SlideShare a Scribd company logo
1 of 65
1
2
Today’s reality…
• Construction is complex and challenging.
• Delays, changes, disputes, accidents cost
more than ever.
• Construction contracts are among the most
complex forms of contract around because
determinations of satisfactory performance of
the obligation is difficult to determine.
3
INTRODUCTION
 A contract is a formalized means of
communication between two parties.
 This facility is used very commonly by the
project manager and owner to control the
delivery of their projects.
 A contract has the added advantage of forcing
owners to define their, requirements, organize
and arrange their thinking, and make a
commitment to their project.
BASIC REASONS FOR A CONTRACT
 BASIC REASONS
1. It defines the work and the owner’s
delegation of responsibilities to the
various parties to complete the work
2. It inherently defines the nature and
extent of risk to various parties.
3. It defines the transfer of financial
incentives to complete the work.
CONTRACT
• THE WORD CONTRACT IS DERIVED
FROM LATIN WORD ‘CONTRACTUM’
WHICH MEANS DRAWN TOGETHER;
6
WHAT IS A CONTRACT?
 A contract may be defined as a voluntary
agreement enforceable at law, made between two
or more parties, whereby rights are acquired by
one party to act or forbearances by the other.
According to the Construction Specification
Institute (CSI) Manual of Practice, a contract is “a
promise or a set of promises for the breach of
which the law gives a remedy of the performance
of which the law recognizes a duty” (CSI 2008).
The agreement is reached by the acceptance of
an offer made by one party to do something for
other for a stipulated consideration.
7
ELEMENTS OF A CONTRACT
These are the five basic elements of a contract
 OFFER
 CONSIDERATION
 ACCEPTANCE
 LEGAL PURPOSE
 LEGAL CAPACITY
8
CONTRACT AGREEMENT
The agreement is designed to formalize
the contract. It brings together all the other
contract documents by reference to them
and is legal instrument verifying the
contract.
9
CONTRACT MANAGEMENT
That function of a project which is responsible for
conformation of performance within the
stipulations of contract.
 CONSTRUCTION CONTRACT
A contract under which one party promises to furnish
service & materials to build a structure for another party
who promises to pay for the work performed. There are
two basic types of construction contracts
 Fixed price (or lump sum)
 Cost type
10
CONSTRUCTION CONTRACT
The success of a project is often judged on
the construction performance because this
activity is highly visible. The success of a
project is also influenced by;
 The accuracy and details of its documentation
 The understanding between parties and
acceptance of their particular responsibilities
 How professionally and accurately the day to day
administration is handled
 How conflict or contractual problems are
resolved.
Construction Project
Development Phases
Typical construction project development phases
includes;
1. Preliminary planning and feasibility studies
2. Preliminary engineering and design
3. Detailed Engineering design
4. Procurement
5. Construction
6. Operation
7. Demolition
Contracts are used during all phases of construction
projects.
In the first phase , which is the feasibility phase,
contracts are formed between an owner and a
consultant, an engineering firm, or an architectural
firm to perform a feasibility and site selection study.
In the construction phase contract are formed
between an owner and a Contractor firm.
Construction Contract Documents
Characteristics of a “good” contract document:
1. Carefully considered
2. Expressed clearly
3. Time-tested
4. Comprehensive
5. Fair
6. Balanced
7. Applicable to the elements of a construction
projects
BIDDING DOCUMENTS
15
A NORMAL SET OF TENDER DOCUMENTS
1. INSTRUCTIONS TO BIDDERS
2. CONDITIONS OF CONTRACT (GENERAL PART-
I & PARTICULAR PART-II)
3. FORMS OF TENDER & CONTRACT SECURITIES
4. SPECIFICATIONS & SPECIAL PROVISIONS
5. BILLS OF QUANTITIES OR SCHEDULES OF
PRICES
6. DRAWINGS
7. SUPPLEMENTARY DATA
16
STAGES OF CONTRACT MANAGEMENT
A. PRE-REQUISITION OF INVITATION TO
TENDER
B. FORMULATION OF TENDER
DOCUMENTS
C. TENDERING/EVALUATION/AWARD
D. CONTRACT ADMINISTRATION
17
STAGES OF CONTRACT MANAGEMENT (Contd.)
A - PRE-REQUISITION FOR INVITATION TO TENDER
A-1. COMPLETION OF FEASIBILITY STUDIES
 TECHNICAL FEASIBILITY
 ECONOMIC VIABILITY
 ENVIRONMENTAL IMPACT ASSESSMENT(EIA)
A-2. DETAILED ENGINEERING DESIGN
 DESIGN OF PROJECT COMPONENTS
 FINALIZATION OF TECHNICAL REPORTS
 SPECIFICATIONS
 COMPUTATION OF QUANTITIES
 FORMULATION OF ENGINEER’S ESTIMATE
18
STAGES OF CONTRACT MANAGEMENT (Contd.)
A-3. ADMINISTRATIVE APPROVAL
 PREPARATION OF PC-1 PROFORMA
 APPROVAL BY THE GOVERNMENT
A-4. ARRANGEMENT OF FINANCES
 LOCAL & FOREIGN EXCHANG COMPONENTS
A-5. LAND ACQUISTION
A-6. PREQUALIFICATION OF CONTRACTORS
19
B. FORMULATION OF TENDER DOCUMENTS
a. Specifications
b. Detailed Design
c. Tender Drawings
d. Estimation of Quantities
e. Decision About Specific Provisions
f. Decision About format-ADB/IDA
g. Conditions of Contract - Part 1 & II.
STAGES OF CONTRACT MANAGEMENT (Contd.)
20
TENDER DOCUMENTS
 General Conditions of Contract
 These define the legal rights and obligations of the
parties and may be described as the regulations under
which the contract will be performed.
 Nominates an independent third person called the
“Engineer” who is responsible for administering the
contract
 General conditions vary from country to country and
organization to organization
 Conditions of Contract internationally
Federation Internationale des Ingenieurs- Counseils
(FIDIC), Switzerland, 1992.
