SlideShare a Scribd company logo
1 of 38
Download to read offline
Indian Institute of Science
Renewable Energy Systems
Reports
A case study of
3-MW scale
grid-connected solar
photovoltaic power plant
at Kolar, Karnataka
Performance assessment &
recommendations
H. Mitavachan, Anandhi Gokhale
and J. Srinivasan
REPORT IISc-DCCC 11 RE 1 AUGUST 2011
NDIAIN
OT EUT FTISNI ECSCIEN
Divecha Centre for
Climate Change
The Divecha Centre for Climate Change was
established at the Indian Institute of Science in
January 2009 with a generous financial
contribution from Arjun and Diana Divecha and the
Grantham Foundation for the Protection of the
Environment.
The primary goal of this Centre is to understand climate
variability and climate change and its impact on the
environment. The Centre has undertaken outreach activities
to create awareness among people and policy makers about
climate change and its consequences. This has been done
through workshops, lectures and quiz contests. An annual
invited public lecture called the ‘Jeremy Grantham Lecture
on Climate Change’ has been organized. The Centre has
identified technologies to mitigate climate change in
collaboration with entrepreneurs and different engineering
departments in the Indian Institute of Science. The Centre is
also working with Grantham Institute for Climate Change
at Imperial College, London, on the impact of climate
change on water.
Indian Institute of Science
Renewable Energy Systems
Reports
H. Mitavachan, Anandhi Gokhale
and J. Srinivasan
REPORT IISc-DCCC 11 RE 1 AUGUST 2011
NDIAIN
OEUT FTITSIN ES CCIEN
Divecha Centre for
Climate Change
A case study of
3-MW scale
grid-connected solar
photovoltaic power plant
at Kolar, Karnataka
Performance assessment &
recommendations
Karnataka Power Corporation Limited (KPCL) has established 3 MW capacitypeak
grid-connected solar photovoltaic power plant near Yalesandra village in Kolar
district of Karnataka, which is the first of its scale in India. After the site
preparations were completed the first segment was installed in 4 months,
followed by the second and third segments in the next two months. The plant
was fully commissioned on 27 December 2009. The Yalesandra plant is one
among 20 such Mega-watt size solar power plants in India, *as on 31st July
2011. India has an ambitious plan to build large grid-connected solar power
plants, with a cumulative installed capacity of 20,000 MWp by 2020, under the
National Solar Mission. Hence, it is essential to document the performance of
the first large-scale grid-connected solar power plant installed in Karnataka. In
this report we discuss the performance of the photovoltaic solar power plant in
Kolar during 2010.
0
The Yalesandra power plant is located at a latitude of 12 53' and a longitude of
0
78 09'. The overall area occupied by photovoltaic modules is 10.3 acres. The
plant has 3 segments with each segment having an installed capacity of 1 MW .p
Each segment has 4 inverters with a capacity of 250 kW each. There are 13,368
modules (557 arrays with 24 modules per array) that contain mono-crystalline
Silicon solar cells. The solar photovoltaic modules are connected such that a
voltage of 415 volts is generated at the output of each inverter. This is stepped up
to 11 kV by a step-up transformer and connected to the existing 11 kV grid.
The total electrical energy generated by the Yaleasandra plant during 2010 was
3.34 million kWh and 3.30 million units were sold to the grid. Although the
performance of the photovoltaic modules was good, there were teething
troubles associated with the inverters, which was the main reason for reduced
energy generation. The impact of temperature variation of modules on their
performance was studied both on daily and yearly basis. It is observed that the
efficiency of the plant is more sensitive to temperature than the solar insolation.
Daily datasets of five minute average data have been used for in-depth analysis.
Some of the maintenance and technical related problems faced by the plant
operators have also been discussed.
*CheckMNREwebsite(http://www.mnre.gov.in/solar-conclave2010.htm)formoredetailson
grid-connectedsolarpowerplantsinIndia
Executive Summary
1. 1
2. 4
2.1 Technical details 5
2.2 Cost details 8
2.3 Plant Maintenance & Operation 8
3. 9
3.1 Segment-1 and Segment-2 10
3.2 PV Modules Temperature 17
3.3 Performance of Inverter-1 18
3.3.1 Effect of temperature on the efficiency 19
3.3.2 Performance of Inverter-1 on good days – Daily plots 20
4. 23
5. 25
6. 26
7. 27
Introduction
Site details
Performance Analysis
Technical and maintenance related problems
Conclusion
References
Acknowledgments
Contents
Karnataka's power sector has three main hydro and other renewable energy sources.
utilities namely; Karnataka Power So, to reduce the dependence on fossil fuels
Corporation Ltd. (KPCL) - the Public Sector and increase the share of renewable energy
generation utility, the Karnataka Power sources, KPCL has started investing in wind
Transmission Corporation Ltd. (KPTCL) - and solar energy technologies.
the Public Sector transmission utility, and its
regional distribution utilities - Electricity
In early 2009, KPCL started the ‘Arunodaya’Supply Companies (ESCOMs). KPCLis the
scheme to demonstrate, popularize andmain power generator in the state with an
increase the usage of solar energy forinstalled capacity of 5975.91 MW of hydel,
electricity generation. Under this scheme,thermal, solar and wind energy, with an
KPCL came up with a proposal for installingadditional 9500 MW in the pipeline.
the country's first 3MW scale photovoltaicp
solar power plant near Yalesandra village in
Till 1985, the state's entire capacity had Kolar district of Karnataka. The intent of the
been hydroelectric, but with 2328 MW of project was to provide power to the farmers
coal based thermal power stations (and a to enable pumping and using of the
few diesel and wind-based plants), the hydro groundwater for irrigation. There are around
share of capacity has dropped to about 61%. 450-500 10-HP pumps in about 14
Further, only about 75% of the hydro surrounding villages and farmers were
capacity is available for utilization; the unable to use these at full capacity because
remaining 25% comprises (a) “non-firm” of inconsistent power supply. The Kolar
capacity (i.e. a part of the water stored in p l a n t w a s f u l l y c o m p l e t e d a n d
some hydro-reservoirs is also meant for commissioned on 27 December 2009 (see
irrigation), (b) unforeseen outages Figure1). Later, two more plants with the
(necessitating a spinning reserve), and (c) same capacity were constructed in Belgaum
maintenance protection reserve. Also, in and Raichur (seeTable1 and Figure2).
years of poor rainfall, the contribution of
hydel plants to annual electricity generation
India has an ambitious plan to build largedecreases further [1]. One of the main
grid-connected solar power plants, with areasons for the power crisis in 2008-09 was
