SlideShare a Scribd company logo
Solutions


Predictive Maintenance Saves
Money Improves Plant Reliability
      ,
A predictive maintenance program started                   Built in 1996, the Cargill Vitamin E Plant   diagnostic data generated by these devices
at the Cargill Vitamin E Plant in Eddyville,            has nearly 1500 HART technology smart           are captured by the AMS Suite: Intelligent
Iowa, has yielded hundreds of thousands of              field devices connected to its distributed      Device Manager software installed nearly
dollars in documented savings since 2001                control system. In addition, digital valve      three years ago. The information obtained
through improved maintenance resulting in               controllers, or smart positioners, are          is integrated into a single database, organ-
decreased process variability and greater               installed on about 350 control valves           ized, processed, and presented on a PC
reliability. Estimated savings through cost             throughout the facility. Massive amounts of     monitor, all without interfering with control
avoidance are even greater. For example,
costly plant shutdowns have probably been
prevented by daily monitoring of 1500
instruments and control valves, and then
scheduling maintenance based on criticali-
ty of devices.
   This is in line with a stated goal of find-
ing cost savings through asset optimization
and predictive maintenance, which were
not previously practiced at the instrument
level in this plant. Prior to 2000, schedule-
based preventive maintenance was sup-
ported by reactive maintenance. We fol-
lowed manufacturers’ recommendations in
caring for their products, and we reacted to
problems as they arose. As long as things
ran smoothly, nothing was done to seek out
potential problems and prevent them from
becoming actual.
   Predictive maintenance is the term given
to the practice of identifying production
equipment needing maintenance attention
before its performance gets to the point that
product quality is reduced or an unplanned
shutdown occurs. Information about the con-
dition of equipment is the key to successful-
ly predicting maintenance requirements in
order to take timely corrective action.
   The information we rely upon principally
comes from smart, microprocessor-based
field instruments that evaluate their own
condition and that of associated equip-
ment in addition to reporting the basic
temperature, pressure, and flow data need-
ed to control production processes. Even
with these advanced devices in place, tech-
nicians formerly had to go into the plant,
locate an instrument, and attach a hand-
held communicator to extract the informa-
tion. The evolution of communications pro-
tocols, such as HART and FOUNDATION
Fieldbus, and asset management software
made it possible for engineers and techni-
cians to communicate with smart field
instruments from one central location.

