as depreciation charge)
must be set aside annually so that by the time the life span
of the plant is over, the collected amount equals the cost of
replacement of the plant.
The following are the commonly used methods for
determining the annual depreciation charge :
(i) Straight line method ;
(ii) Diminishing value method ;
(iii) Sinking fund method.
METHODS OF DETERMINING DEPRECIATION
There is reduction in the value of the equipment and other
property of the plant every year due to depreciation.
Therefore, a suitable amount (known as depreciation charge)
must be set aside annually so that by the time the life span
of the plant is over, the collected amount equals the cost of
replacement of the plant.
The following are the commonly used methods for
determining the annual depreciation charge :
(i) Straight line method ;
(ii) Diminishing value method ;
(iii) Sinking fund method.
METHODS OF DETERMINING DEPRECIATION
(i) Straight line method.
In this method, a constant depreciation charge is made every
year on the basis of total depreciation and the useful life of
the property. Obviously, annual depreciation charge will be
equal to the total depreciation divided by the useful life of
the property. Thus, if the initial cost of equipment is Rs
1,00,000 and its scrap value is Rs 10,000 after a useful life of
20 years, then,
METHODS OF DETERMINING DEPRECIATION
(i) In general, the annual depreciation charge on the straight
line method may be expressed
METHODS OF DETERMINING DEPRECIATION
(ii) Diminishing value method.
In this method, depreciation charge is made every year at a fixed rate
on the diminished value of the equipment. In other words, depreciation
charge is first applied to the initial cost of equipment and then to its
diminished value.
As an example, suppose the initial cost of equipment is Rs 10,000 and
its scrap value after the useful life is zero. If the annual rate of
depreciation is 10%, then depreciation charge for the first year will be
0·1 × 10,000 = Rs 1,000. The value of the equipment is diminished by
Rs 1,000 and becomes Rs 9,000. For the second year, the depreciation
charge will be made on the diminished value (i.e. Rs 9,000) and
becomes 0·1 × 9,000 = Rs 900. The value of the equipment now
becomes 9000 − 900 = Rs 8100. For the third year, the depreciation
METHODS OF DETERMINING DEPRECIATION
(ii) Diminishing value method.
In this method, depreciation charge is made every year at a fixed rate
on the diminished value of the equipment. In other words, depreciation
charge is first applied to the initial cost of equipment and then to its
diminished value.
As an example, suppose the initial cost of equipment is Rs 10,000 and
its scrap value after the useful life is zero. If the annual rate of
depreciation is 10%, then depreciation charge for the first year will be
0·1 × 10,000 = Rs 1,000. The value of the equipment is diminished by
Rs 1,000 and becomes Rs 9,000. For the second year, the depreciation
charge will be made on the diminished value (i.e. Rs 9,000) and
becomes 0·1 × 9,000 = Rs 900. The value of the equipment now
becomes 9000 − 900 = Rs 8100. For the third year, the depreciation
METHODS OF DETERMINING DEPRECIATION
Mathematical treatment:
Let P = Capital cost of equipment
n = Useful life of equipment in years
S = Scrap value after useful life
Suppose the annual unit* depreciation is x. It is desired to find the
value of x in terms of P, n and S.
* If annual depreciation is 10%, then we can say that annual unit
depreciation is 0·1.
Similarly, annual depreciation charge for the subsequent years can be
calculated.
METHODS OF DETERMINING DEPRECIATION
(iii) Sinking fund method.
In this method, a fixed depreciation charge is made every
year and interest compounded on it annually. The constant
depreciation charge is such that total of annual instalments
plus the interest accumulations equal to the cost of
replacement of equipment after its useful life.
Let P = Initial value of equipment
n = Useful life of equipment in years
S = Scrap value after useful life
r = Annual rate of interest expressed as a decimal
Cost of replacement = P − S
METHODS OF DETERMINING DEPRECIATION
Let us suppose that an amount of q is set aside as
depreciation charge every year and interest compounded on
it so that an amount of P− S is available after n years.
The value of q gives the uniform annual depreciation charge.
MATHEMATICAL PROBLEMS
Problem 1. A transformer costing Rs 90,000 has a useful life
of 20 years. Determine the annual depreciation charge using
straight line method. Assume the salvage value of the
equipment to be Rs 10,000.
Solution :
Initial cost of transformer, P = Rs 90,000
Useful life, n = 20 years
Salvage value, S = Rs 10,000
Using straight line method,
MATHEMATICAL PROBLEMS
Problem 2. A distribution transformer costs Rs 2,00,000 and
has a useful life of 20 years. If the salvage value is Rs 10,000
and rate of annual compound interest is 8%, calculate the
amount to be saved annually for replacement of the
transformer after the end of 20 years by sinking fund
method.Solution :
Initial cost of transformer, P = Rs 2,00,000
Salvage value of transformer, S = Rs 10,000
Useful life, n = 20 years
Annual interest rate, r = 8% = 0· 08
MATHEMATICAL PROBLEMS
Annual payment for sinking fund,
MATHEMATICAL PROBLEMS
Problem 3. The equipment in a power station costs Rs
15,60,000 and has a salvage value of Rs 60,000 at the end of
25 years. Determine the depreciated value of the equipment
at the end of 20 years on the following methods :
(i) Straight line method ;
(ii) Diminishing value method ;
(iii) Sinking fund method at 5% compound interest annually.
MATHEMATICAL PROBLEMS
Solution :
Initial cost of equipment, P = Rs 15,60,000
Salvage value of equipment, S = Rs 60,000
Useful life, n = 25 years
MATHEMATICAL PROBLEMS
MATHEMATICAL PROBLEMS
THANK YOU

