The document outlines lock out tag out (LOTO) procedures for electrical work on the Opera Grand Tower Project in Downtown Dubai. It assigns responsibilities for the LOTO system and describes permit requirements and processes. Key elements include appointing authorized engineers and competent persons, implementing safe isolation procedures before work, maintaining a permit log book, and having emergency response plans and contact details. The goal is to ensure electrical hazards are controlled whenever employees or others could be exposed to risks like electric shock or burns during work.
This document discusses permit to work (PTW) and lock out tag out (LOTO) training. It includes questions about energy sources, energy isolation, lock out devices, tag out devices, and the potential consequences of not following LOTO procedures. It also discusses the roles and responsibilities in a PTW system including the permit issuer, originator, acceptor, user, area authority, and site checker. Key steps in developing a LOTO program and performing energy isolation are also outlined.
The document discusses permit to work (PTW) procedures at an NGI training center. It defines what a PTW is, its purpose of ensuring work is planned and hazards identified, and that it is a legal document. It describes what types of work require a PTW, including hot work and cold work. It outlines the PTW process including initiation, authorization, cancellation. It defines roles and responsibilities of personnel involved in the PTW process. Finally, it discusses complementary permits that may be required for different types of work, such as electrical isolation or confined space entry.
The document outlines AHEC's Lock Out Tag Out (LOTO) program. It describes LOTO as procedures to prevent accidental startup of equipment being serviced and ensure stored energy cannot be released. The program requires written energy control procedures, documented training, periodic inspections, and compliance with OSHA's LOTO standard. Supervisors are responsible for equipment-specific LOTO procedures and affected employees must be trained and follow all procedures.
This document discusses procedures for loop checking and field instrument testing. It suggests developing standardized procedures to make the process more efficient. Specifically, it proposes: [1] Having a common guideline procedure for loop checking. [2] Illustrating all required drawings, specifications and forms. [3] Creating a flow chart illustrating the process. The comments provide examples of procedures companies use and emphasize the importance of documentation.
Work permit system, By Bimal Chandra Das, safety management, safety tips, sharing of safety knowledge, It is sharing of knowledge. By Bimal Chandra Das, Rtd. AGM (Safety), Bokaro Steel Plant,/ Bokaro. Kolkata
The document discusses the purpose and procedures of a work permit system. It is intended to ensure that all work is carried out safely by defining responsibilities, requiring appropriate training, and providing safety equipment. A work permit specifies the conditions and safety procedures that must be followed for particular jobs. It is required for non-routine and hazardous routine work, and when third parties are involved. A work permit must be prepared with relevant parties and approved before work begins to ensure all hazards are addressed.
This document outlines the lockout/tagout (LOTO) energy control program. LOTO procedures are designed to prevent injuries during service or maintenance by controlling hazardous energy. Lockout uses locks to isolate energy sources and keep equipment from starting, while tagout uses tags to warn others that the equipment is being serviced. The program defines roles like authorized workers who perform lockout and affected workers in the area. It provides requirements for energy control procedures, training, and program evaluation to ensure personnel safety during maintenance or repair of equipment.
The document outlines the key aspects of a permit to work (PTW) system, including:
1) The PTW system controls and executes potentially hazardous jobs through a formal written process and serves as communication between departments on job safety.
2) Permit issuers and receivers must be trained and authorized based on their experience and knowledge of job hazards. They are responsible for providing a safe work environment.
3) The roles and responsibilities of issuers, receivers, safety officers, and management are defined to ensure jobs are properly planned, hazards are identified, and safety is maintained and overseen.
This document discusses permit to work (PTW) and lock out tag out (LOTO) training. It includes questions about energy sources, energy isolation, lock out devices, tag out devices, and the potential consequences of not following LOTO procedures. It also discusses the roles and responsibilities in a PTW system including the permit issuer, originator, acceptor, user, area authority, and site checker. Key steps in developing a LOTO program and performing energy isolation are also outlined.
The document discusses permit to work (PTW) procedures at an NGI training center. It defines what a PTW is, its purpose of ensuring work is planned and hazards identified, and that it is a legal document. It describes what types of work require a PTW, including hot work and cold work. It outlines the PTW process including initiation, authorization, cancellation. It defines roles and responsibilities of personnel involved in the PTW process. Finally, it discusses complementary permits that may be required for different types of work, such as electrical isolation or confined space entry.
