SlideShare a Scribd company logo
1 of 17
Photovoltaic Cell
Part-III: PV Array Design &
Cost Estimation
Arpan Deyasi
Dept of ECE, RCCIIT, Kolkata, India
Course: EI605D
4/26/2020 1Arpan Deyasi, EI605D
4/26/2020 Arpan Deyasi, EI605D 2
Major system components of PV array
[i] PV modules
[ii] Solar charge controller
[iii] Inverter
[iv] Battery bank
[v] Auxiliary appliances
4/26/2020 Arpan Deyasi, EI605D 3
PV Modules
Converts sunlight into
DC electrical energy
Temperature, shading
and dust affect the
performance of PV modules
4/26/2020 Arpan Deyasi, EI605D 4
Solar Charge Controller
Regulates electrical parameters
coming from PV panels
Prevents battery from
overcharging, and hence,
increases lifetime of battery
Must be set to correct presets
depending on battery and its
requirements
4/26/2020 Arpan Deyasi, EI605D 5
Inverter
Converts DC signal
into AC signal
Three types of inverters
are used: Off-grid,
Grid-tied, Hybrid
4/26/2020 Arpan Deyasi, EI605D 6
Off-Grid Inverter
Not connected
with the grid
Produces power
independent of
the grid
24 hours supply
Costly to install
Requires more
maintenance
4/26/2020 Arpan Deyasi, EI605D 7
Grid-Tied Inverter
Most common type of inverter
Connected with electrical grid
Allow people to use
both solar energy
and electricity
Less expensive due to no use of battery
Little maintenance required
Will not produce power if
there is no power in grid
4/26/2020 Arpan Deyasi, EI605D 8
Hybrid Inverter
Combination of off-grid
and grid-ties systems
Works as off-grid with
utility back-up power
Works as grid-tied with
extra battery storage
Less expansive than off-grid
Expansive than grid-tied
4/26/2020 Arpan Deyasi, EI605D 9
Battery bank
Store energies for supplying
to electrical appliances
as per requirement
Battery must not be
discharged more than 50%
4/26/2020 Arpan Deyasi, EI605D 10
Complete system
4/26/2020 Arpan Deyasi, EI605D 11
COST ESTIMATION OF A PV SYSTEM
A solar PV system design can be done in following steps:
Load estimation
Estimation of power produced per unit time
Estimation of number of PV panels
Cost estimation of the system
4/26/2020 Arpan Deyasi, EI605D 12
The total energy requirement of the system (total load) i.e
Total connected load to PV panel system
=
No. of units × rating of equipment
COST ESTIMATION OF A PV SYSTEM
Total watt-hours rating of the system
=
Total connected load (watts) × Operating hours
Load estimation
4/26/2020 Arpan Deyasi, EI605D 13
COST ESTIMATION OF A PV SYSTEM
Actual power output of a PV panel
=
Peak power rating × operating factor*
Estimation of power produced per unit time
* ‘operating factor’ is used to estimate the actual output from a PV
module. [The operating factor between 0.60 and 0.90 (implying the
output power is 60 to 80% lower than rated output power) in normal
operating conditions, depending on temperature, dust on module, etc.]
4/26/2020 Arpan Deyasi, EI605D 14
COST ESTIMATION OF A PV SYSTEM
Energy produced by one panel in a day
=
Actual power output × 8 hours/day (peak equivalent)
Estimation of power produced per unit time
* combined efficiency = inverter efficiency × battery efficiency
The power used at the end use is less (due to lower combined
efficiency of the system
=
Actual power output of a panel × combined efficiency*
4/26/2020 Arpan Deyasi, EI605D 15
Number of solar panels required to satisfy given
estimated daily load
=
(Total watt-hour rating (daily load) / (Daily energy
produced by a panel)
COST ESTIMATION OF A PV SYSTEM
Estimation of number of PV panels
4/26/2020 Arpan Deyasi, EI605D 16
COST ESTIMATION OF A PV SYSTEM
A. Cost of arrays = No. of PV modules × Cost/Module
B. Cost of batteries = No. of Batteries × Cost/Module
C. Cost of Inverter = No. of inverters × Cost/Inverter
Total cost of system = A + B + C
Cost estimation of the system
4/26/2020 Arpan Deyasi, EI605D 17
1. Non conventional Energy, A. V. Desai, New Age International
Publishers Ltd.
2. Renewable energy resources and emerging technologies, D.P.
Kothari, Prentice Hall of India Pvt. Ltd.
3. Er. R K Rajput, Non-Conventional Energy Sources and Utilisation
(Energy Engineering), S. Chand Publishing
4. B.H Khan, Non Conventioanl Energy Resources, Tata McGraw-Hill
Education
References

