Wall-to-floor ratios
• Go to unit 9 and download the wall-to-floor ratio ppt

• Read through the ppt and complete the task for building B

• Name your file wall to floor ratio and Submit your ppt to
  moodle unit 9 under the link “Submit wall floor ration ppt
  here”
Wall-to-floor ratios
The following activity asks you to look at the wall-to-floor ratios and form a
financial comparison between two designs. The smaller the ratio the more floor
space is created which in financial terms for a client would be rentable areas.

Building A
Plan area = 35m x 35m
Height = 35m
Storey height = 3.5m



Building B
Plan area = 22.5m x 22.5m

Height               = 24.75m
Storey height = 2.75m

If the floor budget construction cost is £50/m2 and the wall area construction cost £25/m2,
calculate the wall to floor ratio for both buildings.
• Find : The Wall-to-floor ratios



•   Worked example Building A
•   Number of floors = 35/3.5 = 10 floors
•   Total floor area = 10 x 35 x 35 = 12,250m2
•   Total wall area = 35 x 4 x 35 = 4900m2
•   Total wall cost   = 4900 x £25/m2 = £122,500
•   Total floor cost = 12,250 x £50/ m2 = £612,500
•   Wall/floor ratio = £122,500 = 0.20


•   Building B
•   Number of floors = 24.75/2.75 = ? floors
•   Total floor area = 9 x 22.5 x 22.5 = ? m2
•   Total wall area  = 24.75 x 4 x 22.5 = ? m2
•   Total wall cost   = 1114 x £25/m2 = ? £
•   Total floor cost  = 4556 x £50/m2 = ? £
•   Wall/floor ratio  = ? £ = What amount a decinal

More Related Content

What's hot

Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)
Kai Yun Pang
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
Timun Loh
 
Methods of Documentation and Measured Drawing
Methods of Documentation and Measured DrawingMethods of Documentation and Measured Drawing
Methods of Documentation and Measured Drawing
kimberleyee95
 
Contract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeContract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction Practice
Zhao Wei Kim
 
Modular construction
Modular constructionModular construction
Modular construction
Kiran Gill
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
ahmong4
 
Building services report
Building services report Building services report
Building services report Soh Shing
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
xingxin_GOh
 
Fire regulations for buildings
Fire regulations for buildingsFire regulations for buildings
Fire regulations for buildings
Deepak KUMAR
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
Construction Tech. and Mgmt., VNIT Nagpur
 
Nbc ppt
Nbc pptNbc ppt
Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Khyati Tewari
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
Aditya Sanyal
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdf
Joshua Lee
 
Occupancy Load
Occupancy Load Occupancy Load
Occupancy Load
Tala Jazzy
 
Building Economics (Group Assignment) - Preliminary Cost Appraisal
Building Economics (Group Assignment) - Preliminary Cost AppraisalBuilding Economics (Group Assignment) - Preliminary Cost Appraisal
Building Economics (Group Assignment) - Preliminary Cost Appraisal
Yee Len Wan
 

What's hot (20)

Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Methods of Documentation and Measured Drawing
Methods of Documentation and Measured DrawingMethods of Documentation and Measured Drawing
Methods of Documentation and Measured Drawing
 
Contract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeContract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction Practice
 
Modular construction
Modular constructionModular construction
Modular construction
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
 
Building services report
Building services report Building services report
Building services report
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Fire regulations for buildings
Fire regulations for buildingsFire regulations for buildings
Fire regulations for buildings
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Nbc ppt
Nbc pptNbc ppt
Nbc ppt
 
Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdf
 
Occupancy Load
Occupancy Load Occupancy Load
Occupancy Load
 
Building Economics (Group Assignment) - Preliminary Cost Appraisal
Building Economics (Group Assignment) - Preliminary Cost AppraisalBuilding Economics (Group Assignment) - Preliminary Cost Appraisal
Building Economics (Group Assignment) - Preliminary Cost Appraisal
 
Introduction To Building Services
Introduction To Building ServicesIntroduction To Building Services
Introduction To Building Services
 
Lift Design
Lift  DesignLift  Design
Lift Design
 

More from Daniel Ross

Bayes theorem explained
Bayes theorem explainedBayes theorem explained
Bayes theorem explainedDaniel Ross
 
Calculus concrete and decibel calculation
Calculus concrete and decibel calculationCalculus concrete and decibel calculation
Calculus concrete and decibel calculation
Daniel Ross
 