The document outlines AHEC's Lock Out Tag Out (LOTO) program. It describes LOTO as procedures to prevent accidental startup of equipment being serviced and ensure stored energy cannot be released. The program requires written energy control procedures, documented training, periodic inspections, and compliance with OSHA's LOTO standard. Supervisors are responsible for equipment-specific LOTO procedures and affected employees must be trained and follow all procedures.
This document discusses procedures for loop checking and field instrument testing. It suggests developing standardized procedures to make the process more efficient. Specifically, it proposes: [1] Having a common guideline procedure for loop checking. [2] Illustrating all required drawings, specifications and forms. [3] Creating a flow chart illustrating the process. The comments provide examples of procedures companies use and emphasize the importance of documentation.
Work permit system, By Bimal Chandra Das, safety management, safety tips, sharing of safety knowledge, It is sharing of knowledge. By Bimal Chandra Das, Rtd. AGM (Safety), Bokaro Steel Plant,/ Bokaro. Kolkata
The document discusses the purpose and procedures of a work permit system. It is intended to ensure that all work is carried out safely by defining responsibilities, requiring appropriate training, and providing safety equipment. A work permit specifies the conditions and safety procedures that must be followed for particular jobs. It is required for non-routine and hazardous routine work, and when third parties are involved. A work permit must be prepared with relevant parties and approved before work begins to ensure all hazards are addressed.
This document outlines the lockout/tagout (LOTO) energy control program. LOTO procedures are designed to prevent injuries during service or maintenance by controlling hazardous energy. Lockout uses locks to isolate energy sources and keep equipment from starting, while tagout uses tags to warn others that the equipment is being serviced. The program defines roles like authorized workers who perform lockout and affected workers in the area. It provides requirements for energy control procedures, training, and program evaluation to ensure personnel safety during maintenance or repair of equipment.
The document outlines the key aspects of a permit to work (PTW) system, including:
1) The PTW system controls and executes potentially hazardous jobs through a formal written process and serves as communication between departments on job safety.
2) Permit issuers and receivers must be trained and authorized based on their experience and knowledge of job hazards. They are responsible for providing a safe work environment.
3) The roles and responsibilities of issuers, receivers, safety officers, and management are defined to ensure jobs are properly planned, hazards are identified, and safety is maintained and overseen.
1. Lock out tag out (LOTO) procedures are used to safeguard workers during service or maintenance of machines and equipment by isolating hazardous energy sources.
2. LOTO is required when employees could be harmed by equipment startup or release of stored energy while working on or near machines. It involves shutting down and isolating equipment, then locking out energy sources and attaching warning tags.
3. Proper LOTO procedures include preparing for the job, shutting down and isolating equipment, applying locks and tags, relieving stored energy, verifying isolation, getting approval before re-energizing, informing workers, and periodic inspections.
Important of issuing the PTW for safety .pdfRazFazwan
The document discusses work permits in construction. It defines a work permit as a written authorization for jobs involving serious hazards. Work permits identify the work, hazards, and necessary precautions. Key points made include:
- Work permits communicate job details and identify related hazards to minimize risks.
- Major works requiring permits include inspection, construction, hot work, and confined space entry.
- The permit procedure involves an issuer authorizing the permit after inspection, a receiver overseeing the work, and cancellation upon completion.
- Non-compliance can occur if permits are invalid or workers don't understand the system. Safety watches also monitor hazards and alert workers.
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAhmadNadzir4
1. The document describes a work permit system which consists of standard procedures to ensure potentially hazardous routine and non-routine work is carried out safely.
2. A work permit specifies the work to be done, authorizes its start, and requires agreement of all concerned parties after reviewing safety measures.
3. A work permit is required for work involving hazards like oxygen deficiency, fires, chemicals, or confined spaces and for non-routine, hazardous routine works or those done by contractors.
Lock Out Tag Out (LOTO) is an important safety procedure to prevent unexpected startup of machines and equipment during service or maintenance. It involves shutting down and isolating machines, applying personal lockout devices, releasing stored energy, and verifying isolation before work. The six key steps are: 1) prepare for shutdown, 2) shutdown equipment, 3) isolate energy sources, 4) apply locks and tags, 5) release stored energy, and 6) verify isolation. Proper LOTO training and compliance is needed to protect authorized and affected employees from hazardous energy during service and maintenance work.
