SlideShare a Scribd company logo
Validation Exceptions – Managing
life’s little (and big) unexpected events
              (      g)     p
         Brian K. Nunnally, Ph.D.
What is an exception?
                   p

An error or a failure which occurs during
Verification or Validation

William Shakespeare: "It is neither good nor
bad, but thinking makes it so."
Types of Exceptions
     yp          p

Three levels of exceptions:
  Critical
  Non-critical
  N       iti l
  Simple
Simple Exceptions
       p       p

Simple exceptions are documentation or
protocol errors
  These errors are found prior to execution or are
  Th                f    d i t         ti
  “obvious” errors or typos
These e ceptions ha e no impact on the
        exceptions have
validation (e.g. no risk)
Simple Exceptions examples
       p       p          p

Wrong test selected for product
Incorrect specification for product
Loss of power to the equipment being
tested.

Other examples from the participants?
Non-critical Exceptions
                     p

Non-critical
Non critical exceptions are errors in the
protocol or execution of the validation which
have no impact on the validation
  These errors are found during or after execution
  Assessment is needed t d t
  A          ti      d d to determine no i
                                   i      impactt
  Need to document the risk (or lack thereof)
Non-critical Exceptions
    examples
          l
Operator not trained to perform the operation
An interruption in the computer system or
the
th equipment’s performance
        i     t’     f

Other examples from the participants?
Critical Exceptions
                 p

Critical exceptions are errors which have an
impact on the validation
  These errors are found during or after execution
  Th               f     dd i       ft        ti
  Assessment is used to determine impact
  Need to document th risk
  N dt d            t the i k
Critical Exceptions examples
                 p          p

Acceptance criterion failure
An interruption in the computer system or
the
th equipment’s performance
        i     t’     f

Other examples from the participants?
Basic Exception Process Flow
          p

                SME involvement throughout is
                critical
                You cannot document enough,
                even if all of it does not make it
                into the final event write-up
                CAPA may not be needed for
                simple events, but consider if
                there are many of them or the
                same ones repeatedly
General Process Considerations

Commence exception resolution process as soon
as event is observed
Involve SMEs/QA throughout process as
appropriate
  Get agreement on next steps and/or results
        g                      p
  Prior to execution, or after the completion
  Including all elements of the process
Immediately notify the relevant SME/QA if there is
any potential Product/Material impact
Conduct a risk assessment to determine impact
and actions
What is the risk and impact of
    the exception?
Event severity x Testing Stage = Impact
Event Severity:
  What kind of event is it? How was the event
  caused?
Testing Stage:
  Where are we in the validation/verification
  process? Installation? Performance
  Qualification?
Event Types
            yp
Typographical errors
  These errors are found prior to execution or are “obvious” errors or
  typos
External Issues
  Failures caused by factors external to the process or system under
  test
Execution Errors
  Failures to follow instructions within the Test Document or
  referenced procedures.
Document Generation Errors
  Incorrect detail in procedures, acceptance criteria or referenced
  documentation
Acceptance Criteria Failures
  Pre-defined acceptance criteria have not been achieved.
Testing Stage
          g    g

New system installation and the exception
does not impact the validation intent
New system i t ll ti and th exception
N       t     installation d the      ti
does impact the validation intent
New or Existing system qualification
Process Validation
Re-qualification
Should testing stop?
                 g    p

Depends on the impact score
Depends on consultation with SMEs and QA
Are you willing to live with a failure?
Will it open more q
         p         questions than it solves?

Note: It does not depend on the timeline!
Exception example #1
         p         p

An acceptance criterion was failed
                            failed.
  However, the acceptance criterion was poorly set
  (
  (limited knowledge was available to set the acceptance
                  g                               p
  criterion).
What level of exception is this?
What do you do?
Exception example #2
         p         p

The acceptance criterion was passed but the
                               passed,
result was right at the limit.
  Assay variability is high for the test.
Is this an exception? Why or why not?
What do you do?
Exception example #3
         p         p

During validation of the cleaning process the
                                  process,
Operator executing the protocol failed to sample
the correct locations.
Is this an exception? Why or why not?
What do you do?
Preventing Exceptions
The key to preventing
    exceptions
         ti
Understanding and reducing variation
                              variation.
Systems thinking (managing the flow through the
entire process as an entity)
                     entity).
Types of Variation (Including
    Sampling,
    Sampling Analytical and Production)

Variation in Quality Characteristic (specific activity
                                              activity,
potency, pH, temperature…etc.
Process variation Variation in the way our
         variation.
processes behave and are managed or controlled.
Variation in volume flowing through a process.
Why focus on variability?
      y                    y
Reduced variation in Quality Characteristics
reduces rejects, rework and deviations. It
provides high First Pass Yields.
Reduced variation in Volume (smoother flow)
increases output capacity and reduces capital
requirements.
requirements
Reduced variation in Volume (smoother flow)
decreases cycle time and Work-In-Progress.
            y                         g
Which one will be more likely to
                                    fail an acceptance criterion?