More Related Content

What's hot

Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
Dr. Rohit Singh Lather, Ph.D.
 
Power plant Engineering ppt
Power plant Engineering ppt Power plant Engineering ppt
Power plant Engineering ppt
Prabhat Kumar
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
Md. Rimon Mia
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
ra m
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
CraZzy Shubh
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
Niraj Solanki
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Nishkam Dhiman
 
Coal based thermal power plant
Coal based thermal power plant Coal based thermal power plant
Coal based thermal power plant
Eklavya Sharma
 
Diesel power plant
Diesel power plantDiesel power plant
Diesel power plant
rajesharayankara
 
Power generation and economics
Power generation and economicsPower generation and economics
Power generation and economics
SiraskarCom
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
Vasanthan Ravichandran
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load Plant
Satish Taji
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTS
S.Vijaya Bhaskar
 
power plant engineering Unit 1
power plant engineering Unit 1power plant engineering Unit 1
power plant engineering Unit 1
BHUPALAM VENKATESH
 
Generation of Electrical Power - Power Plants and Transmission Systems.
Generation of Electrical Power - Power Plants and Transmission Systems.Generation of Electrical Power - Power Plants and Transmission Systems.
Generation of Electrical Power - Power Plants and Transmission Systems.
maneesh001
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
Sourabh sharma
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
S.Vijaya Bhaskar
 
Diesel engine powerplant
Diesel engine powerplantDiesel engine powerplant
Diesel engine powerplant
Sangeeth Soman
 
Cogeneration
CogenerationCogeneration
Cogeneration
Nishkam Dhiman
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
MANOJ KUMAR MAHARANA
 

What's hot (20)

Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 
Power plant Engineering ppt
Power plant Engineering ppt Power plant Engineering ppt
Power plant Engineering ppt
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Coal based thermal power plant
Coal based thermal power plant Coal based thermal power plant
Coal based thermal power plant
 
Diesel power plant
Diesel power plantDiesel power plant
Diesel power plant
 
Power generation and economics
Power generation and economicsPower generation and economics
Power generation and economics
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load Plant
 
Unit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTSUnit_IV-HYDRO ELECTRIC POWER PLANTS
Unit_IV-HYDRO ELECTRIC POWER PLANTS
 
power plant engineering Unit 1
power plant engineering Unit 1power plant engineering Unit 1
power plant engineering Unit 1
 
Generation of Electrical Power - Power Plants and Transmission Systems.
Generation of Electrical Power - Power Plants and Transmission Systems.Generation of Electrical Power - Power Plants and Transmission Systems.
Generation of Electrical Power - Power Plants and Transmission Systems.
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
 