 Engineering Council
21
Tender Documents (Contd.)
 Special Conditions of Contract
 These are additions to, deletions from or amendments to
the General Conditions to make them project or party
specific.
 Specifications
 Give full description of work to be carried out
 Detail the materials and workmanship that the Contractor
is to utilize in the project
 Define the quality and standards of workmanship required
 Act as a legal evidence in the event of litigation
22
Tender Documents (Contd.)
 Drawings
 Bill of Quantities
 Quantities are estimates only and should have
limits of accuracy
 Tender
 Formal offer to undertake the project. Price,
conditions and method statements are detailed.
It should be noted that all documents submitted
with a tender form part of the tender
 Letter of Acceptance
 Relevant Correspondence
 This often include points of clarification of either
the Tender Documents or a tender.
23
INSTRUCTIONS TO BIDDERS
This Contains Information's And Instructions Which A
Prospective Contractor Is Required To Know Or Abide
By For Participation In Tendering:-
 Name Of Work To Be Constructed
 Source Of Funds For The Works
 Eligibility & Qualification Requirement
 Firms And Persons Authorized To Submit Tender
 Cost On Tendering Not Reimbursable
 What Makes A Tender Non-responsive
 Holding Of Pre-tender Conference, If Required
24
Stages of Contract Management (Contd.)
C. TENDERING/EVALUATION
C-1.Tendering
• Tendering Process
• Packaging
• LCB/ICB Tendering
• Types of Tender
25
Stages of Contract Management (Contd.)
C-2. Evaluation
• Tender Opening
• Preliminary Evaluation
• Detailed Evaluation
• Procedure for Preference
26
C-2 TENDER EVALUATION
C-2.1 AT TENDER OPENING
• IS TENDER SECURITY ACCOMPANIED WITH TENDER?
• IS TENDER SIGNED, STAMPED & ACCOMPANIED BY?
• POWER OF ATTORNEY
• JOINT VENTURE AGREEMENT
• DISCOUNT (IF ANY)?
27
TENDER EVALUATION (Contd.)
 GENERAL CONFORMITY OF:
 Legal & Contractual Evaluation
 Cost & Financial Evaluation
 Technical Evaluation
 Deviations:
• Major
• Minor
28
TENDER EVALUATION (Contd.)
C-2.2 PRELIMINARY EXAMINATION OF ALL TENDERS
 ELIGIBILITY & QUALIFICATION
 ARITHMETIC CHECK
 CURRENCY PROPORTION
 ADJUSTMENT ON ACCOUNT OF FOREIGN
COMPONENT?
29
TENDER EVALUATION (Contd.)
C-3. Detailed Evaluation Of Substantially Responsive
Tenders Only
 Detailed Scrutiny Of Minor Deviations:
 LEGAL & CONTRACTUAL ASPECTS
 TECHNICAL ASPECTS
 COST & FINANCIAL EVALUATION
 Clarifications (If Required)
 Loadings Of Tenders For Minor Deviations
30
LEGAL & CONTRACTUAL EVALUATION
• Evaluation for Responsiveness
• Evaluation of legal & Contractual
Aspects
• Comparison with Pre-qualification
Status
31
Cost & Financial Evaluation
• Correction of Errors
• Adjustment of Foreign Currency Components
• Interest Rate for Delayed Payments
• Price Adjustments
• Evaluated Tender Price
• Balanced Tender
32
TECHNICAL EVALUATION
• Program of Work
• Key Personnel
• Mobilization
• Method of Construction
• Equipment
• Dewatering
• Sub-Contractors
• Materials
33
TENDER EVALUATION (Contd.)
 RANKING OF SUBSTANTIALLY RESPONSIVE
TENDERS
 COMPARISON OF TENDERS AFTER ALLOWING
DOMESTIC PREFERENCE
 ISSUANCE OF LOA
 PERFORMANCE SECURITY
34
• Design phase
• Preparation of Pre-qualification Documents
• Advertisement
• Pre-qualification Criteria
• Pre-qualification Finalization
• List of pre-qualified Contractors
• Invitation to Pre-qualified Bidders
• Instructions to Bidders
• Bid submission Process
• Pre-bid meeting
• Evaluation of bids
• Lowest Evaluated Bid
• Letter of Acceptance
• Submission of Performance Bond
• Signing of Contract Agreement
• Letter of Commencement/ Notice to proceed
• Financial Assistance in form of Mobilization Advance
OVERALL FLOW OF CONTRACT PROCESS
35
Bidder Conferences/Pre-Bid Meetings
Bidder conferences (sometimes called contractor
conferences, vendor conferences, and pre-bid
conferences) are meetings with all prospective sellers
and buyers prior to submittal of a bid or proposal) are
meetings with all prospective sellers have a clear and
common understanding of the procurement (both
technical and contractual requirements), and that no
bidder receive preferential treatment.
• Responses to questions can be incorporated in to the
procurement documents as amendments.
• To be fair, buyers must take great care to ensure that
all prospective sellers hear every question from any
individual prospective seller and every answer from the
buyer.
36
TENDER SECURITY/BID BOND
• Bid Bonds are used to protect owners when the
contractor that is lowest, responsible ,
responsive bidder on a competitively bid project
refuses to enter into the contract for the project.
• Amount of security shall be in form of Cash
Deposit, Certified Cheque, Bank Draft, Letter of
Credit, Guarantee from a Scheduled Bank in
India or Foreign Bank Acceptable to Employer.
• If Tender is not accompanied by an acceptable
Tender Security (1-3% of Est. Cost, whereas
3% for smaller Contracts). It will be rejected
being non-responsive and having major
deviation.