                         Day shift                                                                        Following night shift
                  2600
                  2400
                  2200
1-Point Average




                  2000
                  1800
                  1600
                  1400
                  1200
                  1000
                    50


                          70


                               90


                                       0


                                              0


                                                     0


                                                            0


                                                                   0


                                                                          0


                                                                                 0


                                                                                        0


                                                                                               0


                                                                                                      0


                                                                                                             0


                                                                                                                    0


                                                                                                                           0


                                                                                                                                  0


                                                                                                                                         0


                                                                                                                                                0


                                                                                                                                                       0


                                                                                                                                                              0


                                                                                                                                                                     0


                                                                                                                                                                            0
                                    11


                                           13


                                                  15


                                                         17


                                                                19


                                                                       21


                                                                              23


                                                                                     25


                                                                                            27


                                                                                                   29


                                                                                                          31


                                                                                                                 33


                                                                                                                        35


                                                                                                                               37


                                                                                                                                      39


                                                                                                                                             41


                                                                                                                                                    43


                                                                                                                                                           45


                                                                                                                                                                  47


                                                                                                                                                                         49
More examples…
          p
Potency
      y




pH
Correlation?

                                      2
                                                    Before Project
  27                                 R = 0.2594

  25

  23

  21

  19

  17

  15
   3000   4000   5000   6000   7000          8000




  29                             2
                                R = 0.9107
                                                    After Project
  27

  25

  23

  21

  19

  17

  15
   3000   4000   5000   6000   7000          8000
What should you do?
                       y

                   CRITICAL ERRORS PER WORKER PER WEEK

                                  WEEK
       1   2   3   4    5     6     7    8     9     10   11    12     TOTAL


Mary   0   0   0   0    0     0     0    0     0     0    0      0       0
Joe    0   0   0   0    0     0     0    0     0     0    0      0       0
Eva    1   0   0   2    0     0     3    0     0     1    0      0       7
Fred   0   0   0   1    0     0     2    0     0     0    0      0       3
Jim    0   0   0   0    0     0     0    0     0     0    0      0       0
Ed     0   0   0   0    0     2     0    0     0     0    0      0       2
Kate   0   0   0   0    0     0     0    0     0     0    0      0       0
Carl   0   0   0   1    0     0     0    0     0     0    0      0       1
                                                               TOTAL    13
The lesson from Tribus
Bring a team together to focus on ensuring the aim
is clear to all participants
Focus on systems to reduce and remove possibility
for errors
Improve systems as a way to prevent human error.
Be very careful when assigning blame to human
error or to a specific p
                p       person
Expectations on Exceptions
Three keys to exceptions
           y         p

Document
Document
Document!
Keep it simple!
       p       p

Document the standard questions:
  Who
  What
  Wh t
  When
  Why
  Where
  How
Other requirements
            q
Root Cause Determination
  If root cause is unknown, a study should be
  co duc ed
  conducted
Impact Determination
  How severe is the exception?
  What is the impact to intent?
Corrective Action Determination
  How will this be prevented in routine use?
Re Testing Re execution
Re-Testing / Re-execution
  Is it necessary? Why or why not?
More exceptions examples…
Exception example #4
         p         p

During the annual re qualification / re-verification of
                   re-qualification re verification
the performance of an autoclave which has been
used for manufacturing of p
                      g product, the
                                   ,
thermocouples did not achieve the required
temperature.
Is this an exception? Why or why not?
What do you do?
Exception example #5
         p         p

During the verification of the installation of Vessel
which has not been used to manufacture product,
p
power was lost during testing of the agitator.
                      g       g          g
Is this an exception? Why or why not?
What do you do?
Exception example #6
         p         p

During the re validation / re verification of Cleaning
            re-validation re-verification
validation of a process which has NOT been used
to manufacture product, some samples were
                  p      ,            p
accidentally not taken.
Is this an exception? Why or why not?
                p          y       y
What do you do?
Exception example #7
         p         p

During the execution of an alarm check
(operational verification) for a system not used to
manufacture product, the test document had the
              p        ,
incorrect sequence of events.
Is this an exception? Why or why not?
               p            y      y
What do you do?

More Related Content

Viewers also liked

Planificacion de la unidad
Planificacion de la unidad Planificacion de la unidad
Planificacion de la unidad
Elizabeth Carhuamaca
 
A WrightWay Venture
A WrightWay VentureA WrightWay Venture
A WrightWay Venture
Darrell Wright
 
Wrightwayventure more ns
Wrightwayventure more nsWrightwayventure more ns
Wrightwayventure more ns
Darrell Wright
 
CC Portfolio-small
CC Portfolio-smallCC Portfolio-small
CC Portfolio-smallJoey Lam
 
RETURNING STUDENTS SUPPORT GROUP-RSSG
RETURNING STUDENTS SUPPORT GROUP-RSSGRETURNING STUDENTS SUPPORT GROUP-RSSG
RETURNING STUDENTS SUPPORT GROUP-RSSG
Darrell Wright
 
Notification Tactics for Improved Notification Tactics For Improved Field Act...
Notification Tactics for Improved Notification Tactics For Improved Field Act...Notification Tactics for Improved Notification Tactics For Improved Field Act...
Notification Tactics for Improved Notification Tactics For Improved Field Act...
Institute of Validation Technology
 
CC Portfolio-small
CC Portfolio-smallCC Portfolio-small
CC Portfolio-smallJoey Lam
 