cumulative installed capacity of 20,000 MWPthe failure of the monsoon, which reduced
by 2020, under the National Solar Mission.the reservoir levels in the major hydel
Hence, it is essential to document thereservoirs (viz., Linganamakki, Supa and
performance of the first large-scaleMani) by 26% compared to 2007-08 and this
grid-connected solar power plant installedled to a reduction of 29.51% (2261 MU) in
in Karnataka. This report contains thehydro generation [2]. All of these are leading
analysis of the performance of theto an increased dependence on thermal
photovoltaic solar power plant in Kolarplants, whose GHG emissions are high and
during 2010.pollute the environment more compared to
1
1. Introduction
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 1 : Photovoltaic Solar Power Plant at Yalesandra, Kolar, Karnataka
Table 1 : Mega Watt scale Solar PV Plants in Karnataka State (all are under KPCL)
Place
Yalesandra
Kolar
Itnal, Chikkodi
Belgaum
Yapaldinni
Raichur
Shivanasamudra
Mandya
Cost per Mega Watt
(Approximate figures)
Rs. 20 crore
Rs. 20 crore
Rs. 14.5 crore
-
Total Nominal
Capacity (MW)
3
3
3
5
Contractor
Titan Energy Systems Ltd.
Photon Energy Systems Ltd.
BHEL
(yet to be commissioned)
-
2
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 2 : Karnataka map showing the locations of all the three 3MW Solar PV Power Plants
3
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
2. Site details
The Yalesandra plant installation site has a room, substation and other ancillary
steep slope with a level difference of about structures. The general information
15 m and there are rock outcrops in the site. regarding the climatic conditions of Kolar
The structures for the Power Plant district and description of the Plant are given
comprises Solar Arrays, PCUs, control in theTables 2 and 3.
Table 2 : General Climatic conditions of Kolar district [3]
Height above sea level
Ambient Air Temperature
Relative Humidity
Rainfall
882 m
o
Maximum: 40 C
Minimum: 18o
C
Maximum: 99.1% (during monsoon)
Minimum: 18.3%
Annual average: 1549 mm
Period: 4 months
Table 3 : General description of Yalesandra PV Plant
Place of Installation Near Yalesandra Village, Kolar, Karnataka,
India
Latitude & Longitude of the place 12
0
53’ & 78
0
09’
Allotted Land Area 15 acres (10.3 acres effectively used)
Nominal Capacity of the PV Plant 3 MW
Date of Commission 27th December 2009
Owner Karnataka Power Corporation Limited
(KPCL)
Installed by (Contractor) Titan Energy Systems Ltd., Secunderabad
Modules Titan S6-60 series
SCADA for diagnosing and monitoring Yes
PCU (Inverters) 250 kW (12 Nos)
HT Transformer and switchgear for 1.25 MVA for each MW
evacuation
4
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
2.1 Technical details
Segments
The 3 MW Plant is divided into three single Inverter, and each array consists of 24
independent segments of one MW each. modules connected in series. The power
Each segment is equipped with four generated from 3 MW PV Plant at 0.415 kVp
Inverters of 250 kW each and grouped is stepped up to 11 kV with the help of three
together to form one LT panel. Depending on step-up transformers and connected to
the mix of 225 & 240 Wp modules, 45 to 46 existing 11 kV lines. The simple block
PVArrays are connected in parallel to each diagram of the Plant is shown in Figure 3.
Figure 3 : Simple block diagram of the PV Plant
LT PANEL 3
z
=
z
=
z
=
z
=
z
=
z
=
z
=
z
=
z
=
z
=
z
=
z
=
HT
METERING
CUBICLE
LT PANEL 2
PV Arrays PCUs MCBs
TRANSFORMER 2
LT PANEL 1
TO SCADA
TO SCADA
TO SCADA
SPARE
11 kV
KPTCL lines
11 kV HT PANELTRANSFORMER 1
TRANSFORMER 3
5
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Tables 4 and 5 give the general technical details and the module specifications of the Plant.
Table 4 : Technical data of Solar PV
225 W & 240 Wp pTwo type of S6- 60 series modules are used
13,368
[10,152 - 225 W ;p 3216 – 240 Wp ]
Total number of modules
Mono-Crystalline SiliconSolar Cell material
24 Modules1 Array
45-46 (Total 557 Arrays with 12 Inverters)No. of Arrays per Inverter(250 kW)
1st MW – 181
2nd & 3rd MW– 188 per MW
Arrays per MW
5.4 acreTotal SolarCells area
15 degreeInclination of Modules
Table 5 : Module Specifications [4]
Type S6-60 series
Maximum Power, Pmp (W) 225 240
Maximum Power Voltage (Vmp) 28.63 V 29.62 V
Maximum Power Current (Imp) 7.93 A 8.12A
Open Circuit Voltage (Voc) 37.50 V 37.62 V
Short Circuit Current (Isc) 8.52 A 8.55A
Module dimensions (mm) 1657 x 987 x 42
Number, type and arrangement of cells 60, Mono-Crystalline, 6 x 10 Matrix
Cell Size 156 x 156 (mm)
Nominal Operating Cell Temp (°C)NOCT– 45
Weight (Kg) 19
Glass Type and Thickness 3.2mm Thick, Low iron, Tempered
6
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Power Conditioning Units (PCUs) Transformers
All the twelve PCUs are identical and are The full load rating of the Transformers is
supplied by the single manufacturer 1.25 MVA. All the three oil - cooled
BONFIGLIOLI (VECTRON, RPS 450 type). Transformers are supplied by the
The MPPT device is in-built in the control manufacturer Pan Electro Technic
system which allows operating at constant Enterprises Pvt. Ltd. The efficiency is
voltage. The efficiency of the PCUs is 98.91% at rated voltage and 99.3% at
around 96% at nominal load. The rated maximum flux density.
capacity of the PCU is 250 kW.
Mounting structure
Type
6 x 4 Module Array
(24 modules per )Structure
Material Mild Steel
Overall dimensions (mm) 6780x 6030
Coating Galvanized
Wind rating 160 km per hour
Tilt angle 150
Foundation PCC
Fixing type Nut Bolts
Timelines
Foundation was laid on 9th January 2009 30th September 2009, 2 MW on 12th
and the site handed over to TITAN on 28th November and 3 MW on 27th December
May 2009. 1MW was completed onp 2009.
p
p
7
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
2.2 Cost details
Table 6 : Cost breakup of 3 MWp Yalesandra PV power plant [3] [5]
The total cost of installing the Power Plant The detailed Cost breakup of 3 MW Kolar PV
including the maintenance charges for first plant is given inTable 6.
three years is approximately Rs. 60 crores.
Item
SPV Arrays totaling to 3 MWp
PCUs
Mounting structures
Cables & Hardware
Junction box & distribution boxes
Lightning Arrester, Earthing kit
PVC pipes & accessories
Spares for 3 years
SCADA system
Taxes, CST/KVAT, etc.
Design, engineering, quality surveillance,
testing, transportation, insurance coverage, etc.
Total Supply of Equipments (for 3 MW)
Erection & Commissioning
10 kW additional solar PV system with
Battery support
Cost (in Rupees)
43,50,00,000
5,40,00,000
3,00,00,000
50,00,000
9,00,000
12,00,000
3,00,000
5,00,000
20,00,000
1,05,78,000
1,80,99,400
55,75,77,400
2,98,00,000
31,00,000
Note: Miscellaneous expenses have not been taken into account
2.3 Plant Maintenance & Operation
In addition to 3 MW , one more 10 kW PV regularly to meet the water requirements of
the Plant. The other two pump sets remainplant has been installed on the rooftop of
