SlideShare a Scribd company logo
POST TENSIONED
FLOOR SYSTEM
Prepared by
Aditya Shah (M.Tech CPM)
Building Construction System
INTRODUCTION
Post-tensioning is
simply a method of
producing
prestressed
concrete, masonry,
and other
structural
elements
process of
introducing internal
stress into a concrete
during the
construction process
in order to
counteract the
external loads
applied when the
structure is put into
use
Internal forces are
applied by
tensioning HS
steel
WORKINGOF
PT FLOOR
EXECUTION
METHODOLOGY
 Construction of post-tensioned slabs on grade is very similar to
using reinforcing steel, except for the tensioning step. Step wise
construction of post tension floor is given below.
 1. Form work setup
 2. Placing of bottom reinforcement
 3. Fixing of bar chair for PT tendon
 4. Placing PT tendon
 5. Fixing anchorage burstling reinforcement
 6. Placing of top reinforcement
 7. Placing anchorage pocket former and grout vent
 8. Fixing slab edge formwork with pocket former
 9. Concreting of slab
 10. Removal of slab edge formwork
 11. Remove pocket former
 12. Placing anchor head and wedge in position
 13. Stressing
 14. Cutting end of strand
 15. Capping stressing recess with cement mortar
 16. Grouting
 17. Repeat for next floor slab
COMPONENTS
ADVANTAGES
OF PT FLOOR
Lighter and
Slender
members are
possible.
remains un-
cracked under
Service load.
improves
serviceability
Fast
construction
can achieved
Flat soffit
reduces
shuttering,
plastering and
painting cost.
Reduces
building height
DISADVANTAGES
Chances of
corrosion are
high
Complexity of
work
Lead to
accidents
ECONOMICS
• Post-tensioned should
be considered as a
possible economic
alternative for most
structures when spans
exceed 7.0 meters.
ECONOMICS
 P-T reduces the concrete volume by 10 to 20%.
 Cost of PT is typically 20 to 30% less as compared to
conventional reinforced structure.
 For flat slab in 8m x 8m or 9m x 9m Grid, P-T costs approximately
Rs. 40 to 50 per sq. ft. with any kind of desired geometry
availed better than R.C.C.
 Since the reinforcement is protected, P-T reinforced structures
have lower annual maintenance costs overtime
SPEED OF
CONSTRUCTION
 The comparison of PT and RCC slab is carried out on Strata SE1
project located in center London. The building is a residential high-
rise 147 meters in height with 41 post-tensioned flat slabs.
 The average area of the slab is 630 sqm.
 The floor cycle estimates using the same criteria for PT and RCC
are respectively 5 and 6.5.
 This yields a total increase of 60 working days between PT
and RCC.
 Time saving on the PT option is due to less material and hence less
installation time and labor, to stressing of the tendons and
consequently early deshoring.
 The actual floor-cycle achieved on the PT slab was 4.5 days on
average.
REFERENCES
 [1] “POST-TENSIONING IN BUILDING STRUCTURES”, Ed Cross1
BE, Grad.Dip(Tech.Mgt), MIEAust, CPEng.
 [2] POST-TENSIONEDSLABS, PUBLISHED BYVSL
INTERNATIONAL LTD.
 [3] Sanfield (India) LTD., PT Slab brochure.
 [4] “A PROJECT-BASEDCOMPARISON BETWEEN REINFORCED
AND POST-TENSIONED STRUCTURES FROMA SUSTAINABILITY
PERSPECTIVE.”,Carol Hayek & Saleem Kalil.
 [5] www.concreteconstruction.net
Thank you

More Related Content

What's hot

Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed Concrete
Davinderpal Singh
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 
Prestressed Concrete Basics
Prestressed Concrete BasicsPrestressed Concrete Basics
Prestressed Concrete Basics
Sachin Kulkarni
 
Pt slabs
Pt slabsPt slabs
Pt slabs
ajay nagaraj
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
Anuj Singhal
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
JenilPatel22
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
Hanzlahakhlaq
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .
Udayram Patil
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Rajesh Burde
 
Precast structure
Precast structurePrecast structure
Precast structure
piyush9392
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
Parag Pal
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
Sofia Rajesh
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
Ghanashyam Prajapati
 
Underpinning
UnderpinningUnderpinning
Underpinning
Khuzema Olia
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
AMSYSCO Inc.
 
Structural System in High Rise building
Structural System in High Rise buildingStructural System in High Rise building
Structural System in High Rise building
Civil Millennium Design Complex (CMDC)
 

What's hot (20)

Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed Concrete
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Prestressed Concrete Basics
Prestressed Concrete BasicsPrestressed Concrete Basics
Prestressed Concrete Basics
 
Pt slabs
Pt slabsPt slabs
Pt slabs
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
Posttension vs flat slab
Posttension vs flat slabPosttension vs flat slab
Posttension vs flat slab
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Precast structure
Precast structurePrecast structure
Precast structure
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Structural System in High Rise building
Structural System in High Rise buildingStructural System in High Rise building
Structural System in High Rise building
 

Similar to Post tension Floor System

Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
Sudhan Sathe
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
RijuDasgupta
 
