1 M11 STABILISATION WORKS GEOBEAR
The project involved emergency remedial works at junction 14 of the A14 Cambridge to
Huntingdon Major Improvement scheme. The junction comprises a two-lane slip road section
of motorway with cloverleaf junction that links the M11 to the A428 and A14. This section of the
northbound M11 carries around 40,000 vehicles a day and forms part of the strategic highway
network which also serves Stansted Airport and provides access to strategic ferry ports.
Issues with the embankments to the bridge abutments on the M11 overbridge at Jct 14 had
been identified by Highways England as part of routine maintenance inspections. Further
investigation through visual and ground penetrating surveys and dynamic probing identified
the presence of voids beneath the carriageway close to the abutments which, if left, could
have resulted in significant risk of settlement or collapse of the carriageway.
An urgent solution was needed that would meet both technical and programme requirements
without compromising safety. The solution required the improvement of the foundation strata
compressive strength to 4MPa, implemented with minimal disruption to road users and the
wider improvement scheme. Geobear were consulted by WSP and subsequently designed
an innovative and time efficient solution that could be implemented from the carriageway
surface with minimal disturbance to the carriageway surface, and minimal reinstatement
works.Karl Brooks, Highways England
M11 Stabilisation
Geobear’s solution to the essential
embankment repair at M11 Girton
interchange has been a highlight of this
year’s 2018/19 programme of works.
2 M11 STABILISATION WORKS GEOBEAR
Four Geobear crews worked through the
night over a three week period to deliver
the emergency works.
Specialist two-component geopolymer
material was used to fill the voiding
beneath the M11 and stabilise the area.
The material is mixed on site and pumped
into the void through steel tubes.
3 M11 STABILISATION WORKS GEOBEAR
A drilling rig was used to core 50mm holes
into the road surface and through the
slab. The holes would accomodate the
steel tubes and also be used for a cctv
monitoring.
With the drilling completed the
programme of injection works could be
agreed. Sequences of material placement
were designed by the Geobear engineering
team.
4 M11 STABILISATION WORKS GEOBEAR
Laser monitoring is used while material
is injected into the ground to ensure no
vertical movement of the slab.
Steel tubes
are positioned
through the slab
to place material.
5 M11 STABILISATION WORKS GEOBEAR
Geopolymer injection
Material is pumped
directly from the self
contained Geobear
units through a hose
and controlled with an
injection mechanism .
6 M11 STABILISATION WORKS GEOBEAR
The material injections are sequentially
planned, but engineering teams on-site
make variations as required.
Technical teams keep a record of the
quantity of material injected through each
steel tube into the void. This, together with
visual surveys ensures the voids are filled.
7 M11 STABILISATION WORKS GEOBEAR
The methodology allows for teams to work
in localised areas ensuring crucial routes
can be kept open.
Once a voided area has been filled and stabilised,
the steel tubes are cut and the holes in the road
surface filled.
Project was completed on time and and within
budget. The scheme of works was recognised as a
finanlist at the 2019 Ground Engineering Awards.

More Related Content

Similar to M11 stabilisation by Geobear

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
AmirShafiq25
 
CV_Emanuil Videnov
CV_Emanuil VidenovCV_Emanuil Videnov
CV_Emanuil Videnov
Emanuil Videnov
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
ADAM DUKE
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
Jayanta Sen
 
Construction Forensic
Construction ForensicConstruction Forensic
Construction Forensic
Dr. ABEER KHALID MANSOUR
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
Muhammed Sulfeek
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
IJERA Editor
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
Eric Boothman
 
Cheyenne Landfill Project
Cheyenne Landfill ProjectCheyenne Landfill Project
Cheyenne Landfill Project
Fabricated Geomembrane
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Jacobs Engineering
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster Wheeler
Gareth White
 
South Jetty
South JettySouth Jetty
South Jetty
Hassan Halhoul
 
Tunneling (2).ppt
Tunneling (2).pptTunneling (2).ppt
Tunneling (2).ppt
METRYCMUSICA
 
