SlideShare a Scribd company logo
1 of 38
Download to read offline
CEE320
Winter2006
Signalized Intersections
CEE 320
Steve Muench
CEE320
Winter2006
Outline
1. Key Definitions
2. Baseline Assumptions
3. Control Delay
4. Signal Analysis
a. D/D/1
b. Random Arrivals
c. LOS Calculation
d. Optimization
CEE320
Winter2006
Key Definitions (1)
• Cycle Length (C)
– The total time for a signal to complete a cycle
• Phase
– The part of the signal cycle allocated to any combination
of traffic movements receiving the ROW simultaneously
during one or more intervals
• Green Time (G)
– The duration of the green indication of a given
movement at a signalized intersection
• Red Time (R)
– The period in the signal cycle during which, for a given
phase or lane group, the signal is red
CEE320
Winter2006
Key Definitions (2)
• Change Interval (Y)
– Yellow time
– The period in the signal cycle during which, for a given
phase or lane group, the signal is yellow
• Clearance Interval (AR)
– All red time
– The period in the signal cycle during which all
approaches have a red indication
CEE320
Winter2006
Key Definitions (3)
• Start-up Lost Time (l1)
– Time used by the first few vehicles in a queue while reacting
to the initiation of the green phase and accelerating.
2 seconds is typical.
• Clearance Lost Time (l2)
– Time between signal phases during which an intersection is
not used by traffic. 2 seconds is typical.
• Lost Time (tL)
– Time when an intersection is not effectively used by any
approach. 4 seconds is typical.
– tL = l1 + l2
• Total Lost Time (L)
– Total lost time per cycle during which the intersection is not
used by any movement.
CEE320
Winter2006
Key Definitions (4)
• Effective Green Time (g)
– Time actually available for movement
– g = G + Y + AR – tL
• Extension of Effective Green Time (e)
– The amount of the change and clearance interval at the
end of a phase that is usable for movement of vehicles
• Effective Red Time (r)
– Time during which a movement is effectively not
permitted to move.
– r = R + tL
– r = C – g
CEE320
Winter2006
Key Definitions (5)
• Saturation Flow Rate (s)
– Maximum flow that could pass through an intersection if
100% green time was allocated to that movement.
– s = 3600/h
• Approach Capacity (c)
– Saturation flow times the proportion of effective green
– c = s × g/C
• Peak Hour Factor (PHF)
– The hourly volume during the maximum-volume hour of
the day divided by the peak 15-minute flow rate within
the peak hour; a measure of traffic demand fluctuation
within the peak hour.
CEE320
Winter2006
Key Definitions (6)
• Flow Ratio
– The ratio of actual flow rate (v) to saturation flow rate (s)
for a lane group at an intersection
• Lane Group
– A set of lanes established at an intersection approach
for separate analysis
• Critical Lane Group
– The lane group that has the highest flow ratio (v/s) for a
given signal phase
• Critical Volume-to-Capacity Ratio (Xc)
– The proportion of available intersection capacity used
by vehicles in critical lane groups
– In terms of v/c and NOT v/s
fromHighwayCapacityManual2000
CEE320
Winter2006
Baseline Assumptions
• D/D/1 queuing
• Approach arrivals < departure capacity
– (no queue exists at the beginning/end of a
cycle)
CEE320
Winter2006
Quantifying Control Delay
• Two approaches
– Deterministic (uniform) arrivals (Use D/D/1)
– Probabilistic (random) arrivals (Use empirical equations)
• Total delay can be expressed as
– Total delay in an hour (vehicle-hours, person-hours)
– Average delay per vehicle (seconds per vehicle)
CEE320
Winter2006
D/D/1 Signal Analysis (Graphical)
Arrival
Rate
Departure
Rate
Time
Vehicles
Maximum delay
Maximum queue
Total vehicle delay per cycle
Red Red RedGreen Green Green
Queue dissipation
CEE320
Winter2006
D/D/1 Signal Analysis – Numerical
• Time to queue dissipation after the start of effective green
• Proportion of the cycle with a queue
• Proportion of vehicles stopped


  0.1
 



1
0
r
t
c
tr
Pq
0

 
  qs P
c
tr
gr
tr
P 




 00

  
  c
t
c
t
gr
tr
Ps



 000




CEE320
Winter2006
D/D/1 Signal Analysis – Numerical
• Maximum number of vehicles in a queue
• Total delay per cycle
• Average vehicle delay per cycle
• Maximum delay of any vehicle (assume FIFO)