37
CONTRACT ADMINISTRATION
• Performance Bond
• Financial Assistance/Mobilization Advance
• Appointment of the Engineer and Authority
• Priority of Contract Documents
• Retention Money
• Insurances and risk management
• Clause 14 Work Program
• Liquidated Damages
• Bonus
• Variation Orders
• Claims
• Dispute Resolution
• Price adjustment Clause
• Taking over Certificate
• Defect Liability Certificate
38
Performance Bonds
Performance bonds are guarantees by the surety that a
contractor will perform the work as required by all of the
conditions and terms of the contract
The Performance Security shall be of an amount equal to
10% of the Contract Price stated in the Letter of Acceptance.
Such Security shall, at the option of the bidder, be in the form
of either (a) bank guarantee from any Scheduled Bank in
India or (b) bank guarantee from a bank located outside India
duly counter-guaranteed by a Scheduled Bank in India or (c)
an insurance company having at least AA rating from
PACRA/JCR.
"Commencement Date" means the date upon which the Contractor
receives the notice to commence issued by the Engineer
pursuant to Clause 41.
“The Engineer" means the person appointed by the Employer to
act as Engineer for the purposes of the Contract. The
Engineer shall obtain the specific approval of the Employer
before carrying out his duties in accordance with the
Clauses mentioned in document e.g.:
• Consenting to the sub-letting of any part of the Works
under Sub-Clause 4.1 “Subcontracting”.
"Letter of Acceptance" means the formal acceptance by the
Employer of the Tender.
41
Liquidated Damages
Rather Than have a contractor be in breach of
contract if he or she is not able to complete a
project as scheduled, liquidated damages
provides compensation to owners when this
situation occurs at the end of a construction
project.
Fixed per day maximum amount 10% of contract
price
• Insurance of Works and Contractor's Equipment
• Damage to Persons and Property
• Insurance Against Accident to Workmen
The Contractor shall, except if and so far as the Contract
provides otherwise, indemnify the Employer against all
losses and claims in respect of:
(a) death of or injury to any person, or
(b) loss of or damage to any property (other than the
Works),
• Third Party Insurance (including Employer's
Property)
Changes in plans and specs
• clarification, correction, modifications prior to bid are referred
to as “addenda”
• owner must maintain a system of distributing and
acknowledging receipt of addendum
• plan and spec changes after award are referred to as
“revisions”, and generally require issuance of a Variation
order(s)
51.1Variations
• The Engineer shall make any variation of the form, qualify or
quantity of the Works or any part thereof that may, in his opinion,
be necessary and for that purpose, or if for any other reason it
shall, in his opinion, be appropriate, he shall have the authority to
instruct the Contractor to do and the Contractor shall do any of
the following:
(a) increase or decrease the quantity of any work included in
the Contract,
(b) omit any such work (but not if the omitted work is to be
carried out by the Employer or by another contractor),
(c) change the character or quality or kind of any such work,
(d) change the levels, lines, position and dimensions of any part
of the Works,
(e) execute additional work of any kind necessary for the
completion of the Works, or
(f) change any specified sequence or timing of construction of
any part of the Works.
Variations Orders
• a written order issued by the owner to the contractor for a
change to the contract within the scope of work
• change orders are written for:
• extra work
• increasing or decreasing the contract quantities
• alterations
• change orders state the basis and amount of payment and
time extensions
Ability to influence cost over time
• Greatest potential to influence cost is during
the pre-construction design phase
• Claims avoidance begins during pre-
construction
• Design phase
• Intensive preparation and review of contract documents
• Careful consideration of methods and equipment =
consider overall constructability
Extension of Time for Completion
In the event of:
(a) the amount or nature of extra or additional work,
(b) any cause of delay referred to in these Conditions,
(c) exceptionally adverse climatic conditions,
(d) any delay, impediment or prevention by the
Employer, or
(e) other special circumstances which may occur, other
than through a default of or breach of contract by the
Contractor or for which he is responsible,
Taking-Over Certificate
When the whole of the Works have been
substantially completed and have satisfactorily
passed any Tests on Completion prescribed by the
Contract, the Contractor may give a notice to that
effect to the Engineer with a copy to the Employer,
accompanied by a written undertaking to finish with
due expedition any outstanding work during the
Defects Liability Period.
Defects Liability Certificate
The Contract shall not be considered as completed until a Defects
Liability Certificate shall have been signed by the Engineer and
delivered to the Employer, with a copy to the Contractor, stating the
date on which the Contractor shall have completed his obligations to
execute and complete the Works and remedy any defects therein to
the Engineer's satisfaction.
The Defects Liability Certificate shall be given by the Engineer within
28 days after the expiration of the Defects Liability Period, or, if
different defects liability periods shall become applicable to different
Sections or parts of the Permanent Works, the expiration of the latest
such period, or as soon thereafter as any works instructed, pursuant
to Clause 49 and 50, have been completed to the satisfaction of the
Engineer. Provided that the issue of the Defects Liability Certificate
shall not be a condition precedent to payment to the Contractor of the
second portion of the Retention Money in accordance with the
conditions set out in Sub-Clause 60.3.
51
ADMINISTER PROCUREMENT:
Claims Administration
Contested changes and potential constructive changes are those
requested changes where the buyer and seller cannot reach an
agreement on compensation for the change, or cannot agree that a
change has occurred.
These contested changes are variously called claims, disputes, or
appeals.
Claims are documented, processed, monitored, and managed
throughout the contract life cycle, usually in accordance with the
terms of the contract.
If the parties themselves do not resolve a claim, it may have to be
handled in accordance with alternative dispute resolution (ADR)
typically following procedures established in the Contract.
Settlement of all claims and dispute through negotiation is the
preferred method.
CONTRACT CLAIMS
• Contract Claims could occur at any stage in the execution of a
project.
