SlideShare a Scribd company logo
StructuresCentre.xyz
1
POSSIBLE SOLUTION TO STRUCT-HUB: DESIGN ASSESSMENT
II
Omotoriogun Victor Femi
Copyright ©Structures centre, 2021. All rights reserved
18th February 2021
structurescentre@gmail.com
1.0 DESIGN SOLUTION
Preliminary sizing of the structural element has been carried using the guidance provided
in: Preliminary sizing of structural elements as well as the guidance provided in the
publication by the Concrete Centre- Economic Concrete Frame Elements.
StructuresCentre.xyz
2
3.1 Actions
3.1 1 Roof
Permanent Actions = 1.5𝑘𝑁/𝑚
Variable Actions = 0.6𝑘𝑁/𝑚
3.1.2 Floors
Permanent Actions:
i. Self weight of slab = 0.20 × 25 = 5𝑘𝑁/𝑚 (𝐶𝑙𝑎𝑠𝑠𝑟𝑜𝑜𝑚)
= 0.15 × 25 = 3.75𝑘𝑁/𝑚 (𝑊𝑎𝑙𝑘𝑤𝑎𝑦)
ii. Finishes & Services = 1.5𝑘𝑁/𝑚
iii. Partition Allowances = 1.0𝑘𝑁/𝑚
Total Permanent Actions = 𝑔 = 7.5𝑘𝑁/𝑚 & 6.25𝑘𝑁/𝑚
Variable Actions:
i. Floor Imposed Loading (Classroom & Walkways) = 𝑞 = 3.0𝑘𝑁/𝑚
Design Value of Actions:
By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation
6.13b of BS EN 1990 will give the most unfavourable results.
Roof
Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 1.5) + (1.5 × 0.6) = 2.77𝑘𝑁𝑚
Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 1.5 = 1.87𝑘𝑁/𝑚
Classroom Panels
Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 7.5) + (1.5 × 3) = 13.87𝑘𝑁𝑚
Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 7.5 = 9.37𝑘𝑁/𝑚
Walkway Panels
Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 6.25) + (1.5 × 3) = 12.30𝑘𝑁𝑚
StructuresCentre.xyz
3
Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 6.25 = 7.80𝑘𝑁/𝑚
3.2 Slab Panels
3.2.1 Classroom Panels
𝐿
𝐿
=
9000
7500
= 1.2 (𝑇𝑤𝑜 𝑤𝑎𝑦 𝑆𝑙𝑎𝑏 − 𝑇𝑤𝑜 𝐴𝑑𝑗𝑎𝑐𝑒𝑛𝑡 𝑆𝑖𝑑𝑒𝑠 𝐷𝑖𝑠𝑐𝑜𝑛𝑡𝑖𝑛𝑜𝑢𝑠)
Using coefficients from table for two ways slabs with two adjacent sides discontinuous.
Short span coefficients = −0.064 & 0.047
Long span coefficients = −0.045 & 0.034
3.2.1.1 Flexural Design
Negative Moment at Support (Short Span)
𝑀 = −0.064𝑛 , 𝑙 = −0.064 × 13.87 × 7.5 = −49.93𝑘𝑁. 𝑚/𝑚
Assuming cover to reinforcement of 20mm, 12mm bars
d = h − c + links +
∅
= 200 − 20 + = 174mm; b = 1000mm
k =
M
bd f
=
49.93 × 10
1000 × 174 × 20
= 0.0825
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.0825) ≤ 0.95d
=0.92d = 0.92 × 174 = 160.08mm
A =
M
0.87f z
=
49.93 × 10
0.87 × 410 × 160.08
= 874.42mm /m
Try Y12mm bars @ 125mm Centres (As, prov = 904mm2
)
Positive Moment at Midspan (Short Span)
𝑀 = 0.047𝑛 , 𝑙 = 0.047 × 13.87 × 7.5 = 36.67𝑘𝑁. 𝑚/𝑚
Assuming cover to reinforcement of 20mm, 12mm bars
StructuresCentre.xyz
4
d = h − c + links +
∅
= 200 − 20 + = 174mm; b = 1000mm
k =
M
bd f
=
36.67 × 10
1000 × 174 × 20
= 0.0606
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.0606) ≤ 0.95d
=0.94d = 0.94 × 174 = 163.56mm
A =
M
0.87f z
=
36.67 × 10
0.87 × 410 × 163.56
= 628.54mm /m
Try Y12mm bars @ 125mm Centres (As, prov = 904mm2
)
Negative Moment at Support (Long Span)
𝑀 = −0.045𝑛 , 𝑙 = −0.045 × 13.87 × 7.5 = −35.11𝑘𝑁. 𝑚/𝑚
Assuming cover to reinforcement of 20mm, 12mm bars
d = h − c + links +
∅
+ ∅ = 200 − 20 + + 12 = 162mm; b = 1000mm
k =
M
bd f
=
35.11 × 10
1000 × 162 × 20
= 0.067
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.067) ≤ 0.95d
=0.94d = 0.94 × 162 = 152.28mm
A =
M
0.87f z
=
35.11 × 10
0.87 × 410 × 152.28
= 646.38mm /m
Try Y12mm bars @ 150mm Centres (As, prov = 753mm2
)
Positive Moment at Midspan (Long Span)
𝑀 = 0.034𝑛 , 𝑙 = 0.034 × 13.87 × 7.5 = 26.53𝑘𝑁. 𝑚/𝑚
Assuming cover to reinforcement of 20mm, 12mm bars
d = h − c + links +
∅
+ ∅ = 200 − 20 + + 12 = 162mm; b = 1000mm
StructuresCentre.xyz
5
k =
M
bd f
=
26.53 × 10
1000 × 162 × 20
= 0.051
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.051) ≤ 0.95d
=0.95d = 0.95 × 162 = 153.9mm
A =
M
0.87f z
=
26.53 × 10
0.87 × 410 × 153.9
= 483.28mm /m
Try Y12mm bars @ 150mm Centres (As, prov = 753mm2
/m)
3.2.1.2 Deflection Verification
Deflection verification can be carried using either of the two alternative method provided in
section 7.4 of Eurocode 2 (Part 1). The conservative span-effective method and the rigorous
calculation approach which involve using theoretical expression to estimate the actual
deflection of the slab. The span-effective method is used here, the rigorous method is not
suitable for hand calculations, spreadsheets or finite element software’s are required for fast
calculations.
Basic Requirement: ≥
= 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3
𝜌 =
𝐴 ,
𝐴
=
𝐴 ,
𝑏𝑑
=
628.54
(1000 × 174)
= 0.36%
ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ
N = 11 +
1.5 f ρ
ρ
+ 3.2 f
ρ
ρ
− 1 = 11 +
1.5√20 × 0.45
0.36
+ 3.2√20
0.45
0.36
− 1
= 21.20
F1 = 1.0
K = 1.3 (end spans)
StructuresCentre.xyz
6
F2 =
7.0
l
=
7.0
7.5
= 0.93
F3 =
310
σ
≤ 1.5
σ =
f
γ
g + φq
n
A ,
A ,
∙
1
δ
=
410
1.15
×
7.5 + 0.6(3)
13.87
×
628.54
904
= 166.21Mpa
F3 =
310
166.21
= 1.87 > 1.5
L
d
= 21.20 × 1.3 × 1.0 × 0.93 × 1.50 = 38.45
L
d
=
span
effective depth
=
7500
174
= 43.10
Since actual span-effective depth ratio is greater than the limiting span-effective depth ratio. It
shows that we might have a deflection problem. Hence, the options available includes, increasing
the slab thickness, the concrete class or even the steel bars grade. However, readers are reminded
that, the span/effective depth approach is only a fast and conservative method of verifying
deflection. In this case the rigorous calculation method was used and the slab found to perform
satisfactory with respect to deflection.
3.2.1.3 Detailing Checks.
The minimum area of steel required in panel:
A , = 0.26
f
f
𝑏 d ≥ 0.0013bd
f = 0.30f = 0.3 × 20 = 2.21Mpa
A , = 0.26 ×
2.21
410
× 1000 × 174 ≥ 0.0013 × 1000 × 174
= 243.85mm . By observation it is not critical anywhere in slab. Hence adopt all steel
bars.
3.2.2 Walkway Panels
The walkways panel are one-way slabs which can be idealized as propped cantilevers.
StructuresCentre.xyz
7
Moment in Spans
𝑀 =
𝑛 , 𝑙
10
=
12.30 × 2.25
10
= 6.23𝑘𝑁. 𝑚/𝑚
Since moment is relatively low. Provide Y12 @ 200mm Centres (As, prov = 565mm2
/m)
3.3 Concrete Beams
3.3.1 Beam C-C (300x750)
3.3.1.1 Actions on Beam
Permanent Actions:
Span 1
a. Equivalent uniformly distributed load transferred from slab to beam
= 2 ×
𝑛 𝑙
6
3 −
𝑙
𝑙
= 2 ×
7.5 × 7.5
6
3 −
7.5
9.0
= 43.31kN/m
b. self-weight of beam = (0.75 − 0.2) × 0.3 × 25 = 4.125kN/m
c. Walls = (3.75 − 0.75) × 3.5 = 10.5kN/m
Permanent Actions G = 43.31 + 4.125 + 10.5 = 57.94kN/m
Span 2
a. Equivalent uniformly distributed load transferred from slab to beam = 0kN/m
b. self-weight of beam = (0.45 − 0.15) × 0.3 × 25 = 2.25kN/m
Permanent Actions G = 2.25kN/m
Variable Actions:
Span 1
a. Equivalent uniformly distributed load transferred from slab to beam
= 2 ×
𝑛 𝑙
6
3 −
𝑙
𝑙
= 2 ×
3.0 × 7.5
6
3 −
7.5
9.0
= 17.32kN/m
Variable Actions Q = 17.32kN/m
Design Value of Actions on Beam
StructuresCentre.xyz
8
By inspection the permanent actions are less than 4.5 times the variable actions, therefore
equation 6.13b of BS EN 1990 will give the most unfavourable results.
Span 1:
Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 57.94) + (1.5 × 17.32) = 𝟗𝟖. 𝟑𝒌𝑵/𝒎
Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 57.94 = 𝟕𝟐. 𝟒𝒌𝑵/𝒎
Span 2:
Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 2.25) + (1.5 × 0) = 𝟑. 𝟖𝟎𝒌𝑵/𝒎
Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 2.25 = 𝟑. 𝟖𝟎𝒌𝑵/𝒎
3.3.1.2 Analysis of Beam
Approximate methods of analysis could be used, this requires, the use of simple coefficients
reflecting the approximate value of the internal forces within the structural element.
However, an analysis of the subframe will be carried out here, with the basic aim of obtaining
the loads & moment transferred to the column as well as the internal forces on the beam.
Only the shear and bending moment diagrams are presented here. The reader is expected to
already have a basic knowledge on analysis of subframes. However, guidance can be obtained
from: How to Analyse Element in Frames.
The load cases considered are:
 All spans loaded with the maximum design loads
 Alternate spans loaded with the maximum design load while the other spans are loaded
with the design permanent actions
StructuresCentre.xyz
9
Figure 1: Subframe C-C
Figure 2: Bending Moment Envelope
Figure 3: Shear Force Envelope
StructuresCentre.xyz
10
3.3.1.3 Flexural Design
End Support (3-2)
M = 200.6kN. m
Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm
links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 450 − 25 + 10 + = 402.5mm; b = 300mm
k =
M
bd f
=
200.6 × 10
300 × 402.5 × 20
= 0.021 > 0.168 (Section is doubly reinforced)
𝐴 =
(𝑘 − 𝑘 )𝑓 𝑏𝑑
0.87𝑓 (𝑑 − 𝑑 )
=
(0.21 − 0.168) × 20 × 300 × 404.5
0.87 × 410 × (402.5 − 43)
= 321.54𝑚𝑚
Try 3Y16mm bars Bottom (As, prov = 602mm2
).
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.21) ≤ 0.95d
=0.75d = 0.75 × 402.5 = 301.88mm
A =
𝑘𝑓 𝑏𝑑
0.87f z
+ 𝐴 =
0.168 × 20 × 300 × 402.5
0.87 × 410 × 301.88
+ 321.54 = 1838.08mm
Try 4Y25mm bars Top (As, prov = 1962mm2
).
Interior Support (2-1)
M = 531.4kN. m
Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm
links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 702.5mm; b = 300mm
k =
M
bd f
=
531.4 × 10
300 × 702.5 × 20
= 0.018 > 0.168 (Section is doubly reinforced)
StructuresCentre.xyz
11
𝐴 =
(𝑘 − 𝑘 )𝑓 𝑏𝑑
0.87𝑓 (𝑑 − 𝑑 )
=
(0.18 − 0.168) × 20 × 300 × 702.5
0.87 × 410 × (702.5 − 43)
= 151.05𝑚𝑚
Try 3Y16mm bars Bottom (As, prov = 602mm2
) .
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.18) ≤ 0.95d
=0.80d = 0.80 × 702.5 = 562mm
A =
𝑘𝑓 𝑏𝑑
0.87f z
+ 𝐴 =
0.168 × 20 × 300 × 702.5
0.87 × 410 × 562
+ 151.05 = 2632.55mm
Try 4Y25mm + 4Y20mm bars Top (As, prov = 3218mm2
). To be spread across the effective width.
b = b + b , + b , ≤ b
b , = 0.1l = 0.1 × 0.15(l + l ) = 0.1 × 0.15(2250 + 7500) = 146.25mm
b = 300 + 146.25 + 146.25 = 592.5mm
Therefore, this reinforcement will be spread across a width of 592.5mm.
Span (2-1)
M = 524.2kN. m
Assuming cover to reinforcement of 25mm, two layers of 25mm tensile bars, 16mm compression
bars & 8mm links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 677.5mm;
b = b = b + b , + b , ≤ b
b , = b , = 0.2b + 0.1𝑙 ≤ 0.2𝑙
𝑏 =
7500 − 150 − 150
2
= 3600𝑚𝑚
𝑙 = 0.85𝑙 = 0.85 × 9000 = 7650𝑚𝑚
b , = b , = (0.2 × 3600) + (0.1 × 7650) ≤ (0.2 × 7650) = 1485𝑚𝑚
b = 300 + 1485 + 1485 = 3270mm ≤ 3600mm
k =
M
bd f
=
524.2 × 10
3270 × 677.5 × 20
= 0.017
StructuresCentre.xyz
12
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.017) ≤ 0.95d
=0.95d = 0.95 × 677.5 = 643.63mm
We have to verify the position of the neutral axis:
x = 2.5(d − z) = 2.5(677.5 − 643.63) = 84.68mm