                  Cargill's Eddyville, Iowa facility.
tation used for process control as well as        Documentation Benefits
                                                          the intelligent device management soft-           NIST-traceable calibration certificates must
                                                          ware. This resource is too valuable to be         be provided as a part of the regulatory doc-
                                                          ignored, which could happen if a specific         umentation in the Vitamin E facility. With
                                                          person does not have this as a full time          our system, a calibration certificate on any
                                                          responsibility with authority to take whatev-     instrument on the control network can be
                                                          er action is necessary to protect the integri-    printed out showing that instrument’s cali-
                                                          ty of the processing system.                      bration history, accuracy, date last tested,
                                                                                                            condition “as found”, condition “as left”, etc.
                                                          Predictive Maintenance                               To calibrate a transmitter, all the data
                                                          Emerson’s Intelligent Device Manager soft-        required is downloaded from the Intelligent
                                                          ware makes predictive maintenance possi-          Device Manager database to a documenting
                                                          ble. Once the process control system is           calibrator, which is taken to where the actu-
                                                          optimized and all the loops are running as        al calibration is done. At the end of the day,
                                                          well as they can possibly run, monitoring of      the results are uploaded to the PC and
                                                          the field instrumentation helps sustain that      archived in the database. Some instruments
Wade Howarth, Automation Manager at the Cargill           level of efficiency. We now catch potential       do not have to be calibrated periodically as
Vitamin E plant in Eddyville, Iowa, has helped his        problems before they can impact quality or        long as we can verify that their calibration
company achieve "hundreds of thousands of dollars in      productivity. A case in point is a recent trav-   parameters are within design specifications.
documented savings" over the last three years by apply-   el deviation alert on a control valve that        The documentation within the instrument
ing a predictive maintenance strategy based on asset
                                                          caused technicians to check out the valve,        database serves as a reliable source for that
management software.
                                                          which seemed from the control room to be          verification, making these histories
system inputs and outputs. Using this tool,               operating properly. They found a plastic air      extremely valuable.
technicians are able to look deeply into the              supply line that was too close to a steam
process in a way never before possible.                   line had melted and collapsed, restricting        Conclusion
From the safety and comfort of the mainte-                the passage of air to the valve actuator. As a    It is difficult to quantify the actual value of
nance shop, they’re able to perform all the               result, the valve was responding very slowly      predictive maintenance in dollars. Savings
functions generally associated with the                   to control signals and introducing a lot of       in some cases, such as preventing the loss
handheld communicator - instrument com-                   variability into the process, but the opera-      of nitrogen, are easily computed. If variabil-
missioning, configuration, and trou-                      tors didn’t know anything was wrong.              ity on a steam loop is decreased, the energy
bleshooting of potential problems. Status                    In another instance, technicians checking      saving can be calculated, but how can you
Alerts inform them if the performance of                  out the report of a “non-responding” instru-      put a value on decreasing loop variability?
specific instruments begins to slip. In addi-             ment found that it had been disconnected          Similarly, it is impossible to assign a dollar
tion, all maintenance activities are automat-             at the termination panel. This “fail-open”        amount to time saved by technicians - often
ically documented.                                        valve was allowing the loss of nitrogen,          because no data is available for compari-
                                                          which went unnoticed by operators for six         son. We are satisfied to say that enough has
Asset Management                                          months. While the process was not affected,       been saved to pay for the software.
To ensure that this software is fully utilized,           fixing the problem prevented the further              A word of caution; do not expect immedi-
we employ an asset manager, whose job it is               loss of nitrogen and reduced the loading on       ate results! It is important for the individu-
to monitor the instrumentation, keep all                  a scrubber by about 20 percent.                   als working with the software to understand
configurations and calibrations current, and                 Many potential problems are simply             it and learn how to recognize potential
maintain the database. Based on informa-                  avoided because the asset manager system-         problem areas. A tool is valuable only if it is
tion received from the field instrumenta-                 atically checks every instrument on the net-      used properly. If a predictive maintenance
tion, the asset manager determines mainte-                work, looking for the warning signs that          program is implemented, an asset manager
nance needs and generates work orders as                  indicate an impending failure. When he            put in charge, and work practices changed
appropriate. He helped establish the pre-                 catches a transmitter before it gets too far      as needed, savings should become appar-
dictive maintenance system and trains                     out of calibration or expires, he is helping to   ent within 12 to 24 months.
other maintenance personnel to use it.                    maintain the reliability of the production            Our work practices have certainly
   He is also responsible for continuously                system. If early action by the asset manager      changed. We have been able to shift our
monitoring the health and status of the 30                avoids a plant shutdown, the savings could        focus to prevent from correct, and the docu-
Critical Control Points identified as essen-              be substantial.                                   mented savings are significant. We intend to
tial to the safety and quality of our product.               Since the predictive maintenance pro-          keep exploiting the predictive maintenance
Monitoring these critical points for baseline             gram began functioning, the reduction in          environment and avoiding unexpected
and calibration certification using NIST-                 work orders has been noteworthy, with             stoppages. The more we can plan and
traceable procedures allowed changing the                 maintenance following a more orderly plan         schedule our work, the more efficient we will
quality control procedure from fully analyti-             and schedule. Previously, a great deal of         be, and that is our ultimate goal.
cal to a process instrumentation-based sys-               time was spent reacting when something
tem. The reduction of in-process testing has              broke. We’re still doing reactive mainte-
saved us enormous amounts of analytical                   nance, but now we’re reacting to predictions
testing time and dollars.                                 based on field-based information and not
   It is essential in any processing plant that           breakdowns. Instead of smoke coming out
                                                                                                            — By Wade Howarth
one individual be designated as asset man-                of a motor housing, we react to an indica-        Automation Manager
ager. That person must be very knowledge-                 tion that there will be smoke unless some-        Cargill Vitamin E Plant
able about the process and the instrumen-                 thing is done to prevent it.                      Eddyville, Iowa


