Programme Acceptance It is important to first explain the key differences in Programme Acceptance between NEC3 and NEC4 Contract Types. As covered in our past article, within NEC3 in the absence of a Project Manager’s response, the contract provided that the programme was simply ‘not accepted’, putting all the risk onto the Contractor in allowing the Project Manager to to withhold 25% of the price of work done to date if the Contractor does not provide a programme in accordance with Cl.31. Within NEC4 the position is improved and the contract includes a provision whereby in the absence of a Project Manager’s response to the submitted programme within two weeks, the Contractor can serve notice of a further week. After this, if there is still no response then the contractor’s programme is ‘deemed accepted’ under the contract.