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
IRJET Journal
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
FOYSOLMAHMUD1
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
632k18BilalAhmad
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
Ramin Vaghei
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Parag Pal
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
IRJET Journal
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slab
Erik Ong
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
Penny3688
 
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
IRJET Journal
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
Dhrumil Pandya
 
A comparative review on behavioural aspect of post tensioning voided flat sl...
A comparative review on behavioural aspect of post  tensioning voided flat sl...A comparative review on behavioural aspect of post  tensioning voided flat sl...
A comparative review on behavioural aspect of post tensioning voided flat sl...
haseeb11h4
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET Journal
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Mukesh Singh Ghuraiya
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
NisshantSinghSaud
 
PS18_P176_V.Greepala.pdf
PS18_P176_V.Greepala.pdfPS18_P176_V.Greepala.pdf
PS18_P176_V.Greepala.pdf
Vatwong Greepala
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 

Similar to Post tension Floor System (20)

Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
Comparative Study of Post Tensioned and RCC Flat Slab in Multi-Storey Commerc...
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Difogfufl l
Difogfufl lDifogfufl l
Difogfufl l
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slab
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
 
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
IRJET - Review on Behavior of Composite Column and Post-Tension Flat Slab in ...
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
A comparative review on behavioural aspect of post tensioning voided flat sl...
A comparative review on behavioural aspect of post  tensioning voided flat sl...A comparative review on behavioural aspect of post  tensioning voided flat sl...
A comparative review on behavioural aspect of post tensioning voided flat sl...
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 
Ayush
AyushAyush
Ayush
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
PS18_P176_V.Greepala.pdf
PS18_P176_V.Greepala.pdfPS18_P176_V.Greepala.pdf
PS18_P176_V.Greepala.pdf
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 

Recently uploaded

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 

Recently uploaded (20)

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 

Post tension Floor System

  • 1. POST TENSIONED FLOOR SYSTEM Prepared by Aditya Shah (M.Tech CPM) Building Construction System
  • 2. INTRODUCTION Post-tensioning is simply a method of producing prestressed concrete, masonry, and other structural elements process of introducing internal stress into a concrete during the construction process in order to counteract the external loads applied when the structure is put into use Internal forces are applied by tensioning HS steel
  • 4. EXECUTION METHODOLOGY  Construction of post-tensioned slabs on grade is very similar to using reinforcing steel, except for the tensioning step. Step wise construction of post tension floor is given below.  1. Form work setup  2. Placing of bottom reinforcement  3. Fixing of bar chair for PT tendon  4. Placing PT tendon  5. Fixing anchorage burstling reinforcement  6. Placing of top reinforcement  7. Placing anchorage pocket former and grout vent  8. Fixing slab edge formwork with pocket former  9. Concreting of slab
  • 5.  10. Removal of slab edge formwork  11. Remove pocket former  12. Placing anchor head and wedge in position  13. Stressing  14. Cutting end of strand  15. Capping stressing recess with cement mortar  16. Grouting  17. Repeat for next floor slab
  • 7.
  • 8. ADVANTAGES OF PT FLOOR Lighter and Slender members are possible. remains un- cracked under Service load. improves serviceability Fast construction can achieved Flat soffit reduces shuttering, plastering and painting cost. Reduces building height
  • 9.
  • 11. ECONOMICS • Post-tensioned should be considered as a possible economic alternative for most structures when spans exceed 7.0 meters.
  • 12. ECONOMICS  P-T reduces the concrete volume by 10 to 20%.  Cost of PT is typically 20 to 30% less as compared to conventional reinforced structure.  For flat slab in 8m x 8m or 9m x 9m Grid, P-T costs approximately Rs. 40 to 50 per sq. ft. with any kind of desired geometry availed better than R.C.C.  Since the reinforcement is protected, P-T reinforced structures have lower annual maintenance costs overtime
  • 13. SPEED OF CONSTRUCTION  The comparison of PT and RCC slab is carried out on Strata SE1 project located in center London. The building is a residential high- rise 147 meters in height with 41 post-tensioned flat slabs.  The average area of the slab is 630 sqm.  The floor cycle estimates using the same criteria for PT and RCC are respectively 5 and 6.5.  This yields a total increase of 60 working days between PT and RCC.
  • 14.  Time saving on the PT option is due to less material and hence less installation time and labor, to stressing of the tendons and consequently early deshoring.  The actual floor-cycle achieved on the PT slab was 4.5 days on average.
  • 15. REFERENCES  [1] “POST-TENSIONING IN BUILDING STRUCTURES”, Ed Cross1 BE, Grad.Dip(Tech.Mgt), MIEAust, CPEng.  [2] POST-TENSIONEDSLABS, PUBLISHED BYVSL INTERNATIONAL LTD.  [3] Sanfield (India) LTD., PT Slab brochure.  [4] “A PROJECT-BASEDCOMPARISON BETWEEN REINFORCED AND POST-TENSIONED STRUCTURES FROMA SUSTAINABILITY PERSPECTIVE.”,Carol Hayek & Saleem Kalil.  [5] www.concreteconstruction.net