idle most of the time.office building to take care of domestic
lighting and cooling loads of the Plant, Cleaning of PV Modules:
including the load of exhaust fans. At
Generally, the modules are cleaned by
present, the plant is maintained by 13
spraying water with the help of extendable
workers which includes 2 technical persons
hosepipes. Occasionally, wipers are used to
who look after data collection and
remove the accumulated dirt and bird
monitoring.
droppings, say once in a month. On an
Three bore - wells have been installed at average, each module is cleaned once in a
the site with pump-set capacities of 2 HP, week on rotational basis.
5 HP and 10 HP. The 2 HP pump set is used
p
8
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
3. Performance analysis
The total Energy produced by 3 MW Plant generation during 2010. Since Segment-3
was not performing satisfactorily for a fewduring the year 2010 was 3,347,480 units.
months, which is evident from the figure, weOut of this, 3,303,200 units were sold to the
will restrict our analysis to the first twogrid. Figure 4 shows the contribution of all
Segments only.the three Segments in the total power
p
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
450000
400000
350000
300000
250000
200000
150000
100000
50000
0
MonthlyEnergyGeneration(kWh)
Energy generated by 3 MW Plant - 2010
Segment-3
Segment-2
Segment-1
Figure 4 : Contribution of all the three segments in the total power generation during 2010
9
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
The performance of the first two segments mean output of 6655.4 kWh per day. The
and their cumulative production over the capacity factor for this 2 MW plant was
year 2010 is shown in Figures 5 and 6 around 14.52% at the generation end
respectively. The total cumulative Energy (impact of grid-off times and maintenance
generated by both the Segments together down times are not included).
for the year 2010 was 2,429,219.6 kWh with
3.1 Segment-1 and Segment-2
Figure 5 : Daily Performance of Segment 1 & 2 during 2010
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
1000
2000
3000
4000
5000
6000
EnergyGeneratedperday[kWh/day]
Time [Daily]
Segment-1
Segment-2
10
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
500000
1000000
1500000
2000000
2500000
Energyproduced[kWh]
Time [Daily]
2,429,219.6 kWh
Figure 6 : Cumulative Energy Produced by Segment 1 & 2 for the year 2010
The highest power generation achieved was temperature and Plant efficiency of 6663
o
11812.4 kWh on 5th February 2010, with the Wh/sqm/day, 42 C and 12.24% respectively.
recorded insolation, average module
11
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
The decline in energy generation during number of cloudy days during that period
August to November period in Figure 7 was (see Figures 8 and 9). The declination can
mainly due to the improper functioning of be seen more clearly in Fig. 11 which shows
four Inverters (two in Segment-1 and the the variation of daily efficiency for the 2 MW
other two in Segment-2), and partially plant during the year 2010.
because of higher plant downtime and more
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
2000
4000
6000
8000
10000
12000
EnergyProduced[kWh]
Time [Daily]
Figure 7: Daily energy production of 2MW Plant [Seg.1 & 2]
12
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 8: Daily performance of all the 8 inverters
Figure 8 shows the daily performance of all 2, 3, 5 and 7 (which are shown in red) were
the inverters, first four come under malfunctioning during the period August to
Segment-1 and the next four under November, as compared with the remaining
Segment-2. It can be seen that the Inverters four inverters.
Inverter 6
Inverter 3
Jan Mar May Jul Sep Nov
Inverter 6
Date
0.0
200.0k
400.0k
600.0k
800.0k
1.0M
1.2M
1.4M
1.6M
Inverter 4
EnergyGen(wh/day)
Inverter 1
0.0
200.0k
400.0k
600.0k
800.0k
1.0M
1.2M
1.4M
1.6M
EnergyGen(wh/day)
Jan Mar May Jul Sep Nov
0.0
200.0k
400.0k
600.0k
800.0k
1.0M
1.2M
1.4M
1.6M
Inverter 7
EnergyGen(wh/day)
Date
Inverter 5
Inverter 2
Inverter 8
Jan Mar May Jul Sep Nov
Date
13
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 9: Monthly Plant down-time in hours-2010
Grid-off times: Figure 9 shows the was observed that the grid-offs occurred
cumulative monthly grid-off times during the mainly during the peak hours (11.30 am –
year 2010. Out of the 357 days of the Plant's 2 pm), that is, when the availability of solar
operation, there were 75 days on which the insolation is maximal.
grid was off for less than an hour and 57 days
The Plant was shut down for 8 days during
with grid-offs more than one hour. Totally the
November for repairing the faulty cables and
grid was off for about 201.4 hours. Also, it
Inverters.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
20
40
60
80
100
Downtime(Hours)
Month
Plant Shut Down
Grid-Off Times
14
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
The Plant is equipped with a Pyranometer mid May to mid June, due to some problem
o
in the Pyranometer. The highest recordedinstalled at an angle of 15 , equal to the
daily insolation was 7199 Wh/sqm on 2ndinclination of the Modules. The Solar
March 2010. The yearly average insolationInsolation recorded at the site is shown in
on the panels was about 4789 Wh/sqm/day.Figure 10. The Insolation data is not
available for about 44 days, especially from
Solar Insolation
o
Figure 10: Daily Solar Insolation at the site - 2010 [@15 . inclination]
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1000
2000
3000
4000
5000
6000
7000
8000
Time [Daily]
15
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Insolation[15Wh/m2]
o
Efficiency
The 2-MW plant efficiency is the combined insolation of 2561 Wh/sqm and an average
0
efficiencies of segments 1 and 2 after the module temperature of 28.63 C. The daily
dc-ac conversion by inverters to 415 Volts efficiency of the 2MW plant ranged from 5%
and just before stepping up to 11 kV ac. So, to 13.41% depending on the performance of
this should not to be confused with the arrays, inverters, average module
overall plant efficiency. temperature and the solar insolation. The
yearly average daily efficiency of the plant
Figure 11 shows the efficiency of the 2 MW
was about 10.14%, considering the days
plant, that is combined efficiency of
which have grid-offs for less than half an
segments 1 & 2, over the study period. The
hour or no grid-offs. The abnormal drop in
highest efficiency achieved was 13.41% on
the efficiency during the last few months was
24th July 2010. The total energy generated
mainly due to inverter related problems.
on that day was 4975.8 kWh with solar
Figure 11: Daily Efficiency of 2 MW Plant [Seg.1&2]
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0
2
4
6
8
10
12
14
16
PlantEfficiency(%)
Time [Daily]
16
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 12: Daily average temperature of PV modules (During day time) – 2010
