© 2009 VMware Inc. All rights reserved 
Migration Process Validation 
Process Flowcharts
Participants 
S-2 
Color Key 
All Participants 
Migration PMO 
Migration Team 
BU / Application Owners
Preparation 
S-3 
Conduct planning and outreach to key stakeholders 
Compile inventory details and run book repository 
Process migration readiness checklists 
Initiate scheduling process 
Resolve approval or technical issues 
Compile technical run books 
Test run books 
Resolve issues with run books 
Initiate organizational change control process 
Resolve change control or technical issues 
OK change control process 
Y 
N 
Y 
N 
Y 
N 
Approve checklist
Scheduling 
S-4 
Add migration- ready workloads 
Release to migration team(s) 
Approve schedule 
Resolve scheduling issues 
Release workload to pre-candidate status 
N 
Y 
Y 
N 
Create migration schedule
Migration 
S-5 
Demote workload to pre-candidate status 
Initiate validation process 
Validate workload info 
Validate vSphere 
Validate migration schedule 
Execute migration 
Execute post- migration checklist 
Execute pre- migration checklist 
Resolve issues in window? 
Resolve issues in window? 
Resolve issues in window? 
Y 
Y 
Y 
Y 
Y 
Y 
N 
N 
N 
N 
N 
N
Validate 
S-6 
Issue failback notification to Migration PMO 
Resolve login issue? 
Resolve application issue? 
Conduct UI script validation 
Approve migration 
Conduct regression or load testing 
Resolve testing issues? 
Conduct application validation 
Y 
Y 
Y 
N 
N 
N

P2V migration process

  • 1.
    © 2009 VMwareInc. All rights reserved Migration Process Validation Process Flowcharts
  • 2.
    Participants S-2 ColorKey All Participants Migration PMO Migration Team BU / Application Owners
  • 3.
    Preparation S-3 Conductplanning and outreach to key stakeholders Compile inventory details and run book repository Process migration readiness checklists Initiate scheduling process Resolve approval or technical issues Compile technical run books Test run books Resolve issues with run books Initiate organizational change control process Resolve change control or technical issues OK change control process Y N Y N Y N Approve checklist
  • 4.
    Scheduling S-4 Addmigration- ready workloads Release to migration team(s) Approve schedule Resolve scheduling issues Release workload to pre-candidate status N Y Y N Create migration schedule
  • 5.
    Migration S-5 Demoteworkload to pre-candidate status Initiate validation process Validate workload info Validate vSphere Validate migration schedule Execute migration Execute post- migration checklist Execute pre- migration checklist Resolve issues in window? Resolve issues in window? Resolve issues in window? Y Y Y Y Y Y N N N N N N
  • 6.