Case study - Kettering train station
Case study - Kettering train stationCase study - Kettering train station
Case study - Kettering train station
Alex Collman MCIWM CRWM
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
AGNIVORAY1
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
May Begum
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
Hayley Sharp
 

Similar to M11 stabilisation by Geobear (20)

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
CV_Emanuil Videnov
CV_Emanuil VidenovCV_Emanuil Videnov
CV_Emanuil Videnov
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Construction Forensic
Construction ForensicConstruction Forensic
Construction Forensic
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
 
Cheyenne Landfill Project
Cheyenne Landfill ProjectCheyenne Landfill Project
Cheyenne Landfill Project
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster Wheeler
 
South Jetty
South JettySouth Jetty
South Jetty
 
Tunneling (2).ppt
Tunneling (2).pptTunneling (2).ppt
Tunneling (2).ppt
 
Case study - Kettering train station
Case study - Kettering train stationCase study - Kettering train station
Case study - Kettering train station
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 

Recently uploaded

bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 

Recently uploaded (20)

bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 

M11 stabilisation by Geobear

  • 1. 1 M11 STABILISATION WORKS GEOBEAR The project involved emergency remedial works at junction 14 of the A14 Cambridge to Huntingdon Major Improvement scheme. The junction comprises a two-lane slip road section of motorway with cloverleaf junction that links the M11 to the A428 and A14. This section of the northbound M11 carries around 40,000 vehicles a day and forms part of the strategic highway network which also serves Stansted Airport and provides access to strategic ferry ports. Issues with the embankments to the bridge abutments on the M11 overbridge at Jct 14 had been identified by Highways England as part of routine maintenance inspections. Further investigation through visual and ground penetrating surveys and dynamic probing identified the presence of voids beneath the carriageway close to the abutments which, if left, could have resulted in significant risk of settlement or collapse of the carriageway. An urgent solution was needed that would meet both technical and programme requirements without compromising safety. The solution required the improvement of the foundation strata compressive strength to 4MPa, implemented with minimal disruption to road users and the wider improvement scheme. Geobear were consulted by WSP and subsequently designed an innovative and time efficient solution that could be implemented from the carriageway surface with minimal disturbance to the carriageway surface, and minimal reinstatement works.Karl Brooks, Highways England M11 Stabilisation Geobear’s solution to the essential embankment repair at M11 Girton interchange has been a highlight of this year’s 2018/19 programme of works.
  • 2. 2 M11 STABILISATION WORKS GEOBEAR Four Geobear crews worked through the night over a three week period to deliver the emergency works. Specialist two-component geopolymer material was used to fill the voiding beneath the M11 and stabilise the area. The material is mixed on site and pumped into the void through steel tubes.
  • 3. 3 M11 STABILISATION WORKS GEOBEAR A drilling rig was used to core 50mm holes into the road surface and through the slab. The holes would accomodate the steel tubes and also be used for a cctv monitoring. With the drilling completed the programme of injection works could be agreed. Sequences of material placement were designed by the Geobear engineering team.
  • 4. 4 M11 STABILISATION WORKS GEOBEAR Laser monitoring is used while material is injected into the ground to ensure no vertical movement of the slab. Steel tubes are positioned through the slab to place material.
  • 5. 5 M11 STABILISATION WORKS GEOBEAR Geopolymer injection Material is pumped directly from the self contained Geobear units through a hose and controlled with an injection mechanism .
  • 6. 6 M11 STABILISATION WORKS GEOBEAR The material injections are sequentially planned, but engineering teams on-site make variations as required. Technical teams keep a record of the quantity of material injected through each steel tube into the void. This, together with visual surveys ensures the voids are filled.
  • 7. 7 M11 STABILISATION WORKS GEOBEAR The methodology allows for teams to work in localised areas ensuring crucial routes can be kept open. Once a voided area has been filled and stabilised, the steel tubes are cut and the holes in the road surface filled. Project was completed on time and and within budget. The scheme of works was recognised as a finanlist at the 2019 Ground Engineering Awards.