Figure 12 shows the daily average Although the solar insolation level is more in
temperature of PV modules for the year March compared to January, the efficiency
0
during March is low. This may be due to2010. It ranged from a minimum of 24.65 C
0
increase in the daily average temperature of(on 6th Dec) to a maximum of 51.9 C (on
PV modules during that month, as seen from23rdApril).
the Figure. But this is not very clear because
Figure 13 shows the combined plots of plant
of too much noise in the data. To reduce the
efficiency, daily average modules
noise and explore the issue further, we
temperature and daily solar insolation with
decided to analyze a single inverter which
reference to time scale. It appears from the
had performed well during the study period.
figure that the efficiency is more sensitive to
modules temperature than the insolation.
3.2 PV Modules Temperature
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10
20
30
40
50
60
Temperature[deg.Celsius]
DATE
17
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 13: Daily variation of average modules temperature, insolation (in Wh) and efficiency of the 2MW Plant
3.3 Performance of Inverter-1
As the performance of Inverter-1 is good energy generation by Inverter-1 versus the
compared to other Inverters (see Figure 8), incident solar insolation on that day for the
we chose this Inverter for more in-depth year 2010. The energy generation increases
study. Figure 14 shows the plot of daily linearly with the increase in solar insolation.
18
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Inverter-1
0 1000 2000 3000 4000 5000 6000 7000 8000
0
200
400
600
800
1000
1200
1400
1600
EnergyGenerated(kWh)
Solar Insolation (Wh/m
2
/day)
Figure 14: Annual plot of daily energy generated by Inverter-1 versus solar insolation
3.3.1 Effect of temperature on efficiency
Figure 15 shows the variation in energy This is mainly because of increase in the
generation of solar modules with insolation temperature of modules, which negatively
and the effect of module temperature on impacts the efficiency more during that time
their efficiency. The plots are made using the [see Figure 15(B)]. Figure 16 shows the
5 minutes average values from 10 am to variation in efficiency of the modules with
3 pm on 21st January, 2010. variation in temperature of modules, along
with color mapped values for average solar
Even though the energy generation shows
irradiance. The efficiency of the modules
direct dependency on the incident solar o
decreases from 14.5% at 30 C to 11.5% at
insolation [see Figure 15(A)] and reaches o
55 C. It is also clear from the Figure that thethe maximum during peak insolation hours,
temperature of modules increases with thethe efficiency of the modules decreases and
increase in solar insolation and reaches thereaches the minimum during peak hours.
19
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00
11.2
12.0
12.8
Efficiency
Temperature
Time, 21-Jan
Efficiency(%)
42
49
56
Temperature(
o
C)
maximum during peak insolation hours, values) for the year 2010. Due to lots of
leading to reduced conversion efficiency. noise below 20 , the temperature values
0 0
Thus, the Plant's capacity to produce were binned between 20 C and 55 C. Then
maximum power is retarded during peak the efficiency values were binned between
insolation hours, when the availability of 10% and 15% choosing only the maximum
incident solar radiation is highest, because points. The plot shows linear decrease in the
of increase in modules temperature. daily efficiency of modules from 14.5% to
11.5% with increase in the daily averagedFigure 17 shows the annual plot of daily o o
modules temperature from 25 C to 50 C.efficiency of modules in Inverter-1 versus
daily averaged module temperature (binned
0
C
3.3.2 Performance of Inverter-1 on good days – Daily plots
Figure 18 shows the daily performance plots efficiency of Inverter-1 with modules
of Inverter-1 on 24th March, 11th May, 18th temperature. The values of solar insolation,
June, 24th July and 20th September. The modules temperature and efficiency are
plots on the left side show the variation of averaged for every 5 minute interval. The
energy generation with solar insolation and energy generation values are the cumulative
the right side plots show the variation in figures generated for the same time period.
Figure A: Insolation and Energy Generation (of Invereter-1) Figure B: Efficiency and Temperature of Modules (of Invereter-1)
Figure15: Plots of insolation, & temperature of
Inverter-1 modules on January 21
energy generation, efficiency
09:00 10:00 11:00 12:00 13:00 14:00 15:00
650
700
750
800
850
900
950
1000
1050
1100
1150
1200
Insolation
Energy Generated
Time, Jan 21
Insolation(W)
12000
13000
14000
15000
16000
17000
EnergyGenerated(Wh)
20
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
25 30 35 40 45 50 55 60
11.0
11.5
12.0
12.5
13.0
13.5
14.0
14.5
15.0
5 Min Avg. Efficiency
Efficiency(%)
0
Temperature ( C)
20.00
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000
SCALE FOR AVG
SOL IRR (W/m2)
Figure 16: Efficiency v/s Temperature of modules of Inverter-1
on January 21, 2010 (Color scale : Average Solar Irradiance)
(5 min average values)
Figure 17: Plot of daily maximum efficiency versus temperature of modules in Inverter-1 for 2010
11.0
11.5
12.0
12.5
13.0
13.5
14.0
14.5
25 30 35 40 45 50 55
Temperature ( )0
C
MaximumEfficiency(%)
Maximum Efficiency
Linear Fit of Maximum Efficiency
Plot Maximum Efficiency vs Temperature of Modules in Inverter 1
21
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 18: (Left) Daily plots showing variation of energy generation with insolation;
(Right) Daily plots showing variation of efficiency with modules temperature
09:36 10:48 12:00 13:12 14:24 15:36 16:48
20
30
40
50
60
70
Time (July-24)
TempMod(DegC)
6
7
8
9
10
11
12
13
14
15
Efficiency(%)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
100
200
300
400
500
600
700
800
900
1000
1100
1200
Time (July-24)
SolarInsolation(W/m
2
)
2000
4000
6000
8000
10000
12000
14000
16000
18000
EnergyGeneration(Wh)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
100
200
300
400
500
600
700
800
900
1000
1100
1200
Time (March-24)
SolarInsolation(W/m
2
)
2000
4000
6000
8000
10000
12000
14000
16000
18000
EnergyGeneration(Wh)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
20
30
40
50
60
70
Time (March-24)
TempMod(Deg.C)
6
7
8
9
10
11
12
13
14
15
Efficiency(%)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
100
200
300
400
500
600
700
800
900
1000
1100
1200
Time (Sept-20)
SolarInsolation(W/m
2
)
2000
4000
6000
8000
10000
12000
14000
16000
18000
EnergyGeneration(Wh)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
20
30
40
50
60
70
Time (Sept-20)
TempMod(DegC)
6
8
10
12
14
Efficiency(%)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
100
200
300
400
500
600
700
800
900
1000
1100
1200
Time (June-18)