Statistical Tools for the Quality Control Laboratory and Validation Studies
Statistical Tools for the Quality Control Laboratory and Validation StudiesStatistical Tools for the Quality Control Laboratory and Validation Studies
Statistical Tools for the Quality Control Laboratory and Validation Studies
Institute of Validation Technology
 
Task 1 facebook brief final (4)
Task 1 facebook brief final (4)Task 1 facebook brief final (4)
Task 1 facebook brief final (4)Anneka Shah
 
Management Strategies to Facilitate Continual Quality Improvement
Management Strategies to Facilitate Continual Quality ImprovementManagement Strategies to Facilitate Continual Quality Improvement
Management Strategies to Facilitate Continual Quality Improvement
Institute of Validation Technology
 

Viewers also liked (13)

Competència lectora 1
Competència  lectora 1Competència  lectora 1
Competència lectora 1
 
Planificacion de la unidad
Planificacion de la unidad Planificacion de la unidad
Planificacion de la unidad
 
Change control and configuration
Change control and configurationChange control and configuration
Change control and configuration
 
Affects of
Affects ofAffects of
Affects of
 
A WrightWay Venture
A WrightWay VentureA WrightWay Venture
A WrightWay Venture
 
Wrightwayventure more ns
Wrightwayventure more nsWrightwayventure more ns
Wrightwayventure more ns
 
CC Portfolio-small
CC Portfolio-smallCC Portfolio-small
CC Portfolio-small
 
RETURNING STUDENTS SUPPORT GROUP-RSSG
RETURNING STUDENTS SUPPORT GROUP-RSSGRETURNING STUDENTS SUPPORT GROUP-RSSG
RETURNING STUDENTS SUPPORT GROUP-RSSG
 
Notification Tactics for Improved Notification Tactics For Improved Field Act...
Notification Tactics for Improved Notification Tactics For Improved Field Act...Notification Tactics for Improved Notification Tactics For Improved Field Act...
Notification Tactics for Improved Notification Tactics For Improved Field Act...
 
CC Portfolio-small
CC Portfolio-smallCC Portfolio-small
CC Portfolio-small
 
Statistical Tools for the Quality Control Laboratory and Validation Studies
Statistical Tools for the Quality Control Laboratory and Validation StudiesStatistical Tools for the Quality Control Laboratory and Validation Studies
Statistical Tools for the Quality Control Laboratory and Validation Studies
 
Task 1 facebook brief final (4)
Task 1 facebook brief final (4)Task 1 facebook brief final (4)
Task 1 facebook brief final (4)
 
Management Strategies to Facilitate Continual Quality Improvement
Management Strategies to Facilitate Continual Quality ImprovementManagement Strategies to Facilitate Continual Quality Improvement
Management Strategies to Facilitate Continual Quality Improvement
 

Similar to Determine Exceptions to Validation

Site Speed Tuneup: Putting Your Code On A Diet
Site Speed Tuneup: Putting Your Code On A DietSite Speed Tuneup: Putting Your Code On A Diet
Site Speed Tuneup: Putting Your Code On A Diet
mm_merchant
 
Copy Of Cost Of Goods Formula 3 Year
Copy Of Cost Of Goods Formula 3 YearCopy Of Cost Of Goods Formula 3 Year
Copy Of Cost Of Goods Formula 3 YearRatElegance
 
Forward backward roll and g scale
Forward  backward roll and g scaleForward  backward roll and g scale
Forward backward roll and g scaleLeo Crossfield
 
QA overview
QA overviewQA overview
QA overview
Rasha Bazbaz
 
White.p.johnson.k
White.p.johnson.kWhite.p.johnson.k
White.p.johnson.kNASAPMC
 
Presenting objective and subjective uncertainty information for spatial syste...
Presenting objective and subjective uncertainty information for spatial syste...Presenting objective and subjective uncertainty information for spatial syste...
Presenting objective and subjective uncertainty information for spatial syste...
University of Adelaide
 
3. project charter, check sheet, pareto analysis & c&e diagram & matrix
3. project charter, check sheet, pareto analysis & c&e diagram & matrix3. project charter, check sheet, pareto analysis & c&e diagram & matrix
3. project charter, check sheet, pareto analysis & c&e diagram & matrix
Hakeem-Ur- Rehman
 
A Retrospective Look at A Retrospective Look at Classifier System ResearchCl...
A Retrospective Look at  A Retrospective Look at  Classifier System ResearchCl...A Retrospective Look at  A Retrospective Look at  Classifier System ResearchCl...
A Retrospective Look at A Retrospective Look at Classifier System ResearchCl...
Xavier Llorà
 
Application delivery 2 0
Application delivery 2 0Application delivery 2 0
Application delivery 2 0Interop
 
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
David Parsons
 
Introduction to Performance Testing Part 1
Introduction to Performance Testing Part 1Introduction to Performance Testing Part 1
Introduction to Performance Testing Part 1
C.T.Co
 
Medical Device Integration - Alliance Of Chicago UIC Team Analysis
Medical Device Integration - Alliance Of Chicago UIC Team AnalysisMedical Device Integration - Alliance Of Chicago UIC Team Analysis
Medical Device Integration - Alliance Of Chicago UIC Team Analysis
Dinesh Jayapathy
 