This document outlines lockout/tagout safety procedures for maintenance and construction personnel at Raytheon Polar Services Company stations. It describes responsibilities, definitions, requirements, and procedures for locking and tagging out electrical devices to prevent energization during service or maintenance. The procedures supplement the company's lockout/tagout program and provide specific guidance for locking out equipment to ensure worker safety.
This document outlines an organization's Lock Out Tag Out (LOTO) program. It discusses the importance of LOTO for preventing injuries from unexpected energy releases. It details OSHA's LOTO standard and requirements for the program including: written procedures, employee training, inspections, responsibilities, hazardous energy sources, lock and tag requirements. The program requirements cover preparing for lockout, applying locks/tags, releasing stored energy, removing locks/restoring equipment, exceptions, equipment specific procedures, periodic inspections, and assistance resources.
LOTO 2022 - Energy Isolation Process .pptxNigel Brown
The document discusses lockout/tagout (LOTO) procedures for energy isolation. It covers the following key points in 3 sentences:
The LOTO process exists to protect workers from hazardous energy sources on equipment through controlling energy isolation. It outlines identifying energy sources, applying locks and tags to energy isolating devices to prevent accidental startup, and procedures for removing locks and tags after work is complete. The document provides guidance on LOTO application steps, requirements for employee training, contractors, examples of energy isolating devices, and ensuring locks can be applied to safely isolate hazardous energy.
This document outlines lockout/tagout procedures for isolating hazardous energy sources during maintenance and construction activities. It discusses:
- Roles and responsibilities of approving, issuing, and isolation authorities
- Procedure for isolating electrical, mechanical, pressure, and other energy sources, including using locks and tags
- Requirements for completing lockout logs and obtaining approvals before removing locks
- Specific procedures for isolating electrical systems, mechanical equipment, and other energy sources like pipes and valves
The document discusses Graves Construction's lockout/tagout (LOTO) safety training. It defines LOTO as blocking energy from power sources to equipment using locks and tags to warn of the disconnection. The training covers regulatory requirements, types of lockout devices, energy sources requiring LOTO, typical equipment, responsibilities of authorized employees who perform work, affected employees who operate equipment, supervisors, and the company, as well as procedures for performing LOTO safely. Training is required for authorized and affected employees initially and annually or when procedures change.
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdfOkeke Livinus
The document provides guidance on energy isolation procedures at Seqwater workplaces. It outlines:
1. Critical and additional controls for energy isolations including requirements for isolation instructions, verification of isolations, and different types of isolations.
2. Who can perform isolations including requirements for authorised isolators and isolation officers.
3. Procedures for planning isolations, developing isolation instructions, performing simple, complex and tiered isolations.
4. Requirements for verifying isolations are effective, handing over isolated plant, breaking and resuming work, and removing isolations.
The document discusses the testing and commissioning process for a Main Distribution Board (MDB). It describes three key cases for testing the MDB: 1) Testing only the interconnecting cables between transformers and MDBs which involves physical inspection, Megger testing, and energizing the panel while recording readings. 2) Repeating the steps from case 1 for all cables coming to the panel. 3) Additional steps that must be taken like inspections and permitting when work is being done on cables connected to an upstream panel to minimize shutdowns.
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
This document provides an overview of safety systems and procedures for mechanical and electrical work on a construction project. It summarizes SEE Group's approach to risk management, which includes daily safe start briefings, safe working rules, permit systems for high-risk work, isolation procedures, pressure testing, hot work permits, and COSHH assessments. Safety topics such as housekeeping, inspections, working at height, and accreditations are also addressed.
This curriculum vitae outlines the work experience and qualifications of Damian Filip, a Romanian instrumentation supervisor. Over 30 years of experience includes positions in Kazakhstan, Belgium, Scotland, Azerbaijan, Nigeria, Canada, and Romania working on projects in oil refineries, chemical plants, and other industrial facilities. Responsibilities included loop checking, commissioning, calibration, and maintenance of instrumentation systems.
Weeks 16 17 pe 3231 maintenance and fault findingCharlton Inao
Prof. Charlton S. Inao provides documentation on PLC systems, including internal relays, SET and RESET functions, shift registers, common causes of faults, fault finding, maintenance, and installation/commissioning. The document covers topics like how internal relays in a PLC simulate physical relays using bits, examples of SET and RESET functions, examples of shift registers in different PLC systems, common causes of PLC faults like environment and electrical design, steps for fault finding and maintenance including checking voltages, backups, and updates.
