The document discusses planning for a large concrete pour for a building's foundation. It involved:
1) 120 cement trucks convening over six locations for Toronto's largest residential concrete pour, which used 10,000 tons of concrete.
2) Extensive five month planning process and large construction crew of 180 people.
3) Pour took 12 hours with 120 trucks running simultaneously, totaling 420 million pounds of concrete for the 1,250,000 square foot project.
4) Police controlled traffic and concrete flow, resulting in a 55-story building with 253 rooms.