SolarInsolation(W/m
2
)
2000
4000
6000
8000
10000
12000
14000
16000
18000
EnergyGeneration(Wh)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
20
30
40
50
60
70
Time (June-18)
TempMod(Deg.C)
6
7
8
9
10
11
12
13
14
15
Efficiency(%)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
100
200
300
400
500
600
700
800
900
1000
1100
1200
Time (May-11)
SolarInsolation(W/m
2
)
2000
4000
6000
8000
10000
12000
14000
16000
18000
EnergyGeneration(Wh)
09:36 10:48 12:00 13:12 14:24 15:36 16:48
20
30
40
50
60
70
Time (May-11)
TempMod(Deg.C)
6
7
8
9
10
11
12
13
14
15
Efficiency(%)
Solar Insolation Energy Generation
Temp Mod Efficiency
22
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
4. Technical and maintenance related problems
Some of the major technical & maintenance ?Presently the modules are cleaned by
related problems faced by the plant spraying water. But the dust
operators are as follows: accumulated on the modules turns into
paste form once the modules are water
?The power of the PV plant cannot be fed sprayed, making it difficult to remove.
to the grid if the power supply from the Also, the height of the modules
grid stops. Due to this, the power from mounting structures (see Figure 19)
the PV Plant is not available when it is makes it impossible to remove the dirt
needed most and the capacity of the completely with wipers while standing
Plant to work effectively has been on the ground. This has led inevitably, to
retarded. the option of cleaning the modules by
climbing on top of them (and then using?There is no tracking mechanism to
wipers!). This will weaken the strengthlocate the modules if they fail. If a
of solar modules as well as mountingmodule fails, it is very tiresome to
structures in the long run and also affectidentify it because no sensors have
the power production. Hence, it is feltbeen installed for this purpose. The only
that there is a need to address this issuesolution presently available is to wait till
by developing alternate method/the peak time to identify the Inverter
technology for cleaning the PV(from which the output is lower). Then
modules.the Inverter has to be isolated and all
the 45-46 arrays connected to this ?Recently, some of the modules have
inverter should be checked. Once the shown change in color (see Figure 20).
faulty array is located, all the connected It is yet to be ascertained whether this
modules need to be checked to identify color change in the modules has any
the faulty one. negative impact on their performance.
0
Figure 19: Photo of PV Plant showing the modules mounting structures inclined at 15 .
23
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Figure 20: Visual color change of the photovoltaic modules
24
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
5. Conclusion
The performance of the 3 MW Yalesandra afternoon. The daily efficiency of modulesp
varied from 14.5% to 11.5% with thesolar photovoltaic power plant has been
variation in the daily averaged modulesanalyzed for the year 2010. The total
o o
temperature from 25 C to 50 C. Hence,electrical energy generated by the
cooling of the solar modules may beYalesandra power plant during 2010 was
desirable to increase the efficiency. There is3.34 million kWh and 3.30 million units were
a need to evaluate if the additional energysold to the grid. Based on the performance of
required for cooling the solar modules will bethe first two segments we estimate the mean
less than the additional energy generatedoutput to be 6655 kWh per day. This is lower
due to higher efficiency.than expected for a solar power plant and is
on account of teething trouble associated
with inverters and the grid-encountered in
The daily plots showing the variation ofthe first year of the operation of the plant. It
efficiency with modules temperature and thewas found that failure in inverters were the
variation of energy generation with solarmost frequent incidents. This is mostly
insolation have been plotted for five differentcaused by lack of experience in the initial
days of the year. Also, some of the presentproduction stage and some unexplained
maintenance and technical problems facedinverter failures might be caused by
by plant operators, including the colordisturbance from the grid and other
change in PV modules and cleaning issues,interconnected issues [6].
have been discussed.
The impact of temperature variation (of
It is also suggested that more measuringmodules) on the performance of
instruments such as Pyrheliometer, Rainphotovoltaic mono-crystalline silicon
Gauge, Thermocouple (Thermometer) formodules was studied both on daily and
measuring ambient temperature, to beyearly basis (daily average values). It is
installed in the plant and the existingobserved that the efficiency of modules is
instruments to be calibrated for greatermore sensitive to temperature than the solar
accuracy. This will enable further technicalinsolation. The normal daily trend is that the
analysis of India’s first 3MW scale plant andefficiency of Plant is high during morning
help KPCL in their future solar power planthours but low during the middle of the day
projects.and again starts increasing from late
25
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
6. References
1.AntonetteD'SaandK.V.NarasimhaMurthy,Karnataka'sPowerSector&SuggestedWays
Forward,InternationalEnergyInitiative,discussionpaper,2002.
2.K.Jairaj,EnergyscenarioinKarnataka,powerpointpresentation,EnergyDepartment,
GovernmentofKarnataka.
3.SolarPVPowerPlants,contractagreementforsupplyofequipments,CE(EI&TA)/SPV,
KPCLandTitanEnergySystemsLtd.,Secunderabad.
4.Operationmanual,TitanEnergySystemsLtd.,Secunderabad.
5.ContractagreementforErection,testingandcommissioningof3MWSolarPVpowerplant,
KPCLandTitanEnergySystemsLtd.,Secunderabad.
6.MohamedA.EltawilandZhengmingZhao,Grid-connectedphotovoltaicpowersystems:
Technicalandpotentialproblems-Areview,RenewableandSustainableEnergyReviews,
14,2010,112–129.
26
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
7. Acknowledgements
WewishtothankMr.B.R.Nagaraju,Ex-ChiefEngineer,REProjects,KarnatakaPower
CorporationLtd.(KPCL)forparticipatingintheprojectbygivingauthorizationtocollectanduse
dataforthisresearch.WethankMr.A.V.V.Reddy,ExecutiveEngineer,in-chargeofKolarPV
Plantforgivingustheperformancedataoftheplant.Wealsoappreciatehisspendingvaluable
timewithusandsharinghisconcernsabouttheplantduringourfieldvisits.WealsothankMr.D.
C.Krishnamurthy,ExecutiveEngineer,ElectricalDivision,KPCLforhelpingusingettingthedata
andotherinformationrelatedtotheplant.
WealsoacknowledgeMr.M.K.NagarajandtheofficestaffatDivechaCentreforClimate
Change,fortheirkindsupportduringthecourseofthisproject.
27
3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka
ReportIISc-DCCC11RE1
Satellite image of the 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka
DIVECHA CENTRE FOR CLIMATE CHANGE
INDIAN INSTITUTE OF SCIENCE
Bangalore
REPORT IISc-DCCC 11 RE 1
AUGUST 2011