Therefore x < h = 84.68 < 200 (neutral axis is within the flange)
Hence, we can design as a rectangular section.
A =
M
0.87f z
=
524.2 × 10
0.87 × 410 × 643.63
= 2283.27mm
Try 5Y25mm bars Bottom in two layers (As, prov = 2452.5mm2
).
End Support (1-2)
M = 412.6kN. m
Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm
links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 702.5mm; b = 300mm
k =
M
bd f
=
412.6 × 10
300 × 702.5 × 20
= 0.14 < 0.168 (Section is singly reinforced)
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.14) ≤ 0.95d
=0.86d = 0.86 × 702.5 = 604.15mm
A =
M
0.87f z
=
412.6 × 10
0.87 × 410 × 604.15
= 1914.6mm
Try 3Y25mm +3Y20mm bars Top (As, prov = 2413mm2
). To be spread across the effective width.
3.3.1.4 Shear Design
By inspection, the critical section for shear occurs at the interior support 2, hence can be used to
conservatively size the shear reinforcement for the whole beam.
StructuresCentre.xyz
13
𝑉 = (455.6 − 0.6775 × 98.3) = 389.0𝑘𝑁
𝑉 , =
0.18
𝛾
𝑘(100𝜌 𝑓 ) 𝑏 𝑑 ≥ 0.035𝑘 𝑓 𝑏 𝑑
𝑘 = 1 +
200
677.5
= 1 +
200
677.5
= 1.54 < 2
𝐴 = 2453𝑚𝑚
𝑏 = 300𝑚𝑚
𝜌 =
𝐴
𝑏 𝑑
=
2453
300 × 677.5
= 0.012
𝑉 , =
0.18
1.5
× 1.54 × (100 × 0.012 × 20) ∙ 300 × 677.5
≥ 0.035 × 1.54 × √20 × 300 × 677.5 = 108.34kN
Since 𝑉 > 𝑉 , (389.0𝑘𝑁 > 108.34𝑘𝑁) therefore shear reinforcement is required.
𝜃 = 0.5𝑠𝑖𝑛
5.56𝑉
𝑏 𝑑(1 −
𝑓
250
)𝑓
= 0.5𝑠𝑖𝑛
5.56 × 389.0 × 10
300 × 677.5 1 −
20
250
20
= 17.66°
cot 𝜃 = cot 17.66 = 3.14 > 2.5 Hence take cot 𝜃 = 2.5
≥ where z = 0.9d = 0.9 × 677.5 = 609.75mm
A
S
≥
389.0 × 10
609.75 × 2.5 × 410
= 0.62
max spacing = 0.75d = 0.75 × 677.5 = 508.13mm
𝐴 ,
𝑆
=
0.08 𝑓 𝑏
𝑓
=
0.08 × √20 × 300
410
= 0.26
Use Y10 @ 200mm centres (0.78).
3.3.1.5 Deflection Verification
Deflection seems not to be critical in this beam, however for the purpose of illustration, the 9.0m
span will be verified using the span-effective depth ratios.
StructuresCentre.xyz
14
= 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3
𝜌 =
𝐴 ,
𝐴
=
𝐴 ,
𝑏 𝑑 + (𝑏 − 𝑏 )ℎ
=
2283.27
(300 × 677.5) + (3270 − 300)200
= 0.29%
ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ
N = 11 +
1.5 f ρ
ρ
+ 3.2 f
ρ
ρ
− 1 = 11 +
1.5√20 × 0.45
0.29
+ 3.2√30
0.45
0.29
− 1
= 29.81
F1 = 0.82
K = 1.3 (end spans)
F2 =
7.5
𝑙
=
7.5
9.0
= 0.83
F3 =
310
σ
≤ 1.5
σ =
f
γ
g + φq
n
A ,
A ,
∙
1
δ
=
410
1.15
×
57.94 + 0.6(17.32)
98.3
×
2283.27
2453
= 230.7Mpa
F3 =
310
230.7
= 1.34
L
d
= 29.81 × 1.3 × 0.82 × 0.83 × 1.34 = 35.34
L
d
=
span
effective depth
=
9000
677.5
= 13.28
Since the limiting span-effective depth ratio is greater than the actual span-effective depth ratio. It
therefore follows that deflection has been satisfied in the end spans.
3.3.1.6 Detailing Checks
Minimum Area of Steel
A , = 0.26
f
f
𝑏 d ≥ 0.0013bd
f = 0.30f = 0.3 × 20 = 2.21Mpa
StructuresCentre.xyz
15
Hogging at Supports
A , = 0.26 ×
2.21
410
× 300 × 702.5 ≥ 0.0013 × 300 × 702.5
= 295.4mm . By observation it is not critical anywhere at the supports.
Sagging in Spans
A , = 0.26 ×
2.21
410
× 300 × 677.5 ≥ 0.0013 × 300 × 677.5
= 284.99mm . By observation it is not critical anywhere in the spans. Hence adopt all
attempted bars.
3.3.2 Beam 2-2 (225x750)
3.3.2.1 Actions on Beam
Permanent Actions:
Span 1 & 2
a. Equivalent uniformly distributed load transferred from slab to beam
=
𝑛 , 𝑙 ,
3
+
𝑛 , 𝑙 ,
2
=
(7.5 × 7.5)
3
+
(6.25 × 2.25)
2
= 25.8kN/m
b. self-weight of beam = (0.75 − 0.2) × 0.225 × 25 = 3.1kN/m
c. Walls = (3.75 − 0.75) × 3.5 = 10.5kN/m
Permanent Actions G = 25.8 + 3.1 + 10.5 = 39.4kN/m
Variable Actions:
Span 1 & 2
a. Equivalent uniformly distributed load transferred from slab to beam
=
𝑛 , 𝑙 ,
3
+
𝑛 , 𝑙 ,
2
=
(3.0 × 7.5)
3
+
(3.0 × 2.25)
2
= 10.88kN/m
Variable Actions Q = 10.88kN/m
Design Value of Actions on Beam
By inspection the permanent actions are less than 4.5 times the variable actions, therefore
equation 6.13b of BS EN 1990 will give the most unfavourable results.
StructuresCentre.xyz
16
Span 1 & 2:
Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 39.4) + (1.5 × 10.88) = 𝟔𝟓. 𝟓𝟐𝒌𝑵/𝒎
Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 39.4 = 𝟒𝟗. 𝟐𝟎𝒌𝑵/𝒎
3.3.2.2 Analysis of Beam
Coefficients for beam analysis can be used to determine the internal forces in this beam, since
the spans are equal and uniformly loaded. However, in-order to determine the column
moments, analysis of the entire subframe 2-2 will be carried out
The load cases considered are:
 All spans loaded with the maximum design loads
 Alternate spans loaded with the maximum design load while the other spans are loaded
with the design permanent actions
Figure 4: Subframe 2-2
StructuresCentre.xyz
17
Figure 5: Bending Moment Envelope
Figure 6: Shear Force Envelope
3.3.2.3 Flexural Design
End Support (A & D)
M = 172.5kN. m
Assuming cover to reinforcement of 25mm, 20mm tensile bars, 16mm compression bars & 8mm
links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 705mm; b = 225mm
StructuresCentre.xyz
18
k =
M
bd f
=
172.5 × 10
225 × 705 × 20
= 0.078 < 0.168 (Section is singly reinforced)
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.078) ≤ 0.95d
=0.93d = 0.93 × 705 = 655.7mm
A =
M
0.87f z
=
172.5 × 10
0.87 × 410 × 655.7
= 737.53mm
Try 4Y16mm bars Top (As, prov = 1608mm2
).
Span (2-1)
M = 206.0kN. m
Assuming cover to reinforcement of 25mm, 20mm tensile bars, 16mm compression bars & 8mm
links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 705mm;
b = b = b + b , + b , ≤ b
b , = 0.2𝑏 + 0.1𝑙 , ≤ 0.2𝑙 ,
𝑏 =
9000 − 112.5 − 112.5
2
= 4387.5𝑚𝑚
𝑙 , = 0.85𝑙 = 0.85 × 7500 = 6375𝑚𝑚
b , = (0.2 × 4387.5) + (0.1 × 6375) ≤ (0.2 × 6375) = 1275𝑚𝑚
b , = 0.2𝑏 + 0.1𝑙 , ≤ 0.2𝑙 ,
𝑏 =
2250 − 112.5 − 112.5
2
= 1012.5𝑚𝑚
𝑙 , = 0.85𝑙 = 0.85 × 7500 = 6375𝑚𝑚
b , = (0.2 × 1012.5) + (0.1 × 6375) ≤ (0.2 × 6375) = 840𝑚𝑚
b = 225 + 1275 + 840 = 2340mm ≤ 4387.5mm
StructuresCentre.xyz
19
k =
M
bd f
=
206 × 10
2340 × 705 × 20
= 0.009
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.009) ≤ 0.95d
=0.95d = 0.95 × 705 = 669.75mm
We have to verify the position of the neutral axis:
x = 2.5(d − z) = 2.5(705 − 669.75) = 88.13mm
Therefore x < h = 88.13 < 200 (neutral axis is within the flange)
Hence, we can design as a rectangular section.
A =
M
0.87f z
=
206 × 10
0.87 × 410 × 669.75
= 862.3mm
Try 3Y20mm bars Bottom in two layers (As, prov = 942mm2
).
Interior Support (C)
M = 373.1kN. m
Assuming cover to reinforcement of 25mm, two layers of 20mm tensile bars, 16mm compression
bars & 8mm links
d = c + links +
∅
2
= 25 + 10 +
16
2
= 43𝑚𝑚
d = h − c + links +
∅
= 750 − 25 + 10 + = 705mm; b = 225mm
k =
M
bd f
=
373.1 × 10
225 × 685 × 20
= 0.167 < 0.168 (Section is singly reinforced)
z = d 0.5 + √0.25 − 0.882k ≤ 0.95d
=d 0.5 + 0.25 − 0.882(0.167) ≤ 0.95d
=0.82d = 0.82 × 705 = 578.1mm
A =
M
0.87f z
=
373.1 × 10
0.87 × 410 × 578.1
= 1809.3mm
Try 6Y20mm bars Top (As, prov = 1884mm2
) Spread across effective width of the beam.
StructuresCentre.xyz
20
3.3.2.4 Shear Design
By inspection, the critical section for shear occurs at the interior support C, hence can be used to
conservatively size the shear reinforcement for the whole beam.
𝑉 = (273.5 − 0.705 × 65.52) = 227.3𝑘𝑁
𝑉 , =
0.18
𝛾
𝑘(100𝜌 𝑓 ) 𝑏 𝑑 ≥ 0.035𝑘 𝑓 𝑏 𝑑
𝑘 = 1 +
200
705
= 1 +
200
705
= 1.53 < 2
𝐴 = 942𝑚𝑚
𝑏 = 225𝑚𝑚
𝜌 =
𝐴
𝑏 𝑑
=
942
225 × 705
= 0.0059
𝑉 , =
0.18
1.5
× 1.53 × (100 × 0.0059 × 20) ∙ 225 × 705
≥ 0.035 × 1.53 × √20 × 225 × 705 = 66.3kN
Since 𝑉 > 𝑉 , (389.0𝑘𝑁 > 66.3𝑘𝑁) therefore shear reinforcement is required.
𝜃 = 0.5𝑠𝑖𝑛
5.56𝑉
𝑏 𝑑(1 −
𝑓
250
)𝑓
= 0.5𝑠𝑖𝑛
5.56 × 227.3 × 10
225 × 705 1 −
20
250
20
= 12.8°
cot 𝜃 = cot 12.8 = 4.40 > 2.5 Hence take cot 𝜃 = 2.5
≥ where z = 0.9d = 0.9 × 705 = 634.5mm
A
S
≥
227.3 × 10
634.5 × 2.5 × 410
= 0.34
max spacing = 0.75d = 0.75 × 705 = 528.75mm
𝐴 ,
𝑆
=
0.08 𝑓 𝑏
𝑓
=
0.08 × √20 × 225
410
= 0.26
Use Y10 @ 200mm centres (0.78).
StructuresCentre.xyz
21
3.3.2.5 Deflection Verification
= 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3
𝜌 =
𝐴 ,
𝐴
=
𝐴 ,
𝑏 𝑑 + (𝑏 − 𝑏 )ℎ
=
862.3
(225 × 705) + (2270 − 225)200
= 0.15%
ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ
N = 11 +
1.5 f ρ
ρ
+ 3.2 f
ρ
ρ
− 1 = 11 +
1.5√20 × 0.45
0.15
+ 3.2√20
0.45
0.15
− 1
= 63.1
F1 = 0.82
K = 1.3 (end spans)
F2 = 1.0
F3 =
310
σ
≤ 1.5
σ =
f
γ
g + φq
n
A ,
A ,
∙
1
δ
=
410
1.15
×
39.4 + 0.6(10.88)
65.52
×
862.3
942
= 228.8Mpa
F3 =
310
228.8
= 1.35
L
d
= 63.1 × 1.3 × 0.82 × 1.0 × 1.35 = 90.81
L
d
=
span
effective depth
=
7500
705
= 10.64
Since the limiting span-effective depth ratio is greater than the actual span-effective depth ratio. It
therefore follows that deflection has been satisfied.
3.3.2.6 Detailing Checks
Minimum Area of Steel
A , = 0.2687
f
f
𝑏 d ≥ 0.0013bd
f = 0.30f = 0.3 × 20 = 2.21Mpa
StructuresCentre.xyz
22
Hogging at Supports & Sagging in Spans
A , = 0.26 ×
2.21
410
× 225 × 705 ≥ 0.0013 × 300 × 702.5
= 222.3mm . By observation it is not critical anywhere at the supports. Hence adopt all
attempted bars.
3.4 Concrete Columns
3.4.1 Column C2
3.4.1.1 Actions on Column
Roof
Permanent Action:
a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 1.5 ×
. ×( . . )
= 63.28𝑘𝑁
b. Beam self weight = 3.2 ×
. . . .
= 42𝑘𝑁
c. Column Weight = (0.4 × 0.4 × 3.3) × 25 = 13.2𝑘𝑁
𝑮𝒌,𝒓𝒐𝒐𝒇 = 𝟔𝟑. 𝟔𝒌𝑵
Variable Actions:
a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 0.6 ×
. ×( . . )
= 25.3𝑘𝑁
𝑸𝒌,𝒓𝒐𝒐𝒇 = 𝟐𝟓. 𝟑𝒌𝑵
Floors
Permanent Action:
a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 7.5 ×
. ×
+ 6.25 ×
. × .
= 305.86𝑘𝑁
b. Beam self weight = 3.2 ×
. . . .
= 42𝑘𝑁
c. Walls = 10.5 ×
. . . .
= 137.81𝑘𝑁
d. Column Weight = (0.4 × 0.4 × 3.0) × 25 = 12𝑘𝑁
𝑮𝒌,𝒇𝒍𝒐𝒐𝒓𝒔 = 𝟒𝟗𝟕. 𝟕𝒌𝑵
Variable Actions:
a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 3.0 ×
. ×( . . )
= 126.6𝑘𝑁
StructuresCentre.xyz
23
𝑸𝒌,𝒓𝒐𝒐𝒇 = 𝟏𝟐𝟔. 𝟔𝒌𝑵
Imposed Reduction Factors
α = 1 − = 1 −
( . × )
= 0.83 ≥ 0.75 ; 𝛼 = 0.83 (same for all floors)
α = 1 −
0
10
= 1 −
0
10
= 1.0 for 3rd − Roof
α = 1 −
1
10
= 1 −
1
10
= 0.9 for 2nd − 3rd floor
α = 1 −
2
10
= 1 −
2
10
= 0.8 for 1st − 2nd floor
α = 1 −
3
10
= 1 −
3
10
= 0.7 for Ground − 1st floor
Table 1: Load Take Down for Column C2
Floors 𝛼 𝛼 𝐺 (kN) 𝐺 (kN) . 𝑄 (kN) 𝑄 (kN) . 𝑄 (kN) .
3rd
-Roof 0.83 1.0 63.6 63.6 25.3 25.3 21.0
2nd
– 3rd
Floor 0.83 0.9 497.7 561.3 126.6 151.9 126.1
1st
– 2nd
Floor 0.83 0.8 497.7 1059 126.6 278.5 222.8
G – 1st
Floor 0.83 0.7 497.7 1556.7 126.6 405.1 283.57
The bending moment on the column is obtained from the analysis of the subframes 2-2 and C-C.
The roof subframe have not been analysed, the roof moments are also determined through a
similar process applied at the floors.
Table 2: Bending Moments on Column C2
Floor 𝑀 , 𝑀 , 𝑀 , 𝑀 ,
