 KSTPS is the first coal based power plant in Rajasthan.
 It is located ideally on the bank of CHAMBAL River at the
upstream of KOTA BARRAGE.
 Its first unit of capacity 110 MW is commissioned on 1983 and
last one on 2009.
 It is one of the highest power generating plant with installed
capacity of 1240 MW.
INTRODUCTION:-
STAGES
Unit 6 – 195 MW
Unit 1 – 110 MW
Unit 2 – 110 MW
Unit 3 – 210 MW
Unit 4 – 210 MW
Unit 5 – 210 MW
Unit 7 – 195 MW
Stage I
Stage II Stage III Stage IV
Stage V
DESIGN:-
110 + 110 + 210 + 210 + 210 + 195 +195 = 1240 MW
CONTENTS OF THE PRESENTATION:-
 GENERAL LAYOUT
 COAL HANDLING PLANT
 BOILER
 PROCESS OF STEAM GENERATION
 TURBINE
 GENERATOR
 COOLING SYSTEM
 WATER TREWATMENT PLANT
 SWITCHYARD
 CONTROL PANNEL
LAYOUT OF KSTPS:-
COAL STORAGE
COAL
HANDLING
BOILER
FURNANCE
AIR
AIR
PREHEATER
FORCED DRAFT FAN
C
H
I
M
N
E
Y
EXHAUT
ASH
HANDING
ASH
STORAGE
SUPER HEATER
TURBINE
CKT BREAKER
CONDESERFWH
RAW
WATER
TANK
PLANT OVERVIEW:-
It is called the HEART of thermal power
plant because it provides the fuel for
combustion in boiler.
There are 14 tracks for transportation
COAL HANDLING PLANT:-
20000 tons coal requirement per day.
The main coal sources are:
1. Coal India Ltd. (CIL)
2.South Eastern Coalfield Ltd. (SECL)
3. Northern Coalfield Ltd. (NCL)
(coal comes from 1000 km distance)
Everyday 3- 4 trains of coal are unloaded, each train consists 58
wagons.(approx.3500-3800 tons)
Coal is unloaded from wagons by means of WAGON TRIPPLER
Stock yard Capacity -5.0 lack tons
COAL HANDLING PLANT:-
Bunkers Crusher house Hoppers
Row coal feeders
Coal mills
(pulverization
)
BOILER FURNACE
TANGENTIAL FIRING OF PULVERISED COAL
OVERVIEW OF COAL HANDLING PLANT:-
Row coal from COAL
INDIA LIMITED
To KSTPS from gurla via a
single railway track
Wagon trippler
CONVEYING SYSTEM
Coal size reduced by 20 mm
BOILER:-
 It is a closed vessel in which water under pressure is converted
into steam.
 Hot water or steam used to transfer heat to a process.
 A boiler is always designed to absorb maximum amount of
heat released in process of combustion.
 Furnace:- It is primary part of boiler where the fuel is burnt to
liberate the heat energy.
Flue gases
Boiler water tubes
& various stages
Boiler
furnace
Pulverized
coal
Air from
environment
via draft fans
Ash
handling
plant
DM water
Super
heated
steam
OVER VIEW OF BOILER:-
BOILER AT KSTPS
SUPER HEATER:-
Super heater consists group of tubes made by chromium -
molybdenum.
The tubes are heated by the heat of flue gases travelling from
the furnace to chimney , so the temperature increased.
Super heater removes the moisture from the steam leaving from
the boiler.
ECONOMISER:-
Function-To extract some part of
heat from flue gases & heat the
feed water
Process- Counter flow of flue
gases & water
Benefits- Increases efficiency by
10-12% & causes saving in fuel
consumption 5-15%
AIR PREHEATER:-
Function- To raise the
temperature of air supplied
to boiler furnace for coal
combustion.
Benefits- Increase the
efficiency of plant.
Type- Plate, Tubular,
Regenerative.
KSTPS uses Regenerative
type.
CONDENSER:-