This document provides an overview of lockout/tagout (LOTO) procedures for machine operators. LOTO is done to isolate all energy sources to equipment during maintenance, cleaning, or other activities where guards are removed. It prevents accidental startup of machines and injury. The document explains why LOTO is important for safety, types of energy sources, proper use of locks and tags, process steps for applying and removing LOTO, and shift changeover procedures. Training boards and examples of LOTO devices are also shown.
Failure to properly de-energize equipment results in over 120 fatalities and 50,000 injuries annually according to OSHA. The document discusses energy sources that can be present, affected vs authorized employees, lockout/tagout procedures and safety, typical lockout/tagout procedures, prohibited actions, lockout/tagout devices, locks, and requirements for contractors and vendors. A proper lockout/tagout procedure is critical for safely servicing, maintaining or repairing equipment.
This document discusses lockout/tagout (LOTO) procedures for controlling hazardous energy sources. It covers:
1. The purpose of LOTO is to prevent injuries from unexpected equipment energization, start-up, or release of stored energy during maintenance or service.
2. LOTO requirements include written procedures, employee training, locks/tags, and procedures for isolating all types of hazardous energy sources such as electrical, mechanical, chemical, thermal, hydraulic, and pneumatic.
3. The 6 steps of the LOTO procedure are: prepare for shutdown, shutdown equipment, isolate all energy sources, apply locks and tags, release stored energy, and verify isolation before starting work. Positive isolation of all
This document discusses lockout/tagout (LOTO) procedures for controlling hazardous energy sources. It covers the purpose of LOTO, which is to prevent injuries from unexpected equipment energization. Requirements include written procedures, training, locks/tags, and verifying isolation. Hazardous energy types are electrical, mechanical, chemical, thermal, hydraulic, and pneumatic. The 6-step LOTO procedure is outlined as preparing for shutdown, shutting down equipment, isolating energy sources, placing locks and tags, releasing stored energy, and verifying isolation. Stored energy must be assessed and relieved before work. Only authorized employees who have gone through training can perform LOTO procedures.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
1. Lock out tag out (LOTO) procedures are used to safeguard workers during service or maintenance of machines and equipment by isolating hazardous energy sources.
2. LOTO is required when employees could be harmed by equipment startup or release of stored energy while working on or near machines. It involves shutting down and isolating equipment, then locking out energy sources and attaching warning tags.
3. Proper LOTO procedures include preparing for the job, shutting down and isolating equipment, applying locks and tags, relieving stored energy, verifying isolation, getting approval before re-energizing, informing workers, and periodic inspections.
Important of issuing the PTW for safety .pdfRazFazwan
The document discusses work permits in construction. It defines a work permit as a written authorization for jobs involving serious hazards. Work permits identify the work, hazards, and necessary precautions. Key points made include:
- Work permits communicate job details and identify related hazards to minimize risks.
- Major works requiring permits include inspection, construction, hot work, and confined space entry.
- The permit procedure involves an issuer authorizing the permit after inspection, a receiver overseeing the work, and cancellation upon completion.
- Non-compliance can occur if permits are invalid or workers don't understand the system. Safety watches also monitor hazards and alert workers.
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAhmadNadzir4
1. The document describes a work permit system which consists of standard procedures to ensure potentially hazardous routine and non-routine work is carried out safely.
2. A work permit specifies the work to be done, authorizes its start, and requires agreement of all concerned parties after reviewing safety measures.
3. A work permit is required for work involving hazards like oxygen deficiency, fires, chemicals, or confined spaces and for non-routine, hazardous routine works or those done by contractors.
Lock Out Tag Out (LOTO) is an important safety procedure to prevent unexpected startup of machines and equipment during service or maintenance. It involves shutting down and isolating machines, applying personal lockout devices, releasing stored energy, and verifying isolation before work. The six key steps are: 1) prepare for shutdown, 2) shutdown equipment, 3) isolate energy sources, 4) apply locks and tags, 5) release stored energy, and 6) verify isolation. Proper LOTO training and compliance is needed to protect authorized and affected employees from hazardous energy during service and maintenance work.