Diesel engine powerplant
Diesel engine powerplantDiesel engine powerplant
Diesel engine powerplant
 
Cogeneration
CogenerationCogeneration
Cogeneration
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 

Similar to Power plant economics

Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Power System Operation
 
Economics of Power Generation(4) h.pdf
Economics of Power Generation(4)       h.pdfEconomics of Power Generation(4)       h.pdf
Economics of Power Generation(4) h.pdf
Mahamad Jawhar
 
Economics of wind energy
Economics of wind energyEconomics of wind energy
Economics of wind energy
ASHWANI BHARATI
 
Unit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptxUnit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptx
prakash0712
 
Cost of electricity by source
Cost of electricity by sourceCost of electricity by source
Cost of electricity by sourcerohitjain21120
 
Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptx
Mahamad Jawhar
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET Journal
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenanceSTACY DAVIS
 
ECONOMICS OF POWER GENERATION- TARIFF METHODS
ECONOMICS OF POWER GENERATION-  TARIFF METHODSECONOMICS OF POWER GENERATION-  TARIFF METHODS
ECONOMICS OF POWER GENERATION- TARIFF METHODS
Dr. Gudipudi Nageswara Rao
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
Leonardo ENERGY
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
AFAQAHMED JAMADAR
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economics
Swapnil Gadgune
 
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATIONFEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
Wayan Santika
 
paper presentation_national
paper presentation_nationalpaper presentation_national
paper presentation_nationalvishal laddha
 
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Dayana Mastura FCCA CA
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
IOSR Journals
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.ppt
JeanClaudeEid1
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdf
ssuser5feb82
 
Economic of power generation (1) h.pptx
Economic of power generation (1)       h.pptxEconomic of power generation (1)       h.pptx
Economic of power generation (1) h.pptx
Mahamad Jawhar
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.ppt
gadha13
 

Similar to Power plant economics (20)

Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4Principles of Power Systems V.K Mehta Complete Book - Chapter 4
Principles of Power Systems V.K Mehta Complete Book - Chapter 4
 
Economics of Power Generation(4) h.pdf
Economics of Power Generation(4)       h.pdfEconomics of Power Generation(4)       h.pdf
Economics of Power Generation(4) h.pdf
 
Economics of wind energy
Economics of wind energyEconomics of wind energy
Economics of wind energy
 
Unit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptxUnit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptx
 
Cost of electricity by source
Cost of electricity by sourceCost of electricity by source
Cost of electricity by source
 
Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptx
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
ECONOMICS OF POWER GENERATION- TARIFF METHODS
ECONOMICS OF POWER GENERATION-  TARIFF METHODSECONOMICS OF POWER GENERATION-  TARIFF METHODS
ECONOMICS OF POWER GENERATION- TARIFF METHODS
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economics
 
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATIONFEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
FEASIBILITY ANALYSIS OF GRID/WIND/PV HYBRID SYSTEMS FOR INDUSTRIAL APPLICATION
 
paper presentation_national
paper presentation_nationalpaper presentation_national
paper presentation_national
 
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.ppt
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdf
 
Economic of power generation (1) h.pptx
Economic of power generation (1)       h.pptxEconomic of power generation (1)       h.pptx
Economic of power generation (1) h.pptx
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.ppt
 

More from Tarek Erin

2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
2. Atomic, molecular, crytalline and amorphous structures for metals.pptx2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
Tarek Erin
 
Engineering Materials; Types, Properties.pptx
Engineering Materials; Types, Properties.pptxEngineering Materials; Types, Properties.pptx
Engineering Materials; Types, Properties.pptx
Tarek Erin
 
Introduction to Production Planning & Control & Manufacturing.pptx
Introduction to Production Planning & Control & Manufacturing.pptxIntroduction to Production Planning & Control & Manufacturing.pptx
Introduction to Production Planning & Control & Manufacturing.pptx
Tarek Erin
 
Chip formation & cutting tool geometry
Chip formation & cutting tool geometryChip formation & cutting tool geometry
Chip formation & cutting tool geometry
Tarek Erin
 
Gas turbine power plant
Gas turbine power plantGas turbine power plant
Gas turbine power plant
Tarek Erin
 
Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plant
Tarek Erin
 
Power plant, an overview of power sector of Bangladesh
Power plant, an overview of power sector of BangladeshPower plant, an overview of power sector of Bangladesh
Power plant, an overview of power sector of Bangladesh
Tarek Erin
 
Design and-construction-of-soil-moisture-measurement-system
Design and-construction-of-soil-moisture-measurement-systemDesign and-construction-of-soil-moisture-measurement-system
Design and-construction-of-soil-moisture-measurement-system
Tarek Erin
 
Design and Construction of Digital Locking System
Design and Construction of Digital Locking SystemDesign and Construction of Digital Locking System
Design and Construction of Digital Locking System
Tarek Erin
 
TEMPERATURE BASED FAN SPEED CONTROLLER
TEMPERATURE  BASED  FAN  SPEED  CONTROLLERTEMPERATURE  BASED  FAN  SPEED  CONTROLLER
TEMPERATURE BASED FAN SPEED CONTROLLER
Tarek Erin
 

More from Tarek Erin (10)

2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
2. Atomic, molecular, crytalline and amorphous structures for metals.pptx2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
2. Atomic, molecular, crytalline and amorphous structures for metals.pptx
 
Engineering Materials; Types, Properties.pptx
Engineering Materials; Types, Properties.pptxEngineering Materials; Types, Properties.pptx
Engineering Materials; Types, Properties.pptx
 
Introduction to Production Planning & Control & Manufacturing.pptx
Introduction to Production Planning & Control & Manufacturing.pptxIntroduction to Production Planning & Control & Manufacturing.pptx
Introduction to Production Planning & Control & Manufacturing.pptx
 
Chip formation & cutting tool geometry
Chip formation & cutting tool geometryChip formation & cutting tool geometry
Chip formation & cutting tool geometry
 
Gas turbine power plant
Gas turbine power plantGas turbine power plant
Gas turbine power plant
 
Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plant
 
Power plant, an overview of power sector of Bangladesh
Power plant, an overview of power sector of BangladeshPower plant, an overview of power sector of Bangladesh
Power plant, an overview of power sector of Bangladesh
 
Design and-construction-of-soil-moisture-measurement-system
Design and-construction-of-soil-moisture-measurement-systemDesign and-construction-of-soil-moisture-measurement-system
Design and-construction-of-soil-moisture-measurement-system
 
Design and Construction of Digital Locking System
Design and Construction of Digital Locking SystemDesign and Construction of Digital Locking System
Design and Construction of Digital Locking System
 
TEMPERATURE BASED FAN SPEED CONTROLLER
TEMPERATURE  BASED  FAN  SPEED  CONTROLLERTEMPERATURE  BASED  FAN  SPEED  CONTROLLER
TEMPERATURE BASED FAN SPEED CONTROLLER
 

Recently uploaded

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 

Recently uploaded (20)