It condenses exhaust steam & also removes air from steam.
Steam condensed by condenser used as a good source of feed
water to boiler.
It improves the overall plant efficiency.
PROCESS OF STEAM GENERATION:-
K.S.T.P.S
STEAM
TURBINE
MECHANICAL
ENERGY
GENERATOR
ELECTRICAL
ENERGY
WORKING OF TURBINE & GENERATOR:-
TURBINE:-
FUNCTION- Turbine is a machine in which shaft is rotated by the
impact of the working fluid such as steam , water etc.
TECHNICAL SPECIFICATION-
 Rated output -- 110 MW
 Rated speed – 3000 rpm
 Direction of rotation – clockwise
 Type -3 cylinder, impulse reaction
BOILER & SUPERHEATER
I P TURBINE
H P TURBINE
L P TURBINE
REHEATER
STEAM AT
531 C
STEAM AT
531 C
STEAM AT
344 C
STEAM TURBINE:-
It converts mechanical power into electrical power.
PRINCIPLE- Electromechanical energy conversion
TECHNICAL SPECIFICATION-
 Active output - 110 MW
 Power factor – 0.85 lag
 Excitation voltage - 230 Volt
 Rated voltage – 11 KV
 Rated speed – 3000 rpm
 Phase connection – star-star
GENERATOR:-
COOLING SYSTEM:-
In KSTPS hydrogen cooling system is employed for generator
cooling.
Hydrogen is used because of its superior cooling properties &
low density.
Thermal conductivity of H2 7.3 times of air.
Water cooling also used for any kind of fire.
COOLING TOWER:-
Warm water is feed to the top.
Flows from the top to bottom. The
water drops falling from the top
come in contact with air, lose heat to
the air and get cooled.
Its purpose is to reuse of the water.
It increases the efficiency of plant.
It increases the per capital
investment of plant.
In K.S.T.P.S. only unit 6th and 7th has
cooling tower.
ASH HANDLING PLANT:-
In thermal plants 25% is
boiler furnace bottom ash and
75% is pulverized fuel ash.
Electrostatic Precipitator is
used in ash handling plant to
remove fly ash.
WATER TREATMENT PLANT:-
 The principle problems in boiler are corrosion and steam
impurities so they require clean and soft water for longer life
& better efficiency .
( corrosion costs power station crores of rupees in repair )
 Therefore , it is required that water is first purified and
softened by chemical treatment & then delivered to the
boiler.
WATER TREATMENT PLANT:-
 Pressure filter removes
undisclosed impurities from raw
water.
 Carbon filter removes excess
chlorine from clarified water.
 D.M. plant removes dissolved
impurities from clarified water.
 Conductivity ,pH & silica content
of this water must be checked
time to time.
SWITCHYARD:-
 The 220 KV Switch yard is the main part of the KTPS.
 There are 11 feeders connected at 220 KV switchyard
PLACES NO.
SAKATPURA 4
SANGANER 1
PGCIL NANTA 2
HEERAPURA 1
GULABPURA 1
BEAWAR 1
MORAK 1
TOTEL OUTGOING FEEDERS:-
COMPONENTS OF SWITCHYARD:-
BUSBARS
LIGHTING ARRESTORS
C.T
P.T.
WAVE TRAP
POWER TRANSFORMER
ISOLATORS
C.B.
RELAYS
 In control room various controls are provided & various
measurements are made . Instrumentation Limited Kota is
major supplier of apparatus.
 Automatic control is provided for combustion , feed water
regulation & reheat temperature.
CONTROL ROOM
ANY QUERIES ? ? ?
THANK YOU…!!!
&