• Typical causes of claims include:
• Differing site conditions
• Delays
• Design error or changes
• Interpretation differences
• Acceleration or suspension of work
• Additional work
• Deleted work
• Construction failures
Claims Avoidance
• producing comprehensive, accurate, contract
documents
• constructability review
• clear understanding of contract requirements prior to
bidding
• having good administrative procedures in place
• open and honest communication
• timely troubleshooting
• Claims avoidance begins in the pre-
construction phase
Procedure for Claims
53.1Notice of Claims
Notwithstanding any other provision of the Contract, if the Contractor intends to claim any additional
payment pursuant to any Clause of these Conditions or otherwise, he shall give notice of his intention to the
Engineer with a copy to the Employer, within 28 days after the event giving rise to the claim has first arisen.
53.2Contemporary Records
• Upon the happening of the event referred to in Sub-Clause 53.1, the Contractor shall keep such
contemporary records as may reasonably be necessary to support any claim he may subsequently wish to
make. Without necessarily admitting the Employer's liability, the Engineer shall, on receipt of a notice under
Sub-Clause 53.1, inspect such contemporary records and may instruct the Contractor to keep any further
contemporary records as are reasonable and may be material to the claim of which notice has been given.
The Contractor shall permit the Engineer to inspect all records kept pursuant to this Sub-Clause and shall
supply him with copies thereof as and when the Engineer so instructs.
53.3Substantiation of Claims
• Within 28 days, or such other reasonable time as may be agreed by the Engineer, of giving notice under
Sub-Clause 53.1, the Contractor shall send to the Engineer an account giving detailed particulars of the
amount claimed and the grounds upon which the claim is based. Where the event giving rise to the claim
has a continuing effect, such account shall be considered to be an interim account and the Contractor shall,
at such intervals as the Engineer may reasonably require, send further interim accounts giving the
accumulated amount of the claim and any further grounds upon which it is based. In cases where interim
accounts are sent to the Engineer, the Contractor shall send a final account within 28 days of the end of the
effects resulting from the event. The Contractor shall, if required by the Engineer so to do, copy to the
Employer all accounts sent to the Engineer pursuant to this Sub-Clause.
Disputes
Under Construction—Problems & Disputes
Settlement of Disputes
67.1 Engineer's Decision
If a dispute of any kind whatsoever arises between the Employer and the Contractor in connection
with, or arising out of, the Contract or the execution of the Works, whether during the execution of the
Works or after their completion and whether before or after repudiation or other termination of the
Contract, including any dispute as to any opinion, instruction, determination, certificate or valuation of
the Engineer, the matter in dispute shall, in the first place, be referred in writing to the Engineer, with
a copy to the other party. Such reference shall state that it is made pursuant to this Clause. No later
than the eighty-fourth day after the day on which he received such reference the Engineer shall give
notice of his decision to the Employer and the Contractor. Such decision shall state that it is made
pursuant to this Clause.
Unless the Contract has already been repudiated or terminated, the Contractor shall, in every case,
continue to proceed with the Works with all due diligence and the Contractor and the Employer shall
give effect forthwith to every such decision of the Engineer unless and until the same shall be
revised, as hereinafter provided, in an amicable settlement or an arbitral award.
• Amicable Settlement
Where notice of intention to commence arbitration as to a dispute has been given in accordance with
Sub-Clause 67.1, the parties shall attempt to settle such dispute amicably before the commencement
of arbitration. Provided that, unless the parties otherwise agree, arbitration may be commenced on or
after the fifty-sixth day after the day on which notice of intention to commence arbitration of such
dispute was given, even if no attempt at amicable settlement thereof has been made
PRICE ADJUSTMENT IN
CONSTRUCTION CONTRACTS
58
INCREASE OR DECREASE OF COST
• It is not in the best interest of the Employer
to ask tenderers to quote firm prices with
no provision of adjustments, especially for
long-term contracts.
• In bidding documents having provisions for
price adjustment, the Employer is expected
to receive more competitive offers from
reputable parties and will have to meet the
net variations in cost as may actually
occur.
59
S.
No.
MATERIAL MARKET
PRICE
MARKET PRICE Difference
Dec-07/
Jan 08
31st
May-08 %
1 Cement 240 300 25.00
2 Reinforcement 47000 84000 78.72
3 Diesel 37.8 50.21 32.83
4 Bitumen 36395 48195 32.42
5
Labour
(unskilled) 250 300 20.00
60
PRICE INCREASE
DEC 07/Jan 08
to
31st May 2008
March 2008
to
31st May 2008
39.40% 21.29%
61
Why a formula?
• Make price adjustment (as a reasonable
compensation against variation in prices
of the selected materials and inputs) as
close as possible to the actual;
• Set out a simple procedure;
• Minimize ambiguities; and
• Make the contract more equitable.
62
1.COMPLETION PERIOD OF THE
CONTRACT
Only contracts having duration of six months
or more should be liable to price adjustment.
2.COST OF THE CONTRACT
The Price Adjustment shall be applicable
only for the contracts having contract price
exceeding financial limit of PEC Contractors
Registration Category C-5 (Rs. 30 Million).
63
Particular Conditions of Contract Part-II
Clause 70- Increase or Decrease of Cost
Adjustment Formula
Pn= A+ b*Ln/Lo+ c*Fn/Fo + d*Cn/Co+ e*Sn/So+
f*En/Eo + g*Mn/Mo ……..
64
APPENDIX-C
Cost
Element
Description Base
Cost
Weighta
ges
Applicable index
(i) Fixed Portion - 0.35
(ii) Labour Government of India (GP)
Federal Bureau of Statistics
(FBS) Monthly Statistical
Bulletin.
(iii) Cement- in bag FBS
(iv) Reinforcement
Steel
India Steel Mills/ FBS
(v) HSD OIL PSU
(vi) Bricks FBS
(vii) Bitumen National Refinery
Total 1.0
65
3. DECISION ABOUT ELEMENTS TO BE COVERED
4. WEIGHTAGE OF EACH COST ELEMENT
5. SELECTION OF SOURCE
In case the price adjustable elements are not
covered in the Federal Bureau of Statistics, the Base
price and the source thereof shall be mentioned by
the Employer.