More Related Content

What's hot

Green fuel technologies
Green fuel technologiesGreen fuel technologies
Green fuel technologiesdimensions24
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantShahbaz Makandar A.
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case StudyLeonardo ENERGY
 
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...IRJET Journal
 
Implementation of solar pv battery and diesel generator based electric vehic...
Implementation of solar pv  battery and diesel generator based electric vehic...Implementation of solar pv  battery and diesel generator based electric vehic...
Implementation of solar pv battery and diesel generator based electric vehic...Asoka Technologies
 
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}Must hybrid power generation station {wind turbine(hawt)&solar (pv)}
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}Mohammed Ahmed Ramadan
 
Study of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverterStudy of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverterIAEME Publication
 
Solar and wind power intigration by vishwanath tu rvce.
Solar and wind power intigration by vishwanath tu rvce.Solar and wind power intigration by vishwanath tu rvce.
Solar and wind power intigration by vishwanath tu rvce.Vishwanath Vishwanath
 
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET-  	  Simulation of Solar PV and DG based Hybrid Micro GridIRJET-  	  Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET- Simulation of Solar PV and DG based Hybrid Micro GridIRJET Journal
 
Solar Wind Hybrid Generation System Integration with Grid
Solar Wind Hybrid Generation System Integration with GridSolar Wind Hybrid Generation System Integration with Grid
Solar Wind Hybrid Generation System Integration with Gridijtsrd
 
Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}
 Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)} Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}
Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}Mohammed Ahmed Ramadan
 
A report on Solar Load Calculation
A report on Solar Load CalculationA report on Solar Load Calculation
A report on Solar Load CalculationMilan Ghimire
 
Construction of a Fuel less Generator
Construction of a Fuel less GeneratorConstruction of a Fuel less Generator
Construction of a Fuel less Generatorpaperpublications3
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV systemRajesh Pindoriya
 
Emergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsEmergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsSwarnim Srivastava
 

What's hot (20)

Green fuel technologies
Green fuel technologiesGreen fuel technologies
Green fuel technologies
 
Final presentation
Final  presentationFinal  presentation
Final presentation
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
 
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...
Real Time Monitoring and Simulation Analysis of 30WP off Grid Solar Rooftop P...
 
Pv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar DesignPv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar Design
 
Implementation of solar pv battery and diesel generator based electric vehic...
Implementation of solar pv  battery and diesel generator based electric vehic...Implementation of solar pv  battery and diesel generator based electric vehic...
Implementation of solar pv battery and diesel generator based electric vehic...
 
Solar plant
Solar plantSolar plant
Solar plant
 
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}Must hybrid power generation station {wind turbine(hawt)&solar (pv)}
Must hybrid power generation station {wind turbine(hawt)&solar (pv)}
 
Study of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverterStudy of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverter
 
Solar and wind power intigration by vishwanath tu rvce.
Solar and wind power intigration by vishwanath tu rvce.Solar and wind power intigration by vishwanath tu rvce.
Solar and wind power intigration by vishwanath tu rvce.
 
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET-  	  Simulation of Solar PV and DG based Hybrid Micro GridIRJET-  	  Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
 
Solar Wind Hybrid Generation System Integration with Grid
Solar Wind Hybrid Generation System Integration with GridSolar Wind Hybrid Generation System Integration with Grid
Solar Wind Hybrid Generation System Integration with Grid
 
The way to off grid power
The way to off grid powerThe way to off grid power
The way to off grid power
 
Dssim
DssimDssim
Dssim
 
Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}
 Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)} Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}
Must-hybrid-power-generation-station {wind turbine (hawt)&solar (pv)}
 