"Make problems visible and users happy" by Catherine Chabiron
"Make problems visible and users happy" by Catherine Chabiron"Make problems visible and users happy" by Catherine Chabiron
"Make problems visible and users happy" by Catherine Chabiron
Operae Partners
 
Basic right hand backward roll
Basic right hand backward rollBasic right hand backward roll
Basic right hand backward rollLeo Crossfield
 
Education 3.0: Better Learning Through Technology
Education 3.0:  Better Learning Through TechnologyEducation 3.0:  Better Learning Through Technology
Education 3.0: Better Learning Through Technology
Centre for Distance Education
 
Basic right hand forward roll
Basic right hand forward rollBasic right hand forward roll
Basic right hand forward rollLeo Crossfield
 

Similar to Determine Exceptions to Validation (20)

Risk log
Risk logRisk log
Risk log
 
Risk Log
Risk LogRisk Log
Risk Log
 
Cashflow statement form
Cashflow statement formCashflow statement form
Cashflow statement form
 
Site Speed Tuneup: Putting Your Code On A Diet
Site Speed Tuneup: Putting Your Code On A DietSite Speed Tuneup: Putting Your Code On A Diet
Site Speed Tuneup: Putting Your Code On A Diet
 
Copy Of Cost Of Goods Formula 3 Year
Copy Of Cost Of Goods Formula 3 YearCopy Of Cost Of Goods Formula 3 Year
Copy Of Cost Of Goods Formula 3 Year
 
Forward backward roll and g scale
Forward  backward roll and g scaleForward  backward roll and g scale
Forward backward roll and g scale
 
Empty template
Empty templateEmpty template
Empty template
 
QA overview
QA overviewQA overview
QA overview
 
White.p.johnson.k
White.p.johnson.kWhite.p.johnson.k
White.p.johnson.k
 
Presenting objective and subjective uncertainty information for spatial syste...
Presenting objective and subjective uncertainty information for spatial syste...Presenting objective and subjective uncertainty information for spatial syste...
Presenting objective and subjective uncertainty information for spatial syste...
 
3. project charter, check sheet, pareto analysis & c&e diagram & matrix
3. project charter, check sheet, pareto analysis & c&e diagram & matrix3. project charter, check sheet, pareto analysis & c&e diagram & matrix
3. project charter, check sheet, pareto analysis & c&e diagram & matrix
 
A Retrospective Look at A Retrospective Look at Classifier System ResearchCl...
A Retrospective Look at  A Retrospective Look at  Classifier System ResearchCl...A Retrospective Look at  A Retrospective Look at  Classifier System ResearchCl...
A Retrospective Look at A Retrospective Look at Classifier System ResearchCl...
 
Application delivery 2 0
Application delivery 2 0Application delivery 2 0
Application delivery 2 0
 
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
The Impact of Methods and Techniques on Outcomes from Agile Software Developm...
 
Introduction to Performance Testing Part 1
Introduction to Performance Testing Part 1Introduction to Performance Testing Part 1
Introduction to Performance Testing Part 1
 
Medical Device Integration - Alliance Of Chicago UIC Team Analysis
Medical Device Integration - Alliance Of Chicago UIC Team AnalysisMedical Device Integration - Alliance Of Chicago UIC Team Analysis
Medical Device Integration - Alliance Of Chicago UIC Team Analysis
 
"Make problems visible and users happy" by Catherine Chabiron
"Make problems visible and users happy" by Catherine Chabiron"Make problems visible and users happy" by Catherine Chabiron
"Make problems visible and users happy" by Catherine Chabiron
 
Basic right hand backward roll
Basic right hand backward rollBasic right hand backward roll
Basic right hand backward roll
 
Education 3.0: Better Learning Through Technology
Education 3.0:  Better Learning Through TechnologyEducation 3.0:  Better Learning Through Technology
Education 3.0: Better Learning Through Technology
 
Basic right hand forward roll
Basic right hand forward rollBasic right hand forward roll
Basic right hand forward roll
 

More from Institute of Validation Technology

Incorporate Domestic and International Regulations for Effective GMP Auditing
Incorporate Domestic and International Regulations for Effective GMP AuditingIncorporate Domestic and International Regulations for Effective GMP Auditing
Incorporate Domestic and International Regulations for Effective GMP Auditing
Institute of Validation Technology
 
Lifecycle Approach to Cleaning Validation
Lifecycle Approach to Cleaning ValidationLifecycle Approach to Cleaning Validation
Lifecycle Approach to Cleaning Validation
Institute of Validation Technology
 
Computer System Validation Then and Now — Learning Management in the Cloud
Computer System Validation Then and Now — Learning Management in the CloudComputer System Validation Then and Now — Learning Management in the Cloud
Computer System Validation Then and Now — Learning Management in the Cloud
Institute of Validation Technology
 
Applying QbD to Biotech Process Validation
Applying QbD to Biotech Process ValidationApplying QbD to Biotech Process Validation
Applying QbD to Biotech Process Validation
Institute of Validation Technology
 
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
Institute of Validation Technology
 