66
6. BASE COST PRICES
The base cost prices shall be those applying 28 days
prior to the latest day for submission of bids.
67

More Related Content

What's hot

Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxssuserc0bf9b
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptTouqeer1
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?maria_singh
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 

What's hot (20)

Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Contracts
ContractsContracts
Contracts
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Construction contract
Construction contract Construction contract
Construction contract
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 

Similar to contract_management.ppt

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBESahl Buhary
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2shensin1015
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfHamsathFarludeen
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptxRiazMuhammad35
 

Similar to contract_management.ppt (20)

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

contract_management.ppt

  • 1. 1
  • 2. 2 Today’s reality… • Construction is complex and challenging. • Delays, changes, disputes, accidents cost more than ever. • Construction contracts are among the most complex forms of contract around because determinations of satisfactory performance of the obligation is difficult to determine.
  • 3. 3 INTRODUCTION  A contract is a formalized means of communication between two parties.  This facility is used very commonly by the project manager and owner to control the delivery of their projects.  A contract has the added advantage of forcing owners to define their, requirements, organize and arrange their thinking, and make a commitment to their project.
  • 4. BASIC REASONS FOR A CONTRACT  BASIC REASONS 1. It defines the work and the owner’s delegation of responsibilities to the various parties to complete the work 2. It inherently defines the nature and extent of risk to various parties. 3. It defines the transfer of financial incentives to complete the work.
  • 5. CONTRACT • THE WORD CONTRACT IS DERIVED FROM LATIN WORD ‘CONTRACTUM’ WHICH MEANS DRAWN TOGETHER;
  • 6. 6 WHAT IS A CONTRACT?  A contract may be defined as a voluntary agreement enforceable at law, made between two or more parties, whereby rights are acquired by one party to act or forbearances by the other. According to the Construction Specification Institute (CSI) Manual of Practice, a contract is “a promise or a set of promises for the breach of which the law gives a remedy of the performance of which the law recognizes a duty” (CSI 2008). The agreement is reached by the acceptance of an offer made by one party to do something for other for a stipulated consideration.
  • 7. 7 ELEMENTS OF A CONTRACT These are the five basic elements of a contract  OFFER  CONSIDERATION  ACCEPTANCE  LEGAL PURPOSE  LEGAL CAPACITY
  • 8. 8 CONTRACT AGREEMENT The agreement is designed to formalize the contract. It brings together all the other contract documents by reference to them and is legal instrument verifying the contract.
  • 9. 9 CONTRACT MANAGEMENT That function of a project which is responsible for conformation of performance within the stipulations of contract.  CONSTRUCTION CONTRACT A contract under which one party promises to furnish service & materials to build a structure for another party who promises to pay for the work performed. There are two basic types of construction contracts  Fixed price (or lump sum)  Cost type
  • 10. 10 CONSTRUCTION CONTRACT The success of a project is often judged on the construction performance because this activity is highly visible. The success of a project is also influenced by;  The accuracy and details of its documentation  The understanding between parties and acceptance of their particular responsibilities  How professionally and accurately the day to day administration is handled  How conflict or contractual problems are resolved.
  • 11. Construction Project Development Phases Typical construction project development phases includes; 1. Preliminary planning and feasibility studies 2. Preliminary engineering and design 3. Detailed Engineering design 4. Procurement 5. Construction 6. Operation 7. Demolition
  • 12. Contracts are used during all phases of construction projects. In the first phase , which is the feasibility phase, contracts are formed between an owner and a consultant, an engineering firm, or an architectural firm to perform a feasibility and site selection study. In the construction phase contract are formed between an owner and a Contractor firm.
  • 13. Construction Contract Documents Characteristics of a “good” contract document: 1. Carefully considered 2. Expressed clearly 3. Time-tested 4. Comprehensive 5. Fair 6. Balanced 7. Applicable to the elements of a construction projects
  • 15. 15 A NORMAL SET OF TENDER DOCUMENTS 1. INSTRUCTIONS TO BIDDERS 2. CONDITIONS OF CONTRACT (GENERAL PART- I & PARTICULAR PART-II) 3. FORMS OF TENDER & CONTRACT SECURITIES 4. SPECIFICATIONS & SPECIAL PROVISIONS 5. BILLS OF QUANTITIES OR SCHEDULES OF PRICES 6. DRAWINGS 7. SUPPLEMENTARY DATA
  • 16. 16 STAGES OF CONTRACT MANAGEMENT A. PRE-REQUISITION OF INVITATION TO TENDER B. FORMULATION OF TENDER DOCUMENTS C. TENDERING/EVALUATION/AWARD D. CONTRACT ADMINISTRATION
  • 17. 17 STAGES OF CONTRACT MANAGEMENT (Contd.) A - PRE-REQUISITION FOR INVITATION TO TENDER A-1. COMPLETION OF FEASIBILITY STUDIES  TECHNICAL FEASIBILITY  ECONOMIC VIABILITY  ENVIRONMENTAL IMPACT ASSESSMENT(EIA) A-2. DETAILED ENGINEERING DESIGN  DESIGN OF PROJECT COMPONENTS  FINALIZATION OF TECHNICAL REPORTS  SPECIFICATIONS  COMPUTATION OF QUANTITIES  FORMULATION OF ENGINEER’S ESTIMATE
  • 18. 18 STAGES OF CONTRACT MANAGEMENT (Contd.) A-3. ADMINISTRATIVE APPROVAL  PREPARATION OF PC-1 PROFORMA  APPROVAL BY THE GOVERNMENT A-4. ARRANGEMENT OF FINANCES  LOCAL & FOREIGN EXCHANG COMPONENTS A-5. LAND ACQUISTION A-6. PREQUALIFICATION OF CONTRACTORS
  • 19. 19 B. FORMULATION OF TENDER DOCUMENTS a. Specifications b. Detailed Design c. Tender Drawings d. Estimation of Quantities e. Decision About Specific Provisions f. Decision About format-ADB/IDA g. Conditions of Contract - Part 1 & II. STAGES OF CONTRACT MANAGEMENT (Contd.)