This document outlines lockout/tagout safety procedures for maintenance and construction personnel at Raytheon Polar Services Company stations. It describes responsibilities, definitions, requirements, and procedures for locking and tagging out electrical devices to prevent energization during service or maintenance. The procedures supplement the company's lockout/tagout program and provide specific guidance for locking out equipment to ensure worker safety.
This document outlines an organization's Lock Out Tag Out (LOTO) program. It discusses the importance of LOTO for preventing injuries from unexpected energy releases. It details OSHA's LOTO standard and requirements for the program including: written procedures, employee training, inspections, responsibilities, hazardous energy sources, lock and tag requirements. The program requirements cover preparing for lockout, applying locks/tags, releasing stored energy, removing locks/restoring equipment, exceptions, equipment specific procedures, periodic inspections, and assistance resources.
LOTO 2022 - Energy Isolation Process .pptxNigel Brown
The document discusses lockout/tagout (LOTO) procedures for energy isolation. It covers the following key points in 3 sentences:
The LOTO process exists to protect workers from hazardous energy sources on equipment through controlling energy isolation. It outlines identifying energy sources, applying locks and tags to energy isolating devices to prevent accidental startup, and procedures for removing locks and tags after work is complete. The document provides guidance on LOTO application steps, requirements for employee training, contractors, examples of energy isolating devices, and ensuring locks can be applied to safely isolate hazardous energy.
This document outlines lockout/tagout procedures for isolating hazardous energy sources during maintenance and construction activities. It discusses:
- Roles and responsibilities of approving, issuing, and isolation authorities
- Procedure for isolating electrical, mechanical, pressure, and other energy sources, including using locks and tags
- Requirements for completing lockout logs and obtaining approvals before removing locks
- Specific procedures for isolating electrical systems, mechanical equipment, and other energy sources like pipes and valves
The document discusses Graves Construction's lockout/tagout (LOTO) safety training. It defines LOTO as blocking energy from power sources to equipment using locks and tags to warn of the disconnection. The training covers regulatory requirements, types of lockout devices, energy sources requiring LOTO, typical equipment, responsibilities of authorized employees who perform work, affected employees who operate equipment, supervisors, and the company, as well as procedures for performing LOTO safely. Training is required for authorized and affected employees initially and annually or when procedures change.
PRO-00014 Corporate Safety - Energy Tag and Lockout Procedure.pdfOkeke Livinus
The document provides guidance on energy isolation procedures at Seqwater workplaces. It outlines:
1. Critical and additional controls for energy isolations including requirements for isolation instructions, verification of isolations, and different types of isolations.
2. Who can perform isolations including requirements for authorised isolators and isolation officers.
3. Procedures for planning isolations, developing isolation instructions, performing simple, complex and tiered isolations.
4. Requirements for verifying isolations are effective, handing over isolated plant, breaking and resuming work, and removing isolations.
The document discusses the testing and commissioning process for a Main Distribution Board (MDB). It describes three key cases for testing the MDB: 1) Testing only the interconnecting cables between transformers and MDBs which involves physical inspection, Megger testing, and energizing the panel while recording readings. 2) Repeating the steps from case 1 for all cables coming to the panel. 3) Additional steps that must be taken like inspections and permitting when work is being done on cables connected to an upstream panel to minimize shutdowns.
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
This document provides an overview of safety systems and procedures for mechanical and electrical work on a construction project. It summarizes SEE Group's approach to risk management, which includes daily safe start briefings, safe working rules, permit systems for high-risk work, isolation procedures, pressure testing, hot work permits, and COSHH assessments. Safety topics such as housekeeping, inspections, working at height, and accreditations are also addressed.
This curriculum vitae outlines the work experience and qualifications of Damian Filip, a Romanian instrumentation supervisor. Over 30 years of experience includes positions in Kazakhstan, Belgium, Scotland, Azerbaijan, Nigeria, Canada, and Romania working on projects in oil refineries, chemical plants, and other industrial facilities. Responsibilities included loop checking, commissioning, calibration, and maintenance of instrumentation systems.