  0.1
rQm 
 



12
2
r
Dt
   





12
1
12
22
c
r
c
r
Dt
rdm 
CEE320
Winter2006
Signal Analysis – Random Arrivals
• Webster’s Formula (1958) - empirical
d’ = avg. veh. delay assuming random arrivals
d = avg. veh. delay assuming uniform arrivals (D/D/1)
x = ratio of arrivals to departures (c/g)
g = effective green time (sec)
c = cycle length (sec)
 
)/(52
3/1
2
2
65.0
12
' cg
x
c
x
x
dd 










CEE320
Winter2006
Signal Analysis – Random Arrivals
• Allsop’s Formula (1972) - empirical
d’ = avg. veh delay assuming random arrivals
d = avg. veh delay assuming uniform arrivals
(D/D/1)
x = ratio of arrivals to departures (c/g)
 







x
x
dd
1210
9
'
2

CEE320
Winter2006
Definition – Level of Service (LOS)
• Chief measure of “quality of service”
– Describes operational conditions within a traffic
stream
– Does not include safety
– Different measures for different facilities
• Six levels of service (A through F)
CEE320
Winter2006
Signalized Intersection LOS
• Based on control delay per vehicle
– How long you wait, on average, at the stop light
from Highway Capacity Manual 2000
CEE320
Winter2006
Typical Approach
• Split control delay into three parts
– Part 1: Delay calculated assuming uniform arrivals (d1).
This is essentially a D/D/1 analysis.
– Part 2: Delay due to random arrivals (d2)
– Part 3: Delay due to initial queue at start of analysis time
period (d3). Often assumed zero.
  321 ddPFdd 
d = Average signal delay per vehicle in s/veh
PF = progression adjustment factor
d1, d2, d3 = as defined above
CEE320
Winter2006
Uniform Delay (d1)
  












C
g
X
C
g
C
d
,1min1
15.0
1
d1 = delay due to uniform arrivals (s/veh)
C = cycle length (seconds)
g = effective green time for lane group (seconds)
X = v/c ratio for lane group
CEE320
Winter2006
Incremental Delay (d2)
    






cT
kIX
XXTd
8
11900
2
2
d2 = delay due to random arrivals (s/veh)
T = duration of analysis period (hours). If the analysis is based on the
peak 15-min. flow then T = 0.25 hrs.
k = delay adjustment factor that is dependent on signal controller mode.
For pretimed intersections k = 0.5. For more efficient intersections k
< 0.5.
I = upstream filtering/metering adjustment factor. Adjusts for the effect of
an upstream signal on the randomness of the arrival pattern. I = 1.0
for completely random. I < 1.0 for reduced variance.
c = lane group capacity (veh/hr)
X = v/c ratio for lane group
CEE320
Winter2006
Initial Queue Delay (d3)
• Applied in cases where X > 1.0 for the
analysis period
– Vehicles arriving during the analysis period
will experience an additional delay because
there is already an existing queue
• When no initial queue…
– d3 = 0
CEE320
Winter2006
Control Optimization
• Conflicting Operational Objectives
– minimize vehicle delay
– minimize vehicle stops
– minimize lost time
– major vs. minor service (progression)
– pedestrian service
– reduce accidents/severity
– reduce fuel consumption
– Air pollution
CEE320
Winter2006
The “Art” of Signal Optimization
• Long Cycle Length
– High capacity (reduced lost time)
– High delay on movements that are not served
– Pedestrian movements? Number of Phases?
• Short Cycle Length
– Reduced capacity (increased lost time)
– Reduced delay for any given movement
CEE320
Winter2006
Minimum Cycle Length









 n
i ci
c
c
s
v
X
XL
C
1
min
Cmin = estimated minimum cycle length (seconds)
L = total lost time per cycle (seconds), 4 seconds per
phase is typical
(v/s)ci = flow ratio for critical lane group, i (seconds)
Xc = critical v/c ratio for the intersection
CEE320
Winter2006
Optimum Cycle Length Estimation
 









 n
i ci
opt
s
v
L
C
1
1
55.1
Copt = estimated optimum cycle length (seconds) to
minimize vehicle delay
L = total lost time per cycle (seconds), 4 seconds per
phase is typical
(v/s)ci = flow ratio for critical lane group, i (seconds)
CEE320
Winter2006
Green Time Estimation













ii
i
X
C
s
v
g
g = effective green time for phase, i (seconds)
(v/s)i = flow ratio for lane group, i (seconds)
C = cycle length (seconds)
Xi = v/c ratio for lane group i
CEE320
Winter2006
Pedestrian Crossing Time
ft.10for7.22.3 





