SlideShare a Scribd company logo
Opera Grand Tower Project, Downtown Dubai
Employer: Project Management: Lead Consultant: Main Contractor: MEP Contractor
Live Panels with Locks
Live Bus bars with Locks
 LOTO - Brief Introduction
 Project Organizational Arrangements
 Responsibilities
 Permit control System
 Authorized Person Responsibilities
 Permit Types
 Permit Process
 Supply to Third Parties
 Emergency Procedures
Live Panels with Locks
The purpose of the RCC Lock Out / Tag Out Procedures are to ensure that
where employees and others, are exposed to work situations that carry a
risk of
• Electrical shock
• Electrocution
• Electrical burns
• Fire
• Explosion
that the work situation is assessed and that suitable control measures' and
systems are implemented to ensure that electrical risks / hazards are
removed or reduced as far as reasonably practicable.
The ‘Lock Out / Tag Out’ procedure is implemented in situations where a
part of the Electrical System has been made LIVE before the work on the
system has been completed and RCC has assumed the role of ‘Duty
Holder’ for the installation.
The electrical system energized rooms keys will be under the control of RCC,
permit system to be followed to work in the rooms by all parties.
•Project LOTO Appointed Person
MD Irfan (ELT Supervisor)
Site LOTO Execution
Team
Authorized Engineer
Eng Safvan
Competent Persons
Trained/Competent
Electrical Team
Authorized Project Manager
• Overviews company’s Lock Out / Tag Out requirements
• Appoints Project Authorizing Engineers
• Overall responsibility for the LOTO system
• Periodic audit of complete company/project LOTO procedures
Project LOTO Appointed Person
Appointed by the Authorizing Manager is responsible for
• Assessment of project specific LOTO procedures
• Accept duty holder responsibilities for electrical system for RCC
• Implementation of appropriate Lock Out / Tag Out procedures
• Assessment and appointments of authorized persons
• Maintain a register of authorized persons
• Regular audit of project specific operation of LOTO
AUTHORISED ENGINEERS
• Acknowledge Lock Out / Tag Out
• Understand the Lock Out / Tag Out
• Implement and monitor the Lock Out / Tag Out
• Issue permits and ensure receivers understand requirements of
the Lock Out / Tag Out
• Check on training/induction status of permit receivers
• Close-out permits
COMPETENT PERSONS
• Acknowledge the Lock Out / Tag Out
• Understand the requirements of the system of work
• Implement and comply with the Lock Out / Tag Out
This is a formalized written procedure for the control of
high voltage systems or complex low voltage systems.
Authorised Engineers in control of works on electrical system
A log of all switching operations
Safe and secure isolation
Issue of permit to work/test/access
Mimic diagram for safe switching/operation
Connection of supplies
Formal handover/return of electrical system
Safe supply to third parties
Control of Keys to Electrical Areas and Isolations
Live Panels with Locks
Key Locker
All keys and
padlocks
Kept here when
not in use
Key Safe
Key safe contains keys to
restricted access areas
Keys to key lockers
Keys to padlocks which
are fitted to system while
work in progress
AP has only key to key safe
Control of Keys to Electrical Areas and Isolations
Generator with signages
LV ROOM Live Panels with Locks
Emergency Number
Generator with
Overhead protection
Generator’s Emergency
Button
EHS Manager provided LOTO
training to all operatives including
supervisor and safety.
A permanently displayed single line diagram showing the electrical
system (LV system). The diagram will be displayed in the “permit office”
and relevant switch room. The status of switches, circuit breakers and
isolators will be indicated by means of colored pins.
 RED WILL DENOTE SWITCH ON
 GREEN WILL DENOTE SWITCH OFF
 BLUE WILL DENOTE SWITCH EARTHED
Mimic Diagrams
When switching off a
circuit, carry out the
switching first
then alter the diagram
When switching on a
circuit, alter the diagram
first
then carry out the
switching operation
Always display
“work on system in
progress”
notice when
carrying out
switching
operations
Maintaining Site Log / permit Book
The site log book must have the following
• Switching operations log
sheet
• Permit to Work Log Sheet
(This will involved switching operations)
• Sanction for test Log Sheet
(This will involved Testing , after energized)
• Limitation of Access Log Sheet
(This will not any switching Operation & only provide
access to energized room (Cleaning, Civil Works, etc.))
Maintaining Site Log/ permit Book
The Site Permit book has the following