3rd
-Roof -21.5 165.4 -5.7 18.3
2nd
-3rd
Floor -165.4 165.4 -18.3 18.3
1st
-2nd
Floor -165.4 165.4 -18.3 18.3
G-1st
Floor -165.4 82.7 -18.3 9.2
StructuresCentre.xyz
24
3.4.1.1 Column Design
The column has been sized to be “stocky” hence slenderness need not to be verified.
3rd Floor - Roof
Design Axial Action
By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation
6.13b of BS EN 1990 will give the most unfavourable results.
𝑁 = 1.35𝜉𝐺 + 1.5𝑄 = 1.35(0.925 × 63.6) + (1.5 × 21) = 𝟏𝟏𝟎. 𝟗𝒌𝑵
Design Moments
Y-Y Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 +
0.75 × 3750
400
× 110.9 ∙ 10 = 166.2𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (110.9 × 20) ∙ 10 = 2.2𝑘𝑁. 𝑚
M , = max|166.2 ; 2.2| = 𝟏𝟔𝟔. 𝟐𝐤𝐍. 𝐦
Z-Z Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 +
0.75 × 3750
400
× 110.9 ∙ 10 = 19.1𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (110.9 × 20) ∙ 10 = 2.2𝑘𝑁. 𝑚
M , = max|19.1 ; 2.2| = 𝟏𝟗. 𝟏𝐤𝐍. 𝐦
Having obtained our design moments, the column is designed in the most critical direction (y-y
axis) and we then conclude by checking out biaxial bending.
StructuresCentre.xyz
25
Design Using Chart
𝑑 = ℎ − 𝑐 +
∅
2
+ 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 +
20
2
+ 8 = 357𝑚𝑚
𝑑
ℎ
=
357
400
= 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85
𝑁
𝑏ℎ𝑓
=
110.9 × 10
(400 × 400) × 20
= 0.03;
𝑀
𝑏ℎ𝑓
=
166.2 × 10
(400 × 400 ) × 20
= 0.13
𝐴 𝑓
𝑏ℎ𝑓
= 0.35
𝐴 = 0.35
𝑏ℎ𝑓
𝑓
0.35 ×
(400 × 400) × 20
410
= 𝟐𝟕𝟐𝟑. 𝟕𝒎𝒎𝟐
Try 10Y20mm Bars (As.prov = 3140mm2
)
𝐴 , = 0.1
𝑁
0.87𝑓
≥ 0.002𝐴 = 0.1 ×
110.9 × 10
0.87 × 410
≥ 0.002(400 × 400) = 320𝑚𝑚
𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚
𝐴 , < 𝐴 < 𝐴 , = (320𝑚𝑚 < 2723.7𝑚𝑚 < 6400𝑚𝑚 ) O.K
Use 10Y20 bars 𝑨𝒔,𝒑𝒓𝒐 (𝟑𝟏𝟒𝟎𝒎𝒎𝟐
)
– Containment Links
Link diameter = 𝑚𝑎𝑥 6 ;
∅
= 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚
Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm
Use 2T8 links at 200mm centre.
By inspection, biaxial bending is not critical for this column stack, hence the check can be
ignored.
2nd - 3rd Floor
Design Axial Action
By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation
6.13b of BS EN 1990 will give the most unfavourable results.
StructuresCentre.xyz
26
𝑁 = 1.35𝜉𝐺 + 1.5𝑄 = 1.35(0.925 × 561.3) + (1.5 × 126.1) = 𝟖𝟗𝟏𝒌𝑵
Design Moments
Y-Y Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 +
0.75 × 3750
400
× 891 ∙ 10 = 171.7𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (891 × 20) ∙ 10 = 17.82𝑘𝑁. 𝑚
M , = max|171.7 ; 17.82| = 𝟏𝟕𝟏. 𝟕𝐤𝐍. 𝐦
Z-Z Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 +
0.75 × 3750
400
× 891 ∙ 10 = 24.6𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (891 × 20) ∙ 10 = 17.82𝑘𝑁. 𝑚
M , = max|24.6 ; 17.82| = 𝟏𝟗. 𝟏𝐤𝐍. 𝐦
The column is designed in the most critical direction (y-y axis) and we then conclude by checking
out biaxial bending.
Design Using Chart
𝑑 = ℎ − 𝑐 +
∅
2
+ 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 +
25
2
+ 8 = 354.5𝑚𝑚
𝑑
ℎ
=
354.5
400
= 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85
𝑁
𝑏ℎ𝑓
=
891 × 10
(400 × 400) × 20
= 0.3;
𝑀
𝑏ℎ𝑓
=
171.7 × 10
(400 × 400 ) × 20
= 0.13
𝐴 𝑓
𝑏ℎ𝑓
= 0.20
𝐴 = 0.20
𝑏ℎ𝑓
𝑓
StructuresCentre.xyz
27
0.20 ×
(400 × 400) × 20
410
= 𝟏𝟓𝟔𝟏𝒎𝒎𝟐
Try 10Y20mm Bars (As.prov = 3140mm2
)
𝐴 , = 0.1
𝑁
0.87𝑓
≥ 0.002𝐴 = 0.1 ×
891 × 10
0.87 × 410
≥ 0.002(400 × 400) = 320𝑚𝑚
𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚
𝐴 , < 𝐴 < 𝐴 , = (320𝑚𝑚 < 1561𝑚𝑚 < 6400𝑚𝑚 ) O.K
Use 10Y20 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟑𝟏𝟒𝟎𝒎𝒎𝟐
)
– Containment Links
Link diameter = 𝑚𝑎𝑥 6 ;
∅
= 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚
Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm
Use 2T8 links at 200mm centre.
By inspection, biaxial bending is not critical for this column stack, hence the check can be
ignored.
1st - 2nd Floor
Design Axial Action
By inspection the permanent actions are greater than 4.5 times the variable actions, therefore
equation 6.13a of BS EN 1990 will give the most unfavourable results.
𝑁 = 1.35𝐺 + 1.5𝜓𝑄 = 1.35(1059) + (1.5 × 0.7 × 126.1) = 𝟏𝟓𝟔𝟐. 𝟏𝒌𝑵
Design Moments
Y-Y Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 +
0.75 × 3750
400
× 1562.1 ∙ 10
= 176.4𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (1562.1 × 20) ∙ 10 = 31.2𝑘𝑁. 𝑚
StructuresCentre.xyz
28
M , = max|176.4 ; 31.2| = 𝟏𝟕𝟔. 𝟒𝐤𝐍. 𝐦
Z-Z Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 +
0.75 × 3750
400
× 1562.1 ∙ 10 = 29.3𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (1562.1 × 20) ∙ 10 = 31.2𝑘𝑁. 𝑚
M , = max|29.3 ; 31.2| = 𝟑𝟏. 𝟐𝐤𝐍. 𝐦
The column is designed in the most critical direction (y-y axis) and we then conclude by checking
out biaxial bending.
Design Using Chart
𝑑 = ℎ − 𝑐 +
∅
2
+ 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 +
25
2
+ 8 = 354.5𝑚𝑚
𝑑
ℎ
=
354.5
400
= 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85
𝑁
𝑏ℎ𝑓
=
1562.1 × 10
(400 × 400) × 20
= 0.49;
𝑀
𝑏ℎ𝑓
=
176.4 × 10
(400 × 400 ) × 20
= 0.14
𝐴 𝑓
𝑏ℎ𝑓
= 0.40
𝐴 = 0.40
𝑏ℎ𝑓
𝑓
0.40 ×
(400 × 400) × 20
410
= 𝟑𝟏𝟐𝟐𝒎𝒎𝟐
Try 12Y20mm Bars (As.prov = 3768mm2
)
𝐴 , = 0.1
𝑁
0.87𝑓
≥ 0.002𝐴 = 0.1 ×
1562.1 × 10
0.87 × 410
≥ 0.002(400 × 400) = 438𝑚𝑚
𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚
𝐴 , < 𝐴 < 𝐴 , = (438𝑚𝑚 < 3122𝑚𝑚 < 6400𝑚𝑚 ) O.K
Use 12Y20 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟑𝟕𝟖𝟖𝒎𝒎𝟐
)
StructuresCentre.xyz
29
– Containment Links
Link diameter = 𝑚𝑎𝑥 6 ;
∅
= 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚
Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm
Use 2T8 links at 200mm centre.
By inspection, biaxial bending is not critical for this column stack, hence the check can be
ignored.
Ground – 1st Floor
Design Axial Action
By inspection the permanent actions are greater than 4.5 times the variable actions, therefore
equation 6.13a of BS EN 1990 will give the most unfavourable results.
𝑁 = 1.35𝐺 + 1.5𝜓𝑄 = 1.35(1556.7) + (1.5 × 0.7 × 283.57) = 𝟐𝟑𝟗𝟗. 𝟑𝒌𝑵
Design Moments
Y-Y Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 +
0.75 × 3750
400
× 2399.3 ∙ 10
= 182.3𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (2399.3 × 20) ∙ 10 = 47.99𝑘𝑁. 𝑚
M , = max|182.3 ; 47.99| = 𝟏𝟖𝟐. 𝟑𝐤𝐍. 𝐦
Z-Z Direction
𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 |
𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 +
0.75 × 3750
400
× 2399.3 ∙ 10 = 35.17𝑘𝑁. 𝑚
𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚
𝑀 , = (2399.3 × 20) ∙ 10 = 47.99𝑘𝑁. 𝑚
StructuresCentre.xyz
30
M , = max|35.17 ; 47.99| = 𝟒𝟕. 𝟗𝟗𝐤𝐍. 𝐦
The column is designed in the most critical direction (y-y axis) and we then conclude by checking
out biaxial bending.
Design Using Chart
𝑑 = ℎ − 𝑐 +
∅
2
+ 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 +
25
2
+ 8 = 354.5𝑚𝑚
𝑑
ℎ
=
354.5
400
= 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85
𝑁
𝑏ℎ𝑓
=
2399.3 × 10
(400 × 400) × 20
= 0.75;
𝑀
𝑏ℎ𝑓
=
182.3 × 10
(400 × 400 ) × 20
= 0.142
𝐴 𝑓
𝑏ℎ𝑓
= 0.65
𝐴 = 0.65
𝑏ℎ𝑓
𝑓
0.65 ×
(400 × 400) × 20
410
= 𝟓𝟎𝟕𝟑. 𝟐𝒎𝒎𝟐
Try 12Y25mm Bars (As.prov = 5886mm2
)
𝐴 , = 0.1
𝑁
0.87𝑓
≥ 0.002𝐴 = 0.1 ×
2339.3 × 10
0.87 × 410
≥ 0.002(400 × 400) = 438𝑚𝑚
𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚
𝐴 , < 𝐴 < 𝐴 , = (655.8𝑚𝑚 < 5073.2𝑚𝑚 < 6400𝑚𝑚 ) O.K
Use 12Y25 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟓𝟖𝟖𝟔𝒎𝒎𝟐
)
– Containment Links
Link diameter = 𝑚𝑎𝑥 6 ;
∅
= 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚
Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 25 ; 400 ; 400𝑚𝑚} = 240mm
Use 2T8 links at 200mm centre.
By inspection, biaxial bending is not critical for this column stack, hence the check can be
ignored.
StructuresCentre.xyz
31
3.5 Pad Foundation to Column C2
3.5.1 Serviceability Limit State
𝐺 = 1556.7𝑘𝑁 𝑄 = 283.57𝑘𝑁
𝑁 = 1.0𝐺 + 1.0𝑄 = 1556.7 + 283.57 = 1840.3𝑘N
Assume 10% increase in axial actions to actions to account for footing self weight
𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 = (1 + 0.1) × 1840.3 = 2024.3𝑘𝑁
𝐴𝑟𝑒𝑎 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 =
𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑
𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑟𝑒𝑠𝑖𝑠𝑡𝑎𝑛𝑐𝑒
=
2024.3
150
= 13.5𝑚
Assume a square base: length = breadth √13.5 = 3.67𝑚
Provide a Base of 3.7m × 3.7m (say 0.6m deep) 𝐴𝑟𝑒𝑎 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = 13.69𝑚
3.5.1 Ultimate Limit State
N = 1.35G + 1.5Q = (1.35 × 1556.7) + (1.5 × 283.57) = 2527kN
bearing pressure =
Design axial action
Area provided
=
N
A
=
2527
(3.7 × 3.7)
= 184.6kN/m
Punching check at Column face
Assume cover to reinforcement is 50mm and reinforcement of 16mm
d = h − c +
ϕ
2
= 600 − 50 +
16
2
= 542mm
Verify that N ≤ V ,
𝑉 , = 0.2 1 −
𝑓
250
𝑓 𝑝 𝑑 = 0.2 1 −
20
250
20 × (4 × 400) × 542 × 10 = 3191.3𝑘𝑁
Thus (𝑁 = 2527𝑘𝑁) < 𝑉 , = (3191.3kN) O. K
Flexural Design
𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 @ 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑐𝑜𝑙𝑢𝑚𝑛 =
(3.7 − 0.40)
2
= 1.65𝑚
𝑀 =
𝑝𝑙
2
=
184.6 × 1.65
2
= 162.0𝑘𝑁. 𝑚/m
𝑘 =
𝑀
𝑏𝑑 𝑓
=
162 × 10
10 × 542 × 20
= 0.028 < 0.168
𝑧 = 𝑑 0.5 + √0.25 − 0.882𝑘 ≤ 0.95𝑑
StructuresCentre.xyz
32
= 0.95𝑑 = 0.95 × 542 = 514.9𝑚𝑚
𝐴 =
𝑀
0.87𝑓 𝑧
=
162 × 10
0.87 × 410 × 514.9
= 882.04𝑚𝑚 /m
𝑇𝑟𝑦 𝑌16 − 150 𝑐𝑒𝑛𝑡𝑟𝑒𝑠 𝑏𝑜𝑡ℎ 𝑤𝑎𝑦𝑠 𝐴 , = 1340𝑚𝑚 /𝑚
Punching Shear at Basic Control Perimeter 2.0d from column face
𝑉 = 𝑁 − ∆𝑉
∆𝑉 = 𝑝A
𝐴 = 𝑐 𝑐 + 𝜋(2𝑑) + 4(𝑐 + 𝑐 )𝑑 = 400 + 𝜋(2 × 542) + 4(400 + 400)542 = 5.6𝑚
𝑝 = 2(𝑐 + 𝑐 ) + 4𝜋𝑑 = 2(400 + 400) + 4𝜋(542) = 8414𝑚𝑚
𝑉 = 2527 − 184.6(5.6) = 1493𝑘𝑁
𝑣 =
𝑉
𝑝 𝑑
=
1493 × 10
8414 × 542
= 0.33𝑀𝑝𝑎
𝑣 , = 0.12𝑘(100𝜌𝑓 ) /
≥ 0.035𝑘 /
𝑓
𝜌 = =
×
= 0.0025 ; 𝑘 = 1 + = 1 + = 1.61 < 2
𝑣 , = 0.12 × 1.61(100 × 0.0025 × 20) /
≥ 0.035 × 1.61 √20 = 0.33𝑀𝑝𝑎
𝑆𝑖𝑛𝑐𝑒 (𝑣 = 0.33𝑀𝑝𝑎) ≤ (𝑣 , = 0.33𝑀𝑝𝑎) 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙 𝑏𝑢𝑡 𝑂. 𝑘.
Transverse shear: Taken at 1.0d from the face of the column
𝑉 = 𝑝(1.325 − 1.0d) = 184.6 × (1.65 − 0.542) = 204.6𝑘𝑁/𝑚
𝑣 =
𝑉
𝑏𝑑
=
204.6 × 10
1000 × 542
= 0.38
𝑣 , = 0.33𝑀𝑝𝑎 (as before)
(𝑣 = 0.36𝑀𝑝𝑎) = (𝑣 , = 0.36𝑀𝑝𝑎) 𝑁𝑜𝑡 𝑂. 𝐾.
Since the base is barely passing in punching and failing in transverse shear, the base thickness
can be increased to 650mm.
Verify Minimum Area of Steel
𝐴 , =
0.078𝑓
/
𝑓
𝑏 d ≥ 0.0013𝑏 𝑑
StructuresCentre.xyz
33
𝐴 , =
0.078(20) /
410
× 1000 × 542 ≥ 0.0013 × 1000 × 542
= 876.5𝑚𝑚 < 1340𝑚𝑚 o. k
Use 24T16-150 both ways
3.6 Design Summary
Figure 7: Slab Reinforcement Summary
StructuresCentre.xyz
34
Figure 8: Summary of Reinforcement in Beam C-C
Figure 9: Summary of Reinforcement in Beam 2-2
StructuresCentre.xyz
35
Figure 10: Summary of Reinforcement in Column C2
Figure 11: Summary of Pad Base to Column C2