 E
E
ped
p
p W
W
N
S
L
G
  ft.10for27.02.3  Eped
p
p WN
S
L
G
Gp = minimum green time required for pedestrians (seconds)
L = crosswalk length (ft)
Sp = average pedestrian speed (ft/s) – often assumed 4 ft/s
WE = effective crosswalk width (ft)
3.2 = pedestrian startup time (seconds)
Nped = number of pedestrians crossing during an interval
CEE320
Winter2006
Effective Width (WE)
from Highway Capacity Manual 2000
CEE320
Winter2006
Example
An intersection operates using a
simple 3-phase design as
pictured.
NB
SB
EB
WB
Phase Lane
group
Saturation Flows
1 SB 3400 veh/hr
2 NB 3400 veh/hr
3 EB 1400 veh/hr
WB 1400 veh/hr
CEE320
Winter2006
Example
SB
NB
EB
WB
30
150
50
30
400
100
1000
200
300
20
What is the sum of the flow ratios for the critical lane groups?
What is the total lost time for a signal cycle assuming 2 seconds of
clearance lost time and 2 seconds of startup lost time per phase?
CEE320
Winter2006
Example
Calculate an optimal signal timing (rounded up to the nearest 5
seconds) using Webster’s formula.
 
 


 n
i
ci
opt
sv
L
C
1
1
55.1
CEE320
Winter2006
Example
Determine the green times allocation using v/c equalization.
Assume the extension of effective green time = 2 seconds and
startup lost time = 2 seconds.













ii
i
X
C
s
v
g
LC
C
s
v
X
n
i i
c








1
CEE320
Winter2006
Example
What is the intersection Level of Service (LOS)? Assume in all
cases that PF = 1.0, k = 0.5 (pretimed intersection), I = 1.0 (no
upstream signal effects).



i
i
i
ii
A
v
vd
d



k
k
k
kk
I
v
vd
d
CEE320
Winter2006
Example
Is this signal adequate for pedestrians? A pedestrian count showed
5 pedestrians crossing the EB and WB lanes on each side of the
intersection and 10 pedestrians crossing the NB and SB
crosswalks on each side of the intersection. Lanes are 12 ft. wide.
The effective crosswalk widths are all 10 ft.
  ft10for27.02.3  Eped
p
p WN
S
L
G
CEE320
Winter2006
Signal Installation: “Warrants”
• Manual of Uniform Traffic Control
Devices (MUTCD)
• Apply these rules to determine if a
signal is “warranted” at an
intersection
• If warrants are met, doesn’t mean
signals or control is mandatory
• 8 major warrants
• Multiple warrants usually required
for recommending control
http://mutcd.fhwa.dot.gov/
FYI – NOT TESTABLE
CEE320
Winter2006
Intersection Control Type
from Highway Capacity Manual 2000
FYI – NOT TESTABLE
CEE320
Winter2006
Primary References
• Mannering, F.L.; Kilareski, W.P. and Washburn, S.S. (2003).
Principles of Highway Engineering and Traffic Analysis, Third Edition
(Draft). Chapter 7
• Transportation Research Board. (2000). Highway Capacity Manual.
National Research Council, Washington, D.C.

More Related Content

What's hot

intelligent transportation system
intelligent transportation systemintelligent transportation system
intelligent transportation systemkvn virinchi
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric designBashaFayissa1
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume surveyRashed Alam
 
Traffic signal co ordination
Traffic signal co ordinationTraffic signal co ordination
Traffic signal co ordinationKartik Yadiyapur
 
Intelligent Transportation Systems - ITS
Intelligent Transportation Systems - ITSIntelligent Transportation Systems - ITS
Intelligent Transportation Systems - ITSVijai Krishnan V
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit systemEddy Ankit Gangani
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodMd. Abdul Kader
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal DesignVijai Krishnan V
 
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...Hossam Shafiq I
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIEStp jayamohan
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Vijai Krishnan V
 
Origin – Destination survey
Origin – Destination surveyOrigin – Destination survey
Origin – Destination surveykezangkl11
 
Traffic volume-study-presentation-final
Traffic volume-study-presentation-finalTraffic volume-study-presentation-final
Traffic volume-study-presentation-finalStone Rayhan
 

What's hot (20)

intelligent transportation system
intelligent transportation systemintelligent transportation system
intelligent transportation system
 
04 transport modelling
04 transport modelling04 transport modelling
04 transport modelling
 
Chapter 3 geometric design
Chapter 3 geometric  designChapter 3 geometric  design
Chapter 3 geometric design
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
 
Traffic signal co ordination
Traffic signal co ordinationTraffic signal co ordination
Traffic signal co ordination
 
Intelligent Transportation Systems - ITS
Intelligent Transportation Systems - ITSIntelligent Transportation Systems - ITS
Intelligent Transportation Systems - ITS
 
Highway geometric design
Highway geometric designHighway geometric design
Highway geometric design
 
Traffic studies
Traffic studiesTraffic studies
Traffic studies
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit system
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
O & d survey
O & d survey O & d survey
O & d survey
 
Trip generation
Trip generation Trip generation
Trip generation
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
 
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...
8 capacity-analysis ( Transportation and Traffic Engineering Dr. Sheriff El-B...
 
TRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIESTRAFFIC VOLUME STUDIES
TRAFFIC VOLUME STUDIES
 
traffic engineering
traffic engineeringtraffic engineering
traffic engineering
 
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
 
Origin – Destination survey
Origin – Destination surveyOrigin – Destination survey
Origin – Destination survey
 
Traffic flow model
Traffic flow modelTraffic flow model
Traffic flow model
 
Traffic volume-study-presentation-final
Traffic volume-study-presentation-finalTraffic volume-study-presentation-final
Traffic volume-study-presentation-final
 

Viewers also liked

Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Hossam Shafiq I
 
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...Hossam Shafiq I
 
Traffic signal design (1)
Traffic signal design (1)Traffic signal design (1)
Traffic signal design (1)Syed Ali
 
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...Hossam Shafiq I
 
Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Hossam Shafiq I
 
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
Traffic Solutions 2pi Presentation
Traffic  Solutions 2pi  PresentationTraffic  Solutions 2pi  Presentation
Traffic Solutions 2pi PresentationBelisario H. Romo
 
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...Hossam Shafiq I
 
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...Hossam Shafiq I
 
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) Tools
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) ToolsA Survey of Recent Advances in Network Planning/Traffic Engineering (TE) Tools
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) ToolsVishal Sharma, Ph.D.
 
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...Hossam Shafiq I
 
Lec 02 Human Factor (Transportation Engineering Dr.Lina Shbeeb)
Lec 02  Human Factor (Transportation Engineering Dr.Lina Shbeeb) Lec 02  Human Factor (Transportation Engineering Dr.Lina Shbeeb)
Lec 02 Human Factor (Transportation Engineering Dr.Lina Shbeeb) Hossam Shafiq I
 
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb)
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb) Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb)
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb) Hossam Shafiq I
 
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Hossam Shafiq I
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Hossam Shafiq I
 

Viewers also liked (20)

Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 01 Introduction (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
 
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...
Lecture 06 Signalized Intersections (Traffic Engineering هندسة المرور & Dr. U...
 
Traffic signal design (1)
Traffic signal design (1)Traffic signal design (1)
Traffic signal design (1)
 
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)
Driver Vehicle (Transportation Engineering Dr.Lina Shbeeb)
 
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...
Lecture 03 Intersection Control (Traffic Engineering هندسة المرور & Dr. Usama...
 
Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering)
 
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
 
Traffic Solutions 2pi Presentation
Traffic  Solutions 2pi  PresentationTraffic  Solutions 2pi  Presentation
Traffic Solutions 2pi Presentation
 
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...
7-Traffic-Introduction ( Transportation and Traffic Engineering Dr. Sheriff E...
 
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
03-Properties of Asphalt Traditional ( Highway and Airport Engineering Dr. Sh...
 
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)
Lec 07 Intersection Design (Transportation Engineering Dr.Lina Shbeeb)
 
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) Tools
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) ToolsA Survey of Recent Advances in Network Planning/Traffic Engineering (TE) Tools
A Survey of Recent Advances in Network Planning/Traffic Engineering (TE) Tools
 
Traffic signal design study
Traffic signal design studyTraffic signal design study
Traffic signal design study
 
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)
Lec 13 Traffic Light Signals (Transportation Engineering Dr.Lina Shbeeb)
 
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...
05-Superpave Binder Specification ( Highway and Airport Engineering Dr. Sheri...
 
Lec 02 Human Factor (Transportation Engineering Dr.Lina Shbeeb)
Lec 02  Human Factor (Transportation Engineering Dr.Lina Shbeeb) Lec 02  Human Factor (Transportation Engineering Dr.Lina Shbeeb)
Lec 02 Human Factor (Transportation Engineering Dr.Lina Shbeeb)
 
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)
Lec 08 Cross Section (Transportation Engineering Dr.Lina Shbeeb)
 
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb)
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb) Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb)
Lec 03 Vehicle Motion (Transportation Engineering Dr.Lina Shbeeb)
 
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah) Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
Lecture 05 Roundabout (Traffic Engineering هندسة المرور & Dr. Usama Shahdah)
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
 