Effective Use of Environmental Monitoring Data Trending
Effective Use of Environmental Monitoring Data TrendingEffective Use of Environmental Monitoring Data Trending
Effective Use of Environmental Monitoring Data Trending
Institute of Validation Technology
 
Mock Inspection Case Studies
Mock Inspection Case StudiesMock Inspection Case Studies
Mock Inspection Case Studies
Institute of Validation Technology
 
Validation Master Plan
Validation Master PlanValidation Master Plan
Validation Master Plan
Institute of Validation Technology
 
Designing Stability Studies for Early Stages of Pharmaceutical Development
Designing Stability Studies for Early Stages of Pharmaceutical DevelopmentDesigning Stability Studies for Early Stages of Pharmaceutical Development
Designing Stability Studies for Early Stages of Pharmaceutical Development
Institute of Validation Technology
 
Conduct a Gap Analysis of a Validation Programme
Conduct a Gap Analysis of a Validation ProgrammeConduct a Gap Analysis of a Validation Programme
Conduct a Gap Analysis of a Validation Programme
Institute of Validation Technology
 
FDA Inspection
FDA InspectionFDA Inspection
Incorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation PlanIncorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation Plan
Institute of Validation Technology
 
Compliance by Design and Compliance Master Plan
Compliance by Design and Compliance Master PlanCompliance by Design and Compliance Master Plan
Compliance by Design and Compliance Master Plan
Institute of Validation Technology
 
Introduction to Statistical Applications for Process Validation
Introduction to Statistical Applications for Process ValidationIntroduction to Statistical Applications for Process Validation
Introduction to Statistical Applications for Process Validation
Institute of Validation Technology
 
Risk-Based Approaches in GMP’s Project Life Cycles
Risk-Based Approaches in GMP’s Project Life CyclesRisk-Based Approaches in GMP’s Project Life Cycles
Risk-Based Approaches in GMP’s Project Life Cycles
Institute of Validation Technology
 
GMP Systems Integration–Combine Results and Utilize as a Compliance Tool
GMP Systems Integration–Combine Results and Utilize as a Compliance ToolGMP Systems Integration–Combine Results and Utilize as a Compliance Tool
GMP Systems Integration–Combine Results and Utilize as a Compliance Tool
Institute of Validation Technology
 
A Lifecycle Approach to Process Validation
A Lifecycle Approach to Process ValidationA Lifecycle Approach to Process Validation
A Lifecycle Approach to Process Validation
Institute of Validation Technology
 
Setting Biological Process Specifications
Setting Biological Process SpecificationsSetting Biological Process Specifications
Setting Biological Process Specifications
Institute of Validation Technology
 
Handling deviations & unexpected results during method validation
Handling deviations & unexpected results during method validationHandling deviations & unexpected results during method validation
Handling deviations & unexpected results during method validation
Institute of Validation Technology
 

More from Institute of Validation Technology (20)

Incorporate Domestic and International Regulations for Effective GMP Auditing
Incorporate Domestic and International Regulations for Effective GMP AuditingIncorporate Domestic and International Regulations for Effective GMP Auditing
Incorporate Domestic and International Regulations for Effective GMP Auditing
 
Lifecycle Approach to Cleaning Validation
Lifecycle Approach to Cleaning ValidationLifecycle Approach to Cleaning Validation
Lifecycle Approach to Cleaning Validation
 
Computer System Validation Then and Now — Learning Management in the Cloud
Computer System Validation Then and Now — Learning Management in the CloudComputer System Validation Then and Now — Learning Management in the Cloud
Computer System Validation Then and Now — Learning Management in the Cloud
 
Applying QbD to Biotech Process Validation
Applying QbD to Biotech Process ValidationApplying QbD to Biotech Process Validation
Applying QbD to Biotech Process Validation
 
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
Understand the Evolving Regulations for Aseptic Cleaning and Environmental Mo...
 
Effective Use of Environmental Monitoring Data Trending
Effective Use of Environmental Monitoring Data TrendingEffective Use of Environmental Monitoring Data Trending
Effective Use of Environmental Monitoring Data Trending
 
Mock Inspection Case Studies
Mock Inspection Case StudiesMock Inspection Case Studies
Mock Inspection Case Studies
 
Validation Master Plan
Validation Master PlanValidation Master Plan
Validation Master Plan
 
Designing Stability Studies for Early Stages of Pharmaceutical Development
Designing Stability Studies for Early Stages of Pharmaceutical DevelopmentDesigning Stability Studies for Early Stages of Pharmaceutical Development
Designing Stability Studies for Early Stages of Pharmaceutical Development
 
Conduct a Gap Analysis of a Validation Programme
Conduct a Gap Analysis of a Validation ProgrammeConduct a Gap Analysis of a Validation Programme
Conduct a Gap Analysis of a Validation Programme
 
FDA Inspection
FDA InspectionFDA Inspection
FDA Inspection
 
Incorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation PlanIncorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation Plan
 
Compliance by Design and Compliance Master Plan
Compliance by Design and Compliance Master PlanCompliance by Design and Compliance Master Plan
Compliance by Design and Compliance Master Plan
 
Introduction to Statistical Applications for Process Validation
Introduction to Statistical Applications for Process ValidationIntroduction to Statistical Applications for Process Validation
Introduction to Statistical Applications for Process Validation
 