More Related Content

What's hot

Stress&strain part 2
Stress&strain part 2Stress&strain part 2
Stress&strain part 2
AHMED SABER
 
Chapter 03 MECHANICS OF MATERIAL
Chapter 03 MECHANICS OF MATERIALChapter 03 MECHANICS OF MATERIAL
Chapter 03 MECHANICS OF MATERIAL
abu_mlk
 
Deflection and member deformation
Deflection and member deformationDeflection and member deformation
Deflection and member deformation
Mahmoud Youssef Abido
 
Areas related to circles ppt by jk
Areas related to circles ppt by jkAreas related to circles ppt by jk
Areas related to circles ppt by jk
Jyothikumar M
 
Problemas esfuerzos en vigas
Problemas esfuerzos en vigasProblemas esfuerzos en vigas
Problemas esfuerzos en vigas
José Grimán Morales
 
Chapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFAChapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFA
Mustafa Al Bakri
 
Determine bending moment and share force diagram of beam
Determine bending moment and share force diagram of beamDetermine bending moment and share force diagram of beam
Determine bending moment and share force diagram of beam
Turja Deb
 
0136023126 ism 06(1)
0136023126 ism 06(1)0136023126 ism 06(1)
0136023126 ism 06(1)
aryaanuj1
 
Design of an automotive differential with reduction ratio greater than 6
Design of an automotive differential with reduction ratio greater than 6Design of an automotive differential with reduction ratio greater than 6
Design of an automotive differential with reduction ratio greater than 6
eSAT Publishing House
 
Solution manual 16
Solution manual 16Solution manual 16
Solution manual 16
Rafi Flydarkzz
 
Bending stress and shear stress for Asymmetric I-Section.
Bending stress and shear stress for Asymmetric  I-Section.Bending stress and shear stress for Asymmetric  I-Section.
Bending stress and shear stress for Asymmetric I-Section.
Dr.Abhinav .
 
09 review
09 review09 review
09 review
Liezel Abante
 
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOFCASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
Rituraj Dhar
 
Solutions completo elementos de maquinas de shigley 8th edition
Solutions completo elementos de maquinas de shigley 8th editionSolutions completo elementos de maquinas de shigley 8th edition
Solutions completo elementos de maquinas de shigley 8th edition
fercrotti
 
Design of Bioclimatic Structure with Insulation of Cavity Wall
Design of  Bioclimatic Structure with Insulation of Cavity WallDesign of  Bioclimatic Structure with Insulation of Cavity Wall
Design of Bioclimatic Structure with Insulation of Cavity Wall
IRJET Journal
 
Solution manual 17 19
Solution manual 17 19Solution manual 17 19
Solution manual 17 19
Rafi Flydarkzz
 
Truss examples
Truss examplesTruss examples
Truss examples
AHMED SABER
 
ME 5720 Fall 2015 - Wind Turbine Project_FINAL
ME 5720 Fall 2015 - Wind Turbine Project_FINALME 5720 Fall 2015 - Wind Turbine Project_FINAL
ME 5720 Fall 2015 - Wind Turbine Project_FINAL
Omar Latifi
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
physicsbook
 
Problemas de cables
Problemas de cablesProblemas de cables
Problemas de cables
José Grimán Morales
 

What's hot (20)

Stress&strain part 2
Stress&strain part 2Stress&strain part 2
Stress&strain part 2
 
Chapter 03 MECHANICS OF MATERIAL
Chapter 03 MECHANICS OF MATERIALChapter 03 MECHANICS OF MATERIAL
Chapter 03 MECHANICS OF MATERIAL
 
Deflection and member deformation
Deflection and member deformationDeflection and member deformation
Deflection and member deformation
 
Areas related to circles ppt by jk
Areas related to circles ppt by jkAreas related to circles ppt by jk
Areas related to circles ppt by jk
 
Problemas esfuerzos en vigas
Problemas esfuerzos en vigasProblemas esfuerzos en vigas
Problemas esfuerzos en vigas
 
Chapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFAChapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFA
 
Determine bending moment and share force diagram of beam
Determine bending moment and share force diagram of beamDetermine bending moment and share force diagram of beam
Determine bending moment and share force diagram of beam
 
0136023126 ism 06(1)
0136023126 ism 06(1)0136023126 ism 06(1)
0136023126 ism 06(1)
 
Design of an automotive differential with reduction ratio greater than 6
Design of an automotive differential with reduction ratio greater than 6Design of an automotive differential with reduction ratio greater than 6
Design of an automotive differential with reduction ratio greater than 6
 
Solution manual 16
Solution manual 16Solution manual 16
Solution manual 16
 
Bending stress and shear stress for Asymmetric I-Section.
Bending stress and shear stress for Asymmetric  I-Section.Bending stress and shear stress for Asymmetric  I-Section.
Bending stress and shear stress for Asymmetric I-Section.
 