Similar to Lec 13A Signalized Intersections (Transportation Engineering Dr.Lina Shbeeb)

IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross Road
IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross RoadIRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross Road
IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross RoadIRJET Journal
 
Basics of Signal Designing
Basics of Signal DesigningBasics of Signal Designing
Basics of Signal DesigningPranuthi Konda
 
L11 Signal Timing Design
L11 Signal Timing Design L11 Signal Timing Design
L11 Signal Timing Design Hossam Shafiq I
 
Channelizing Traffic Flow by Reducing Delay at Intersection
Channelizing Traffic Flow by Reducing Delay at Intersection                  Channelizing Traffic Flow by Reducing Delay at Intersection
Channelizing Traffic Flow by Reducing Delay at Intersection IRJET Journal
 
L15 Actuated Signal Timing Design
L15 Actuated Signal Timing DesignL15 Actuated Signal Timing Design
L15 Actuated Signal Timing DesignHossam Shafiq I
 
its project
its projectits project
its projectp71089
 
Central moments of traffic delay at a signalized intersection
Central moments of traffic delay at a signalized intersectionCentral moments of traffic delay at a signalized intersection
Central moments of traffic delay at a signalized intersectionAlexander Decker
 
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...IES / IAQM
 
Hk icth2016 14th_june2016_htw_website version
Hk icth2016 14th_june2016_htw_website versionHk icth2016 14th_june2016_htw_website version
Hk icth2016 14th_june2016_htw_website versionHaneen Khreis
 
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 
Handouts advance traffic camp 6.0 2020
Handouts advance traffic camp 6.0 2020Handouts advance traffic camp 6.0 2020
Handouts advance traffic camp 6.0 2020SaifulbahariMohd
 
RAHUL KUMAR PPT ON OSD.pptx
RAHUL KUMAR PPT ON OSD.pptxRAHUL KUMAR PPT ON OSD.pptx
RAHUL KUMAR PPT ON OSD.pptxRohitRodhia3
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow ParametersHossam Shafiq I
 
IRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary DesignIRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary DesignIRJET Journal
 

Similar to Lec 13A Signalized Intersections (Transportation Engineering Dr.Lina Shbeeb) (20)

HIGHWAY TRAFFIC
HIGHWAY TRAFFICHIGHWAY TRAFFIC
HIGHWAY TRAFFIC
 
IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross Road
IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross RoadIRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross Road
IRJET- Traffic Survey and Signal Design at Kalwa-Court Naka Cross Road
 
Basics of Signal Designing
Basics of Signal DesigningBasics of Signal Designing
Basics of Signal Designing
 
L11 Signal Timing Design
L11 Signal Timing Design L11 Signal Timing Design
L11 Signal Timing Design
 
Channelizing Traffic Flow by Reducing Delay at Intersection
Channelizing Traffic Flow by Reducing Delay at Intersection                  Channelizing Traffic Flow by Reducing Delay at Intersection
Channelizing Traffic Flow by Reducing Delay at Intersection
 
L15 Actuated Signal Timing Design
L15 Actuated Signal Timing DesignL15 Actuated Signal Timing Design
L15 Actuated Signal Timing Design
 
its project
its projectits project
its project
 
L16 Progression
L16 ProgressionL16 Progression
L16 Progression
 
30120130405026
3012013040502630120130405026
30120130405026
 
Central moments of traffic delay at a signalized intersection
Central moments of traffic delay at a signalized intersectionCentral moments of traffic delay at a signalized intersection
Central moments of traffic delay at a signalized intersection
 
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...
Dr Glyn Rhys-Tyler - Road vehicle exhaust emissions; 'an age of uncertainty' ...
 
lec7.ppt
lec7.pptlec7.ppt
lec7.ppt
 
Hk icth2016 14th_june2016_htw_website version
Hk icth2016 14th_june2016_htw_website versionHk icth2016 14th_june2016_htw_website version
Hk icth2016 14th_june2016_htw_website version
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
Lec 12 Capacity Analysis (Transportation Engineering Dr.Lina Shbeeb)
 
Lect 30- traffic signal i
Lect 30- traffic signal iLect 30- traffic signal i
Lect 30- traffic signal i
 
Handouts advance traffic camp 6.0 2020
Handouts advance traffic camp 6.0 2020Handouts advance traffic camp 6.0 2020
Handouts advance traffic camp 6.0 2020
 
