The importance of 3 Core NEC Time Clauses when submitting a programme
 27th January 2022
 SiteAdmin
 Cost Control Management, NEC, Project Planning
https://www.big-dada.co.uk/2022/01/27/3-core-nec-time-
clauses/?MC=1&FirstName=Andrew&LastName=Ng&Email=Andrewngadelaide@outlook.com&ut
m_source=Fellow+Conference+Exhibitors+List&utm_campaign=d18258ff08-
Fellow_Conference_Exhibitors_List_19042022&utm_medium=email&utm_term=0_aa06dea8f4-
d18258ff08-443207378&ct=t(Fellow_Conference_Exhibitors_List_19042022)
Via our chat function we received an interesting question…
Morning , just a quick query under NEC4 when you submit a clause 32 programme do you use the
clause 31 or last accepted clause 32 as Baseline. Many planners are using different methods I use
the accepted Clause 31 and add CE’s to accepted Clause 32 and then add to Clause 31 is this
correct ?
Regards Mr J [real name redacted]
Unfortunately Mr J (real name anonymised) was in a rush and did not provide their e-mail address for
us to post an answer, but we still thought it was a cracking question…
So we thought we would do it here!
Programme Acceptance
It is important to first explain the key differences in Programme Acceptance between NEC3 and NEC4
Contract Types.
As covered in our past article, within NEC3 in the absence of a Project Manager’s response, the contract
provided that the programme was simply ‘not accepted’, putting all the risk ontothe Contractor in
allowing the Project Managerto to withhold 25% of the price of work done to date if the
Contractor does not provide a programme in accordance with Cl.31.
Within NEC4 the position is improved and the contract includes a provision whereby in the absence of a
Project Manager’s response to the submitted programme within two weeks, the Contractor can
serve notice of a further week. After this, if there is still no response then the contractor’s
programme is ‘deemed accepted’ under the contract.
Preparation of Compensation Events Costs
Another key difference between NEC3 and NEC4, is that the newer version allows recovery of costs
even where the Project Manager proposes an instruction which is not accepted. The past exclusion
for the cost of preparing compensation events has been deleted and is now recoverable underall
Options. There is now the introduction of new CE clause 60(1)(20) (“where the PM notifies the
Contractor that a quotation for a proposed instruction is not accepted”).
3 Core Time Clauses
Within NEC Professional Services Contract, there are 3 core Schedule related clauses within the
Professional Services Contract which we shall use to answer the original question posed:
 Clause 30 Starting, Completion and Key Dates
 Clause 31 The programme
 Clause 32 Revising the programme
To answer Mr J’s question the two key concept to understand is that there is a “Planned Completion
Date” and the ‘Completion Date’.
Under Clause 31.2 the programme issued for acceptance will show the “Planned Completion Date”,
which will be driven by the any event that affects the criticalpath.
The other is the “Completion Date“, which can only be changed ‘in accordance with the Contract. This
reflecting that the contractoris contractually obliged to achieve ‘Completion’ on or before the
‘Completion Date’, under clause 30.1.
So under Clause 14.1 “acceptance of a programme” cannot and will not change that responsibility of
meeting the ‘Completion Date’ in Clause 11.2(3), that being ‘Completion Date’ in the contract data.
NEC contract documentation does set out when the date can be changed (eg., 44.2, 36.3 and 65.4),
however acceptance of the programme, does not by itself change the “Completion Date”.
As covered under clause 31.3 the Project Manager has to accept or not accept a programme within two
weeks of submission. Any non-acceptance having to be communicated backto the Contractor in
sufficient detail to Contactor tocorrect the submission (via a separate response under Clause 13.7).
The four reasons reasons for non-acceptance are:
1. Contractor’s plans shown are not practicable
2. It does not show the information which this contract requires
3. It does not represent the Contractors plans realistically
4. It does not comply with the Scope
As such the programme should show the starting date, access dates, key dates and completion dates
when the Contractor plans to meet each condition stated for the Key Dates. It should also show the
Planned dates when the contractor plans to complete work required to allow others to carry out
works. It also needs to show the dates when the Contractor needs access to the site if this is later
than their planned access dates. Acceptances, plant, materials and other things to be provided by
the Client should also be identified. Finally for each operation, a statement of how the Contractor
plans to do the work should be given.
If not met, the Project Manager can respond under Clause 13.7 on the reason for non-acceptance. If the
Project Manager chooses not to accept for any other reason, then by default that would be a
compensation event under 60.1(9).
In revising the programme under Clause 32.1, to update the accepted programme under Clause 31, Mr
J should remember…that the acceptance of a programme does not change the responsibility to
‘Provide the Works’ in clause 11.2(13).
However it should be borne in mind that Clause (14.1) states that acceptance of any communication
does not transfer liability away from the Contractor to comply with their obligations underthe
contract. And so, the “Completion Date” as defined by 11.2 remains. That said, acceptance of the
programme is still significant as it recognises that the Client has given affirmation that from their
perspective that the programme is realistic, practicable and shows the information that the
contract requires.
The “Accepted Programme” as laid out under Clause 31, and defined under 11.2, is thereby the
reference point for all compensation events and change that occur. If there is no recent “Accepted
Programme” then commercial resolution is made the more difficult as reference will have to be
made to the last “Accepted Programme”, which will inevitably differ from the latest “Revised
Programme” under 32.1.
The workflow below can be used to explain a scenario how the under 32.1 the Contractor is responsible
for correcting all Work which the Client has found to be defective or which fails to conform to the
Contract Documents whetherobserved before or after Substantial Completion.
NECProject ManagementProject Portfolio Management (PPM)
Share This