09 review
09 review09 review
09 review
 
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOFCASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
CASE STUDY - STRUCTURAL DESIGN FOR MODERN INSULATOR'S SHUTTLE KILN ROOF
 
Solutions completo elementos de maquinas de shigley 8th edition
Solutions completo elementos de maquinas de shigley 8th editionSolutions completo elementos de maquinas de shigley 8th edition
Solutions completo elementos de maquinas de shigley 8th edition
 
Design of Bioclimatic Structure with Insulation of Cavity Wall
Design of  Bioclimatic Structure with Insulation of Cavity WallDesign of  Bioclimatic Structure with Insulation of Cavity Wall
Design of Bioclimatic Structure with Insulation of Cavity Wall
 
Solution manual 17 19
Solution manual 17 19Solution manual 17 19
Solution manual 17 19
 
Truss examples
Truss examplesTruss examples
Truss examples
 
ME 5720 Fall 2015 - Wind Turbine Project_FINAL
ME 5720 Fall 2015 - Wind Turbine Project_FINALME 5720 Fall 2015 - Wind Turbine Project_FINAL
ME 5720 Fall 2015 - Wind Turbine Project_FINAL
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
 
Problemas de cables
Problemas de cablesProblemas de cables
Problemas de cables
 

Similar to Possible solution struct_hub_design assessment

Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
Raghav Sankar
 
RCC BMD
RCC BMDRCC BMD
Design ppt
Design pptDesign ppt
Design ppt
tishu001
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
EngGalaydh Farah Axmed
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
Luan Truong Van
 
1 reinforced concrete lectures-t-beam2
1 reinforced concrete lectures-t-beam21 reinforced concrete lectures-t-beam2
1 reinforced concrete lectures-t-beam2
Malika khalil
 
Muro contension raul1
Muro contension raul1Muro contension raul1
Muro contension raul1
Diego Rodriguez
 
Flanged beams design for t beam
Flanged beams   design for t beamFlanged beams   design for t beam
Flanged beams design for t beam
Selvakumar Palanisamy
 
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDINGPLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
Seranjeevi Seranjeevi
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
luantvconst
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
Afgaab Cumar
 
Design of Structures Chapter2.pdf
Design of Structures Chapter2.pdfDesign of Structures Chapter2.pdf
Design of Structures Chapter2.pdf
UmarSaba1
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
subhashini214160
 
Power screw application
Power screw applicationPower screw application
Power screw application
alsaid fathy
 
Preliminary design of slab
Preliminary design of slabPreliminary design of slab
Preliminary design of slab
ila vamsi krishna
 
steel question.pdf.pdf
steel question.pdf.pdfsteel question.pdf.pdf
steel question.pdf.pdf
nabal_iitb
 
Puentes
PuentesPuentes
Design of Structures Chapter2.pptx
Design of Structures Chapter2.pptxDesign of Structures Chapter2.pptx
Design of Structures Chapter2.pptx
UmarSaba1
 
Diseño de Escalera
Diseño de EscaleraDiseño de Escalera
Diseño de Escalera
Joel López
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
KiranKr32
 

Similar to Possible solution struct_hub_design assessment (20)

Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
 
RCC BMD
RCC BMDRCC BMD
RCC BMD
 
Design ppt
Design pptDesign ppt
Design ppt
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
1 reinforced concrete lectures-t-beam2
1 reinforced concrete lectures-t-beam21 reinforced concrete lectures-t-beam2
1 reinforced concrete lectures-t-beam2
 
Muro contension raul1
Muro contension raul1Muro contension raul1
Muro contension raul1
 
Flanged beams design for t beam
Flanged beams   design for t beamFlanged beams   design for t beam
Flanged beams design for t beam
 
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDINGPLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
Design of Structures Chapter2.pdf
Design of Structures Chapter2.pdfDesign of Structures Chapter2.pdf
Design of Structures Chapter2.pdf
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 
Power screw application
Power screw applicationPower screw application
Power screw application
 
Preliminary design of slab
Preliminary design of slabPreliminary design of slab
Preliminary design of slab
 
steel question.pdf.pdf
steel question.pdf.pdfsteel question.pdf.pdf
steel question.pdf.pdf
 
Puentes
PuentesPuentes
Puentes
 
Design of Structures Chapter2.pptx
Design of Structures Chapter2.pptxDesign of Structures Chapter2.pptx
Design of Structures Chapter2.pptx
 
Diseño de Escalera
Diseño de EscaleraDiseño de Escalera
Diseño de Escalera
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
 

Recently uploaded

sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 

Recently uploaded (20)

sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 

Possible solution struct_hub_design assessment

  • 1. StructuresCentre.xyz 1 POSSIBLE SOLUTION TO STRUCT-HUB: DESIGN ASSESSMENT II Omotoriogun Victor Femi Copyright ©Structures centre, 2021. All rights reserved 18th February 2021 structurescentre@gmail.com 1.0 DESIGN SOLUTION Preliminary sizing of the structural element has been carried using the guidance provided in: Preliminary sizing of structural elements as well as the guidance provided in the publication by the Concrete Centre- Economic Concrete Frame Elements.
  • 2. StructuresCentre.xyz 2 3.1 Actions 3.1 1 Roof Permanent Actions = 1.5𝑘𝑁/𝑚 Variable Actions = 0.6𝑘𝑁/𝑚 3.1.2 Floors Permanent Actions: i. Self weight of slab = 0.20 × 25 = 5𝑘𝑁/𝑚 (𝐶𝑙𝑎𝑠𝑠𝑟𝑜𝑜𝑚) = 0.15 × 25 = 3.75𝑘𝑁/𝑚 (𝑊𝑎𝑙𝑘𝑤𝑎𝑦) ii. Finishes & Services = 1.5𝑘𝑁/𝑚 iii. Partition Allowances = 1.0𝑘𝑁/𝑚 Total Permanent Actions = 𝑔 = 7.5𝑘𝑁/𝑚 & 6.25𝑘𝑁/𝑚 Variable Actions: i. Floor Imposed Loading (Classroom & Walkways) = 𝑞 = 3.0𝑘𝑁/𝑚 Design Value of Actions: By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation 6.13b of BS EN 1990 will give the most unfavourable results. Roof Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 1.5) + (1.5 × 0.6) = 2.77𝑘𝑁𝑚 Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 1.5 = 1.87𝑘𝑁/𝑚 Classroom Panels Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 7.5) + (1.5 × 3) = 13.87𝑘𝑁𝑚 Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 7.5 = 9.37𝑘𝑁/𝑚 Walkway Panels Design Actions= 1.35𝜉𝑔 + 1.5𝑞 =(1.35 × 0.925 × 6.25) + (1.5 × 3) = 12.30𝑘𝑁𝑚
  • 3. StructuresCentre.xyz 3 Design Permanent Load 1.35𝜉𝑔 = 1.35 × 0.925 × 6.25 = 7.80𝑘𝑁/𝑚 3.2 Slab Panels 3.2.1 Classroom Panels 𝐿 𝐿 = 9000 7500 = 1.2 (𝑇𝑤𝑜 𝑤𝑎𝑦 𝑆𝑙𝑎𝑏 − 𝑇𝑤𝑜 𝐴𝑑𝑗𝑎𝑐𝑒𝑛𝑡 𝑆𝑖𝑑𝑒𝑠 𝐷𝑖𝑠𝑐𝑜𝑛𝑡𝑖𝑛𝑜𝑢𝑠) Using coefficients from table for two ways slabs with two adjacent sides discontinuous. Short span coefficients = −0.064 & 0.047 Long span coefficients = −0.045 & 0.034 3.2.1.1 Flexural Design Negative Moment at Support (Short Span) 𝑀 = −0.064𝑛 , 𝑙 = −0.064 × 13.87 × 7.5 = −49.93𝑘𝑁. 𝑚/𝑚 Assuming cover to reinforcement of 20mm, 12mm bars d = h − c + links + ∅ = 200 − 20 + = 174mm; b = 1000mm k = M bd f = 49.93 × 10 1000 × 174 × 20 = 0.0825 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.0825) ≤ 0.95d =0.92d = 0.92 × 174 = 160.08mm A = M 0.87f z = 49.93 × 10 0.87 × 410 × 160.08 = 874.42mm /m Try Y12mm bars @ 125mm Centres (As, prov = 904mm2 ) Positive Moment at Midspan (Short Span) 𝑀 = 0.047𝑛 , 𝑙 = 0.047 × 13.87 × 7.5 = 36.67𝑘𝑁. 𝑚/𝑚 Assuming cover to reinforcement of 20mm, 12mm bars
  • 4. StructuresCentre.xyz 4 d = h − c + links + ∅ = 200 − 20 + = 174mm; b = 1000mm k = M bd f = 36.67 × 10 1000 × 174 × 20 = 0.0606 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.0606) ≤ 0.95d =0.94d = 0.94 × 174 = 163.56mm A = M 0.87f z = 36.67 × 10 0.87 × 410 × 163.56 = 628.54mm /m Try Y12mm bars @ 125mm Centres (As, prov = 904mm2 ) Negative Moment at Support (Long Span) 𝑀 = −0.045𝑛 , 𝑙 = −0.045 × 13.87 × 7.5 = −35.11𝑘𝑁. 𝑚/𝑚 Assuming cover to reinforcement of 20mm, 12mm bars d = h − c + links + ∅ + ∅ = 200 − 20 + + 12 = 162mm; b = 1000mm k = M bd f = 35.11 × 10 1000 × 162 × 20 = 0.067 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.067) ≤ 0.95d =0.94d = 0.94 × 162 = 152.28mm A = M 0.87f z = 35.11 × 10 0.87 × 410 × 152.28 = 646.38mm /m Try Y12mm bars @ 150mm Centres (As, prov = 753mm2 ) Positive Moment at Midspan (Long Span) 𝑀 = 0.034𝑛 , 𝑙 = 0.034 × 13.87 × 7.5 = 26.53𝑘𝑁. 𝑚/𝑚 Assuming cover to reinforcement of 20mm, 12mm bars d = h − c + links + ∅ + ∅ = 200 − 20 + + 12 = 162mm; b = 1000mm
  • 5. StructuresCentre.xyz 5 k = M bd f = 26.53 × 10 1000 × 162 × 20 = 0.051 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.051) ≤ 0.95d =0.95d = 0.95 × 162 = 153.9mm A = M 0.87f z = 26.53 × 10 0.87 × 410 × 153.9 = 483.28mm /m Try Y12mm bars @ 150mm Centres (As, prov = 753mm2 /m) 3.2.1.2 Deflection Verification Deflection verification can be carried using either of the two alternative method provided in section 7.4 of Eurocode 2 (Part 1). The conservative span-effective method and the rigorous calculation approach which involve using theoretical expression to estimate the actual deflection of the slab. The span-effective method is used here, the rigorous method is not suitable for hand calculations, spreadsheets or finite element software’s are required for fast calculations. Basic Requirement: ≥ = 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3 𝜌 = 𝐴 , 𝐴 = 𝐴 , 𝑏𝑑 = 628.54 (1000 × 174) = 0.36% ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ N = 11 + 1.5 f ρ ρ + 3.2 f ρ ρ − 1 = 11 + 1.5√20 × 0.45 0.36 + 3.2√20 0.45 0.36 − 1 = 21.20 F1 = 1.0 K = 1.3 (end spans)
  • 6. StructuresCentre.xyz 6 F2 = 7.0 l = 7.0 7.5 = 0.93 F3 = 310 σ ≤ 1.5 σ = f γ g + φq n A , A , ∙ 1 δ = 410 1.15 × 7.5 + 0.6(3) 13.87 × 628.54 904 = 166.21Mpa F3 = 310 166.21 = 1.87 > 1.5 L d = 21.20 × 1.3 × 1.0 × 0.93 × 1.50 = 38.45 L d = span effective depth = 7500 174 = 43.10 Since actual span-effective depth ratio is greater than the limiting span-effective depth ratio. It shows that we might have a deflection problem. Hence, the options available includes, increasing the slab thickness, the concrete class or even the steel bars grade. However, readers are reminded that, the span/effective depth approach is only a fast and conservative method of verifying deflection. In this case the rigorous calculation method was used and the slab found to perform satisfactory with respect to deflection. 3.2.1.3 Detailing Checks. The minimum area of steel required in panel: A , = 0.26 f f 𝑏 d ≥ 0.0013bd f = 0.30f = 0.3 × 20 = 2.21Mpa A , = 0.26 × 2.21 410 × 1000 × 174 ≥ 0.0013 × 1000 × 174 = 243.85mm . By observation it is not critical anywhere in slab. Hence adopt all steel bars. 3.2.2 Walkway Panels The walkways panel are one-way slabs which can be idealized as propped cantilevers.
  • 7. StructuresCentre.xyz 7 Moment in Spans 𝑀 = 𝑛 , 𝑙 10 = 12.30 × 2.25 10 = 6.23𝑘𝑁. 𝑚/𝑚 Since moment is relatively low. Provide Y12 @ 200mm Centres (As, prov = 565mm2 /m) 3.3 Concrete Beams 3.3.1 Beam C-C (300x750) 3.3.1.1 Actions on Beam Permanent Actions: Span 1 a. Equivalent uniformly distributed load transferred from slab to beam = 2 × 𝑛 𝑙 6 3 − 𝑙 𝑙 = 2 × 7.5 × 7.5 6 3 − 7.5 9.0 = 43.31kN/m b. self-weight of beam = (0.75 − 0.2) × 0.3 × 25 = 4.125kN/m c. Walls = (3.75 − 0.75) × 3.5 = 10.5kN/m Permanent Actions G = 43.31 + 4.125 + 10.5 = 57.94kN/m Span 2 a. Equivalent uniformly distributed load transferred from slab to beam = 0kN/m b. self-weight of beam = (0.45 − 0.15) × 0.3 × 25 = 2.25kN/m Permanent Actions G = 2.25kN/m Variable Actions: Span 1 a. Equivalent uniformly distributed load transferred from slab to beam = 2 × 𝑛 𝑙 6 3 − 𝑙 𝑙 = 2 × 3.0 × 7.5 6 3 − 7.5 9.0 = 17.32kN/m Variable Actions Q = 17.32kN/m Design Value of Actions on Beam
  • 8. StructuresCentre.xyz 8 By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation 6.13b of BS EN 1990 will give the most unfavourable results. Span 1: Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 57.94) + (1.5 × 17.32) = 𝟗𝟖. 𝟑𝒌𝑵/𝒎 Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 57.94 = 𝟕𝟐. 𝟒𝒌𝑵/𝒎 Span 2: Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 2.25) + (1.5 × 0) = 𝟑. 𝟖𝟎𝒌𝑵/𝒎 Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 2.25 = 𝟑. 𝟖𝟎𝒌𝑵/𝒎 3.3.1.2 Analysis of Beam Approximate methods of analysis could be used, this requires, the use of simple coefficients reflecting the approximate value of the internal forces within the structural element. However, an analysis of the subframe will be carried out here, with the basic aim of obtaining the loads & moment transferred to the column as well as the internal forces on the beam. Only the shear and bending moment diagrams are presented here. The reader is expected to already have a basic knowledge on analysis of subframes. However, guidance can be obtained from: How to Analyse Element in Frames. The load cases considered are:  All spans loaded with the maximum design loads  Alternate spans loaded with the maximum design load while the other spans are loaded with the design permanent actions
  • 9. StructuresCentre.xyz 9 Figure 1: Subframe C-C Figure 2: Bending Moment Envelope Figure 3: Shear Force Envelope
  • 10. StructuresCentre.xyz 10 3.3.1.3 Flexural Design End Support (3-2) M = 200.6kN. m Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 450 − 25 + 10 + = 402.5mm; b = 300mm k = M bd f = 200.6 × 10 300 × 402.5 × 20 = 0.021 > 0.168 (Section is doubly reinforced) 𝐴 = (𝑘 − 𝑘 )𝑓 𝑏𝑑 0.87𝑓 (𝑑 − 𝑑 ) = (0.21 − 0.168) × 20 × 300 × 404.5 0.87 × 410 × (402.5 − 43) = 321.54𝑚𝑚 Try 3Y16mm bars Bottom (As, prov = 602mm2 ). z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.21) ≤ 0.95d =0.75d = 0.75 × 402.5 = 301.88mm A = 𝑘𝑓 𝑏𝑑 0.87f z + 𝐴 = 0.168 × 20 × 300 × 402.5 0.87 × 410 × 301.88 + 321.54 = 1838.08mm Try 4Y25mm bars Top (As, prov = 1962mm2 ). Interior Support (2-1) M = 531.4kN. m Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 702.5mm; b = 300mm k = M bd f = 531.4 × 10 300 × 702.5 × 20 = 0.018 > 0.168 (Section is doubly reinforced)
  • 11. StructuresCentre.xyz 11 𝐴 = (𝑘 − 𝑘 )𝑓 𝑏𝑑 0.87𝑓 (𝑑 − 𝑑 ) = (0.18 − 0.168) × 20 × 300 × 702.5 0.87 × 410 × (702.5 − 43) = 151.05𝑚𝑚 Try 3Y16mm bars Bottom (As, prov = 602mm2 ) . z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.18) ≤ 0.95d =0.80d = 0.80 × 702.5 = 562mm A = 𝑘𝑓 𝑏𝑑 0.87f z + 𝐴 = 0.168 × 20 × 300 × 702.5 0.87 × 410 × 562 + 151.05 = 2632.55mm Try 4Y25mm + 4Y20mm bars Top (As, prov = 3218mm2 ). To be spread across the effective width. b = b + b , + b , ≤ b b , = 0.1l = 0.1 × 0.15(l + l ) = 0.1 × 0.15(2250 + 7500) = 146.25mm b = 300 + 146.25 + 146.25 = 592.5mm Therefore, this reinforcement will be spread across a width of 592.5mm. Span (2-1) M = 524.2kN. m Assuming cover to reinforcement of 25mm, two layers of 25mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 677.5mm; b = b = b + b , + b , ≤ b b , = b , = 0.2b + 0.1𝑙 ≤ 0.2𝑙 𝑏 = 7500 − 150 − 150 2 = 3600𝑚𝑚 𝑙 = 0.85𝑙 = 0.85 × 9000 = 7650𝑚𝑚 b , = b , = (0.2 × 3600) + (0.1 × 7650) ≤ (0.2 × 7650) = 1485𝑚𝑚 b = 300 + 1485 + 1485 = 3270mm ≤ 3600mm k = M bd f = 524.2 × 10 3270 × 677.5 × 20 = 0.017