  • 20. 20 TENDER DOCUMENTS  General Conditions of Contract  These define the legal rights and obligations of the parties and may be described as the regulations under which the contract will be performed.  Nominates an independent third person called the “Engineer” who is responsible for administering the contract  General conditions vary from country to country and organization to organization  Conditions of Contract internationally Federation Internationale des Ingenieurs- Counseils (FIDIC), Switzerland, 1992.  Engineering Council
  • 21. 21 Tender Documents (Contd.)  Special Conditions of Contract  These are additions to, deletions from or amendments to the General Conditions to make them project or party specific.  Specifications  Give full description of work to be carried out  Detail the materials and workmanship that the Contractor is to utilize in the project  Define the quality and standards of workmanship required  Act as a legal evidence in the event of litigation
  • 22. 22 Tender Documents (Contd.)  Drawings  Bill of Quantities  Quantities are estimates only and should have limits of accuracy  Tender  Formal offer to undertake the project. Price, conditions and method statements are detailed. It should be noted that all documents submitted with a tender form part of the tender  Letter of Acceptance  Relevant Correspondence  This often include points of clarification of either the Tender Documents or a tender.
  • 23. 23 INSTRUCTIONS TO BIDDERS This Contains Information's And Instructions Which A Prospective Contractor Is Required To Know Or Abide By For Participation In Tendering:-  Name Of Work To Be Constructed  Source Of Funds For The Works  Eligibility & Qualification Requirement  Firms And Persons Authorized To Submit Tender  Cost On Tendering Not Reimbursable  What Makes A Tender Non-responsive  Holding Of Pre-tender Conference, If Required
  • 24. 24 Stages of Contract Management (Contd.) C. TENDERING/EVALUATION C-1.Tendering • Tendering Process • Packaging • LCB/ICB Tendering • Types of Tender
  • 25. 25 Stages of Contract Management (Contd.) C-2. Evaluation • Tender Opening • Preliminary Evaluation • Detailed Evaluation • Procedure for Preference
  • 26. 26 C-2 TENDER EVALUATION C-2.1 AT TENDER OPENING • IS TENDER SECURITY ACCOMPANIED WITH TENDER? • IS TENDER SIGNED, STAMPED & ACCOMPANIED BY? • POWER OF ATTORNEY • JOINT VENTURE AGREEMENT • DISCOUNT (IF ANY)?
  • 27. 27 TENDER EVALUATION (Contd.)  GENERAL CONFORMITY OF:  Legal & Contractual Evaluation  Cost & Financial Evaluation  Technical Evaluation  Deviations: • Major • Minor
  • 28. 28 TENDER EVALUATION (Contd.) C-2.2 PRELIMINARY EXAMINATION OF ALL TENDERS  ELIGIBILITY & QUALIFICATION  ARITHMETIC CHECK  CURRENCY PROPORTION  ADJUSTMENT ON ACCOUNT OF FOREIGN COMPONENT?
  • 29. 29 TENDER EVALUATION (Contd.) C-3. Detailed Evaluation Of Substantially Responsive Tenders Only  Detailed Scrutiny Of Minor Deviations:  LEGAL & CONTRACTUAL ASPECTS  TECHNICAL ASPECTS  COST & FINANCIAL EVALUATION  Clarifications (If Required)  Loadings Of Tenders For Minor Deviations
  • 30. 30 LEGAL & CONTRACTUAL EVALUATION • Evaluation for Responsiveness • Evaluation of legal & Contractual Aspects • Comparison with Pre-qualification Status
  • 31. 31 Cost & Financial Evaluation • Correction of Errors • Adjustment of Foreign Currency Components • Interest Rate for Delayed Payments • Price Adjustments • Evaluated Tender Price • Balanced Tender
  • 32. 32 TECHNICAL EVALUATION • Program of Work • Key Personnel • Mobilization • Method of Construction • Equipment • Dewatering • Sub-Contractors • Materials
  • 33. 33 TENDER EVALUATION (Contd.)  RANKING OF SUBSTANTIALLY RESPONSIVE TENDERS  COMPARISON OF TENDERS AFTER ALLOWING DOMESTIC PREFERENCE  ISSUANCE OF LOA  PERFORMANCE SECURITY
  • 34. 34 • Design phase • Preparation of Pre-qualification Documents • Advertisement • Pre-qualification Criteria • Pre-qualification Finalization • List of pre-qualified Contractors • Invitation to Pre-qualified Bidders • Instructions to Bidders • Bid submission Process • Pre-bid meeting • Evaluation of bids • Lowest Evaluated Bid • Letter of Acceptance • Submission of Performance Bond • Signing of Contract Agreement • Letter of Commencement/ Notice to proceed • Financial Assistance in form of Mobilization Advance OVERALL FLOW OF CONTRACT PROCESS
  • 35. 35 Bidder Conferences/Pre-Bid Meetings Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences) are meetings with all prospective sellers and buyers prior to submittal of a bid or proposal) are meetings with all prospective sellers have a clear and common understanding of the procurement (both technical and contractual requirements), and that no bidder receive preferential treatment. • Responses to questions can be incorporated in to the procurement documents as amendments. • To be fair, buyers must take great care to ensure that all prospective sellers hear every question from any individual prospective seller and every answer from the buyer.
  • 36. 36 TENDER SECURITY/BID BOND • Bid Bonds are used to protect owners when the contractor that is lowest, responsible , responsive bidder on a competitively bid project refuses to enter into the contract for the project. • Amount of security shall be in form of Cash Deposit, Certified Cheque, Bank Draft, Letter of Credit, Guarantee from a Scheduled Bank in India or Foreign Bank Acceptable to Employer. • If Tender is not accompanied by an acceptable Tender Security (1-3% of Est. Cost, whereas 3% for smaller Contracts). It will be rejected being non-responsive and having major deviation.