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 

Power plant economics

  • 2. KEY CONCEPTS IN POWER GENERATION Electricity demand is commonly viewed in terms of base load vs. peak load Base load is the minimum level of electricity demand required over a period of 24 hours; it is the load below which the demand never falls and therefore must be supplied 100 percent of the time. Base load plants run continuously over extended periods of time, and power from these plants is used to cater the base demand of the grid (e.g. coal power plants, nuclear power plants, hydroelectric plants, geothermal plants, solar thermal
  • 3. KEY CONCEPTS IN POWER GENERATION Peak load is time of high demand often occurring for shorter durations; it is the difference between base demand and the highest demand. Peak load plants generally cater to demand peaks; they are started up whenever there is a spike in demand and stopped when the demand recedes (e.g. gas plants, solar power plants, wind turbines, diesel generators).
  • 4. CHARACTERISTICS INFLUENCING POWER PLANT OPERATIONS Flexibility of the generation source is determined by the minimum run time and ramp times. Minimum run time: the shortest amount of time a plant can operate once it is turned on  Ramp rate: influences how quickly the plant can increase or decrease power output  Ramp time: the amount of time it takes from the moment a generator is turned on to the moment it can start providing energy to the grid at its lower operating limit
  • 5. CHARACTERISTICS INFLUENCING POWER PLANT OPERATIONS Less flexible plants (longer minimum run times and slower ramp times)  generally better suited to provide base load energy More flexible plants (shorter minimum run times and quicker ramp times)  generally better suited to fill peak demand.
  • 6. CHARACTERISTICS INFLUENCING POWER PLANT OPERATIONS Relative comparison of operating cost and operational flexibility for different power plan technologies (this excludes most renewables since their operational flexibility is partially dependent on prevailing weather conditions such as irradiance and wind speed/direction)
  • 7. ECONOMICS OF POWER GENERATION The art of determining the per unit (i.e., one kWh) cost of production of electrical energy is known as economics of power generation. The economics of power generation has assumed a great importance in this fast developing power plant engineering. A consumer will use electric power only if it is supplied at reasonable rate. Therefore, power engineers have to find convenient methods to produce electric power as cheap as possible so that consumers are tempted to use electrical methods. Before passing on to the subject further, it is desirable that the readers get themselves acquainted with the following terms much used in the economics of power generation :
  • 8. ECONOMICS OF POWER GENERATION (i) Interest: The cost of use of money is known as interest. A power station is constructed by investing a huge capital. This money is generally borrowed from banks or other financial institutions and the supply company has to pay the annual interest on this amount. Even if company has spent out of its reserve funds, the interest must be still allowed for, since this amount could have earned interest if deposited in a bank. Therefore, while calculating the cost of production of electrical energy, the interest payable on the capital investment must be included.
  • 9. ECONOMICS OF POWER GENERATION (ii) Depreciation: The decrease in the value of the power plant equipment and building due to constant use is known as depreciation. Cost of Electrical Energy The total cost of electrical energy generated can be divided into three parts, namely ; (i) Fixed cost ; (ii) Semi-fixed cost ; (iii) Running or operating cost.
  • 10. COST OF ELECTRICAL ENERGY (i) Fixed cost. It is the cost which is independent of maximum demand and units generated. The fixed cost is due to the annual cost of central organization, interest on capital cost of land and salaries of high officials.(ii) Semi-fixed cost. It is the cost which depends upon maximum demand but is independent of units generated. The semi-fixed cost is directly proportional to the maximum demand on power station and is on account of annual interest and depreciation on capital investment of building and equipment, taxes, salaries of management and clerical staff. The maximum demand on the power station determines its size and cost of installation. The greater the maximum demand on a power station, the greater is its size and cost of installation.
  • 11. COST OF ELECTRICAL ENERGY (iii) Running cost. It is the cost which depends only upon the number of units generated. The running cost is on account of annual cost of fuel, lubricating oil, maintenance, repairs and salaries of operating staff. Since these charges depend upon the energy output, the running cost is directly proportional to the number of units generated by the station. In other words, if the power station generates more units, it will have higher running cost and vice-versa.
  • 12. METHODS OF DETERMINING DEPRECIATION There is reduction in the value of the equipment and other property of the plant every year due to depreciation. Therefore, a suitable amount (known as depreciation charge) must be set aside annually so that by the time the life span of the plant is over, the collected amount equals the cost of replacement of the plant. The following are the commonly used methods for determining the annual depreciation charge : (i) Straight line method ; (ii) Diminishing value method ; (iii) Sinking fund method.