  • 12. StructuresCentre.xyz 12 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.017) ≤ 0.95d =0.95d = 0.95 × 677.5 = 643.63mm We have to verify the position of the neutral axis: x = 2.5(d − z) = 2.5(677.5 − 643.63) = 84.68mm Therefore x < h = 84.68 < 200 (neutral axis is within the flange) Hence, we can design as a rectangular section. A = M 0.87f z = 524.2 × 10 0.87 × 410 × 643.63 = 2283.27mm Try 5Y25mm bars Bottom in two layers (As, prov = 2452.5mm2 ). End Support (1-2) M = 412.6kN. m Assuming cover to reinforcement of 25mm, 25mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 702.5mm; b = 300mm k = M bd f = 412.6 × 10 300 × 702.5 × 20 = 0.14 < 0.168 (Section is singly reinforced) z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.14) ≤ 0.95d =0.86d = 0.86 × 702.5 = 604.15mm A = M 0.87f z = 412.6 × 10 0.87 × 410 × 604.15 = 1914.6mm Try 3Y25mm +3Y20mm bars Top (As, prov = 2413mm2 ). To be spread across the effective width. 3.3.1.4 Shear Design By inspection, the critical section for shear occurs at the interior support 2, hence can be used to conservatively size the shear reinforcement for the whole beam.
  • 13. StructuresCentre.xyz 13 𝑉 = (455.6 − 0.6775 × 98.3) = 389.0𝑘𝑁 𝑉 , = 0.18 𝛾 𝑘(100𝜌 𝑓 ) 𝑏 𝑑 ≥ 0.035𝑘 𝑓 𝑏 𝑑 𝑘 = 1 + 200 677.5 = 1 + 200 677.5 = 1.54 < 2 𝐴 = 2453𝑚𝑚 𝑏 = 300𝑚𝑚 𝜌 = 𝐴 𝑏 𝑑 = 2453 300 × 677.5 = 0.012 𝑉 , = 0.18 1.5 × 1.54 × (100 × 0.012 × 20) ∙ 300 × 677.5 ≥ 0.035 × 1.54 × √20 × 300 × 677.5 = 108.34kN Since 𝑉 > 𝑉 , (389.0𝑘𝑁 > 108.34𝑘𝑁) therefore shear reinforcement is required. 𝜃 = 0.5𝑠𝑖𝑛 5.56𝑉 𝑏 𝑑(1 − 𝑓 250 )𝑓 = 0.5𝑠𝑖𝑛 5.56 × 389.0 × 10 300 × 677.5 1 − 20 250 20 = 17.66° cot 𝜃 = cot 17.66 = 3.14 > 2.5 Hence take cot 𝜃 = 2.5 ≥ where z = 0.9d = 0.9 × 677.5 = 609.75mm A S ≥ 389.0 × 10 609.75 × 2.5 × 410 = 0.62 max spacing = 0.75d = 0.75 × 677.5 = 508.13mm 𝐴 , 𝑆 = 0.08 𝑓 𝑏 𝑓 = 0.08 × √20 × 300 410 = 0.26 Use Y10 @ 200mm centres (0.78). 3.3.1.5 Deflection Verification Deflection seems not to be critical in this beam, however for the purpose of illustration, the 9.0m span will be verified using the span-effective depth ratios.
  • 14. StructuresCentre.xyz 14 = 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3 𝜌 = 𝐴 , 𝐴 = 𝐴 , 𝑏 𝑑 + (𝑏 − 𝑏 )ℎ = 2283.27 (300 × 677.5) + (3270 − 300)200 = 0.29% ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ N = 11 + 1.5 f ρ ρ + 3.2 f ρ ρ − 1 = 11 + 1.5√20 × 0.45 0.29 + 3.2√30 0.45 0.29 − 1 = 29.81 F1 = 0.82 K = 1.3 (end spans) F2 = 7.5 𝑙 = 7.5 9.0 = 0.83 F3 = 310 σ ≤ 1.5 σ = f γ g + φq n A , A , ∙ 1 δ = 410 1.15 × 57.94 + 0.6(17.32) 98.3 × 2283.27 2453 = 230.7Mpa F3 = 310 230.7 = 1.34 L d = 29.81 × 1.3 × 0.82 × 0.83 × 1.34 = 35.34 L d = span effective depth = 9000 677.5 = 13.28 Since the limiting span-effective depth ratio is greater than the actual span-effective depth ratio. It therefore follows that deflection has been satisfied in the end spans. 3.3.1.6 Detailing Checks Minimum Area of Steel A , = 0.26 f f 𝑏 d ≥ 0.0013bd f = 0.30f = 0.3 × 20 = 2.21Mpa
  • 15. StructuresCentre.xyz 15 Hogging at Supports A , = 0.26 × 2.21 410 × 300 × 702.5 ≥ 0.0013 × 300 × 702.5 = 295.4mm . By observation it is not critical anywhere at the supports. Sagging in Spans A , = 0.26 × 2.21 410 × 300 × 677.5 ≥ 0.0013 × 300 × 677.5 = 284.99mm . By observation it is not critical anywhere in the spans. Hence adopt all attempted bars. 3.3.2 Beam 2-2 (225x750) 3.3.2.1 Actions on Beam Permanent Actions: Span 1 & 2 a. Equivalent uniformly distributed load transferred from slab to beam = 𝑛 , 𝑙 , 3 + 𝑛 , 𝑙 , 2 = (7.5 × 7.5) 3 + (6.25 × 2.25) 2 = 25.8kN/m b. self-weight of beam = (0.75 − 0.2) × 0.225 × 25 = 3.1kN/m c. Walls = (3.75 − 0.75) × 3.5 = 10.5kN/m Permanent Actions G = 25.8 + 3.1 + 10.5 = 39.4kN/m Variable Actions: Span 1 & 2 a. Equivalent uniformly distributed load transferred from slab to beam = 𝑛 , 𝑙 , 3 + 𝑛 , 𝑙 , 2 = (3.0 × 7.5) 3 + (3.0 × 2.25) 2 = 10.88kN/m Variable Actions Q = 10.88kN/m Design Value of Actions on Beam By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation 6.13b of BS EN 1990 will give the most unfavourable results.
  • 16. StructuresCentre.xyz 16 Span 1 & 2: Design Load = 1.35𝜉𝐺 + 1.5𝑄 = (1.35 × 0.925 × 39.4) + (1.5 × 10.88) = 𝟔𝟓. 𝟓𝟐𝒌𝑵/𝒎 Design Permanent Load 1.35𝜉𝐺 = 1.35 × 0.925 × 39.4 = 𝟒𝟗. 𝟐𝟎𝒌𝑵/𝒎 3.3.2.2 Analysis of Beam Coefficients for beam analysis can be used to determine the internal forces in this beam, since the spans are equal and uniformly loaded. However, in-order to determine the column moments, analysis of the entire subframe 2-2 will be carried out The load cases considered are:  All spans loaded with the maximum design loads  Alternate spans loaded with the maximum design load while the other spans are loaded with the design permanent actions Figure 4: Subframe 2-2
  • 17. StructuresCentre.xyz 17 Figure 5: Bending Moment Envelope Figure 6: Shear Force Envelope 3.3.2.3 Flexural Design End Support (A & D) M = 172.5kN. m Assuming cover to reinforcement of 25mm, 20mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 705mm; b = 225mm
  • 18. StructuresCentre.xyz 18 k = M bd f = 172.5 × 10 225 × 705 × 20 = 0.078 < 0.168 (Section is singly reinforced) z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.078) ≤ 0.95d =0.93d = 0.93 × 705 = 655.7mm A = M 0.87f z = 172.5 × 10 0.87 × 410 × 655.7 = 737.53mm Try 4Y16mm bars Top (As, prov = 1608mm2 ). Span (2-1) M = 206.0kN. m Assuming cover to reinforcement of 25mm, 20mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 705mm; b = b = b + b , + b , ≤ b b , = 0.2𝑏 + 0.1𝑙 , ≤ 0.2𝑙 , 𝑏 = 9000 − 112.5 − 112.5 2 = 4387.5𝑚𝑚 𝑙 , = 0.85𝑙 = 0.85 × 7500 = 6375𝑚𝑚 b , = (0.2 × 4387.5) + (0.1 × 6375) ≤ (0.2 × 6375) = 1275𝑚𝑚 b , = 0.2𝑏 + 0.1𝑙 , ≤ 0.2𝑙 , 𝑏 = 2250 − 112.5 − 112.5 2 = 1012.5𝑚𝑚 𝑙 , = 0.85𝑙 = 0.85 × 7500 = 6375𝑚𝑚 b , = (0.2 × 1012.5) + (0.1 × 6375) ≤ (0.2 × 6375) = 840𝑚𝑚 b = 225 + 1275 + 840 = 2340mm ≤ 4387.5mm
  • 19. StructuresCentre.xyz 19 k = M bd f = 206 × 10 2340 × 705 × 20 = 0.009 z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.009) ≤ 0.95d =0.95d = 0.95 × 705 = 669.75mm We have to verify the position of the neutral axis: x = 2.5(d − z) = 2.5(705 − 669.75) = 88.13mm Therefore x < h = 88.13 < 200 (neutral axis is within the flange) Hence, we can design as a rectangular section. A = M 0.87f z = 206 × 10 0.87 × 410 × 669.75 = 862.3mm Try 3Y20mm bars Bottom in two layers (As, prov = 942mm2 ). Interior Support (C) M = 373.1kN. m Assuming cover to reinforcement of 25mm, two layers of 20mm tensile bars, 16mm compression bars & 8mm links d = c + links + ∅ 2 = 25 + 10 + 16 2 = 43𝑚𝑚 d = h − c + links + ∅ = 750 − 25 + 10 + = 705mm; b = 225mm k = M bd f = 373.1 × 10 225 × 685 × 20 = 0.167 < 0.168 (Section is singly reinforced) z = d 0.5 + √0.25 − 0.882k ≤ 0.95d =d 0.5 + 0.25 − 0.882(0.167) ≤ 0.95d =0.82d = 0.82 × 705 = 578.1mm A = M 0.87f z = 373.1 × 10 0.87 × 410 × 578.1 = 1809.3mm Try 6Y20mm bars Top (As, prov = 1884mm2 ) Spread across effective width of the beam.
  • 20. StructuresCentre.xyz 20 3.3.2.4 Shear Design By inspection, the critical section for shear occurs at the interior support C, hence can be used to conservatively size the shear reinforcement for the whole beam. 𝑉 = (273.5 − 0.705 × 65.52) = 227.3𝑘𝑁 𝑉 , = 0.18 𝛾 𝑘(100𝜌 𝑓 ) 𝑏 𝑑 ≥ 0.035𝑘 𝑓 𝑏 𝑑 𝑘 = 1 + 200 705 = 1 + 200 705 = 1.53 < 2 𝐴 = 942𝑚𝑚 𝑏 = 225𝑚𝑚 𝜌 = 𝐴 𝑏 𝑑 = 942 225 × 705 = 0.0059 𝑉 , = 0.18 1.5 × 1.53 × (100 × 0.0059 × 20) ∙ 225 × 705 ≥ 0.035 × 1.53 × √20 × 225 × 705 = 66.3kN Since 𝑉 > 𝑉 , (389.0𝑘𝑁 > 66.3𝑘𝑁) therefore shear reinforcement is required. 𝜃 = 0.5𝑠𝑖𝑛 5.56𝑉 𝑏 𝑑(1 − 𝑓 250 )𝑓 = 0.5𝑠𝑖𝑛 5.56 × 227.3 × 10 225 × 705 1 − 20 250 20 = 12.8° cot 𝜃 = cot 12.8 = 4.40 > 2.5 Hence take cot 𝜃 = 2.5 ≥ where z = 0.9d = 0.9 × 705 = 634.5mm A S ≥ 227.3 × 10 634.5 × 2.5 × 410 = 0.34 max spacing = 0.75d = 0.75 × 705 = 528.75mm 𝐴 , 𝑆 = 0.08 𝑓 𝑏 𝑓 = 0.08 × √20 × 225 410 = 0.26 Use Y10 @ 200mm centres (0.78).
  • 21. StructuresCentre.xyz 21 3.3.2.5 Deflection Verification = 𝑁 × 𝐾 × 𝐹1 × 𝐹2 × 𝐹3 𝜌 = 𝐴 , 𝐴 = 𝐴 , 𝑏 𝑑 + (𝑏 − 𝑏 )ℎ = 862.3 (225 × 705) + (2270 − 225)200 = 0.15% ρ = 10 f = 10 × √20 = 0.45% since ρ < ρ N = 11 + 1.5 f ρ ρ + 3.2 f ρ ρ − 1 = 11 + 1.5√20 × 0.45 0.15 + 3.2√20 0.45 0.15 − 1 = 63.1 F1 = 0.82 K = 1.3 (end spans) F2 = 1.0 F3 = 310 σ ≤ 1.5 σ = f γ g + φq n A , A , ∙ 1 δ = 410 1.15 × 39.4 + 0.6(10.88) 65.52 × 862.3 942 = 228.8Mpa F3 = 310 228.8 = 1.35 L d = 63.1 × 1.3 × 0.82 × 1.0 × 1.35 = 90.81 L d = span effective depth = 7500 705 = 10.64 Since the limiting span-effective depth ratio is greater than the actual span-effective depth ratio. It therefore follows that deflection has been satisfied. 3.3.2.6 Detailing Checks Minimum Area of Steel A , = 0.2687 f f 𝑏 d ≥ 0.0013bd f = 0.30f = 0.3 × 20 = 2.21Mpa
  • 22. StructuresCentre.xyz 22 Hogging at Supports & Sagging in Spans A , = 0.26 × 2.21 410 × 225 × 705 ≥ 0.0013 × 300 × 702.5 = 222.3mm . By observation it is not critical anywhere at the supports. Hence adopt all attempted bars. 3.4 Concrete Columns 3.4.1 Column C2 3.4.1.1 Actions on Column Roof Permanent Action: a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 1.5 × . ×( . . ) = 63.28𝑘𝑁 b. Beam self weight = 3.2 × . . . . = 42𝑘𝑁 c. Column Weight = (0.4 × 0.4 × 3.3) × 25 = 13.2𝑘𝑁 𝑮𝒌,𝒓𝒐𝒐𝒇 = 𝟔𝟑. 𝟔𝒌𝑵 Variable Actions: a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 0.6 × . ×( . . ) = 25.3𝑘𝑁 𝑸𝒌,𝒓𝒐𝒐𝒇 = 𝟐𝟓. 𝟑𝒌𝑵 Floors Permanent Action: a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 7.5 × . × + 6.25 × . × . = 305.86𝑘𝑁 b. Beam self weight = 3.2 × . . . . = 42𝑘𝑁 c. Walls = 10.5 × . . . . = 137.81𝑘𝑁 d. Column Weight = (0.4 × 0.4 × 3.0) × 25 = 12𝑘𝑁 𝑮𝒌,𝒇𝒍𝒐𝒐𝒓𝒔 = 𝟒𝟗𝟕. 𝟕𝒌𝑵 Variable Actions: a. Roof Load = 𝑔 , × 𝐴𝑟𝑒𝑎 = 3.0 × . ×( . . ) = 126.6𝑘𝑁
  • 23. StructuresCentre.xyz 23 𝑸𝒌,𝒓𝒐𝒐𝒇 = 𝟏𝟐𝟔. 𝟔𝒌𝑵 Imposed Reduction Factors α = 1 − = 1 − ( . × ) = 0.83 ≥ 0.75 ; 𝛼 = 0.83 (same for all floors) α = 1 − 0 10 = 1 − 0 10 = 1.0 for 3rd − Roof α = 1 − 1 10 = 1 − 1 10 = 0.9 for 2nd − 3rd floor α = 1 − 2 10 = 1 − 2 10 = 0.8 for 1st − 2nd floor α = 1 − 3 10 = 1 − 3 10 = 0.7 for Ground − 1st floor Table 1: Load Take Down for Column C2 Floors 𝛼 𝛼 𝐺 (kN) 𝐺 (kN) . 𝑄 (kN) 𝑄 (kN) . 𝑄 (kN) . 3rd -Roof 0.83 1.0 63.6 63.6 25.3 25.3 21.0 2nd – 3rd Floor 0.83 0.9 497.7 561.3 126.6 151.9 126.1 1st – 2nd Floor 0.83 0.8 497.7 1059 126.6 278.5 222.8 G – 1st Floor 0.83 0.7 497.7 1556.7 126.6 405.1 283.57 The bending moment on the column is obtained from the analysis of the subframes 2-2 and C-C. The roof subframe have not been analysed, the roof moments are also determined through a similar process applied at the floors. Table 2: Bending Moments on Column C2 Floor 𝑀 , 𝑀 , 𝑀 , 𝑀 , 3rd -Roof -21.5 165.4 -5.7 18.3 2nd -3rd Floor -165.4 165.4 -18.3 18.3 1st -2nd Floor -165.4 165.4 -18.3 18.3 G-1st Floor -165.4 82.7 -18.3 9.2