  • 37. 37 CONTRACT ADMINISTRATION • Performance Bond • Financial Assistance/Mobilization Advance • Appointment of the Engineer and Authority • Priority of Contract Documents • Retention Money • Insurances and risk management • Clause 14 Work Program • Liquidated Damages • Bonus • Variation Orders • Claims • Dispute Resolution • Price adjustment Clause • Taking over Certificate • Defect Liability Certificate
  • 38. 38 Performance Bonds Performance bonds are guarantees by the surety that a contractor will perform the work as required by all of the conditions and terms of the contract The Performance Security shall be of an amount equal to 10% of the Contract Price stated in the Letter of Acceptance. Such Security shall, at the option of the bidder, be in the form of either (a) bank guarantee from any Scheduled Bank in India or (b) bank guarantee from a bank located outside India duly counter-guaranteed by a Scheduled Bank in India or (c) an insurance company having at least AA rating from PACRA/JCR. "Commencement Date" means the date upon which the Contractor receives the notice to commence issued by the Engineer pursuant to Clause 41.
  • 39. “The Engineer" means the person appointed by the Employer to act as Engineer for the purposes of the Contract. The Engineer shall obtain the specific approval of the Employer before carrying out his duties in accordance with the Clauses mentioned in document e.g.: • Consenting to the sub-letting of any part of the Works under Sub-Clause 4.1 “Subcontracting”. "Letter of Acceptance" means the formal acceptance by the Employer of the Tender.
  • 40. 41 Liquidated Damages Rather Than have a contractor be in breach of contract if he or she is not able to complete a project as scheduled, liquidated damages provides compensation to owners when this situation occurs at the end of a construction project. Fixed per day maximum amount 10% of contract price
  • 41. • Insurance of Works and Contractor's Equipment • Damage to Persons and Property • Insurance Against Accident to Workmen The Contractor shall, except if and so far as the Contract provides otherwise, indemnify the Employer against all losses and claims in respect of: (a) death of or injury to any person, or (b) loss of or damage to any property (other than the Works), • Third Party Insurance (including Employer's Property)
  • 42. Changes in plans and specs • clarification, correction, modifications prior to bid are referred to as “addenda” • owner must maintain a system of distributing and acknowledging receipt of addendum • plan and spec changes after award are referred to as “revisions”, and generally require issuance of a Variation order(s)
  • 43. 51.1Variations • The Engineer shall make any variation of the form, qualify or quantity of the Works or any part thereof that may, in his opinion, be necessary and for that purpose, or if for any other reason it shall, in his opinion, be appropriate, he shall have the authority to instruct the Contractor to do and the Contractor shall do any of the following: (a) increase or decrease the quantity of any work included in the Contract, (b) omit any such work (but not if the omitted work is to be carried out by the Employer or by another contractor), (c) change the character or quality or kind of any such work, (d) change the levels, lines, position and dimensions of any part of the Works, (e) execute additional work of any kind necessary for the completion of the Works, or (f) change any specified sequence or timing of construction of any part of the Works.
  • 44. Variations Orders • a written order issued by the owner to the contractor for a change to the contract within the scope of work • change orders are written for: • extra work • increasing or decreasing the contract quantities • alterations • change orders state the basis and amount of payment and time extensions
  • 45. Ability to influence cost over time • Greatest potential to influence cost is during the pre-construction design phase • Claims avoidance begins during pre- construction • Design phase • Intensive preparation and review of contract documents • Careful consideration of methods and equipment = consider overall constructability
  • 46. Extension of Time for Completion In the event of: (a) the amount or nature of extra or additional work, (b) any cause of delay referred to in these Conditions, (c) exceptionally adverse climatic conditions, (d) any delay, impediment or prevention by the Employer, or (e) other special circumstances which may occur, other than through a default of or breach of contract by the Contractor or for which he is responsible,
  • 47. Taking-Over Certificate When the whole of the Works have been substantially completed and have satisfactorily passed any Tests on Completion prescribed by the Contract, the Contractor may give a notice to that effect to the Engineer with a copy to the Employer, accompanied by a written undertaking to finish with due expedition any outstanding work during the Defects Liability Period.
  • 48. Defects Liability Certificate The Contract shall not be considered as completed until a Defects Liability Certificate shall have been signed by the Engineer and delivered to the Employer, with a copy to the Contractor, stating the date on which the Contractor shall have completed his obligations to execute and complete the Works and remedy any defects therein to the Engineer's satisfaction. The Defects Liability Certificate shall be given by the Engineer within 28 days after the expiration of the Defects Liability Period, or, if different defects liability periods shall become applicable to different Sections or parts of the Permanent Works, the expiration of the latest such period, or as soon thereafter as any works instructed, pursuant to Clause 49 and 50, have been completed to the satisfaction of the Engineer. Provided that the issue of the Defects Liability Certificate shall not be a condition precedent to payment to the Contractor of the second portion of the Retention Money in accordance with the conditions set out in Sub-Clause 60.3.
  • 49. 51 ADMINISTER PROCUREMENT: Claims Administration Contested changes and potential constructive changes are those requested changes where the buyer and seller cannot reach an agreement on compensation for the change, or cannot agree that a change has occurred. These contested changes are variously called claims, disputes, or appeals. Claims are documented, processed, monitored, and managed throughout the contract life cycle, usually in accordance with the terms of the contract. If the parties themselves do not resolve a claim, it may have to be handled in accordance with alternative dispute resolution (ADR) typically following procedures established in the Contract. Settlement of all claims and dispute through negotiation is the preferred method.