More Related Content

What's hot

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportUtkarsh Chaubey
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training ReportShani Kumar Singh
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plantsagar20jain
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power PlantMd. Rimon Mia
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-reportAnil Saharan
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurAbhishek Mathur
 
Thermal Power Generation Report
Thermal Power Generation ReportThermal Power Generation Report
Thermal Power Generation ReportManish Kumar
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
KOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPTKOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPTMukesh Taneja
 
power point presentation over thermal power plant
power point presentation over thermal power plantpower point presentation over thermal power plant
power point presentation over thermal power plantAnis Haider
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power PlantSmile Hossain
 

What's hot (20)

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
kstps training report
kstps training reportkstps training report
kstps training report
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
 
Training report on thermal power plant
Training report on thermal power plantTraining report on thermal power plant
Training report on thermal power plant
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Power Generation Report
Thermal Power Generation ReportThermal Power Generation Report
Thermal Power Generation Report
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
KOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPTKOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPT
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
power point presentation over thermal power plant
power point presentation over thermal power plantpower point presentation over thermal power plant
power point presentation over thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 

Similar to Kota Super Thermal Power Plant

Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptxParulChandna6
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andalANIL kumar
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plantR G Sanjay Prakash
 
Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingRadhe Shyam
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminarCentury Rayon
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxssuser4c2635
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Stationpukhraj palariya
 
Sunil- Thermal Power Plant
Sunil- Thermal Power PlantSunil- Thermal Power Plant
Sunil- Thermal Power PlantSunil8889
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantHarshit Madaan
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRabi Kumar
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportLovesh Singla
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power stationAshish Agarwal
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plantRama Charan
 
Thermal Power Plant.pptx
Thermal Power Plant.pptxThermal Power Plant.pptx
Thermal Power Plant.pptxGorakshaMakkar
 

Similar to Kota Super Thermal Power Plant (20)

Dev
DevDev
Dev
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptx
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andal
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
 
Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial training
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptx
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Station
 
power plant ppt
power plant pptpower plant ppt
power plant ppt
 
Sunil- Thermal Power Plant
Sunil- Thermal Power PlantSunil- Thermal Power Plant
Sunil- Thermal Power Plant
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power Plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester report
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plant
 
Thermal Power Plant.pptx
Thermal Power Plant.pptxThermal Power Plant.pptx
Thermal Power Plant.pptx
 
Pm ppt
Pm pptPm ppt
Pm ppt
 

Recently uploaded

Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Kota Super Thermal Power Plant