A report on Solar Load Calculation
A report on Solar Load CalculationA report on Solar Load Calculation
A report on Solar Load Calculation
 
Construction of a Fuel less Generator
Construction of a Fuel less GeneratorConstruction of a Fuel less Generator
Construction of a Fuel less Generator
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
Emergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systemsEmergence-of-hybrid renewable energy systems
Emergence-of-hybrid renewable energy systems
 

Similar to Photovoltaic cell part iii

Proposal for 1kwp Roof-Top Solar PV Plant
Proposal for 1kwp Roof-Top Solar PV PlantProposal for 1kwp Roof-Top Solar PV Plant
Proposal for 1kwp Roof-Top Solar PV PlantIRJET Journal
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportShrikant Hiremath
 
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptx
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptxFINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptx
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptxMadhiGeddam
 
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...IRJET Journal
 
Design of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV SystemDesign of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV Systemsangeetkhule
 
EFFICACY OF NET METER IN ACE SOLAR POWER PLANT
EFFICACY OF NET METER IN ACE SOLAR POWER PLANTEFFICACY OF NET METER IN ACE SOLAR POWER PLANT
EFFICACY OF NET METER IN ACE SOLAR POWER PLANTIRJET Journal
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportalatop007
 
Presentation On Solar Installation Project
Presentation On Solar Installation ProjectPresentation On Solar Installation Project
Presentation On Solar Installation ProjectDHiraj Bohara
 
IRJET- Planning and Designing of Zero Energy Residential Building
IRJET-  	  Planning and Designing of  Zero Energy Residential BuildingIRJET-  	  Planning and Designing of  Zero Energy Residential Building
IRJET- Planning and Designing of Zero Energy Residential BuildingIRJET Journal
 
Presentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxPresentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxHafizAsimKhayyam
 
solar PV design.pptx
solar PV design.pptxsolar PV design.pptx
solar PV design.pptxUniversity
 
Solar PV Design & Applications
Solar PV  Design & ApplicationsSolar PV  Design & Applications
Solar PV Design & Applicationsprabakaran G
 
IRJET - Hybrid Power Generation and Power Station for Electric Vehicle
IRJET - Hybrid Power Generation and Power Station for Electric VehicleIRJET - Hybrid Power Generation and Power Station for Electric Vehicle
IRJET - Hybrid Power Generation and Power Station for Electric VehicleIRJET Journal
 
4_5958416552171670667.ppt
4_5958416552171670667.ppt4_5958416552171670667.ppt
4_5958416552171670667.ppthussenbelew
 
Photovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportPhotovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportMAYANK ACHARYA
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential BuildingIRJET Journal
 
Modeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-GridModeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-GridIRJET Journal
 

Similar to Photovoltaic cell part iii (20)

Proposal for 1kwp Roof-Top Solar PV Plant
Proposal for 1kwp Roof-Top Solar PV PlantProposal for 1kwp Roof-Top Solar PV Plant
Proposal for 1kwp Roof-Top Solar PV Plant
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design report
 
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptx
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptxFINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptx
FINAL PPT DESIGN OF OFF-GRID PHOTO VOLTAIC SYSTEM (1).pptx
 
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...
IRJET- Performance Evaluation of Stand-Alone and on Grid Photovoltaic System ...
 
Design of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV SystemDesign of Stand-Alone Solar PV System
Design of Stand-Alone Solar PV System
 
Photovoltaic cell part ii
Photovoltaic cell part iiPhotovoltaic cell part ii
Photovoltaic cell part ii
 
EFFICACY OF NET METER IN ACE SOLAR POWER PLANT
EFFICACY OF NET METER IN ACE SOLAR POWER PLANTEFFICACY OF NET METER IN ACE SOLAR POWER PLANT
EFFICACY OF NET METER IN ACE SOLAR POWER PLANT
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
 
Presentation On Solar Installation Project
Presentation On Solar Installation ProjectPresentation On Solar Installation Project
Presentation On Solar Installation Project
 
IRJET- Planning and Designing of Zero Energy Residential Building
IRJET-  	  Planning and Designing of  Zero Energy Residential BuildingIRJET-  	  Planning and Designing of  Zero Energy Residential Building
IRJET- Planning and Designing of Zero Energy Residential Building
 