  • 24. StructuresCentre.xyz 24 3.4.1.1 Column Design The column has been sized to be “stocky” hence slenderness need not to be verified. 3rd Floor - Roof Design Axial Action By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation 6.13b of BS EN 1990 will give the most unfavourable results. 𝑁 = 1.35𝜉𝐺 + 1.5𝑄 = 1.35(0.925 × 63.6) + (1.5 × 21) = 𝟏𝟏𝟎. 𝟗𝒌𝑵 Design Moments Y-Y Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 + 0.75 × 3750 400 × 110.9 ∙ 10 = 166.2𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (110.9 × 20) ∙ 10 = 2.2𝑘𝑁. 𝑚 M , = max|166.2 ; 2.2| = 𝟏𝟔𝟔. 𝟐𝐤𝐍. 𝐦 Z-Z Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 + 0.75 × 3750 400 × 110.9 ∙ 10 = 19.1𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (110.9 × 20) ∙ 10 = 2.2𝑘𝑁. 𝑚 M , = max|19.1 ; 2.2| = 𝟏𝟗. 𝟏𝐤𝐍. 𝐦 Having obtained our design moments, the column is designed in the most critical direction (y-y axis) and we then conclude by checking out biaxial bending.
  • 25. StructuresCentre.xyz 25 Design Using Chart 𝑑 = ℎ − 𝑐 + ∅ 2 + 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 + 20 2 + 8 = 357𝑚𝑚 𝑑 ℎ = 357 400 = 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85 𝑁 𝑏ℎ𝑓 = 110.9 × 10 (400 × 400) × 20 = 0.03; 𝑀 𝑏ℎ𝑓 = 166.2 × 10 (400 × 400 ) × 20 = 0.13 𝐴 𝑓 𝑏ℎ𝑓 = 0.35 𝐴 = 0.35 𝑏ℎ𝑓 𝑓 0.35 × (400 × 400) × 20 410 = 𝟐𝟕𝟐𝟑. 𝟕𝒎𝒎𝟐 Try 10Y20mm Bars (As.prov = 3140mm2 ) 𝐴 , = 0.1 𝑁 0.87𝑓 ≥ 0.002𝐴 = 0.1 × 110.9 × 10 0.87 × 410 ≥ 0.002(400 × 400) = 320𝑚𝑚 𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚 𝐴 , < 𝐴 < 𝐴 , = (320𝑚𝑚 < 2723.7𝑚𝑚 < 6400𝑚𝑚 ) O.K Use 10Y20 bars 𝑨𝒔,𝒑𝒓𝒐 (𝟑𝟏𝟒𝟎𝒎𝒎𝟐 ) – Containment Links Link diameter = 𝑚𝑎𝑥 6 ; ∅ = 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚 Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm Use 2T8 links at 200mm centre. By inspection, biaxial bending is not critical for this column stack, hence the check can be ignored. 2nd - 3rd Floor Design Axial Action By inspection the permanent actions are less than 4.5 times the variable actions, therefore equation 6.13b of BS EN 1990 will give the most unfavourable results.
  • 26. StructuresCentre.xyz 26 𝑁 = 1.35𝜉𝐺 + 1.5𝑄 = 1.35(0.925 × 561.3) + (1.5 × 126.1) = 𝟖𝟗𝟏𝒌𝑵 Design Moments Y-Y Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 + 0.75 × 3750 400 × 891 ∙ 10 = 171.7𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (891 × 20) ∙ 10 = 17.82𝑘𝑁. 𝑚 M , = max|171.7 ; 17.82| = 𝟏𝟕𝟏. 𝟕𝐤𝐍. 𝐦 Z-Z Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 + 0.75 × 3750 400 × 891 ∙ 10 = 24.6𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (891 × 20) ∙ 10 = 17.82𝑘𝑁. 𝑚 M , = max|24.6 ; 17.82| = 𝟏𝟗. 𝟏𝐤𝐍. 𝐦 The column is designed in the most critical direction (y-y axis) and we then conclude by checking out biaxial bending. Design Using Chart 𝑑 = ℎ − 𝑐 + ∅ 2 + 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 + 25 2 + 8 = 354.5𝑚𝑚 𝑑 ℎ = 354.5 400 = 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85 𝑁 𝑏ℎ𝑓 = 891 × 10 (400 × 400) × 20 = 0.3; 𝑀 𝑏ℎ𝑓 = 171.7 × 10 (400 × 400 ) × 20 = 0.13 𝐴 𝑓 𝑏ℎ𝑓 = 0.20 𝐴 = 0.20 𝑏ℎ𝑓 𝑓
  • 27. StructuresCentre.xyz 27 0.20 × (400 × 400) × 20 410 = 𝟏𝟓𝟔𝟏𝒎𝒎𝟐 Try 10Y20mm Bars (As.prov = 3140mm2 ) 𝐴 , = 0.1 𝑁 0.87𝑓 ≥ 0.002𝐴 = 0.1 × 891 × 10 0.87 × 410 ≥ 0.002(400 × 400) = 320𝑚𝑚 𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚 𝐴 , < 𝐴 < 𝐴 , = (320𝑚𝑚 < 1561𝑚𝑚 < 6400𝑚𝑚 ) O.K Use 10Y20 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟑𝟏𝟒𝟎𝒎𝒎𝟐 ) – Containment Links Link diameter = 𝑚𝑎𝑥 6 ; ∅ = 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚 Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm Use 2T8 links at 200mm centre. By inspection, biaxial bending is not critical for this column stack, hence the check can be ignored. 1st - 2nd Floor Design Axial Action By inspection the permanent actions are greater than 4.5 times the variable actions, therefore equation 6.13a of BS EN 1990 will give the most unfavourable results. 𝑁 = 1.35𝐺 + 1.5𝜓𝑄 = 1.35(1059) + (1.5 × 0.7 × 126.1) = 𝟏𝟓𝟔𝟐. 𝟏𝒌𝑵 Design Moments Y-Y Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 + 0.75 × 3750 400 × 1562.1 ∙ 10 = 176.4𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (1562.1 × 20) ∙ 10 = 31.2𝑘𝑁. 𝑚
  • 28. StructuresCentre.xyz 28 M , = max|176.4 ; 31.2| = 𝟏𝟕𝟔. 𝟒𝐤𝐍. 𝐦 Z-Z Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 + 0.75 × 3750 400 × 1562.1 ∙ 10 = 29.3𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (1562.1 × 20) ∙ 10 = 31.2𝑘𝑁. 𝑚 M , = max|29.3 ; 31.2| = 𝟑𝟏. 𝟐𝐤𝐍. 𝐦 The column is designed in the most critical direction (y-y axis) and we then conclude by checking out biaxial bending. Design Using Chart 𝑑 = ℎ − 𝑐 + ∅ 2 + 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 + 25 2 + 8 = 354.5𝑚𝑚 𝑑 ℎ = 354.5 400 = 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85 𝑁 𝑏ℎ𝑓 = 1562.1 × 10 (400 × 400) × 20 = 0.49; 𝑀 𝑏ℎ𝑓 = 176.4 × 10 (400 × 400 ) × 20 = 0.14 𝐴 𝑓 𝑏ℎ𝑓 = 0.40 𝐴 = 0.40 𝑏ℎ𝑓 𝑓 0.40 × (400 × 400) × 20 410 = 𝟑𝟏𝟐𝟐𝒎𝒎𝟐 Try 12Y20mm Bars (As.prov = 3768mm2 ) 𝐴 , = 0.1 𝑁 0.87𝑓 ≥ 0.002𝐴 = 0.1 × 1562.1 × 10 0.87 × 410 ≥ 0.002(400 × 400) = 438𝑚𝑚 𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚 𝐴 , < 𝐴 < 𝐴 , = (438𝑚𝑚 < 3122𝑚𝑚 < 6400𝑚𝑚 ) O.K Use 12Y20 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟑𝟕𝟖𝟖𝒎𝒎𝟐 )
  • 29. StructuresCentre.xyz 29 – Containment Links Link diameter = 𝑚𝑎𝑥 6 ; ∅ = 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚 Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 20 ; 400 ; 400𝑚𝑚} = 240mm Use 2T8 links at 200mm centre. By inspection, biaxial bending is not critical for this column stack, hence the check can be ignored. Ground – 1st Floor Design Axial Action By inspection the permanent actions are greater than 4.5 times the variable actions, therefore equation 6.13a of BS EN 1990 will give the most unfavourable results. 𝑁 = 1.35𝐺 + 1.5𝜓𝑄 = 1.35(1556.7) + (1.5 × 0.7 × 283.57) = 𝟐𝟑𝟗𝟗. 𝟑𝒌𝑵 Design Moments Y-Y Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 165.4 + 0.75 × 3750 400 × 2399.3 ∙ 10 = 182.3𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (2399.3 × 20) ∙ 10 = 47.99𝑘𝑁. 𝑚 M , = max|182.3 ; 47.99| = 𝟏𝟖𝟐. 𝟑𝐤𝐍. 𝐦 Z-Z Direction 𝑀 , = 𝑚𝑎𝑥|𝑀 ; 𝑀 | 𝑀 , = 𝑚𝑎𝑥 𝑀 ; 𝑀 + 𝑒 𝑁 = 18.3 + 0.75 × 3750 400 × 2399.3 ∙ 10 = 35.17𝑘𝑁. 𝑚 𝑀 , = 𝑁 𝑒 ; 𝑒 = = ≥ 20 = 20𝑚𝑚 𝑀 , = (2399.3 × 20) ∙ 10 = 47.99𝑘𝑁. 𝑚
  • 30. StructuresCentre.xyz 30 M , = max|35.17 ; 47.99| = 𝟒𝟕. 𝟗𝟗𝐤𝐍. 𝐦 The column is designed in the most critical direction (y-y axis) and we then conclude by checking out biaxial bending. Design Using Chart 𝑑 = ℎ − 𝑐 + ∅ 2 + 𝑙𝑖𝑛𝑘𝑠 = 400 − 25 + 25 2 + 8 = 354.5𝑚𝑚 𝑑 ℎ = 354.5 400 = 0.89 ; 𝑈𝑠𝑒 𝑐ℎ𝑎𝑟𝑡 𝑓𝑜𝑟 0.85 𝑁 𝑏ℎ𝑓 = 2399.3 × 10 (400 × 400) × 20 = 0.75; 𝑀 𝑏ℎ𝑓 = 182.3 × 10 (400 × 400 ) × 20 = 0.142 𝐴 𝑓 𝑏ℎ𝑓 = 0.65 𝐴 = 0.65 𝑏ℎ𝑓 𝑓 0.65 × (400 × 400) × 20 410 = 𝟓𝟎𝟕𝟑. 𝟐𝒎𝒎𝟐 Try 12Y25mm Bars (As.prov = 5886mm2 ) 𝐴 , = 0.1 𝑁 0.87𝑓 ≥ 0.002𝐴 = 0.1 × 2339.3 × 10 0.87 × 410 ≥ 0.002(400 × 400) = 438𝑚𝑚 𝐴 , = 0.04𝐴 = 0.04 × (400 × 400) = 6400𝑚𝑚 𝐴 , < 𝐴 < 𝐴 , = (655.8𝑚𝑚 < 5073.2𝑚𝑚 < 6400𝑚𝑚 ) O.K Use 12Y25 bars 𝑨𝒔,𝒑𝒓𝒐 = (𝟓𝟖𝟖𝟔𝒎𝒎𝟐 ) – Containment Links Link diameter = 𝑚𝑎𝑥 6 ; ∅ = 𝑚𝑎𝑥 6 ; ; 𝑈𝑠𝑒 8𝑚𝑚 Link spacing = 𝑚𝑖𝑛{20∅ ; 𝑏 ; 400𝑚𝑚} = min 0.6 × {20 × 25 ; 400 ; 400𝑚𝑚} = 240mm Use 2T8 links at 200mm centre. By inspection, biaxial bending is not critical for this column stack, hence the check can be ignored.
  • 31. StructuresCentre.xyz 31 3.5 Pad Foundation to Column C2 3.5.1 Serviceability Limit State 𝐺 = 1556.7𝑘𝑁 𝑄 = 283.57𝑘𝑁 𝑁 = 1.0𝐺 + 1.0𝑄 = 1556.7 + 283.57 = 1840.3𝑘N Assume 10% increase in axial actions to actions to account for footing self weight 𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 = (1 + 0.1) × 1840.3 = 2024.3𝑘𝑁 𝐴𝑟𝑒𝑎 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑟𝑒𝑠𝑖𝑠𝑡𝑎𝑛𝑐𝑒 = 2024.3 150 = 13.5𝑚 Assume a square base: length = breadth √13.5 = 3.67𝑚 Provide a Base of 3.7m × 3.7m (say 0.6m deep) 𝐴𝑟𝑒𝑎 𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑 = 13.69𝑚 3.5.1 Ultimate Limit State N = 1.35G + 1.5Q = (1.35 × 1556.7) + (1.5 × 283.57) = 2527kN bearing pressure = Design axial action Area provided = N A = 2527 (3.7 × 3.7) = 184.6kN/m Punching check at Column face Assume cover to reinforcement is 50mm and reinforcement of 16mm d = h − c + ϕ 2 = 600 − 50 + 16 2 = 542mm Verify that N ≤ V , 𝑉 , = 0.2 1 − 𝑓 250 𝑓 𝑝 𝑑 = 0.2 1 − 20 250 20 × (4 × 400) × 542 × 10 = 3191.3𝑘𝑁 Thus (𝑁 = 2527𝑘𝑁) < 𝑉 , = (3191.3kN) O. K Flexural Design 𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 @ 𝑓𝑎𝑐𝑒 𝑜𝑓 𝑐𝑜𝑙𝑢𝑚𝑛 = (3.7 − 0.40) 2 = 1.65𝑚 𝑀 = 𝑝𝑙 2 = 184.6 × 1.65 2 = 162.0𝑘𝑁. 𝑚/m 𝑘 = 𝑀 𝑏𝑑 𝑓 = 162 × 10 10 × 542 × 20 = 0.028 < 0.168 𝑧 = 𝑑 0.5 + √0.25 − 0.882𝑘 ≤ 0.95𝑑
  • 32. StructuresCentre.xyz 32 = 0.95𝑑 = 0.95 × 542 = 514.9𝑚𝑚 𝐴 = 𝑀 0.87𝑓 𝑧 = 162 × 10 0.87 × 410 × 514.9 = 882.04𝑚𝑚 /m 𝑇𝑟𝑦 𝑌16 − 150 𝑐𝑒𝑛𝑡𝑟𝑒𝑠 𝑏𝑜𝑡ℎ 𝑤𝑎𝑦𝑠 𝐴 , = 1340𝑚𝑚 /𝑚 Punching Shear at Basic Control Perimeter 2.0d from column face 𝑉 = 𝑁 − ∆𝑉 ∆𝑉 = 𝑝A 𝐴 = 𝑐 𝑐 + 𝜋(2𝑑) + 4(𝑐 + 𝑐 )𝑑 = 400 + 𝜋(2 × 542) + 4(400 + 400)542 = 5.6𝑚 𝑝 = 2(𝑐 + 𝑐 ) + 4𝜋𝑑 = 2(400 + 400) + 4𝜋(542) = 8414𝑚𝑚 𝑉 = 2527 − 184.6(5.6) = 1493𝑘𝑁 𝑣 = 𝑉 𝑝 𝑑 = 1493 × 10 8414 × 542 = 0.33𝑀𝑝𝑎 𝑣 , = 0.12𝑘(100𝜌𝑓 ) / ≥ 0.035𝑘 / 𝑓 𝜌 = = × = 0.0025 ; 𝑘 = 1 + = 1 + = 1.61 < 2 𝑣 , = 0.12 × 1.61(100 × 0.0025 × 20) / ≥ 0.035 × 1.61 √20 = 0.33𝑀𝑝𝑎 𝑆𝑖𝑛𝑐𝑒 (𝑣 = 0.33𝑀𝑝𝑎) ≤ (𝑣 , = 0.33𝑀𝑝𝑎) 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙 𝑏𝑢𝑡 𝑂. 𝑘. Transverse shear: Taken at 1.0d from the face of the column 𝑉 = 𝑝(1.325 − 1.0d) = 184.6 × (1.65 − 0.542) = 204.6𝑘𝑁/𝑚 𝑣 = 𝑉 𝑏𝑑 = 204.6 × 10 1000 × 542 = 0.38 𝑣 , = 0.33𝑀𝑝𝑎 (as before) (𝑣 = 0.36𝑀𝑝𝑎) = (𝑣 , = 0.36𝑀𝑝𝑎) 𝑁𝑜𝑡 𝑂. 𝐾. Since the base is barely passing in punching and failing in transverse shear, the base thickness can be increased to 650mm. Verify Minimum Area of Steel 𝐴 , = 0.078𝑓 / 𝑓 𝑏 d ≥ 0.0013𝑏 𝑑
  • 33. StructuresCentre.xyz 33 𝐴 , = 0.078(20) / 410 × 1000 × 542 ≥ 0.0013 × 1000 × 542 = 876.5𝑚𝑚 < 1340𝑚𝑚 o. k Use 24T16-150 both ways 3.6 Design Summary Figure 7: Slab Reinforcement Summary
  • 34. StructuresCentre.xyz 34 Figure 8: Summary of Reinforcement in Beam C-C Figure 9: Summary of Reinforcement in Beam 2-2
  • 35. StructuresCentre.xyz 35 Figure 10: Summary of Reinforcement in Column C2 Figure 11: Summary of Pad Base to Column C2