                                      Reprinted with permission from Pharmaceutical Processing May 2004

More Related Content

What's hot

Case study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionCase study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during execution
John Kingsley
 
PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial Control
Emerson Exchange
 
Hsg250 guidance on_permit_to_work_systems
Hsg250 guidance on_permit_to_work_systemsHsg250 guidance on_permit_to_work_systems
Hsg250 guidance on_permit_to_work_systemsMayank Agrawal
 
Q4 Product Safety Demo
Q4 Product Safety DemoQ4 Product Safety Demo
Process and Regulated Processes Software Validation Elements
Process and Regulated Processes Software Validation ElementsProcess and Regulated Processes Software Validation Elements
Process and Regulated Processes Software Validation Elements
Arta Doci
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered Maintenance
Dibyendu De
 
Presentation rmc
Presentation   rmcPresentation   rmc
Presentation rmc
olivda77
 
Computer-System-Validation
Computer-System-ValidationComputer-System-Validation
Computer-System-ValidationHal Plant
 
Aips guide element 6 process safety knowledge rev 2
Aips guide   element 6 process safety knowledge rev 2Aips guide   element 6 process safety knowledge rev 2
Aips guide element 6 process safety knowledge rev 2
bitsgian
 
Addressing control applications using wireless hart devices
Addressing control applications using wireless hart devicesAddressing control applications using wireless hart devices
Addressing control applications using wireless hart devices
Emerson Exchange
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process Safety
Chandrashekhar Kulkarni
 
Rcm
RcmRcm
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
Emerson Exchange
 
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
ASK EHS Engineering & Consultants
 
Gamp Riskbased Approch To Validation
Gamp Riskbased Approch To ValidationGamp Riskbased Approch To Validation
Gamp Riskbased Approch To Validation
Rajendra Sadare
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...
Emerson Exchange
 
Overview on “Computer System Validation” CSV
Overview on  “Computer System Validation” CSVOverview on  “Computer System Validation” CSV
Overview on “Computer System Validation” CSV
Anil Sharma
 
(Modifid)condition m0nitoring of longwall face supportd
(Modifid)condition m0nitoring of longwall face supportd(Modifid)condition m0nitoring of longwall face supportd
(Modifid)condition m0nitoring of longwall face supportd
rockyraj19
 

What's hot (20)

Case study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionCase study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during execution
 
PID Advances in Industrial Control
PID Advances in Industrial ControlPID Advances in Industrial Control
PID Advances in Industrial Control
 
FDA 21 CFR Part 11 and Related Regulations and Guidances
FDA 21 CFR Part 11 and Related Regulations and GuidancesFDA 21 CFR Part 11 and Related Regulations and Guidances
FDA 21 CFR Part 11 and Related Regulations and Guidances
 
Hsg250 guidance on_permit_to_work_systems
Hsg250 guidance on_permit_to_work_systemsHsg250 guidance on_permit_to_work_systems
Hsg250 guidance on_permit_to_work_systems
 
Q4 Product Safety Demo
Q4 Product Safety DemoQ4 Product Safety Demo
Q4 Product Safety Demo
 
Process and Regulated Processes Software Validation Elements
Process and Regulated Processes Software Validation ElementsProcess and Regulated Processes Software Validation Elements
Process and Regulated Processes Software Validation Elements
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered Maintenance
 
Presentation rmc
Presentation   rmcPresentation   rmc
Presentation rmc
 
Computer-System-Validation
Computer-System-ValidationComputer-System-Validation
Computer-System-Validation
 
Aips guide element 6 process safety knowledge rev 2
Aips guide   element 6 process safety knowledge rev 2Aips guide   element 6 process safety knowledge rev 2
Aips guide element 6 process safety knowledge rev 2
 
Addressing control applications using wireless hart devices
Addressing control applications using wireless hart devicesAddressing control applications using wireless hart devices
Addressing control applications using wireless hart devices
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process Safety
 
CS003
CS003CS003
CS003
 
Rcm
RcmRcm
Rcm
 
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
SIS “Final Element” Diagnostics Including The SOV, Using A Digital Valve Cont...
 