Weeks 16 17 pe 3231 maintenance and fault findingCharlton Inao
Prof. Charlton S. Inao provides documentation on PLC systems, including internal relays, SET and RESET functions, shift registers, common causes of faults, fault finding, maintenance, and installation/commissioning. The document covers topics like how internal relays in a PLC simulate physical relays using bits, examples of SET and RESET functions, examples of shift registers in different PLC systems, common causes of PLC faults like environment and electrical design, steps for fault finding and maintenance including checking voltages, backups, and updates.
This document provides an overview of lockout/tagout (LOTO) procedures for machine operators. LOTO is done to isolate all energy sources to equipment during maintenance, cleaning, or other activities where guards are removed. It prevents accidental startup of machines and injury. The document explains why LOTO is important for safety, types of energy sources, proper use of locks and tags, process steps for applying and removing LOTO, and shift changeover procedures. Training boards and examples of LOTO devices are also shown.
Failure to properly de-energize equipment results in over 120 fatalities and 50,000 injuries annually according to OSHA. The document discusses energy sources that can be present, affected vs authorized employees, lockout/tagout procedures and safety, typical lockout/tagout procedures, prohibited actions, lockout/tagout devices, locks, and requirements for contractors and vendors. A proper lockout/tagout procedure is critical for safely servicing, maintaining or repairing equipment.
This document discusses lockout/tagout (LOTO) procedures for controlling hazardous energy sources. It covers:
1. The purpose of LOTO is to prevent injuries from unexpected equipment energization, start-up, or release of stored energy during maintenance or service.
2. LOTO requirements include written procedures, employee training, locks/tags, and procedures for isolating all types of hazardous energy sources such as electrical, mechanical, chemical, thermal, hydraulic, and pneumatic.
3. The 6 steps of the LOTO procedure are: prepare for shutdown, shutdown equipment, isolate all energy sources, apply locks and tags, release stored energy, and verify isolation before starting work. Positive isolation of all
This document discusses lockout/tagout (LOTO) procedures for controlling hazardous energy sources. It covers the purpose of LOTO, which is to prevent injuries from unexpected equipment energization. Requirements include written procedures, training, locks/tags, and verifying isolation. Hazardous energy types are electrical, mechanical, chemical, thermal, hydraulic, and pneumatic. The 6-step LOTO procedure is outlined as preparing for shutdown, shutting down equipment, isolating energy sources, placing locks and tags, releasing stored energy, and verifying isolation. Stored energy must be assessed and relieved before work. Only authorized employees who have gone through training can perform LOTO procedures.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
Temple of Asclepius in Thrace. Excavation resultsKrassimira Luka
The temple and the sanctuary around were dedicated to Asklepios Zmidrenus. This name has been known since 1875 when an inscription dedicated to him was discovered in Rome. The inscription is dated in 227 AD and was left by soldiers originating from the city of Philippopolis (modern Plovdiv).
How to Make a Field Mandatory in Odoo 17Celine George
In Odoo, making a field required can be done through both Python code and XML views. When you set the required attribute to True in Python code, it makes the field required across all views where it's used. Conversely, when you set the required attribute in XML views, it makes the field required only in the context of that particular view.
This presentation was provided by Rebecca Benner, Ph.D., of the American Society of Anesthesiologists, for the second session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session Two: 'Expanding Pathways to Publishing Careers,' was held June 13, 2024.
This presentation was provided by Racquel Jemison, Ph.D., Christina MacLaughlin, Ph.D., and Paulomi Majumder. Ph.D., all of the American Chemical Society, for the second session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session Two: 'Expanding Pathways to Publishing Careers,' was held June 13, 2024.
How to Setup Warehouse & Location in Odoo 17 InventoryCeline George
In this slide, we'll explore how to set up warehouses and locations in Odoo 17 Inventory. This will help us manage our stock effectively, track inventory levels, and streamline warehouse operations.
A Visual Guide to 1 Samuel | A Tale of Two HeartsSteve Thomason
These slides walk through the story of 1 Samuel. Samuel is the last judge of Israel. The people reject God and want a king. Saul is anointed as the first king, but he is not a good king. David, the shepherd boy is anointed and Saul is envious of him. David shows honor while Saul continues to self destruct.