More Related Content

Similar to The importance of 3 Core NEC Time Clauses when submitting a programme.docx

Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
Kegler Brown Hill + Ritter
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
Pang Khai Shuen
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
tdartnell
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
seenyeeyong
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
MahSobeh
 
Cm mitemrate ver270206
Cm mitemrate ver270206Cm mitemrate ver270206
Cm mitemrate ver270206
prabandhakavi venkataraju
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
Cerasela Angelescu
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
Shze Hwa Lee
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
fareezsham
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
Cl compilation
Cl compilationCl compilation
Cl compilation
Jessyca Than
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
lucaschinsheng
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 

Similar to The importance of 3 Core NEC Time Clauses when submitting a programme.docx (20)

Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
Cm mitemrate ver270206
Cm mitemrate ver270206Cm mitemrate ver270206
Cm mitemrate ver270206
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 

More from My own

eBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdfeBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdf
My own
 
Procurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docxProcurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docx
My own
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
My own
 
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdfENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
My own
 
Andrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateAndrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateMy own
 
2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing
My own
 
2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 TrainingMy own
 
Cipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassCipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassMy own
 
2010 Ipma Pe Training Beijing
2010 Ipma  Pe Training Beijing2010 Ipma  Pe Training Beijing
2010 Ipma Pe Training BeijingMy own
 
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
My own
 
Countries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management ExcellenceCountries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management Excellence
My own
 
Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012
My own
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
My own
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article One
My own
 
Skills & Experience Compared with Planning Fraternity
Skills & Experience Compared with Planning FraternitySkills & Experience Compared with Planning Fraternity
Skills & Experience Compared with Planning Fraternity
My own
 
Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09
My own
 
Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515
My own
 

More from My own (17)

eBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdfeBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdf
 
Procurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docxProcurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docx
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdfENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
 
Andrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateAndrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor Certificate
 
2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing
 
2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training
 
Cipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassCipa 2009 Contract Master Class
Cipa 2009 Contract Master Class
 
2010 Ipma Pe Training Beijing
2010 Ipma  Pe Training Beijing2010 Ipma  Pe Training Beijing
2010 Ipma Pe Training Beijing
 
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
 
Countries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management ExcellenceCountries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management Excellence
 
Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article One
 
Skills & Experience Compared with Planning Fraternity
Skills & Experience Compared with Planning FraternitySkills & Experience Compared with Planning Fraternity
Skills & Experience Compared with Planning Fraternity
 
Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09
 
Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515
 

Recently uploaded

SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
Lubi Valves
 
Beckhoff Programmable Logic Control Overview Presentation
Beckhoff Programmable Logic Control Overview PresentationBeckhoff Programmable Logic Control Overview Presentation
Beckhoff Programmable Logic Control Overview Presentation
VanTuDuong1
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
uqyfuc
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
wafawafa52
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
Kamal Acharya
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
PreethaV16
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
snaprevwdev
 
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTERUNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
vmspraneeth
 
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
Kuvempu University
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
GOKULKANNANMMECLECTC
 

Recently uploaded (20)

SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
 
Beckhoff Programmable Logic Control Overview Presentation
Beckhoff Programmable Logic Control Overview PresentationBeckhoff Programmable Logic Control Overview Presentation
Beckhoff Programmable Logic Control Overview Presentation
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
Ericsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.pptEricsson LTE Throughput Troubleshooting Techniques.ppt
Ericsson LTE Throughput Troubleshooting Techniques.ppt
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
FULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back EndFULL STACK PROGRAMMING - Both Front End and Back End
FULL STACK PROGRAMMING - Both Front End and Back End
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
 
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTERUNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
UNIT-III- DATA CONVERTERS ANALOG TO DIGITAL CONVERTER
 
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
ELS: 2.4.1 POWER ELECTRONICS Course objectives: This course will enable stude...
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
 