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
Permit to Work (PTW) Software: Permit Control, Isolation & Control, Job Hazar...
 
Gamp Riskbased Approch To Validation
Gamp Riskbased Approch To ValidationGamp Riskbased Approch To Validation
Gamp Riskbased Approch To Validation
 
Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...Maximizing the return on your control investment meet the experts sessions pa...
Maximizing the return on your control investment meet the experts sessions pa...
 
Overview on “Computer System Validation” CSV
Overview on  “Computer System Validation” CSVOverview on  “Computer System Validation” CSV
Overview on “Computer System Validation” CSV
 
(Modifid)condition m0nitoring of longwall face supportd
(Modifid)condition m0nitoring of longwall face supportd(Modifid)condition m0nitoring of longwall face supportd
(Modifid)condition m0nitoring of longwall face supportd
 

Viewers also liked

Nine characteristics of a target customer
Nine characteristics of a target customerNine characteristics of a target customer
Nine characteristics of a target customerkhaneducation
 
Q-store_An Mobile Content Store
Q-store_An Mobile Content StoreQ-store_An Mobile Content Store
Q-store_An Mobile Content Store
VO Tu Duc
 
Violence in the workplace
Violence in the workplaceViolence in the workplace
Violence in the workplace
khaneducation
 
Story real 1
Story real 1Story real 1
Story real 1
Sanjidul Wafi
 
Creative Commons for LIS 502
Creative Commons for LIS 502Creative Commons for LIS 502
Creative Commons for LIS 502
Nicole Forsythe
 
La semaine sociale by armtrong - 100613
La semaine sociale by armtrong - 100613La semaine sociale by armtrong - 100613
La semaine sociale by armtrong - 100613
armstrong
 

Viewers also liked (9)

Ritu mishra(cv)
Ritu mishra(cv)Ritu mishra(cv)
Ritu mishra(cv)
 
Nine characteristics of a target customer
Nine characteristics of a target customerNine characteristics of a target customer
Nine characteristics of a target customer
 
Sandandstone
SandandstoneSandandstone
Sandandstone
 
Q-store_An Mobile Content Store
Q-store_An Mobile Content StoreQ-store_An Mobile Content Store
Q-store_An Mobile Content Store
 
Violence in the workplace
Violence in the workplaceViolence in the workplace
Violence in the workplace
 
Story real 1
Story real 1Story real 1
Story real 1
 
Motivation1
Motivation1Motivation1
Motivation1
 
Creative Commons for LIS 502
Creative Commons for LIS 502Creative Commons for LIS 502
Creative Commons for LIS 502
 
La semaine sociale by armtrong - 100613
La semaine sociale by armtrong - 100613La semaine sociale by armtrong - 100613
La semaine sociale by armtrong - 100613
 

Similar to Pharmprocess0405 predmaint

Ischia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company BrochureIschia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company Brochure
Thorne & Derrick International
 
Plant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringPlant Maintenance & Condition Monitoring
Plant Maintenance & Condition Monitoring
Elena Maria Vaccher
 
Testability
TestabilityTestability
MONITORING PPT.pdf
MONITORING PPT.pdfMONITORING PPT.pdf
MONITORING PPT.pdf
EuphoricThoughtTechn
 
Smart Sustainability Suite for Water and Wastewater Treatment plants
Smart Sustainability Suite for Water and Wastewater Treatment plantsSmart Sustainability Suite for Water and Wastewater Treatment plants
Smart Sustainability Suite for Water and Wastewater Treatment plants
A.T.E. Private Limited
 
Additional vibration analysis with accelerometer.pptx
Additional vibration analysis with accelerometer.pptxAdditional vibration analysis with accelerometer.pptx
Additional vibration analysis with accelerometer.pptx
PrakashDuraisamyCIT
 