• Cancelled Permits-To-Work
• On Issue Permits-To-Work
• Request for Electrical Power
RECORD IN LOG BOOK DETAILS OF THE INTENDED SWITCHING OPERATIONS AND
OTHER SAFETY MEASURES
DISPLAY THE “WORK ON LV SYSTEM IN PROGRESS” NOTICE ON THE MIMIC
DIAGRAM
ISOLATE THE SYSTEM AND CARRY OUT TESTS TO ENSURE CONDUCTORS AND
EQUIPMENT IS DEAD
APPLY LOCKS OR OTHER ADEQUATE MEANS OF MAINTAINING THE INTEGRITY OF
ISOLATION
FIX SAFETY AND CAUTION NOTICES, BARRIERS / EXCLUSION ZONES
TEST TO ENSURE POINT OF WORK IS DEAD. PROVE TEST INSTRUMENT BEFORE
AND AFTER TEST
ALTER MIMIC DIAGRAM TO SHOW THE EXACT STATE OF THE SWITCHES
ENSURE COMPETENT PERSON IS CONVERSANT WITH WORK TO BE CARRIED OUT
Safe Isolation
Safe Isolation
Permit-to-Work
A document issued by an
Authorised Person to a Competent
Person, under signature, defining a
safe system of work which includes
switching operations and other
measures that have been carried
out to ensure that the risks from the
systems are minimised.
It also details the work to be carried
out and any further precautions
required to be observed by the
Competent Person and men under
his control.
Part 1 Issue
Authorized person enters details
system/area & particular work to
be carried out
Part 2 Receipt
Competent person signs to
confirm understanding of the
permit and its limitations.
Accepting responsibility for
carrying out the work on
Part 3 Clearance
On completion of work, the
competent person signs for
clearance and returns it to the
authorized person for close out.
Part 4 Cancellation
Cancellation is done by
authorized person.
 Complete part 1 of permit giving full details of precautions
taken to make equipment safe. Also write exact details of work
to be carried out. (LOTO AP)
 Ensure that competent person in charge of work fully
understands the instructions and acknowledges receipt by
signing part 2 of the permit. explain to the competent person
the rules on the back of the permit. (LOTO AP)
 Top white copy kept in the site permit book. (LOTO AP)
 2nd copy issued to competent person. (LOTO AP)
 The competent person shall retain the 2nd copy in his
possession at all times while the work is being carried out.
(Competent Person)
 A permit will be issued to the competent person in charge of
each working party. The fact that other permits are in use will
be indicated in the permit log giving the serial numbers of other
permits issued. (LOTO AP)
 Any change in scope of work will require cancellation of permit
Permit Issue
 When work is suspended or completed the competent person
shall sign part 3 ‘clearance’ and return permit to the
authorized person. (Competent Person)
 Permit will be cancelled by authorized person by signing part
4. Note - both copies to come together before signing part 4.
(LOTO AP)
 Both copies will be retained as a permanent record by
authorized person and filed in the site permit book. (LOTO
AP)
 Where multiple permits have been issued ensure all permits
have been cancelled before main circuit earths are removed or
power re-established. (LOTO AP)
Permit Cancellation
 Third party must supply inspection/test sheets confirming
plant/equipment safe to energies. (RCC/AGCCIC 3rd Party
Subcontractors)
 Request for electrical power form to be signed by RCC/AGCCIC and
third party in all cases.
 Joint inspection of third party plant/equipment before energization.
 Details of third party safe system of controlling power to be filed in
the project site safety plan.
The Authorizing Engineer will detail in the method statement,
the procedures to be followed in the event of an incident or
emergency.
Including as a minimum:
• Contacts for help (Contact Details are mentioned all over site)
• Means of communication
• Address and phone number of first aid
facility/hospital
LOTO Team
Project LOTO Appointed Person
• Irfan – Mobile 056-4630001
Authorized Engineers
• Muhammad El Shazli – Mobile 055-1492958
• Vinod Babu – Mobile 050-8350564
• Safvan _ Mobile 054-3670077
AGCCIC HSE HOTLINE 052 6418190
Emergency push buttons in LOTO
permit office
OPERATION ONLY BY
AUTHORIZED ENGINEER
LV 1 Main DB with Lock.
Generator Incomer Cables with 3rd party Certificate
Ground Level
Overhead Protection Provided, Signs Posted, Fire
Extinguisher kept, Emergency Numbers Provided,
Trained Operator, Generator Details Posted.
Generator Incomer Cables with Safety Signs & Operator 3rd party Training Certificate
Ground Level
TEMP POWER SCHEMATIC:
ENERGIZATION-LOGISTIC PLAN
TEMPORARY POWER LAYOUT:
TEMPORARY POWER LAYOUT:
SCHEMATIC DIAGRAM OF ENERGIZED AREA
SCHEMATIC DIAGRAM OF ENERGIZED AREA
LOCK OUT TAG OUT MATRIX
Loto presentation.pptx