1. Opera Grand Tower Project, Downtown Dubai
Employer: Project Management: Lead Consultant: Main Contractor: MEP Contractor
Live Panels with Locks
Live Bus bars with Locks
2. LOTO - Brief Introduction
Project Organizational Arrangements
Responsibilities
Permit control System
Authorized Person Responsibilities
Permit Types
Permit Process
Supply to Third Parties
Emergency Procedures
Live Panels with Locks
3. The purpose of the RCC Lock Out / Tag Out Procedures are to ensure that
where employees and others, are exposed to work situations that carry a
risk of
• Electrical shock
• Electrocution
• Electrical burns
• Fire
• Explosion
that the work situation is assessed and that suitable control measures' and
systems are implemented to ensure that electrical risks / hazards are
removed or reduced as far as reasonably practicable.
The ‘Lock Out / Tag Out’ procedure is implemented in situations where a
part of the Electrical System has been made LIVE before the work on the
system has been completed and RCC has assumed the role of ‘Duty
Holder’ for the installation.
The electrical system energized rooms keys will be under the control of RCC,
permit system to be followed to work in the rooms by all parties.
4. •Project LOTO Appointed Person
MD Irfan (ELT Supervisor)
Site LOTO Execution
Team
Authorized Engineer
Eng Safvan
Competent Persons
Trained/Competent
Electrical Team
5. Authorized Project Manager
• Overviews company’s Lock Out / Tag Out requirements
• Appoints Project Authorizing Engineers
• Overall responsibility for the LOTO system
• Periodic audit of complete company/project LOTO procedures
Project LOTO Appointed Person
Appointed by the Authorizing Manager is responsible for
• Assessment of project specific LOTO procedures
• Accept duty holder responsibilities for electrical system for RCC
• Implementation of appropriate Lock Out / Tag Out procedures
• Assessment and appointments of authorized persons
• Maintain a register of authorized persons
• Regular audit of project specific operation of LOTO
6. AUTHORISED ENGINEERS
• Acknowledge Lock Out / Tag Out
• Understand the Lock Out / Tag Out
• Implement and monitor the Lock Out / Tag Out
• Issue permits and ensure receivers understand requirements of
the Lock Out / Tag Out
• Check on training/induction status of permit receivers
• Close-out permits
COMPETENT PERSONS
• Acknowledge the Lock Out / Tag Out
• Understand the requirements of the system of work
• Implement and comply with the Lock Out / Tag Out
7. This is a formalized written procedure for the control of
high voltage systems or complex low voltage systems.
Authorised Engineers in control of works on electrical system
A log of all switching operations
Safe and secure isolation
Issue of permit to work/test/access
Mimic diagram for safe switching/operation
Connection of supplies
Formal handover/return of electrical system
Safe supply to third parties
8. Control of Keys to Electrical Areas and Isolations
Live Panels with Locks
9. Key Locker
All keys and
padlocks
Kept here when
not in use
Key Safe
Key safe contains keys to
restricted access areas
Keys to key lockers
Keys to padlocks which
are fitted to system while
work in progress
AP has only key to key safe
Control of Keys to Electrical Areas and Isolations
10.
11. Generator with signages
LV ROOM Live Panels with Locks
Emergency Number
Generator with
Overhead protection
Generator’s Emergency
Button
12. EHS Manager provided LOTO
training to all operatives including
supervisor and safety.
13. A permanently displayed single line diagram showing the electrical
system (LV system). The diagram will be displayed in the “permit office”
and relevant switch room. The status of switches, circuit breakers and
isolators will be indicated by means of colored pins.
RED WILL DENOTE SWITCH ON
GREEN WILL DENOTE SWITCH OFF
BLUE WILL DENOTE SWITCH EARTHED
Mimic Diagrams
When switching off a
circuit, carry out the
switching first
then alter the diagram
When switching on a
circuit, alter the diagram
first
then carry out the
switching operation
Always display
“work on system in
progress”
notice when
carrying out
switching
operations
14. Maintaining Site Log / permit Book
The site log book must have the following
• Switching operations log
sheet
• Permit to Work Log Sheet
(This will involved switching operations)
• Sanction for test Log Sheet
(This will involved Testing , after energized)
• Limitation of Access Log Sheet
(This will not any switching Operation & only provide
access to energized room (Cleaning, Civil Works, etc.))