RAHUL KUMAR PPT ON OSD.pptx
RAHUL KUMAR PPT ON OSD.pptxRAHUL KUMAR PPT ON OSD.pptx
RAHUL KUMAR PPT ON OSD.pptx
 
L1 Traffic Flow Parameters
L1 Traffic Flow ParametersL1 Traffic Flow Parameters
L1 Traffic Flow Parameters
 
IRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary DesignIRJET- Traffic Congestion Overcome by Rotary Design
IRJET- Traffic Congestion Overcome by Rotary Design
 

More from Hossam Shafiq I

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...Hossam Shafiq I
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...Hossam Shafiq I
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...Hossam Shafiq I
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...Hossam Shafiq I
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...Hossam Shafiq I
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...Hossam Shafiq I
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...Hossam Shafiq I
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...Hossam Shafiq I
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...Hossam Shafiq I
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...Hossam Shafiq I
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...Hossam Shafiq I
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...Hossam Shafiq I
 
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...Hossam Shafiq I
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....Hossam Shafiq I
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...Hossam Shafiq I
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...Hossam Shafiq I
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...Hossam Shafiq I
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...Hossam Shafiq I
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...Hossam Shafiq I
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...Hossam Shafiq I
 

More from Hossam Shafiq I (20)

14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
14 Signalling and Control Systems (Railway Engineering Lectures هندسة السكك ا...
 
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
13 Equipments in Railway Stations and Yards (Railway Engineering Lectures هند...
 
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
12 Points and Crossings (Railway Engineering Lectures هندسة السكك الحديدية & ...
 
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
12 Railway Yards and Terminals (Railway Engineering Lectures هندسة السكك الحد...
 
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
11 Geometric Design of Railway Track [Vertical Alignment] (Railway Engineerin...
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
09 Drainage (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A...
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
07 Construction and Renewal of Tracks (Railway Engineering Lectures هندسة الس...
 
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
06 Creep of Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wa...
 
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
05 Welded Track (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
05 Rail Joints (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walie...
 
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
 
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
04 Ballast (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A....
 
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
04 Rail Sleepers (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wal...
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
 
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
02 Handout #1 (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied...
 
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
02 Rail Transport Systems (Railway Engineering Lectures هندسة السكك الحديدية ...
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
 
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
01 Introduction (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Wali...
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

Lec 13A Signalized Intersections (Transportation Engineering Dr.Lina Shbeeb)