Solar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'tsSolar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'ts
 
Module 7
Module 7Module 7
Module 7
 
Presentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptxPresentation for Final Year Students about Solar.pptx
Presentation for Final Year Students about Solar.pptx
 
solar PV design.pptx
solar PV design.pptxsolar PV design.pptx
solar PV design.pptx
 
Solar PV Design & Applications
Solar PV  Design & ApplicationsSolar PV  Design & Applications
Solar PV Design & Applications
 
IRJET - Hybrid Power Generation and Power Station for Electric Vehicle
IRJET - Hybrid Power Generation and Power Station for Electric VehicleIRJET - Hybrid Power Generation and Power Station for Electric Vehicle
IRJET - Hybrid Power Generation and Power Station for Electric Vehicle
 
4_5958416552171670667.ppt
4_5958416552171670667.ppt4_5958416552171670667.ppt
4_5958416552171670667.ppt
 
Photovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportPhotovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid support
 
IRJET- Implementing Zero Energy Efficiency in Residential Building
IRJET-  	  Implementing Zero Energy Efficiency in Residential BuildingIRJET-  	  Implementing Zero Energy Efficiency in Residential Building
IRJET- Implementing Zero Energy Efficiency in Residential Building
 
Modeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-GridModeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-Grid
 

More from RCC Institute of Information Technology

More from RCC Institute of Information Technology (20)

Carrier scattering and ballistic transport
Carrier scattering and ballistic transportCarrier scattering and ballistic transport
Carrier scattering and ballistic transport
 
Electromagnetic Wave Propagations
Electromagnetic Wave PropagationsElectromagnetic Wave Propagations
Electromagnetic Wave Propagations
 
Biot-Savart law
Biot-Savart lawBiot-Savart law
Biot-Savart law
 
Ampere's circuital law
Ampere's circuital lawAmpere's circuital law
Ampere's circuital law
 
Magnetic Potentials
Magnetic PotentialsMagnetic Potentials
Magnetic Potentials
 
Reflection and Transmission coefficients in transmission line
Reflection and Transmission coefficients in transmission lineReflection and Transmission coefficients in transmission line
Reflection and Transmission coefficients in transmission line
 
Impedance in transmission line
Impedance in transmission lineImpedance in transmission line
Impedance in transmission line
 
Distortionless Transmission Line
Distortionless Transmission LineDistortionless Transmission Line
Distortionless Transmission Line
 
Quantum Hall Effect
Quantum Hall EffectQuantum Hall Effect
Quantum Hall Effect
 
Telegrapher's Equation
Telegrapher's EquationTelegrapher's Equation
Telegrapher's Equation
 
Dielectrics
DielectricsDielectrics
Dielectrics
 
Capacitor
CapacitorCapacitor
Capacitor
 
Electrical Properties of Dipole
Electrical Properties of DipoleElectrical Properties of Dipole
Electrical Properties of Dipole
 
Application of Gauss' Law
Application of Gauss' LawApplication of Gauss' Law
Application of Gauss' Law
 
Fundamentals of Gauss' Law
Fundamentals of Gauss' LawFundamentals of Gauss' Law
Fundamentals of Gauss' Law
 
Fundamentals of Coulomb's Law
Fundamentals of Coulomb's LawFundamentals of Coulomb's Law
Fundamentals of Coulomb's Law
 
Vector Integration
Vector IntegrationVector Integration
Vector Integration
 
Scalar and vector differentiation
Scalar and vector differentiationScalar and vector differentiation
Scalar and vector differentiation
 
Coordinate transformation
Coordinate transformationCoordinate transformation
Coordinate transformation
 
Moletronics
MoletronicsMoletronics
Moletronics
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 