  • 13. METHODS OF DETERMINING DEPRECIATION There is reduction in the value of the equipment and other property of the plant every year due to depreciation. Therefore, a suitable amount (known as depreciation charge) must be set aside annually so that by the time the life span of the plant is over, the collected amount equals the cost of replacement of the plant. The following are the commonly used methods for determining the annual depreciation charge : (i) Straight line method ; (ii) Diminishing value method ; (iii) Sinking fund method.
  • 14. METHODS OF DETERMINING DEPRECIATION (i) Straight line method. In this method, a constant depreciation charge is made every year on the basis of total depreciation and the useful life of the property. Obviously, annual depreciation charge will be equal to the total depreciation divided by the useful life of the property. Thus, if the initial cost of equipment is Rs 1,00,000 and its scrap value is Rs 10,000 after a useful life of 20 years, then,
  • 15. METHODS OF DETERMINING DEPRECIATION (i) In general, the annual depreciation charge on the straight line method may be expressed
  • 16. METHODS OF DETERMINING DEPRECIATION (ii) Diminishing value method. In this method, depreciation charge is made every year at a fixed rate on the diminished value of the equipment. In other words, depreciation charge is first applied to the initial cost of equipment and then to its diminished value. As an example, suppose the initial cost of equipment is Rs 10,000 and its scrap value after the useful life is zero. If the annual rate of depreciation is 10%, then depreciation charge for the first year will be 0·1 × 10,000 = Rs 1,000. The value of the equipment is diminished by Rs 1,000 and becomes Rs 9,000. For the second year, the depreciation charge will be made on the diminished value (i.e. Rs 9,000) and becomes 0·1 × 9,000 = Rs 900. The value of the equipment now becomes 9000 − 900 = Rs 8100. For the third year, the depreciation
  • 17. METHODS OF DETERMINING DEPRECIATION (ii) Diminishing value method. In this method, depreciation charge is made every year at a fixed rate on the diminished value of the equipment. In other words, depreciation charge is first applied to the initial cost of equipment and then to its diminished value. As an example, suppose the initial cost of equipment is Rs 10,000 and its scrap value after the useful life is zero. If the annual rate of depreciation is 10%, then depreciation charge for the first year will be 0·1 × 10,000 = Rs 1,000. The value of the equipment is diminished by Rs 1,000 and becomes Rs 9,000. For the second year, the depreciation charge will be made on the diminished value (i.e. Rs 9,000) and becomes 0·1 × 9,000 = Rs 900. The value of the equipment now becomes 9000 − 900 = Rs 8100. For the third year, the depreciation
  • 18. METHODS OF DETERMINING DEPRECIATION Mathematical treatment: Let P = Capital cost of equipment n = Useful life of equipment in years S = Scrap value after useful life Suppose the annual unit* depreciation is x. It is desired to find the value of x in terms of P, n and S. * If annual depreciation is 10%, then we can say that annual unit depreciation is 0·1. Similarly, annual depreciation charge for the subsequent years can be calculated.
  • 19. METHODS OF DETERMINING DEPRECIATION (iii) Sinking fund method. In this method, a fixed depreciation charge is made every year and interest compounded on it annually. The constant depreciation charge is such that total of annual instalments plus the interest accumulations equal to the cost of replacement of equipment after its useful life. Let P = Initial value of equipment n = Useful life of equipment in years S = Scrap value after useful life r = Annual rate of interest expressed as a decimal Cost of replacement = P − S
  • 20. METHODS OF DETERMINING DEPRECIATION Let us suppose that an amount of q is set aside as depreciation charge every year and interest compounded on it so that an amount of P− S is available after n years. The value of q gives the uniform annual depreciation charge.
  • 21. MATHEMATICAL PROBLEMS Problem 1. A transformer costing Rs 90,000 has a useful life of 20 years. Determine the annual depreciation charge using straight line method. Assume the salvage value of the equipment to be Rs 10,000. Solution : Initial cost of transformer, P = Rs 90,000 Useful life, n = 20 years Salvage value, S = Rs 10,000 Using straight line method,
  • 22. MATHEMATICAL PROBLEMS Problem 2. A distribution transformer costs Rs 2,00,000 and has a useful life of 20 years. If the salvage value is Rs 10,000 and rate of annual compound interest is 8%, calculate the amount to be saved annually for replacement of the transformer after the end of 20 years by sinking fund method.Solution : Initial cost of transformer, P = Rs 2,00,000 Salvage value of transformer, S = Rs 10,000 Useful life, n = 20 years Annual interest rate, r = 8% = 0· 08
  • 24. MATHEMATICAL PROBLEMS Problem 3. The equipment in a power station costs Rs 15,60,000 and has a salvage value of Rs 60,000 at the end of 25 years. Determine the depreciated value of the equipment at the end of 20 years on the following methods : (i) Straight line method ; (ii) Diminishing value method ; (iii) Sinking fund method at 5% compound interest annually.
  • 25. MATHEMATICAL PROBLEMS Solution : Initial cost of equipment, P = Rs 15,60,000 Salvage value of equipment, S = Rs 60,000 Useful life, n = 25 years