Fusion of mantenance and control data A need For the process.pdf
Fusion of mantenance and control data A need For the process.pdfFusion of mantenance and control data A need For the process.pdf
Fusion of mantenance and control data A need For the process.pdf
camilo256481
 
Enterprise network management
Enterprise network managementEnterprise network management
Enterprise network management
ManageEngine, Zoho Corporation
 
Dyna Trace Whitepaper Performance
Dyna Trace Whitepaper PerformanceDyna Trace Whitepaper Performance
Dyna Trace Whitepaper Performancegopi1985
 
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
Yokogawa1
 
BIST (Built-in-Self-Test) Features for Electronic Valve Actuators
BIST (Built-in-Self-Test) Features for Electronic Valve ActuatorsBIST (Built-in-Self-Test) Features for Electronic Valve Actuators
BIST (Built-in-Self-Test) Features for Electronic Valve Actuators
Mead O'Brien, Inc.
 
Technology audit
Technology auditTechnology audit
Technology audit
Arish Roy
 
INSIGHT Management System
INSIGHT Management SystemINSIGHT Management System
INSIGHT Management SystemRobert Molnar
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFrederic Baudart, CMRP
 
Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Dean Bishop
 
Power Generation: Combined Cycle
Power Generation: Combined CyclePower Generation: Combined Cycle
Power Generation: Combined Cycle
GE Measurement & Control
 
HUMS-Final-PPT.pptx
HUMS-Final-PPT.pptxHUMS-Final-PPT.pptx
HUMS-Final-PPT.pptx
NithishChandrashekar
 
Effective Plant Management
Effective Plant ManagementEffective Plant Management
Effective Plant Management
A.T.E. Private Limited
 
Integrating IT with HSE
Integrating IT with HSEIntegrating IT with HSE
Integrating IT with HSEMuzahid Khan
 

Similar to Pharmprocess0405 predmaint (20)

Ischia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company BrochureIschia ATEX Inspection - Paperless Efficiency Company Brochure
Ischia ATEX Inspection - Paperless Efficiency Company Brochure
 
Plant Maintenance & Condition Monitoring
Plant Maintenance & Condition MonitoringPlant Maintenance & Condition Monitoring
Plant Maintenance & Condition Monitoring
 
Testability
TestabilityTestability
Testability
 
MONITORING PPT.pdf
MONITORING PPT.pdfMONITORING PPT.pdf
MONITORING PPT.pdf
 
Smart Sustainability Suite for Water and Wastewater Treatment plants
Smart Sustainability Suite for Water and Wastewater Treatment plantsSmart Sustainability Suite for Water and Wastewater Treatment plants
Smart Sustainability Suite for Water and Wastewater Treatment plants
 
Additional vibration analysis with accelerometer.pptx
Additional vibration analysis with accelerometer.pptxAdditional vibration analysis with accelerometer.pptx
Additional vibration analysis with accelerometer.pptx
 
Fusion of mantenance and control data A need For the process.pdf
Fusion of mantenance and control data A need For the process.pdfFusion of mantenance and control data A need For the process.pdf
Fusion of mantenance and control data A need For the process.pdf
 
Enterprise network management
Enterprise network managementEnterprise network management
Enterprise network management
 
Dyna Trace Whitepaper Performance
Dyna Trace Whitepaper PerformanceDyna Trace Whitepaper Performance
Dyna Trace Whitepaper Performance
 
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
Shift team effectiveness: Don't bother if you can't change "shop floor" shift...
 