Risk-Based Approaches in GMP’s Project Life Cycles
Risk-Based Approaches in GMP’s Project Life CyclesRisk-Based Approaches in GMP’s Project Life Cycles
Risk-Based Approaches in GMP’s Project Life Cycles
 
GMP Systems Integration–Combine Results and Utilize as a Compliance Tool
GMP Systems Integration–Combine Results and Utilize as a Compliance ToolGMP Systems Integration–Combine Results and Utilize as a Compliance Tool
GMP Systems Integration–Combine Results and Utilize as a Compliance Tool
 
A Lifecycle Approach to Process Validation
A Lifecycle Approach to Process ValidationA Lifecycle Approach to Process Validation
A Lifecycle Approach to Process Validation
 
Setting Biological Process Specifications
Setting Biological Process SpecificationsSetting Biological Process Specifications
Setting Biological Process Specifications
 
Method Transfer Crossing Multiple Borders
Method Transfer Crossing Multiple BordersMethod Transfer Crossing Multiple Borders
Method Transfer Crossing Multiple Borders
 
Handling deviations & unexpected results during method validation
Handling deviations & unexpected results during method validationHandling deviations & unexpected results during method validation
Handling deviations & unexpected results during method validation
 

Recently uploaded

Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptxMaxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
Dr. Rabia Inam Gandapore
 
BRACHYTHERAPY OVERVIEW AND APPLICATORS
BRACHYTHERAPY OVERVIEW  AND  APPLICATORSBRACHYTHERAPY OVERVIEW  AND  APPLICATORS
BRACHYTHERAPY OVERVIEW AND APPLICATORS
Krishan Murari
 
Physiology of Special Chemical Sensation of Taste
Physiology of Special Chemical Sensation of TastePhysiology of Special Chemical Sensation of Taste
Physiology of Special Chemical Sensation of Taste
MedicoseAcademics
 
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
i3 Health
 
Antiulcer drugs Advance Pharmacology .pptx
Antiulcer drugs Advance Pharmacology .pptxAntiulcer drugs Advance Pharmacology .pptx
Antiulcer drugs Advance Pharmacology .pptx
Rohit chaurpagar
 
Non-respiratory Functions of the Lungs.pdf
Non-respiratory Functions of the Lungs.pdfNon-respiratory Functions of the Lungs.pdf
Non-respiratory Functions of the Lungs.pdf
MedicoseAcademics
 
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
kevinkariuki227
 
basicmodesofventilation2022-220313203758.pdf
basicmodesofventilation2022-220313203758.pdfbasicmodesofventilation2022-220313203758.pdf
basicmodesofventilation2022-220313203758.pdf
aljamhori teaching hospital
 
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.GawadHemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
NephroTube - Dr.Gawad
 
heat stroke and heat exhaustion in children
heat stroke and heat exhaustion in childrenheat stroke and heat exhaustion in children
heat stroke and heat exhaustion in children
SumeraAhmad5
 
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model SafeSurat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
Savita Shen $i11
 
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness JourneyTom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
greendigital
 
Ocular injury ppt Upendra pal optometrist upums saifai etawah
Ocular injury  ppt  Upendra pal  optometrist upums saifai etawahOcular injury  ppt  Upendra pal  optometrist upums saifai etawah
Ocular injury ppt Upendra pal optometrist upums saifai etawah
pal078100
 
Prix Galien International 2024 Forum Program
Prix Galien International 2024 Forum ProgramPrix Galien International 2024 Forum Program
Prix Galien International 2024 Forum Program
Levi Shapiro
 
24 Upakrama.pptx class ppt useful in all
24 Upakrama.pptx class ppt useful in all24 Upakrama.pptx class ppt useful in all
24 Upakrama.pptx class ppt useful in all
DrSathishMS1
 
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdfAlcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
Dr Jeenal Mistry
 
Triangles of Neck and Clinical Correlation by Dr. RIG.pptx
Triangles of Neck and Clinical Correlation by Dr. RIG.pptxTriangles of Neck and Clinical Correlation by Dr. RIG.pptx
Triangles of Neck and Clinical Correlation by Dr. RIG.pptx
Dr. Rabia Inam Gandapore
 
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in StockFactory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
rebeccabio
 
micro teaching on communication m.sc nursing.pdf
micro teaching on communication m.sc nursing.pdfmicro teaching on communication m.sc nursing.pdf
micro teaching on communication m.sc nursing.pdf
Anurag Sharma
 
KDIGO 2024 guidelines for diabetologists
KDIGO 2024 guidelines for diabetologistsKDIGO 2024 guidelines for diabetologists
KDIGO 2024 guidelines for diabetologists
د.محمود نجيب
 

Recently uploaded (20)

Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptxMaxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
Maxilla, Mandible & Hyoid Bone & Clinical Correlations by Dr. RIG.pptx
 
BRACHYTHERAPY OVERVIEW AND APPLICATORS
BRACHYTHERAPY OVERVIEW  AND  APPLICATORSBRACHYTHERAPY OVERVIEW  AND  APPLICATORS
BRACHYTHERAPY OVERVIEW AND APPLICATORS
 
Physiology of Special Chemical Sensation of Taste
Physiology of Special Chemical Sensation of TastePhysiology of Special Chemical Sensation of Taste
Physiology of Special Chemical Sensation of Taste
 
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
New Directions in Targeted Therapeutic Approaches for Older Adults With Mantl...
 