More Related Content

Similar to Loto presentation.pptx

Loto presentation
Loto presentationLoto presentation
Loto presentation
LalitSharma508
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
HENRY EROMOSELE OIGIANGBE
 
Important of issuing the PTW for safety .pdf
Important of issuing the PTW for safety .pdfImportant of issuing the PTW for safety .pdf
Important of issuing the PTW for safety .pdf
RazFazwan
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AhmadNadzir4
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
CM Tiwari
 
Electricallockoutsop 717
Electricallockoutsop 717Electricallockoutsop 717
Electricallockoutsop 717
MUHAMMAD ISHFAQ
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagout
Noel Regalado
 
LOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptxLOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptx
Nigel Brown
 
Lockout Tagout.ppt
Lockout Tagout.pptLockout Tagout.ppt
Lockout Tagout.ppt
mohammadillias
 
Lockout/Tag Out
Lockout/Tag OutLockout/Tag Out
Lockout/Tag Out
Tristan Hart
 
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdfPRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
Okeke Livinus
 
Main distribution board (mdb) testing and commissioning field instrumentati...
Main distribution board (mdb) testing and commissioning   field instrumentati...Main distribution board (mdb) testing and commissioning   field instrumentati...
Main distribution board (mdb) testing and commissioning field instrumentati...
Multidisciplinary consulting and engineering firm
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
Mark Platten
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIE
damian Filip
 
Weeks 16 17 pe 3231 maintenance and fault finding
Weeks 16 17  pe 3231 maintenance and fault findingWeeks 16 17  pe 3231 maintenance and fault finding
Weeks 16 17 pe 3231 maintenance and fault finding
Charlton Inao
 
Loto basics.
Loto basics.Loto basics.
Loto online slides
Loto online slidesLoto online slides
Loto online slides
Tabatha Dorman
 
Loto.pptx
Loto.pptxLoto.pptx
Loto.pptx
ROHITSINGH83692
 
LOTO
LOTO LOTO
26_SGW-_Permit_To_Work- At Job Site.pptx
26_SGW-_Permit_To_Work- At Job Site.pptx26_SGW-_Permit_To_Work- At Job Site.pptx
26_SGW-_Permit_To_Work- At Job Site.pptx
safetygoodwe
 

Similar to Loto presentation.pptx (20)

Loto presentation
Loto presentationLoto presentation
Loto presentation
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
 
Important of issuing the PTW for safety .pdf
Important of issuing the PTW for safety .pdfImportant of issuing the PTW for safety .pdf
Important of issuing the PTW for safety .pdf
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
 
Electricallockoutsop 717
Electricallockoutsop 717Electricallockoutsop 717
Electricallockoutsop 717
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagout
 
LOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptxLOTO 2022 - Energy Isolation Process .pptx
LOTO 2022 - Energy Isolation Process .pptx
 
Lockout Tagout.ppt
Lockout Tagout.pptLockout Tagout.ppt
Lockout Tagout.ppt
 
Lockout/Tag Out
Lockout/Tag OutLockout/Tag Out
Lockout/Tag Out
 
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdfPRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdf
 
Main distribution board (mdb) testing and commissioning field instrumentati...
Main distribution board (mdb) testing and commissioning   field instrumentati...Main distribution board (mdb) testing and commissioning   field instrumentati...
Main distribution board (mdb) testing and commissioning field instrumentati...
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIE
 
Weeks 16 17 pe 3231 maintenance and fault finding
Weeks 16 17  pe 3231 maintenance and fault findingWeeks 16 17  pe 3231 maintenance and fault finding
Weeks 16 17 pe 3231 maintenance and fault finding
 
Loto basics.
Loto basics.Loto basics.
Loto basics.
 
Loto online slides
Loto online slidesLoto online slides
Loto online slides
 
Loto.pptx
Loto.pptxLoto.pptx
Loto.pptx
 
LOTO
LOTO LOTO
LOTO
 
26_SGW-_Permit_To_Work- At Job Site.pptx
26_SGW-_Permit_To_Work- At Job Site.pptx26_SGW-_Permit_To_Work- At Job Site.pptx
26_SGW-_Permit_To_Work- At Job Site.pptx
 

Recently uploaded

Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
MysoreMuleSoftMeetup
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
Celine George
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
Katrina Pritchard
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
deepaannamalai16
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
National Information Standards Organization (NISO)
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
RamseyBerglund
 
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
National Information Standards Organization (NISO)
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
Nguyen Thanh Tu Collection
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
ssuser13ffe4
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
RidwanHassanYusuf
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 