BIST (Built-in-Self-Test) Features for Electronic Valve Actuators
BIST (Built-in-Self-Test) Features for Electronic Valve ActuatorsBIST (Built-in-Self-Test) Features for Electronic Valve Actuators
BIST (Built-in-Self-Test) Features for Electronic Valve Actuators
 
Technology audit
Technology auditTechnology audit
Technology audit
 
INSIGHT Management System
INSIGHT Management SystemINSIGHT Management System
INSIGHT Management System
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based Maintenance
 
Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)Asset Insight Manager Introduction 2014 (2)
Asset Insight Manager Introduction 2014 (2)
 
Ca rm
Ca rmCa rm
Ca rm
 
Power Generation: Combined Cycle
Power Generation: Combined CyclePower Generation: Combined Cycle
Power Generation: Combined Cycle
 
HUMS-Final-PPT.pptx
HUMS-Final-PPT.pptxHUMS-Final-PPT.pptx
HUMS-Final-PPT.pptx
 
Effective Plant Management
Effective Plant ManagementEffective Plant Management
Effective Plant Management
 
Integrating IT with HSE
Integrating IT with HSEIntegrating IT with HSE
Integrating IT with HSE
 

More from khaneducation

Uco bank poexam,2006reasoningpaper
Uco bank poexam,2006reasoningpaperUco bank poexam,2006reasoningpaper
Uco bank poexam,2006reasoningpaper
khaneducation
 
Uco bank p[1].o.exam2006objectiveenglishpaper
Uco bank p[1].o.exam2006objectiveenglishpaperUco bank p[1].o.exam2006objectiveenglishpaper
Uco bank p[1].o.exam2006objectiveenglishpaper
khaneducation
 
Traditional model limitations
Traditional model limitationsTraditional model limitations
Traditional model limitations
khaneducation
 
Tqm points
Tqm pointsTqm points
Tqm points
khaneducation
 
Time management hs 1
Time management hs 1Time management hs 1
Time management hs 1
khaneducation
 
Three envelopes
Three envelopesThree envelopes
Three envelopes
khaneducation
 
Thoughts
ThoughtsThoughts
Thoughts
khaneducation
 
The top 10 tips for dealing with employee problem behavior
The top 10 tips for dealing with employee problem behavior The top 10 tips for dealing with employee problem behavior
The top 10 tips for dealing with employee problem behavior
khaneducation
 
The law of the seed hs
The law of the seed hsThe law of the seed hs
The law of the seed hs
khaneducation
 
The 7 s formula for sales succes
The 7 s formula for sales succesThe 7 s formula for sales succes
The 7 s formula for sales succes
khaneducation
 
Team leadership do'nt do it
Team leadership do'nt do itTeam leadership do'nt do it
Team leadership do'nt do itkhaneducation
 
Managing the people aspects
Managing the people aspectsManaging the people aspects
Managing the people aspectskhaneducation
 

More from khaneducation (20)

Uco bank poexam,2006reasoningpaper
Uco bank poexam,2006reasoningpaperUco bank poexam,2006reasoningpaper
Uco bank poexam,2006reasoningpaper
 
Uco bank p[1].o.exam2006objectiveenglishpaper
Uco bank p[1].o.exam2006objectiveenglishpaperUco bank p[1].o.exam2006objectiveenglishpaper
Uco bank p[1].o.exam2006objectiveenglishpaper
 
Traditional model limitations
Traditional model limitationsTraditional model limitations
Traditional model limitations
 
Tqm points
Tqm pointsTqm points
Tqm points
 
Time management hs 1
Time management hs 1Time management hs 1
Time management hs 1
 
Three envelopes
Three envelopesThree envelopes
Three envelopes
 
Thoughts
ThoughtsThoughts
Thoughts
 
The top 10 tips for dealing with employee problem behavior
The top 10 tips for dealing with employee problem behavior The top 10 tips for dealing with employee problem behavior
The top 10 tips for dealing with employee problem behavior
 
The law of the seed hs
The law of the seed hsThe law of the seed hs
The law of the seed hs
 
The 7 s formula for sales succes
The 7 s formula for sales succesThe 7 s formula for sales succes
The 7 s formula for sales succes
 
Test
TestTest
Test
 
Teambuilding
TeambuildingTeambuilding
Teambuilding
 
Team leadership do'nt do it
Team leadership do'nt do itTeam leadership do'nt do it
Team leadership do'nt do it
 