Antiulcer drugs Advance Pharmacology .pptx
Antiulcer drugs Advance Pharmacology .pptxAntiulcer drugs Advance Pharmacology .pptx
Antiulcer drugs Advance Pharmacology .pptx
 
Non-respiratory Functions of the Lungs.pdf
Non-respiratory Functions of the Lungs.pdfNon-respiratory Functions of the Lungs.pdf
Non-respiratory Functions of the Lungs.pdf
 
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
TEST BANK for Operations Management, 14th Edition by William J. Stevenson, Ve...
 
basicmodesofventilation2022-220313203758.pdf
basicmodesofventilation2022-220313203758.pdfbasicmodesofventilation2022-220313203758.pdf
basicmodesofventilation2022-220313203758.pdf
 
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.GawadHemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
Hemodialysis: Chapter 3, Dialysis Water Unit - Dr.Gawad
 
heat stroke and heat exhaustion in children
heat stroke and heat exhaustion in childrenheat stroke and heat exhaustion in children
heat stroke and heat exhaustion in children
 
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model SafeSurat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
Surat @ℂall @Girls ꧁❤8527049040❤꧂@ℂall @Girls Service Vip Top Model Safe
 
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness JourneyTom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
Tom Selleck Health: A Comprehensive Look at the Iconic Actor’s Wellness Journey
 
Ocular injury ppt Upendra pal optometrist upums saifai etawah
Ocular injury  ppt  Upendra pal  optometrist upums saifai etawahOcular injury  ppt  Upendra pal  optometrist upums saifai etawah
Ocular injury ppt Upendra pal optometrist upums saifai etawah
 
Prix Galien International 2024 Forum Program
Prix Galien International 2024 Forum ProgramPrix Galien International 2024 Forum Program
Prix Galien International 2024 Forum Program
 
24 Upakrama.pptx class ppt useful in all
24 Upakrama.pptx class ppt useful in all24 Upakrama.pptx class ppt useful in all
24 Upakrama.pptx class ppt useful in all
 
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdfAlcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
Alcohol_Dr. Jeenal Mistry MD Pharmacology.pdf
 
Triangles of Neck and Clinical Correlation by Dr. RIG.pptx
Triangles of Neck and Clinical Correlation by Dr. RIG.pptxTriangles of Neck and Clinical Correlation by Dr. RIG.pptx
Triangles of Neck and Clinical Correlation by Dr. RIG.pptx
 
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in StockFactory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
Factory Supply Best Quality Pmk Oil CAS 28578–16–7 PMK Powder in Stock
 
micro teaching on communication m.sc nursing.pdf
micro teaching on communication m.sc nursing.pdfmicro teaching on communication m.sc nursing.pdf
micro teaching on communication m.sc nursing.pdf
 
KDIGO 2024 guidelines for diabetologists
KDIGO 2024 guidelines for diabetologistsKDIGO 2024 guidelines for diabetologists
KDIGO 2024 guidelines for diabetologists
 