  • 1. SUBMITTED TO:- Mrs Rida Qureshi Ms Juhi Singhal SUBMITTED BY:- Himanshu Dixit Kamlesh Saini
  • 2.  KSTPS is the first coal based power plant in Rajasthan.  It is located ideally on the bank of CHAMBAL River at the upstream of KOTA BARRAGE.  Its first unit of capacity 110 MW is commissioned on 1983 and last one on 2009.  It is one of the highest power generating plant with installed capacity of 1240 MW. INTRODUCTION:-
  • 3. STAGES Unit 6 – 195 MW Unit 1 – 110 MW Unit 2 – 110 MW Unit 3 – 210 MW Unit 4 – 210 MW Unit 5 – 210 MW Unit 7 – 195 MW Stage I Stage II Stage III Stage IV Stage V DESIGN:- 110 + 110 + 210 + 210 + 210 + 195 +195 = 1240 MW
  • 4. CONTENTS OF THE PRESENTATION:-  GENERAL LAYOUT  COAL HANDLING PLANT  BOILER  PROCESS OF STEAM GENERATION  TURBINE  GENERATOR  COOLING SYSTEM  WATER TREWATMENT PLANT  SWITCHYARD  CONTROL PANNEL
  • 6. COAL STORAGE COAL HANDLING BOILER FURNANCE AIR AIR PREHEATER FORCED DRAFT FAN C H I M N E Y EXHAUT ASH HANDING ASH STORAGE SUPER HEATER TURBINE CKT BREAKER CONDESERFWH RAW WATER TANK PLANT OVERVIEW:-
  • 7. It is called the HEART of thermal power plant because it provides the fuel for combustion in boiler. There are 14 tracks for transportation COAL HANDLING PLANT:-
  • 8. 20000 tons coal requirement per day. The main coal sources are: 1. Coal India Ltd. (CIL) 2.South Eastern Coalfield Ltd. (SECL) 3. Northern Coalfield Ltd. (NCL) (coal comes from 1000 km distance) Everyday 3- 4 trains of coal are unloaded, each train consists 58 wagons.(approx.3500-3800 tons) Coal is unloaded from wagons by means of WAGON TRIPPLER Stock yard Capacity -5.0 lack tons COAL HANDLING PLANT:-
  • 9. Bunkers Crusher house Hoppers Row coal feeders Coal mills (pulverization ) BOILER FURNACE TANGENTIAL FIRING OF PULVERISED COAL OVERVIEW OF COAL HANDLING PLANT:- Row coal from COAL INDIA LIMITED To KSTPS from gurla via a single railway track Wagon trippler CONVEYING SYSTEM Coal size reduced by 20 mm
  • 10. BOILER:-  It is a closed vessel in which water under pressure is converted into steam.  Hot water or steam used to transfer heat to a process.  A boiler is always designed to absorb maximum amount of heat released in process of combustion.  Furnace:- It is primary part of boiler where the fuel is burnt to liberate the heat energy.
  • 11. Flue gases Boiler water tubes & various stages Boiler furnace Pulverized coal Air from environment via draft fans Ash handling plant DM water Super heated steam OVER VIEW OF BOILER:-
  • 13. SUPER HEATER:- Super heater consists group of tubes made by chromium - molybdenum. The tubes are heated by the heat of flue gases travelling from the furnace to chimney , so the temperature increased. Super heater removes the moisture from the steam leaving from the boiler.
  • 14. ECONOMISER:- Function-To extract some part of heat from flue gases & heat the feed water Process- Counter flow of flue gases & water Benefits- Increases efficiency by 10-12% & causes saving in fuel consumption 5-15%
  • 15. AIR PREHEATER:- Function- To raise the temperature of air supplied to boiler furnace for coal combustion. Benefits- Increase the efficiency of plant. Type- Plate, Tubular, Regenerative. KSTPS uses Regenerative type.
  • 16. CONDENSER:- It condenses exhaust steam & also removes air from steam. Steam condensed by condenser used as a good source of feed water to boiler. It improves the overall plant efficiency.
  • 17. PROCESS OF STEAM GENERATION:- K.S.T.P.S
  • 19. TURBINE:- FUNCTION- Turbine is a machine in which shaft is rotated by the impact of the working fluid such as steam , water etc. TECHNICAL SPECIFICATION-  Rated output -- 110 MW  Rated speed – 3000 rpm  Direction of rotation – clockwise  Type -3 cylinder, impulse reaction
  • 20. BOILER & SUPERHEATER I P TURBINE H P TURBINE L P TURBINE REHEATER STEAM AT 531 C STEAM AT 531 C STEAM AT 344 C STEAM TURBINE:-
  • 21.
  • 22. It converts mechanical power into electrical power. PRINCIPLE- Electromechanical energy conversion TECHNICAL SPECIFICATION-  Active output - 110 MW  Power factor – 0.85 lag  Excitation voltage - 230 Volt  Rated voltage – 11 KV  Rated speed – 3000 rpm  Phase connection – star-star GENERATOR:-
  • 23. COOLING SYSTEM:- In KSTPS hydrogen cooling system is employed for generator cooling. Hydrogen is used because of its superior cooling properties & low density. Thermal conductivity of H2 7.3 times of air. Water cooling also used for any kind of fire.
  • 24. COOLING TOWER:- Warm water is feed to the top. Flows from the top to bottom. The water drops falling from the top come in contact with air, lose heat to the air and get cooled. Its purpose is to reuse of the water. It increases the efficiency of plant. It increases the per capital investment of plant. In K.S.T.P.S. only unit 6th and 7th has cooling tower.
  • 25. ASH HANDLING PLANT:- In thermal plants 25% is boiler furnace bottom ash and 75% is pulverized fuel ash. Electrostatic Precipitator is used in ash handling plant to remove fly ash.
  • 26. WATER TREATMENT PLANT:-  The principle problems in boiler are corrosion and steam impurities so they require clean and soft water for longer life & better efficiency . ( corrosion costs power station crores of rupees in repair )  Therefore , it is required that water is first purified and softened by chemical treatment & then delivered to the boiler.
  • 27. WATER TREATMENT PLANT:-  Pressure filter removes undisclosed impurities from raw water.  Carbon filter removes excess chlorine from clarified water.  D.M. plant removes dissolved impurities from clarified water.  Conductivity ,pH & silica content of this water must be checked time to time.
  • 28. SWITCHYARD:-  The 220 KV Switch yard is the main part of the KTPS.  There are 11 feeders connected at 220 KV switchyard
  • 29. PLACES NO. SAKATPURA 4 SANGANER 1 PGCIL NANTA 2 HEERAPURA 1 GULABPURA 1 BEAWAR 1 MORAK 1 TOTEL OUTGOING FEEDERS:-
  • 30. COMPONENTS OF SWITCHYARD:- BUSBARS LIGHTING ARRESTORS C.T P.T. WAVE TRAP POWER TRANSFORMER ISOLATORS C.B. RELAYS
  • 31.  In control room various controls are provided & various measurements are made . Instrumentation Limited Kota is major supplier of apparatus.  Automatic control is provided for combustion , feed water regulation & reheat temperature. CONTROL ROOM