  • 50. CONTRACT CLAIMS • Contract Claims could occur at any stage in the execution of a project. • Typical causes of claims include: • Differing site conditions • Delays • Design error or changes • Interpretation differences • Acceleration or suspension of work • Additional work • Deleted work • Construction failures
  • 51. Claims Avoidance • producing comprehensive, accurate, contract documents • constructability review • clear understanding of contract requirements prior to bidding • having good administrative procedures in place • open and honest communication • timely troubleshooting • Claims avoidance begins in the pre- construction phase
  • 52. Procedure for Claims 53.1Notice of Claims Notwithstanding any other provision of the Contract, if the Contractor intends to claim any additional payment pursuant to any Clause of these Conditions or otherwise, he shall give notice of his intention to the Engineer with a copy to the Employer, within 28 days after the event giving rise to the claim has first arisen. 53.2Contemporary Records • Upon the happening of the event referred to in Sub-Clause 53.1, the Contractor shall keep such contemporary records as may reasonably be necessary to support any claim he may subsequently wish to make. Without necessarily admitting the Employer's liability, the Engineer shall, on receipt of a notice under Sub-Clause 53.1, inspect such contemporary records and may instruct the Contractor to keep any further contemporary records as are reasonable and may be material to the claim of which notice has been given. The Contractor shall permit the Engineer to inspect all records kept pursuant to this Sub-Clause and shall supply him with copies thereof as and when the Engineer so instructs. 53.3Substantiation of Claims • Within 28 days, or such other reasonable time as may be agreed by the Engineer, of giving notice under Sub-Clause 53.1, the Contractor shall send to the Engineer an account giving detailed particulars of the amount claimed and the grounds upon which the claim is based. Where the event giving rise to the claim has a continuing effect, such account shall be considered to be an interim account and the Contractor shall, at such intervals as the Engineer may reasonably require, send further interim accounts giving the accumulated amount of the claim and any further grounds upon which it is based. In cases where interim accounts are sent to the Engineer, the Contractor shall send a final account within 28 days of the end of the effects resulting from the event. The Contractor shall, if required by the Engineer so to do, copy to the Employer all accounts sent to the Engineer pursuant to this Sub-Clause.
  • 54. Settlement of Disputes 67.1 Engineer's Decision If a dispute of any kind whatsoever arises between the Employer and the Contractor in connection with, or arising out of, the Contract or the execution of the Works, whether during the execution of the Works or after their completion and whether before or after repudiation or other termination of the Contract, including any dispute as to any opinion, instruction, determination, certificate or valuation of the Engineer, the matter in dispute shall, in the first place, be referred in writing to the Engineer, with a copy to the other party. Such reference shall state that it is made pursuant to this Clause. No later than the eighty-fourth day after the day on which he received such reference the Engineer shall give notice of his decision to the Employer and the Contractor. Such decision shall state that it is made pursuant to this Clause. Unless the Contract has already been repudiated or terminated, the Contractor shall, in every case, continue to proceed with the Works with all due diligence and the Contractor and the Employer shall give effect forthwith to every such decision of the Engineer unless and until the same shall be revised, as hereinafter provided, in an amicable settlement or an arbitral award. • Amicable Settlement Where notice of intention to commence arbitration as to a dispute has been given in accordance with Sub-Clause 67.1, the parties shall attempt to settle such dispute amicably before the commencement of arbitration. Provided that, unless the parties otherwise agree, arbitration may be commenced on or after the fifty-sixth day after the day on which notice of intention to commence arbitration of such dispute was given, even if no attempt at amicable settlement thereof has been made
  • 56. 58 INCREASE OR DECREASE OF COST • It is not in the best interest of the Employer to ask tenderers to quote firm prices with no provision of adjustments, especially for long-term contracts. • In bidding documents having provisions for price adjustment, the Employer is expected to receive more competitive offers from reputable parties and will have to meet the net variations in cost as may actually occur.
  • 57. 59 S. No. MATERIAL MARKET PRICE MARKET PRICE Difference Dec-07/ Jan 08 31st May-08 % 1 Cement 240 300 25.00 2 Reinforcement 47000 84000 78.72 3 Diesel 37.8 50.21 32.83 4 Bitumen 36395 48195 32.42 5 Labour (unskilled) 250 300 20.00
  • 58. 60 PRICE INCREASE DEC 07/Jan 08 to 31st May 2008 March 2008 to 31st May 2008 39.40% 21.29%
  • 59. 61 Why a formula? • Make price adjustment (as a reasonable compensation against variation in prices of the selected materials and inputs) as close as possible to the actual; • Set out a simple procedure; • Minimize ambiguities; and • Make the contract more equitable.
  • 60. 62 1.COMPLETION PERIOD OF THE CONTRACT Only contracts having duration of six months or more should be liable to price adjustment. 2.COST OF THE CONTRACT The Price Adjustment shall be applicable only for the contracts having contract price exceeding financial limit of PEC Contractors Registration Category C-5 (Rs. 30 Million).
  • 61. 63 Particular Conditions of Contract Part-II Clause 70- Increase or Decrease of Cost Adjustment Formula Pn= A+ b*Ln/Lo+ c*Fn/Fo + d*Cn/Co+ e*Sn/So+ f*En/Eo + g*Mn/Mo ……..
  • 62. 64 APPENDIX-C Cost Element Description Base Cost Weighta ges Applicable index (i) Fixed Portion - 0.35 (ii) Labour Government of India (GP) Federal Bureau of Statistics (FBS) Monthly Statistical Bulletin. (iii) Cement- in bag FBS (iv) Reinforcement Steel India Steel Mills/ FBS (v) HSD OIL PSU (vi) Bricks FBS (vii) Bitumen National Refinery Total 1.0
  • 63. 65 3. DECISION ABOUT ELEMENTS TO BE COVERED 4. WEIGHTAGE OF EACH COST ELEMENT 5. SELECTION OF SOURCE In case the price adjustable elements are not covered in the Federal Bureau of Statistics, the Base price and the source thereof shall be mentioned by the Employer.
  • 64. 66 6. BASE COST PRICES The base cost prices shall be those applying 28 days prior to the latest day for submission of bids.
  • 65. 67