Recently uploaded (20)

Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
 
How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17How to Make a Field Mandatory in Odoo 17
How to Make a Field Mandatory in Odoo 17
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
 
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
 
math operations ued in python and all used
math operations ued in python and all usedmath operations ued in python and all used
math operations ued in python and all used
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 

Loto presentation.pptx

  • 1. Opera Grand Tower Project, Downtown Dubai Employer: Project Management: Lead Consultant: Main Contractor: MEP Contractor Live Panels with Locks Live Bus bars with Locks
  • 2.  LOTO - Brief Introduction  Project Organizational Arrangements  Responsibilities  Permit control System  Authorized Person Responsibilities  Permit Types  Permit Process  Supply to Third Parties  Emergency Procedures Live Panels with Locks
  • 3. The purpose of the RCC Lock Out / Tag Out Procedures are to ensure that where employees and others, are exposed to work situations that carry a risk of • Electrical shock • Electrocution • Electrical burns • Fire • Explosion that the work situation is assessed and that suitable control measures' and systems are implemented to ensure that electrical risks / hazards are removed or reduced as far as reasonably practicable. The ‘Lock Out / Tag Out’ procedure is implemented in situations where a part of the Electrical System has been made LIVE before the work on the system has been completed and RCC has assumed the role of ‘Duty Holder’ for the installation. The electrical system energized rooms keys will be under the control of RCC, permit system to be followed to work in the rooms by all parties.
  • 4. •Project LOTO Appointed Person MD Irfan (ELT Supervisor) Site LOTO Execution Team Authorized Engineer Eng Safvan Competent Persons Trained/Competent Electrical Team
  • 5. Authorized Project Manager • Overviews company’s Lock Out / Tag Out requirements • Appoints Project Authorizing Engineers • Overall responsibility for the LOTO system • Periodic audit of complete company/project LOTO procedures Project LOTO Appointed Person Appointed by the Authorizing Manager is responsible for • Assessment of project specific LOTO procedures • Accept duty holder responsibilities for electrical system for RCC • Implementation of appropriate Lock Out / Tag Out procedures • Assessment and appointments of authorized persons • Maintain a register of authorized persons • Regular audit of project specific operation of LOTO
  • 6. AUTHORISED ENGINEERS • Acknowledge Lock Out / Tag Out • Understand the Lock Out / Tag Out • Implement and monitor the Lock Out / Tag Out • Issue permits and ensure receivers understand requirements of the Lock Out / Tag Out • Check on training/induction status of permit receivers • Close-out permits COMPETENT PERSONS • Acknowledge the Lock Out / Tag Out • Understand the requirements of the system of work • Implement and comply with the Lock Out / Tag Out
  • 7. This is a formalized written procedure for the control of high voltage systems or complex low voltage systems. Authorised Engineers in control of works on electrical system A log of all switching operations Safe and secure isolation Issue of permit to work/test/access Mimic diagram for safe switching/operation Connection of supplies Formal handover/return of electrical system Safe supply to third parties
  • 8. Control of Keys to Electrical Areas and Isolations Live Panels with Locks
  • 9. Key Locker All keys and padlocks Kept here when not in use Key Safe Key safe contains keys to restricted access areas Keys to key lockers Keys to padlocks which are fitted to system while work in progress AP has only key to key safe Control of Keys to Electrical Areas and Isolations
  • 10.
  • 11. Generator with signages LV ROOM Live Panels with Locks Emergency Number Generator with Overhead protection Generator’s Emergency Button
  • 12. EHS Manager provided LOTO training to all operatives including supervisor and safety.
  • 13. A permanently displayed single line diagram showing the electrical system (LV system). The diagram will be displayed in the “permit office” and relevant switch room. The status of switches, circuit breakers and isolators will be indicated by means of colored pins.  RED WILL DENOTE SWITCH ON  GREEN WILL DENOTE SWITCH OFF  BLUE WILL DENOTE SWITCH EARTHED Mimic Diagrams When switching off a circuit, carry out the switching first then alter the diagram When switching on a circuit, alter the diagram first then carry out the switching operation Always display “work on system in progress” notice when carrying out switching operations