  • 2. CEE320 Winter2006 Outline 1. Key Definitions 2. Baseline Assumptions 3. Control Delay 4. Signal Analysis a. D/D/1 b. Random Arrivals c. LOS Calculation d. Optimization
  • 3. CEE320 Winter2006 Key Definitions (1) • Cycle Length (C) – The total time for a signal to complete a cycle • Phase – The part of the signal cycle allocated to any combination of traffic movements receiving the ROW simultaneously during one or more intervals • Green Time (G) – The duration of the green indication of a given movement at a signalized intersection • Red Time (R) – The period in the signal cycle during which, for a given phase or lane group, the signal is red
  • 4. CEE320 Winter2006 Key Definitions (2) • Change Interval (Y) – Yellow time – The period in the signal cycle during which, for a given phase or lane group, the signal is yellow • Clearance Interval (AR) – All red time – The period in the signal cycle during which all approaches have a red indication
  • 5. CEE320 Winter2006 Key Definitions (3) • Start-up Lost Time (l1) – Time used by the first few vehicles in a queue while reacting to the initiation of the green phase and accelerating. 2 seconds is typical. • Clearance Lost Time (l2) – Time between signal phases during which an intersection is not used by traffic. 2 seconds is typical. • Lost Time (tL) – Time when an intersection is not effectively used by any approach. 4 seconds is typical. – tL = l1 + l2 • Total Lost Time (L) – Total lost time per cycle during which the intersection is not used by any movement.
  • 6. CEE320 Winter2006 Key Definitions (4) • Effective Green Time (g) – Time actually available for movement – g = G + Y + AR – tL • Extension of Effective Green Time (e) – The amount of the change and clearance interval at the end of a phase that is usable for movement of vehicles • Effective Red Time (r) – Time during which a movement is effectively not permitted to move. – r = R + tL – r = C – g
  • 7. CEE320 Winter2006 Key Definitions (5) • Saturation Flow Rate (s) – Maximum flow that could pass through an intersection if 100% green time was allocated to that movement. – s = 3600/h • Approach Capacity (c) – Saturation flow times the proportion of effective green – c = s × g/C • Peak Hour Factor (PHF) – The hourly volume during the maximum-volume hour of the day divided by the peak 15-minute flow rate within the peak hour; a measure of traffic demand fluctuation within the peak hour.
  • 8. CEE320 Winter2006 Key Definitions (6) • Flow Ratio – The ratio of actual flow rate (v) to saturation flow rate (s) for a lane group at an intersection • Lane Group – A set of lanes established at an intersection approach for separate analysis • Critical Lane Group – The lane group that has the highest flow ratio (v/s) for a given signal phase • Critical Volume-to-Capacity Ratio (Xc) – The proportion of available intersection capacity used by vehicles in critical lane groups – In terms of v/c and NOT v/s
  • 10. CEE320 Winter2006 Baseline Assumptions • D/D/1 queuing • Approach arrivals < departure capacity – (no queue exists at the beginning/end of a cycle)
  • 11. CEE320 Winter2006 Quantifying Control Delay • Two approaches – Deterministic (uniform) arrivals (Use D/D/1) – Probabilistic (random) arrivals (Use empirical equations) • Total delay can be expressed as – Total delay in an hour (vehicle-hours, person-hours) – Average delay per vehicle (seconds per vehicle)
  • 12. CEE320 Winter2006 D/D/1 Signal Analysis (Graphical) Arrival Rate Departure Rate Time Vehicles Maximum delay Maximum queue Total vehicle delay per cycle Red Red RedGreen Green Green Queue dissipation
  • 13. CEE320 Winter2006 D/D/1 Signal Analysis – Numerical • Time to queue dissipation after the start of effective green • Proportion of the cycle with a queue • Proportion of vehicles stopped     0.1      1 0 r t c tr Pq 0      qs P c tr gr tr P       00       c t c t gr tr Ps     000    
  • 14. CEE320 Winter2006 D/D/1 Signal Analysis – Numerical • Maximum number of vehicles in a queue • Total delay per cycle • Average vehicle delay per cycle • Maximum delay of any vehicle (assume FIFO)     0.1 rQm       12 2 r Dt          12 1 12 22 c r c r Dt rdm 
  • 15. CEE320 Winter2006 Signal Analysis – Random Arrivals • Webster’s Formula (1958) - empirical d’ = avg. veh. delay assuming random arrivals d = avg. veh. delay assuming uniform arrivals (D/D/1) x = ratio of arrivals to departures (c/g) g = effective green time (sec) c = cycle length (sec)   )/(52 3/1 2 2 65.0 12 ' cg x c x x dd           
  • 16. CEE320 Winter2006 Signal Analysis – Random Arrivals • Allsop’s Formula (1972) - empirical d’ = avg. veh delay assuming random arrivals d = avg. veh delay assuming uniform arrivals (D/D/1) x = ratio of arrivals to departures (c/g)          x x dd 1210 9 ' 2 
  • 17. CEE320 Winter2006 Definition – Level of Service (LOS) • Chief measure of “quality of service” – Describes operational conditions within a traffic stream – Does not include safety – Different measures for different facilities • Six levels of service (A through F)
  • 18. CEE320 Winter2006 Signalized Intersection LOS • Based on control delay per vehicle – How long you wait, on average, at the stop light from Highway Capacity Manual 2000
  • 19. CEE320 Winter2006 Typical Approach • Split control delay into three parts – Part 1: Delay calculated assuming uniform arrivals (d1). This is essentially a D/D/1 analysis. – Part 2: Delay due to random arrivals (d2) – Part 3: Delay due to initial queue at start of analysis time period (d3). Often assumed zero.   321 ddPFdd  d = Average signal delay per vehicle in s/veh PF = progression adjustment factor d1, d2, d3 = as defined above