More Related Content

What's hot

Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantShahbaz Makandar A.
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projectsshivraj negi
 
Analisa kumparan pada motor induksi
Analisa kumparan pada motor induksiAnalisa kumparan pada motor induksi
Analisa kumparan pada motor induksiBinsar Nainggolan
 
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor LayerDOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor Layerjeep82cj
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwarDevendra khairiya
 
PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11naveen bhati
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystsolpowerpeople
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantL'Obel Solar Power System
 
Presentation on Solar Cells
Presentation on Solar CellsPresentation on Solar Cells
Presentation on Solar Cellsyousuf1234
 
Report on grid substation
Report on grid substationReport on grid substation
Report on grid substationmedhashandilya
 
Internship Training Project Report "PowerGrid"
Internship Training Project Report "PowerGrid"Internship Training Project Report "PowerGrid"
Internship Training Project Report "PowerGrid"Raushan11
 
solar photovolatic power system
solar photovolatic power systemsolar photovolatic power system
solar photovolatic power systemSubir paul
 
On Grid Solar System to Create your own Electricity
On Grid Solar System to Create your own ElectricityOn Grid Solar System to Create your own Electricity
On Grid Solar System to Create your own Electricityrenewgreensolar
 
Electricity and power consumption in india (1)
Electricity and power consumption in india (1)Electricity and power consumption in india (1)
Electricity and power consumption in india (1)Anirudh Sharma
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYRanjan kumar
 
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUS
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUSSMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUS
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUSPower System Operation
 

What's hot (20)

Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
 
Konsep PLTS 2.4
Konsep PLTS 2.4Konsep PLTS 2.4
Konsep PLTS 2.4
 
Basics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig GensolBasics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig Gensol
 
Analisa kumparan pada motor induksi
Analisa kumparan pada motor induksiAnalisa kumparan pada motor induksi
Analisa kumparan pada motor induksi
 
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor LayerDOE Efficiency Enhancing Solar Downconverting Phosphor Layer
DOE Efficiency Enhancing Solar Downconverting Phosphor Layer
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar
 
PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11PPT OF SOLAR NAVEEN' `11
PPT OF SOLAR NAVEEN' `11
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plant
 
High Penetration of Renewable Energy
High Penetration of Renewable EnergyHigh Penetration of Renewable Energy
High Penetration of Renewable Energy
 
Presentation on Solar Cells
Presentation on Solar CellsPresentation on Solar Cells
Presentation on Solar Cells
 
Report on grid substation
Report on grid substationReport on grid substation
Report on grid substation
 
Internship Training Project Report "PowerGrid"
Internship Training Project Report "PowerGrid"Internship Training Project Report "PowerGrid"
Internship Training Project Report "PowerGrid"
 
solar photovolatic power system
solar photovolatic power systemsolar photovolatic power system
solar photovolatic power system
 
On Grid Solar System to Create your own Electricity
On Grid Solar System to Create your own ElectricityOn Grid Solar System to Create your own Electricity
On Grid Solar System to Create your own Electricity
 