  • 14. Maintaining Site Log / permit Book The site log book must have the following • Switching operations log sheet • Permit to Work Log Sheet (This will involved switching operations) • Sanction for test Log Sheet (This will involved Testing , after energized) • Limitation of Access Log Sheet (This will not any switching Operation & only provide access to energized room (Cleaning, Civil Works, etc.))
  • 15. Maintaining Site Log/ permit Book The Site Permit book has the following • Cancelled Permits-To-Work • On Issue Permits-To-Work • Request for Electrical Power
  • 16. RECORD IN LOG BOOK DETAILS OF THE INTENDED SWITCHING OPERATIONS AND OTHER SAFETY MEASURES DISPLAY THE “WORK ON LV SYSTEM IN PROGRESS” NOTICE ON THE MIMIC DIAGRAM ISOLATE THE SYSTEM AND CARRY OUT TESTS TO ENSURE CONDUCTORS AND EQUIPMENT IS DEAD APPLY LOCKS OR OTHER ADEQUATE MEANS OF MAINTAINING THE INTEGRITY OF ISOLATION FIX SAFETY AND CAUTION NOTICES, BARRIERS / EXCLUSION ZONES TEST TO ENSURE POINT OF WORK IS DEAD. PROVE TEST INSTRUMENT BEFORE AND AFTER TEST ALTER MIMIC DIAGRAM TO SHOW THE EXACT STATE OF THE SWITCHES ENSURE COMPETENT PERSON IS CONVERSANT WITH WORK TO BE CARRIED OUT Safe Isolation
  • 18.
  • 19.
  • 20. Permit-to-Work A document issued by an Authorised Person to a Competent Person, under signature, defining a safe system of work which includes switching operations and other measures that have been carried out to ensure that the risks from the systems are minimised. It also details the work to be carried out and any further precautions required to be observed by the Competent Person and men under his control.
  • 21. Part 1 Issue Authorized person enters details system/area & particular work to be carried out Part 2 Receipt Competent person signs to confirm understanding of the permit and its limitations. Accepting responsibility for carrying out the work on Part 3 Clearance On completion of work, the competent person signs for clearance and returns it to the authorized person for close out. Part 4 Cancellation Cancellation is done by authorized person.
  • 22.  Complete part 1 of permit giving full details of precautions taken to make equipment safe. Also write exact details of work to be carried out. (LOTO AP)  Ensure that competent person in charge of work fully understands the instructions and acknowledges receipt by signing part 2 of the permit. explain to the competent person the rules on the back of the permit. (LOTO AP)  Top white copy kept in the site permit book. (LOTO AP)  2nd copy issued to competent person. (LOTO AP)  The competent person shall retain the 2nd copy in his possession at all times while the work is being carried out. (Competent Person)  A permit will be issued to the competent person in charge of each working party. The fact that other permits are in use will be indicated in the permit log giving the serial numbers of other permits issued. (LOTO AP)  Any change in scope of work will require cancellation of permit Permit Issue
  • 23.  When work is suspended or completed the competent person shall sign part 3 ‘clearance’ and return permit to the authorized person. (Competent Person)  Permit will be cancelled by authorized person by signing part 4. Note - both copies to come together before signing part 4. (LOTO AP)  Both copies will be retained as a permanent record by authorized person and filed in the site permit book. (LOTO AP)  Where multiple permits have been issued ensure all permits have been cancelled before main circuit earths are removed or power re-established. (LOTO AP) Permit Cancellation
  • 24.  Third party must supply inspection/test sheets confirming plant/equipment safe to energies. (RCC/AGCCIC 3rd Party Subcontractors)  Request for electrical power form to be signed by RCC/AGCCIC and third party in all cases.  Joint inspection of third party plant/equipment before energization.  Details of third party safe system of controlling power to be filed in the project site safety plan.
  • 25. The Authorizing Engineer will detail in the method statement, the procedures to be followed in the event of an incident or emergency. Including as a minimum: • Contacts for help (Contact Details are mentioned all over site) • Means of communication • Address and phone number of first aid facility/hospital
  • 26. LOTO Team Project LOTO Appointed Person • Irfan – Mobile 056-4630001 Authorized Engineers • Muhammad El Shazli – Mobile 055-1492958 • Vinod Babu – Mobile 050-8350564 • Safvan _ Mobile 054-3670077 AGCCIC HSE HOTLINE 052 6418190
  • 27. Emergency push buttons in LOTO permit office OPERATION ONLY BY AUTHORIZED ENGINEER LV 1 Main DB with Lock.
  • 28. Generator Incomer Cables with 3rd party Certificate Ground Level Overhead Protection Provided, Signs Posted, Fire Extinguisher kept, Emergency Numbers Provided, Trained Operator, Generator Details Posted.
  • 29. Generator Incomer Cables with Safety Signs & Operator 3rd party Training Certificate Ground Level
  • 33. SCHEMATIC DIAGRAM OF ENERGIZED AREA
  • 34. SCHEMATIC DIAGRAM OF ENERGIZED AREA
  • 35. LOCK OUT TAG OUT MATRIX