Thermal studies U Vlaues
Thermal studies U VlauesThermal studies U Vlaues
Thermal studies U Vlaues
Daniel Ross
 
Finding an unknown side of a right angled triangle 2012
Finding an unknown side of a right angled triangle 2012Finding an unknown side of a right angled triangle 2012
Finding an unknown side of a right angled triangle 2012
Daniel Ross
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
Daniel Ross
 
acoustics Sound Fluids Darcy formula
acoustics Sound Fluids Darcy formulaacoustics Sound Fluids Darcy formula
acoustics Sound Fluids Darcy formula
Daniel Ross
 
Baye’s Theorem
Baye’s TheoremBaye’s Theorem
Baye’s Theorem
Daniel Ross
 
Trapezium Rule Practical Substructure And Excavation Presentation1
Trapezium Rule Practical  Substructure And Excavation Presentation1Trapezium Rule Practical  Substructure And Excavation Presentation1
Trapezium Rule Practical Substructure And Excavation Presentation1
Daniel Ross
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
Daniel Ross
 
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula MathsConstruction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Daniel Ross
 
Simultaneous Equations Practical Construction
Simultaneous Equations Practical ConstructionSimultaneous Equations Practical Construction
Simultaneous Equations Practical Construction
Daniel Ross
 

More from Daniel Ross (11)

Bayes theorem explained
Bayes theorem explainedBayes theorem explained
Bayes theorem explained
 
Calculus concrete and decibel calculation
Calculus concrete and decibel calculationCalculus concrete and decibel calculation
Calculus concrete and decibel calculation
 
Thermal studies U Vlaues
Thermal studies U VlauesThermal studies U Vlaues
Thermal studies U Vlaues
 
Finding an unknown side of a right angled triangle 2012
Finding an unknown side of a right angled triangle 2012Finding an unknown side of a right angled triangle 2012
Finding an unknown side of a right angled triangle 2012
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
acoustics Sound Fluids Darcy formula
acoustics Sound Fluids Darcy formulaacoustics Sound Fluids Darcy formula
acoustics Sound Fluids Darcy formula
 
Baye’s Theorem
Baye’s TheoremBaye’s Theorem
Baye’s Theorem
 
Trapezium Rule Practical Substructure And Excavation Presentation1
Trapezium Rule Practical  Substructure And Excavation Presentation1Trapezium Rule Practical  Substructure And Excavation Presentation1
Trapezium Rule Practical Substructure And Excavation Presentation1
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula MathsConstruction  Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
Construction Insitu Rc Suspended Floors Using Bm Bending Moment Formula Maths
 
Simultaneous Equations Practical Construction
Simultaneous Equations Practical ConstructionSimultaneous Equations Practical Construction
Simultaneous Equations Practical Construction
 

measurement wall to floor ratio 2013

  • 2. • Go to unit 9 and download the wall-to-floor ratio ppt • Read through the ppt and complete the task for building B • Name your file wall to floor ratio and Submit your ppt to moodle unit 9 under the link “Submit wall floor ration ppt here”
  • 3.
  • 4.
  • 5.
  • 6. Wall-to-floor ratios The following activity asks you to look at the wall-to-floor ratios and form a financial comparison between two designs. The smaller the ratio the more floor space is created which in financial terms for a client would be rentable areas. Building A Plan area = 35m x 35m Height = 35m Storey height = 3.5m Building B Plan area = 22.5m x 22.5m Height = 24.75m Storey height = 2.75m If the floor budget construction cost is £50/m2 and the wall area construction cost £25/m2, calculate the wall to floor ratio for both buildings.
  • 7. • Find : The Wall-to-floor ratios • Worked example Building A • Number of floors = 35/3.5 = 10 floors • Total floor area = 10 x 35 x 35 = 12,250m2 • Total wall area = 35 x 4 x 35 = 4900m2 • Total wall cost = 4900 x £25/m2 = £122,500 • Total floor cost = 12,250 x £50/ m2 = £612,500 • Wall/floor ratio = £122,500 = 0.20 • Building B • Number of floors = 24.75/2.75 = ? floors • Total floor area = 9 x 22.5 x 22.5 = ? m2 • Total wall area = 24.75 x 4 x 22.5 = ? m2 • Total wall cost = 1114 x £25/m2 = ? £ • Total floor cost = 4556 x £50/m2 = ? £ • Wall/floor ratio = ? £ = What amount a decinal