Electricity and power consumption in india (1)
Electricity and power consumption in india (1)Electricity and power consumption in india (1)
Electricity and power consumption in india (1)
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
 
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUS
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUSSMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUS
SMART METERING, REGULATORY ASPECTS, STANDARDS AND DEVELOPMENT STATUS
 
Power system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter fivePower system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter five
 

Viewers also liked

Solar energy and its applcations
Solar energy and its applcationsSolar energy and its applcations
Solar energy and its applcationssaiganesh seku
 
Solar energy two case studies
Solar energy   two case studiesSolar energy   two case studies
Solar energy two case studiesK Vivek Varkey
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...sdchrosis
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Ashish Verma
 
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Smithers Apex
 
iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iplon
 
Project on Solar Energy
Project on Solar EnergyProject on Solar Energy
Project on Solar Energygagneeshkaur
 

Viewers also liked (10)

Solar energy and its applcations
Solar energy and its applcationsSolar energy and its applcations
Solar energy and its applcations
 
Solar energy two case studies
Solar energy   two case studiesSolar energy   two case studies
Solar energy two case studies
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...
 
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
 
iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011
 
Pv plant references
Pv plant referencesPv plant references
Pv plant references
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Solar Power Plant Design and PV Syst
Solar Power Plant Design and PV SystSolar Power Plant Design and PV Syst
Solar Power Plant Design and PV Syst
 
Project on Solar Energy
Project on Solar EnergyProject on Solar Energy
Project on Solar Energy
 

Similar to Kolar solar pv plant a case study of

Floating Solar Photovoltaic system An Emerging Technology
Floating Solar Photovoltaic system An Emerging TechnologyFloating Solar Photovoltaic system An Emerging Technology
Floating Solar Photovoltaic system An Emerging TechnologyPooja Agarwal
 
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging TechnologyMd Shahabuddin
 
A study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaA study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaKetan Vador
 
Solar Photovoltaic (PV) Grid Integration Issues
Solar Photovoltaic (PV) Grid Integration IssuesSolar Photovoltaic (PV) Grid Integration Issues
Solar Photovoltaic (PV) Grid Integration IssuesIJMTST Journal
 
1 s2.0-s2214157 x13000117-main
1 s2.0-s2214157 x13000117-main1 s2.0-s2214157 x13000117-main
1 s2.0-s2214157 x13000117-mainKusang Sherpa
 
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic Systems
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic SystemsEntrepreneurship Through Start-ups in Hill Areas Using Photovoltaic Systems
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic SystemsjournalBEEI
 
Techno economic analysis of SPV-DG hybrid model using HOMER
Techno economic analysis of SPV-DG hybrid model using HOMERTechno economic analysis of SPV-DG hybrid model using HOMER
Techno economic analysis of SPV-DG hybrid model using HOMERIRJET Journal
 
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaA Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaIRJET Journal
 
Rural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptRural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptlakshmi nidoni
 
Performance Analysis of Grid Connected Solar Captive Power Plant
Performance Analysis of Grid Connected Solar Captive Power PlantPerformance Analysis of Grid Connected Solar Captive Power Plant
Performance Analysis of Grid Connected Solar Captive Power PlantJagan Rampalli
 
Solar System
Solar SystemSolar System
Solar SystemPatel Mit
 
HYBRID ROAD RAIL POWER GENERATOR
HYBRID ROAD RAIL POWER GENERATORHYBRID ROAD RAIL POWER GENERATOR
HYBRID ROAD RAIL POWER GENERATORIRJET Journal
 
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...IJMTST Journal
 
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...IRJET Journal
 
Renewable energy for bts (2)
Renewable energy for bts (2)Renewable energy for bts (2)
Renewable energy for bts (2)nasir12345678900
 
Restrainment of renewable energy systems and smart grids ppt
Restrainment of renewable energy systems and  smart grids pptRestrainment of renewable energy systems and  smart grids ppt
Restrainment of renewable energy systems and smart grids pptBIPUL KUMAR GUPTA
 

Similar to Kolar solar pv plant a case study of (20)

21PESGM2656.pptx
21PESGM2656.pptx21PESGM2656.pptx
21PESGM2656.pptx
 
Floating Solar Photovoltaic system An Emerging Technology
Floating Solar Photovoltaic system An Emerging TechnologyFloating Solar Photovoltaic system An Emerging Technology
Floating Solar Photovoltaic system An Emerging Technology
 
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
 
JSJawa_Feb27.ppt
JSJawa_Feb27.pptJSJawa_Feb27.ppt
JSJawa_Feb27.ppt
 
A study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in indiaA study on charanka solar park and kudankulam nuclear power plant in india
A study on charanka solar park and kudankulam nuclear power plant in india
 
Solar Photovoltaic (PV) Grid Integration Issues
Solar Photovoltaic (PV) Grid Integration IssuesSolar Photovoltaic (PV) Grid Integration Issues
Solar Photovoltaic (PV) Grid Integration Issues
 
1 s2.0-s2214157 x13000117-main
1 s2.0-s2214157 x13000117-main1 s2.0-s2214157 x13000117-main
1 s2.0-s2214157 x13000117-main
 
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic Systems
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic SystemsEntrepreneurship Through Start-ups in Hill Areas Using Photovoltaic Systems
Entrepreneurship Through Start-ups in Hill Areas Using Photovoltaic Systems
 
Techno economic analysis of SPV-DG hybrid model using HOMER
Techno economic analysis of SPV-DG hybrid model using HOMERTechno economic analysis of SPV-DG hybrid model using HOMER
Techno economic analysis of SPV-DG hybrid model using HOMER
 
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaA Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
 
Rural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptRural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar ppt
 
Performance Analysis of Grid Connected Solar Captive Power Plant
Performance Analysis of Grid Connected Solar Captive Power PlantPerformance Analysis of Grid Connected Solar Captive Power Plant
Performance Analysis of Grid Connected Solar Captive Power Plant
 
Solar System
Solar SystemSolar System
Solar System
 
HYBRID ROAD RAIL POWER GENERATOR
HYBRID ROAD RAIL POWER GENERATORHYBRID ROAD RAIL POWER GENERATOR
HYBRID ROAD RAIL POWER GENERATOR
 