Tarun pareek
Tarun pareekTarun pareek
Tarun pareek
 
Servicequality hs
Servicequality hsServicequality hs
Servicequality hs
 
Purva[1]
Purva[1]Purva[1]
Purva[1]
 
Odi i
Odi iOdi i
Odi i
 
Noti ras 08
Noti ras 08Noti ras 08
Noti ras 08
 
Managing the people aspects
Managing the people aspectsManaging the people aspects
Managing the people aspects
 
Love
LoveLove
Love
 

Recently uploaded

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 

Recently uploaded (20)

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 

Pharmprocess0405 predmaint

  • 1. Solutions Predictive Maintenance Saves Money Improves Plant Reliability , A predictive maintenance program started Built in 1996, the Cargill Vitamin E Plant diagnostic data generated by these devices at the Cargill Vitamin E Plant in Eddyville, has nearly 1500 HART technology smart are captured by the AMS Suite: Intelligent Iowa, has yielded hundreds of thousands of field devices connected to its distributed Device Manager software installed nearly dollars in documented savings since 2001 control system. In addition, digital valve three years ago. The information obtained through improved maintenance resulting in controllers, or smart positioners, are is integrated into a single database, organ- decreased process variability and greater installed on about 350 control valves ized, processed, and presented on a PC reliability. Estimated savings through cost throughout the facility. Massive amounts of monitor, all without interfering with control avoidance are even greater. For example, costly plant shutdowns have probably been prevented by daily monitoring of 1500 instruments and control valves, and then scheduling maintenance based on criticali- ty of devices. This is in line with a stated goal of find- ing cost savings through asset optimization and predictive maintenance, which were not previously practiced at the instrument level in this plant. Prior to 2000, schedule- based preventive maintenance was sup- ported by reactive maintenance. We fol- lowed manufacturers’ recommendations in caring for their products, and we reacted to problems as they arose. As long as things ran smoothly, nothing was done to seek out potential problems and prevent them from becoming actual. Predictive maintenance is the term given to the practice of identifying production equipment needing maintenance attention before its performance gets to the point that product quality is reduced or an unplanned shutdown occurs. Information about the con- dition of equipment is the key to successful- ly predicting maintenance requirements in order to take timely corrective action. The information we rely upon principally comes from smart, microprocessor-based field instruments that evaluate their own condition and that of associated equip- ment in addition to reporting the basic temperature, pressure, and flow data need- ed to control production processes. Even with these advanced devices in place, tech- nicians formerly had to go into the plant, locate an instrument, and attach a hand- held communicator to extract the informa- tion. The evolution of communications pro- tocols, such as HART and FOUNDATION Fieldbus, and asset management software made it possible for engineers and techni- cians to communicate with smart field instruments from one central location. Cargill's Eddyville, Iowa facility.
  • 2. tation used for process control as well as Documentation Benefits the intelligent device management soft- NIST-traceable calibration certificates must ware. This resource is too valuable to be be provided as a part of the regulatory doc- ignored, which could happen if a specific umentation in the Vitamin E facility. With person does not have this as a full time our system, a calibration certificate on any responsibility with authority to take whatev- instrument on the control network can be er action is necessary to protect the integri- printed out showing that instrument’s cali- ty of the processing system. bration history, accuracy, date last tested, condition “as found”, condition “as left”, etc. Predictive Maintenance To calibrate a transmitter, all the data Emerson’s Intelligent Device Manager soft- required is downloaded from the Intelligent ware makes predictive maintenance possi- Device Manager database to a documenting ble. Once the process control system is calibrator, which is taken to where the actu- optimized and all the loops are running as al calibration is done. At the end of the day, well as they can possibly run, monitoring of the results are uploaded to the PC and the field instrumentation helps sustain that archived in the database. Some instruments Wade Howarth, Automation Manager at the Cargill level of efficiency. We now catch potential do not have to be calibrated periodically as Vitamin E plant in Eddyville, Iowa, has helped his problems before they can impact quality or long as we can verify that their calibration company achieve "hundreds of thousands of dollars in productivity. A case in point is a recent trav- parameters are within design specifications. documented savings" over the last three years by apply- el deviation alert on a control