Photovoltaic cell part iii

  • 1. Photovoltaic Cell Part-III: PV Array Design & Cost Estimation Arpan Deyasi Dept of ECE, RCCIIT, Kolkata, India Course: EI605D 4/26/2020 1Arpan Deyasi, EI605D
  • 2. 4/26/2020 Arpan Deyasi, EI605D 2 Major system components of PV array [i] PV modules [ii] Solar charge controller [iii] Inverter [iv] Battery bank [v] Auxiliary appliances
  • 3. 4/26/2020 Arpan Deyasi, EI605D 3 PV Modules Converts sunlight into DC electrical energy Temperature, shading and dust affect the performance of PV modules
  • 4. 4/26/2020 Arpan Deyasi, EI605D 4 Solar Charge Controller Regulates electrical parameters coming from PV panels Prevents battery from overcharging, and hence, increases lifetime of battery Must be set to correct presets depending on battery and its requirements
  • 5. 4/26/2020 Arpan Deyasi, EI605D 5 Inverter Converts DC signal into AC signal Three types of inverters are used: Off-grid, Grid-tied, Hybrid
  • 6. 4/26/2020 Arpan Deyasi, EI605D 6 Off-Grid Inverter Not connected with the grid Produces power independent of the grid 24 hours supply Costly to install Requires more maintenance
  • 7. 4/26/2020 Arpan Deyasi, EI605D 7 Grid-Tied Inverter Most common type of inverter Connected with electrical grid Allow people to use both solar energy and electricity Less expensive due to no use of battery Little maintenance required Will not produce power if there is no power in grid
  • 8. 4/26/2020 Arpan Deyasi, EI605D 8 Hybrid Inverter Combination of off-grid and grid-ties systems Works as off-grid with utility back-up power Works as grid-tied with extra battery storage Less expansive than off-grid Expansive than grid-tied
  • 9. 4/26/2020 Arpan Deyasi, EI605D 9 Battery bank Store energies for supplying to electrical appliances as per requirement Battery must not be discharged more than 50%
  • 10. 4/26/2020 Arpan Deyasi, EI605D 10 Complete system
  • 11. 4/26/2020 Arpan Deyasi, EI605D 11 COST ESTIMATION OF A PV SYSTEM A solar PV system design can be done in following steps: Load estimation Estimation of power produced per unit time Estimation of number of PV panels Cost estimation of the system
  • 12. 4/26/2020 Arpan Deyasi, EI605D 12 The total energy requirement of the system (total load) i.e Total connected load to PV panel system = No. of units × rating of equipment COST ESTIMATION OF A PV SYSTEM Total watt-hours rating of the system = Total connected load (watts) × Operating hours Load estimation
  • 13. 4/26/2020 Arpan Deyasi, EI605D 13 COST ESTIMATION OF A PV SYSTEM Actual power output of a PV panel = Peak power rating × operating factor* Estimation of power produced per unit time * ‘operating factor’ is used to estimate the actual output from a PV module. [The operating factor between 0.60 and 0.90 (implying the output power is 60 to 80% lower than rated output power) in normal operating conditions, depending on temperature, dust on module, etc.]
  • 14. 4/26/2020 Arpan Deyasi, EI605D 14 COST ESTIMATION OF A PV SYSTEM Energy produced by one panel in a day = Actual power output × 8 hours/day (peak equivalent) Estimation of power produced per unit time * combined efficiency = inverter efficiency × battery efficiency The power used at the end use is less (due to lower combined efficiency of the system = Actual power output of a panel × combined efficiency*
  • 15. 4/26/2020 Arpan Deyasi, EI605D 15 Number of solar panels required to satisfy given estimated daily load = (Total watt-hour rating (daily load) / (Daily energy produced by a panel) COST ESTIMATION OF A PV SYSTEM Estimation of number of PV panels
  • 16. 4/26/2020 Arpan Deyasi, EI605D 16 COST ESTIMATION OF A PV SYSTEM A. Cost of arrays = No. of PV modules × Cost/Module B. Cost of batteries = No. of Batteries × Cost/Module C. Cost of Inverter = No. of inverters × Cost/Inverter Total cost of system = A + B + C Cost estimation of the system
  • 17. 4/26/2020 Arpan Deyasi, EI605D 17 1. Non conventional Energy, A. V. Desai, New Age International Publishers Ltd. 2. Renewable energy resources and emerging technologies, D.P. Kothari, Prentice Hall of India Pvt. Ltd. 3. Er. R K Rajput, Non-Conventional Energy Sources and Utilisation (Energy Engineering), S. Chand Publishing 4. B.H Khan, Non Conventioanl Energy Resources, Tata McGraw-Hill Education References