The importance of 3 Core NEC Time Clauses when submitting a programme.docx

  • 1. The importance of 3 Core NEC Time Clauses when submitting a programme  27th January 2022  SiteAdmin  Cost Control Management, NEC, Project Planning https://www.big-dada.co.uk/2022/01/27/3-core-nec-time- clauses/?MC=1&FirstName=Andrew&LastName=Ng&Email=Andrewngadelaide@outlook.com&ut m_source=Fellow+Conference+Exhibitors+List&utm_campaign=d18258ff08- Fellow_Conference_Exhibitors_List_19042022&utm_medium=email&utm_term=0_aa06dea8f4- d18258ff08-443207378&ct=t(Fellow_Conference_Exhibitors_List_19042022) Via our chat function we received an interesting question… Morning , just a quick query under NEC4 when you submit a clause 32 programme do you use the clause 31 or last accepted clause 32 as Baseline. Many planners are using different methods I use the accepted Clause 31 and add CE’s to accepted Clause 32 and then add to Clause 31 is this correct ? Regards Mr J [real name redacted] Unfortunately Mr J (real name anonymised) was in a rush and did not provide their e-mail address for us to post an answer, but we still thought it was a cracking question… So we thought we would do it here! Programme Acceptance It is important to first explain the key differences in Programme Acceptance between NEC3 and NEC4 Contract Types. As covered in our past article, within NEC3 in the absence of a Project Manager’s response, the contract provided that the programme was simply ‘not accepted’, putting all the risk ontothe Contractor in allowing the Project Managerto to withhold 25% of the price of work done to date if the Contractor does not provide a programme in accordance with Cl.31. Within NEC4 the position is improved and the contract includes a provision whereby in the absence of a Project Manager’s response to the submitted programme within two weeks, the Contractor can serve notice of a further week. After this, if there is still no response then the contractor’s programme is ‘deemed accepted’ under the contract. Preparation of Compensation Events Costs Another key difference between NEC3 and NEC4, is that the newer version allows recovery of costs even where the Project Manager proposes an instruction which is not accepted. The past exclusion for the cost of preparing compensation events has been deleted and is now recoverable underall Options. There is now the introduction of new CE clause 60(1)(20) (“where the PM notifies the Contractor that a quotation for a proposed instruction is not accepted”). 3 Core Time Clauses Within NEC Professional Services Contract, there are 3 core Schedule related clauses within the Professional Services Contract which we shall use to answer the original question posed:  Clause 30 Starting, Completion and Key Dates  Clause 31 The programme  Clause 32 Revising the programme To answer Mr J’s question the two key concept to understand is that there is a “Planned Completion Date” and the ‘Completion Date’. Under Clause 31.2 the programme issued for acceptance will show the “Planned Completion Date”, which will be driven by the any event that affects the criticalpath. The other is the “Completion Date“, which can only be changed ‘in accordance with the Contract. This reflecting that the contractoris contractually obliged to achieve ‘Completion’ on or before the ‘Completion Date’, under clause 30.1.
  • 2. So under Clause 14.1 “acceptance of a programme” cannot and will not change that responsibility of meeting the ‘Completion Date’ in Clause 11.2(3), that being ‘Completion Date’ in the contract data. NEC contract documentation does set out when the date can be changed (eg., 44.2, 36.3 and 65.4), however acceptance of the programme, does not by itself change the “Completion Date”.
  • 3. As covered under clause 31.3 the Project Manager has to accept or not accept a programme within two weeks of submission. Any non-acceptance having to be communicated backto the Contractor in sufficient detail to Contactor tocorrect the submission (via a separate response under Clause 13.7). The four reasons reasons for non-acceptance are: 1. Contractor’s plans shown are not practicable 2. It does not show the information which this contract requires 3. It does not represent the Contractors plans realistically 4. It does not comply with the Scope As such the programme should show the starting date, access dates, key dates and completion dates when the Contractor plans to meet each condition stated for the Key Dates. It should also show the Planned dates when the contractor plans to complete work required to allow others to carry out
  • 4. works. It also needs to show the dates when the Contractor needs access to the site if this is later than their planned access dates. Acceptances, plant, materials and other things to be provided by the Client should also be identified. Finally for each operation, a statement of how the Contractor plans to do the work should be given. If not met, the Project Manager can respond under Clause 13.7 on the reason for non-acceptance. If the Project Manager chooses not to accept for any other reason, then by default that would be a compensation event under 60.1(9). In revising the programme under Clause 32.1, to update the accepted programme under Clause 31, Mr J should remember…that the acceptance of a programme does not change the responsibility to ‘Provide the Works’ in clause 11.2(13). However it should be borne in mind that Clause (14.1) states that acceptance of any communication does not transfer liability away from the Contractor to comply with their obligations underthe contract. And so, the “Completion Date” as defined by 11.2 remains. That said, acceptance of the programme is still significant as it recognises that the Client has given affirmation that from their perspective that the programme is realistic, practicable and shows the information that the contract requires. The “Accepted Programme” as laid out under Clause 31, and defined under 11.2, is thereby the reference point for all compensation events and change that occur. If there is no recent “Accepted Programme” then commercial resolution is made the more difficult as reference will have to be made to the last “Accepted Programme”, which will inevitably differ from the latest “Revised Programme” under 32.1. The workflow below can be used to explain a scenario how the under 32.1 the Contractor is responsible for correcting all Work which the Client has found to be defective or which fails to conform to the Contract Documents whetherobserved before or after Substantial Completion.
  • 5. NECProject ManagementProject Portfolio Management (PPM) Share This