valve that The documentation within the instrument ing a predictive maintenance strategy based on asset caused technicians to check out the valve, database serves as a reliable source for that management software. which seemed from the control room to be verification, making these histories system inputs and outputs. Using this tool, operating properly. They found a plastic air extremely valuable. technicians are able to look deeply into the supply line that was too close to a steam process in a way never before possible. line had melted and collapsed, restricting Conclusion From the safety and comfort of the mainte- the passage of air to the valve actuator. As a It is difficult to quantify the actual value of nance shop, they’re able to perform all the result, the valve was responding very slowly predictive maintenance in dollars. Savings functions generally associated with the to control signals and introducing a lot of in some cases, such as preventing the loss handheld communicator - instrument com- variability into the process, but the opera- of nitrogen, are easily computed. If variabil- missioning, configuration, and trou- tors didn’t know anything was wrong. ity on a steam loop is decreased, the energy bleshooting of potential problems. Status In another instance, technicians checking saving can be calculated, but how can you Alerts inform them if the performance of out the report of a “non-responding” instru- put a value on decreasing loop variability? specific instruments begins to slip. In addi- ment found that it had been disconnected Similarly, it is impossible to assign a dollar tion, all maintenance activities are automat- at the termination panel. This “fail-open” amount to time saved by technicians - often ically documented. valve was allowing the loss of nitrogen, because no data is available for compari- which went unnoticed by operators for six son. We are satisfied to say that enough has Asset Management months. While the process was not affected, been saved to pay for the software. To ensure that this software is fully utilized, fixing the problem prevented the further A word of caution; do not expect immedi- we employ an asset manager, whose job it is loss of nitrogen and reduced the loading on ate results! It is important for the individu- to monitor the instrumentation, keep all a scrubber by about 20 percent. als working with the software to understand configurations and calibrations current, and Many potential problems are simply it and learn how to recognize potential maintain the database. Based on informa- avoided because the asset manager system- problem areas. A tool is valuable only if it is tion received from the field instrumenta- atically checks every instrument on the net- used properly. If a predictive maintenance tion, the asset manager determines mainte- work, looking for the warning signs that program is implemented, an asset manager nance needs and generates work orders as indicate an impending failure. When he put in charge, and work practices changed appropriate. He helped establish the pre- catches a transmitter before it gets too far as needed, savings should become appar- dictive maintenance system and trains out of calibration or expires, he is helping to ent within 12 to 24 months. other maintenance personnel to use it. maintain the reliability of the production Our work practices have certainly He is also responsible for continuously system. If early action by the asset manager changed. We have been able to shift our monitoring the health and status of the 30 avoids a plant shutdown, the savings could focus to prevent from correct, and the docu- Critical Control Points identified as essen- be substantial. mented savings are significant. We intend to tial to the safety and quality of our product. Since the predictive maintenance pro- keep exploiting the predictive maintenance Monitoring these critical points for baseline gram began functioning, the reduction in environment and avoiding unexpected and calibration certification using NIST- work orders has been noteworthy, with stoppages. The more we can plan and traceable procedures allowed changing the maintenance following a more orderly plan schedule our work, the more efficient we will quality control procedure from fully analyti- and schedule. Previously, a great deal of be, and that is our ultimate goal. cal to a process instrumentation-based sys- time was spent reacting when something tem. The reduction of in-process testing has broke. We’re still doing reactive mainte- saved us enormous amounts of analytical nance, but now we’re reacting to predictions testing time and dollars. based on field-based information and not It is essential in any processing plant that breakdowns. Instead of smoke coming out — By Wade Howarth one individual be designated as asset man- of a motor housing, we react to an indica- Automation Manager ager. That person must be very knowledge- tion that there will be smoke unless some- Cargill Vitamin E Plant able about the process and the instrumen- thing is done to prevent it. Eddyville, Iowa Reprinted with permission from Pharmaceutical Processing May 2004