  • 20. CEE320 Winter2006 Uniform Delay (d1)                C g X C g C d ,1min1 15.0 1 d1 = delay due to uniform arrivals (s/veh) C = cycle length (seconds) g = effective green time for lane group (seconds) X = v/c ratio for lane group
  • 21. CEE320 Winter2006 Incremental Delay (d2)            cT kIX XXTd 8 11900 2 2 d2 = delay due to random arrivals (s/veh) T = duration of analysis period (hours). If the analysis is based on the peak 15-min. flow then T = 0.25 hrs. k = delay adjustment factor that is dependent on signal controller mode. For pretimed intersections k = 0.5. For more efficient intersections k < 0.5. I = upstream filtering/metering adjustment factor. Adjusts for the effect of an upstream signal on the randomness of the arrival pattern. I = 1.0 for completely random. I < 1.0 for reduced variance. c = lane group capacity (veh/hr) X = v/c ratio for lane group
  • 22. CEE320 Winter2006 Initial Queue Delay (d3) • Applied in cases where X > 1.0 for the analysis period – Vehicles arriving during the analysis period will experience an additional delay because there is already an existing queue • When no initial queue… – d3 = 0
  • 23. CEE320 Winter2006 Control Optimization • Conflicting Operational Objectives – minimize vehicle delay – minimize vehicle stops – minimize lost time – major vs. minor service (progression) – pedestrian service – reduce accidents/severity – reduce fuel consumption – Air pollution
  • 24. CEE320 Winter2006 The “Art” of Signal Optimization • Long Cycle Length – High capacity (reduced lost time) – High delay on movements that are not served – Pedestrian movements? Number of Phases? • Short Cycle Length – Reduced capacity (increased lost time) – Reduced delay for any given movement
  • 25. CEE320 Winter2006 Minimum Cycle Length           n i ci c c s v X XL C 1 min Cmin = estimated minimum cycle length (seconds) L = total lost time per cycle (seconds), 4 seconds per phase is typical (v/s)ci = flow ratio for critical lane group, i (seconds) Xc = critical v/c ratio for the intersection
  • 26. CEE320 Winter2006 Optimum Cycle Length Estimation             n i ci opt s v L C 1 1 55.1 Copt = estimated optimum cycle length (seconds) to minimize vehicle delay L = total lost time per cycle (seconds), 4 seconds per phase is typical (v/s)ci = flow ratio for critical lane group, i (seconds)
  • 27. CEE320 Winter2006 Green Time Estimation              ii i X C s v g g = effective green time for phase, i (seconds) (v/s)i = flow ratio for lane group, i (seconds) C = cycle length (seconds) Xi = v/c ratio for lane group i
  • 28. CEE320 Winter2006 Pedestrian Crossing Time ft.10for7.22.3        E E ped p p W W N S L G   ft.10for27.02.3  Eped p p WN S L G Gp = minimum green time required for pedestrians (seconds) L = crosswalk length (ft) Sp = average pedestrian speed (ft/s) – often assumed 4 ft/s WE = effective crosswalk width (ft) 3.2 = pedestrian startup time (seconds) Nped = number of pedestrians crossing during an interval
  • 29. CEE320 Winter2006 Effective Width (WE) from Highway Capacity Manual 2000
  • 30. CEE320 Winter2006 Example An intersection operates using a simple 3-phase design as pictured. NB SB EB WB Phase Lane group Saturation Flows 1 SB 3400 veh/hr 2 NB 3400 veh/hr 3 EB 1400 veh/hr WB 1400 veh/hr
  • 31. CEE320 Winter2006 Example SB NB EB WB 30 150 50 30 400 100 1000 200 300 20 What is the sum of the flow ratios for the critical lane groups? What is the total lost time for a signal cycle assuming 2 seconds of clearance lost time and 2 seconds of startup lost time per phase?
  • 32. CEE320 Winter2006 Example Calculate an optimal signal timing (rounded up to the nearest 5 seconds) using Webster’s formula.        n i ci opt sv L C 1 1 55.1
  • 33. CEE320 Winter2006 Example Determine the green times allocation using v/c equalization. Assume the extension of effective green time = 2 seconds and startup lost time = 2 seconds.              ii i X C s v g LC C s v X n i i c         1
  • 34. CEE320 Winter2006 Example What is the intersection Level of Service (LOS)? Assume in all cases that PF = 1.0, k = 0.5 (pretimed intersection), I = 1.0 (no upstream signal effects).    i i i ii A v vd d    k k k kk I v vd d
  • 35. CEE320 Winter2006 Example Is this signal adequate for pedestrians? A pedestrian count showed 5 pedestrians crossing the EB and WB lanes on each side of the intersection and 10 pedestrians crossing the NB and SB crosswalks on each side of the intersection. Lanes are 12 ft. wide. The effective crosswalk widths are all 10 ft.   ft10for27.02.3  Eped p p WN S L G
  • 36. CEE320 Winter2006 Signal Installation: “Warrants” • Manual of Uniform Traffic Control Devices (MUTCD) • Apply these rules to determine if a signal is “warranted” at an intersection • If warrants are met, doesn’t mean signals or control is mandatory • 8 major warrants • Multiple warrants usually required for recommending control http://mutcd.fhwa.dot.gov/ FYI – NOT TESTABLE
  • 37. CEE320 Winter2006 Intersection Control Type from Highway Capacity Manual 2000 FYI – NOT TESTABLE
  • 38. CEE320 Winter2006 Primary References • Mannering, F.L.; Kilareski, W.P. and Washburn, S.S. (2003). Principles of Highway Engineering and Traffic Analysis, Third Edition (Draft). Chapter 7 • Transportation Research Board. (2000). Highway Capacity Manual. National Research Council, Washington, D.C.