The evaluation assessed the groundwater contamination plume at Site 26 and evaluated alternatives to the existing pump and treat system. Phase I found the plume was stable with natural attenuation occurring. Phase II tested enhanced natural attenuation through nutrient injection, which reduced VOC levels below cleanup standards in test areas. The evaluation recommends monitored natural attenuation to complete the groundwater remediation as plumes are stable with no rebound and risks are low.