15. Maintaining Site Log/ permit Book
The Site Permit book has the following
• Cancelled Permits-To-Work
• On Issue Permits-To-Work
• Request for Electrical Power
16. RECORD IN LOG BOOK DETAILS OF THE INTENDED SWITCHING OPERATIONS AND
OTHER SAFETY MEASURES
DISPLAY THE “WORK ON LV SYSTEM IN PROGRESS” NOTICE ON THE MIMIC
DIAGRAM
ISOLATE THE SYSTEM AND CARRY OUT TESTS TO ENSURE CONDUCTORS AND
EQUIPMENT IS DEAD
APPLY LOCKS OR OTHER ADEQUATE MEANS OF MAINTAINING THE INTEGRITY OF
ISOLATION
FIX SAFETY AND CAUTION NOTICES, BARRIERS / EXCLUSION ZONES
TEST TO ENSURE POINT OF WORK IS DEAD. PROVE TEST INSTRUMENT BEFORE
AND AFTER TEST
ALTER MIMIC DIAGRAM TO SHOW THE EXACT STATE OF THE SWITCHES
ENSURE COMPETENT PERSON IS CONVERSANT WITH WORK TO BE CARRIED OUT
Safe Isolation
20. Permit-to-Work
A document issued by an
Authorised Person to a Competent
Person, under signature, defining a
safe system of work which includes
switching operations and other
measures that have been carried
out to ensure that the risks from the
systems are minimised.
It also details the work to be carried
out and any further precautions
required to be observed by the
Competent Person and men under
his control.
21. Part 1 Issue
Authorized person enters details
system/area & particular work to
be carried out
Part 2 Receipt
Competent person signs to
confirm understanding of the
permit and its limitations.
Accepting responsibility for
carrying out the work on
Part 3 Clearance
On completion of work, the
competent person signs for
clearance and returns it to the
authorized person for close out.
Part 4 Cancellation
Cancellation is done by
authorized person.
22. Complete part 1 of permit giving full details of precautions
taken to make equipment safe. Also write exact details of work
to be carried out. (LOTO AP)
Ensure that competent person in charge of work fully
understands the instructions and acknowledges receipt by
signing part 2 of the permit. explain to the competent person
the rules on the back of the permit. (LOTO AP)
Top white copy kept in the site permit book. (LOTO AP)
2nd copy issued to competent person. (LOTO AP)
The competent person shall retain the 2nd copy in his
possession at all times while the work is being carried out.
(Competent Person)
A permit will be issued to the competent person in charge of
each working party. The fact that other permits are in use will
be indicated in the permit log giving the serial numbers of other
permits issued. (LOTO AP)
Any change in scope of work will require cancellation of permit
Permit Issue
23. When work is suspended or completed the competent person
shall sign part 3 ‘clearance’ and return permit to the
authorized person. (Competent Person)
Permit will be cancelled by authorized person by signing part
4. Note - both copies to come together before signing part 4.
(LOTO AP)
Both copies will be retained as a permanent record by
authorized person and filed in the site permit book. (LOTO
AP)
Where multiple permits have been issued ensure all permits
have been cancelled before main circuit earths are removed or
power re-established. (LOTO AP)
Permit Cancellation
24. Third party must supply inspection/test sheets confirming
plant/equipment safe to energies. (RCC/AGCCIC 3rd Party
Subcontractors)
Request for electrical power form to be signed by RCC/AGCCIC and
third party in all cases.
Joint inspection of third party plant/equipment before energization.
Details of third party safe system of controlling power to be filed in
the project site safety plan.
25. The Authorizing Engineer will detail in the method statement,
the procedures to be followed in the event of an incident or
emergency.
Including as a minimum:
• Contacts for help (Contact Details are mentioned all over site)
• Means of communication
• Address and phone number of first aid
facility/hospital
26. LOTO Team
Project LOTO Appointed Person
• Irfan – Mobile 056-4630001
Authorized Engineers
• Muhammad El Shazli – Mobile 055-1492958
• Vinod Babu – Mobile 050-8350564
• Safvan _ Mobile 054-3670077
AGCCIC HSE HOTLINE 052 6418190
27. Emergency push buttons in LOTO
permit office
OPERATION ONLY BY
AUTHORIZED ENGINEER
LV 1 Main DB with Lock.
28. Generator Incomer Cables with 3rd party Certificate
Ground Level
Overhead Protection Provided, Signs Posted, Fire
Extinguisher kept, Emergency Numbers Provided,
Trained Operator, Generator Details Posted.
29. Generator Incomer Cables with Safety Signs & Operator 3rd party Training Certificate
Ground Level