During the construction of a power plant, various water qualities and quantities were needed for commissioning processes like hydraulic tests and steam blowing. To address this, Degremont Industry provided flexible mobile water treatment plants to produce the water needed. This allowed the client to progress with commissioning as scheduled even while permanent water treatment plants were still being completed, saving potential six-month delay in starting electricity production. The mobile plants produced water for various commissioning phases and inflows and qualities from 10 to 150 cubic meters per hour. This solution allowed the client to finish overall commissioning on time despite delays to permanent plants.