The document discusses three case studies that illustrate how focusing on reliability improvements versus cost reductions alone can impact maintenance costs and production outcomes:
1) A food processing plant that reduced maintenance staff saw temporary cost savings but then costs increased as reliability declined.
2) An chemical plant that aggressively cut maintenance costs initially saved money but reliability dropped, resulting in $1.2 billion in losses over three years before improvements were made.
3) A plant that prioritized reliability improvements like planned maintenance, vibration analysis, and lubrication training saw maintenance costs rise 3% annually for three years as reliability increased, after which costs dropped 40% while reliability reached 92%. Focusing first on reliability drives down long-term maintenance costs.