Determine Exceptions to Validation

  • 1. Validation Exceptions – Managing life’s little (and big) unexpected events ( g) p Brian K. Nunnally, Ph.D.
  • 2. What is an exception? p An error or a failure which occurs during Verification or Validation William Shakespeare: "It is neither good nor bad, but thinking makes it so."
  • 3. Types of Exceptions yp p Three levels of exceptions: Critical Non-critical N iti l Simple
  • 4. Simple Exceptions p p Simple exceptions are documentation or protocol errors These errors are found prior to execution or are Th f d i t ti “obvious” errors or typos These e ceptions ha e no impact on the exceptions have validation (e.g. no risk)
  • 5. Simple Exceptions examples p p p Wrong test selected for product Incorrect specification for product Loss of power to the equipment being tested. Other examples from the participants?
  • 6. Non-critical Exceptions p Non-critical Non critical exceptions are errors in the protocol or execution of the validation which have no impact on the validation These errors are found during or after execution Assessment is needed t d t A ti d d to determine no i i impactt Need to document the risk (or lack thereof)
  • 7. Non-critical Exceptions examples l Operator not trained to perform the operation An interruption in the computer system or the th equipment’s performance i t’ f Other examples from the participants?
  • 8. Critical Exceptions p Critical exceptions are errors which have an impact on the validation These errors are found during or after execution Th f dd i ft ti Assessment is used to determine impact Need to document th risk N dt d t the i k
  • 9. Critical Exceptions examples p p Acceptance criterion failure An interruption in the computer system or the th equipment’s performance i t’ f Other examples from the participants?
  • 10. Basic Exception Process Flow p SME involvement throughout is critical You cannot document enough, even if all of it does not make it into the final event write-up CAPA may not be needed for simple events, but consider if there are many of them or the same ones repeatedly
  • 11. General Process Considerations Commence exception resolution process as soon as event is observed Involve SMEs/QA throughout process as appropriate Get agreement on next steps and/or results g p Prior to execution, or after the completion Including all elements of the process Immediately notify the relevant SME/QA if there is any potential Product/Material impact Conduct a risk assessment to determine impact and actions
  • 12. What is the risk and impact of the exception? Event severity x Testing Stage = Impact Event Severity: What kind of event is it? How was the event caused? Testing Stage: Where are we in the validation/verification process? Installation? Performance Qualification?
  • 13. Event Types yp Typographical errors These errors are found prior to execution or are “obvious” errors or typos External Issues Failures caused by factors external to the process or system under test Execution Errors Failures to follow instructions within the Test Document or referenced procedures. Document Generation Errors Incorrect detail in procedures, acceptance criteria or referenced documentation Acceptance Criteria Failures Pre-defined acceptance criteria have not been achieved.
  • 14. Testing Stage g g New system installation and the exception does not impact the validation intent New system i t ll ti and th exception N t installation d the ti does impact the validation intent New or Existing system qualification Process Validation Re-qualification
  • 15. Should testing stop? g p Depends on the impact score Depends on consultation with SMEs and QA Are you willing to live with a failure? Will it open more q p questions than it solves? Note: It does not depend on the timeline!
  • 16. Exception example #1 p p An acceptance criterion was failed failed. However, the acceptance criterion was poorly set ( (limited knowledge was available to set the acceptance g p criterion). What level of exception is this? What do you do?
  • 17. Exception example #2 p p The acceptance criterion was passed but the passed, result was right at the limit. Assay variability is high for the test. Is this an exception? Why or why not? What do you do?
  • 18. Exception example #3 p p During validation of the cleaning process the process, Operator executing the protocol failed to sample the correct locations. Is this an exception? Why or why not? What do you do?
  • 20. The key to preventing exceptions ti Understanding and reducing variation variation. Systems thinking (managing the flow through the entire process as an entity) entity).
  • 21. Types of Variation (Including Sampling, Sampling Analytical and Production) Variation in Quality Characteristic (specific activity activity, potency, pH, temperature…etc. Process variation Variation in the way our variation. processes behave and are managed or controlled. Variation in volume flowing through a process.
  • 22. Why focus on variability? y y Reduced variation in Quality Characteristics reduces rejects, rework and deviations. It provides high First Pass Yields. Reduced variation in Volume (smoother flow) increases output capacity and reduces capital requirements. requirements Reduced variation in Volume (smoother flow) decreases cycle time and Work-In-Progress. y g
  • 23. Which one will be more likely to fail an acceptance criterion? Day shift Following night shift 2600 2400 2200 1-Point Average 2000 1800 1600 1400 1200 1000 50 70 90 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
  • 24. More examples… p Potency y pH
  • 25. Correlation? 2 Before Project 27 R = 0.2594 25 23 21 19 17 15 3000 4000 5000 6000 7000 8000 29 2 R = 0.9107 After Project 27 25 23 21 19 17 15 3000 4000 5000 6000 7000 8000
  • 26. What should you do? y CRITICAL ERRORS PER WORKER PER WEEK WEEK 1 2 3 4 5 6 7 8 9 10 11 12 TOTAL Mary 0 0 0 0 0 0 0 0 0 0 0 0 0 Joe 0 0 0 0 0 0 0 0 0 0 0 0 0 Eva 1 0 0 2 0 0 3 0 0 1 0 0 7 Fred 0 0 0 1 0 0 2 0 0 0 0 0 3 Jim 0 0 0 0 0 0 0 0 0 0 0 0 0 Ed 0 0 0 0 0 2 0 0 0 0 0 0 2 Kate 0 0 0 0 0 0 0 0 0 0 0 0 0 Carl 0 0 0 1 0 0 0 0 0 0 0 0 1 TOTAL 13
  • 27. The lesson from Tribus Bring a team together to focus on ensuring the aim is clear to all participants Focus on systems to reduce and remove possibility for errors Improve systems as a way to prevent human error. Be very careful when assigning blame to human error or to a specific p p person
  • 29. Three keys to exceptions y p Document Document Document!
  • 30. Keep it simple! p p Document the standard questions: Who What Wh t When Why Where How
  • 31. Other requirements q Root Cause Determination If root cause is unknown, a study should be co duc ed conducted Impact Determination How severe is the exception? What is the impact to intent? Corrective Action Determination How will this be prevented in routine use? Re Testing Re execution Re-Testing / Re-execution Is it necessary? Why or why not?
  • 33. Exception example #4 p p During the annual re qualification / re-verification of re-qualification re verification the performance of an autoclave which has been used for manufacturing of p g product, the , thermocouples did not achieve the required temperature. Is this an exception? Why or why not? What do you do?
  • 34. Exception example #5 p p During the verification of the installation of Vessel which has not been used to manufacture product, p power was lost during testing of the agitator. g g g Is this an exception? Why or why not? What do you do?
  • 35. Exception example #6 p p During the re validation / re verification of Cleaning re-validation re-verification validation of a process which has NOT been used to manufacture product, some samples were p , p accidentally not taken. Is this an exception? Why or why not? p y y What do you do?
  • 36. Exception example #7 p p During the execution of an alarm check (operational verification) for a system not used to manufacture product, the test document had the p , incorrect sequence of events. Is this an exception? Why or why not? p y y What do you do?