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
 
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
 
Final Report
Final ReportFinal Report
Final Report
 
Renewable energy for bts (2)
Renewable energy for bts (2)Renewable energy for bts (2)
Renewable energy for bts (2)
 
H0371056061
H0371056061H0371056061
H0371056061
 
Restrainment of renewable energy systems and smart grids ppt
Restrainment of renewable energy systems and  smart grids pptRestrainment of renewable energy systems and  smart grids ppt
Restrainment of renewable energy systems and smart grids ppt
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 

Kolar solar pv plant a case study of

  • 1. Indian Institute of Science Renewable Energy Systems Reports A case study of 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka Performance assessment & recommendations H. Mitavachan, Anandhi Gokhale and J. Srinivasan REPORT IISc-DCCC 11 RE 1 AUGUST 2011 NDIAIN OT EUT FTISNI ECSCIEN Divecha Centre for Climate Change
  • 2. The Divecha Centre for Climate Change was established at the Indian Institute of Science in January 2009 with a generous financial contribution from Arjun and Diana Divecha and the Grantham Foundation for the Protection of the Environment. The primary goal of this Centre is to understand climate variability and climate change and its impact on the environment. The Centre has undertaken outreach activities to create awareness among people and policy makers about climate change and its consequences. This has been done through workshops, lectures and quiz contests. An annual invited public lecture called the ‘Jeremy Grantham Lecture on Climate Change’ has been organized. The Centre has identified technologies to mitigate climate change in collaboration with entrepreneurs and different engineering departments in the Indian Institute of Science. The Centre is also working with Grantham Institute for Climate Change at Imperial College, London, on the impact of climate change on water.
  • 3. Indian Institute of Science Renewable Energy Systems Reports H. Mitavachan, Anandhi Gokhale and J. Srinivasan REPORT IISc-DCCC 11 RE 1 AUGUST 2011 NDIAIN OEUT FTITSIN ES CCIEN Divecha Centre for Climate Change A case study of 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka Performance assessment & recommendations
  • 4.
  • 5. Karnataka Power Corporation Limited (KPCL) has established 3 MW capacitypeak grid-connected solar photovoltaic power plant near Yalesandra village in Kolar district of Karnataka, which is the first of its scale in India. After the site preparations were completed the first segment was installed in 4 months, followed by the second and third segments in the next two months. The plant was fully commissioned on 27 December 2009. The Yalesandra plant is one among 20 such Mega-watt size solar power plants in India, *as on 31st July 2011. India has an ambitious plan to build large grid-connected solar power plants, with a cumulative installed capacity of 20,000 MWp by 2020, under the National Solar Mission. Hence, it is essential to document the performance of the first large-scale grid-connected solar power plant installed in Karnataka. In this report we discuss the performance of the photovoltaic solar power plant in Kolar during 2010. 0 The Yalesandra power plant is located at a latitude of 12 53' and a longitude of 0 78 09'. The overall area occupied by photovoltaic modules is 10.3 acres. The plant has 3 segments with each segment having an installed capacity of 1 MW .p Each segment has 4 inverters with a capacity of 250 kW each. There are 13,368 modules (557 arrays with 24 modules per array) that contain mono-crystalline Silicon solar cells. The solar photovoltaic modules are connected such that a voltage of 415 volts is generated at the output of each inverter. This is stepped up to 11 kV by a step-up transformer and connected to the existing 11 kV grid. The total electrical energy generated by the Yaleasandra plant during 2010 was 3.34 million kWh and 3.30 million units were sold to the grid. Although the performance of the photovoltaic modules was good, there were teething troubles associated with the inverters, which was the main reason for reduced energy generation. The impact of temperature variation of modules on their performance was studied both on daily and yearly basis. It is observed that the efficiency of the plant is more sensitive to temperature than the solar insolation. Daily datasets of five minute average data have been used for in-depth analysis. Some of the maintenance and technical related problems faced by the plant operators have also been discussed. *CheckMNREwebsite(http://www.mnre.gov.in/solar-conclave2010.htm)formoredetailson grid-connectedsolarpowerplantsinIndia Executive Summary
  • 6.
  • 7. 1. 1 2. 4 2.1 Technical details 5 2.2 Cost details 8 2.3 Plant Maintenance & Operation 8 3. 9 3.1 Segment-1 and Segment-2 10 3.2 PV Modules Temperature 17 3.3 Performance of Inverter-1 18 3.3.1 Effect of temperature on the efficiency 19 3.3.2 Performance of Inverter-1 on good days – Daily plots 20 4. 23 5. 25 6. 26 7. 27 Introduction Site details Performance Analysis Technical and maintenance related problems Conclusion References Acknowledgments Contents
  • 8.
  • 9. Karnataka's power sector has three main hydro and other renewable energy sources. utilities namely; Karnataka Power So, to reduce the dependence on fossil fuels Corporation Ltd. (KPCL) - the Public Sector and increase the share of renewable energy generation utility, the Karnataka Power sources, KPCL has started investing in wind Transmission Corporation Ltd. (KPTCL) - and solar energy technologies. the Public Sector transmission utility, and its regional distribution utilities - Electricity In early 2009, KPCL started the ‘Arunodaya’Supply Companies (ESCOMs). KPCLis the scheme to demonstrate, popularize andmain power generator in the state with an increase the usage of solar energy forinstalled capacity of 5975.91 MW of hydel, electricity generation. Under this scheme,thermal, solar and wind energy, with an KPCL came up with a proposal for installingadditional 9500 MW in the pipeline. the country's first 3MW scale photovoltaicp solar power plant near Yalesandra village in Till 1985, the state's entire capacity had Kolar district of Karnataka. The intent of the been hydroelectric, but with 2328 MW of project was to provide power to the farmers coal based thermal power stations (and a to enable pumping and using of the few diesel and wind-based plants), the hydro groundwater for irrigation. There are around share of capacity has dropped to about 61%. 450-500 10-HP pumps in about 14 Further, only about 75% of the hydro surrounding villages and farmers were capacity is available for utilization; the unable to use these at full capacity because remaining 25% comprises (a) “non-firm” of inconsistent power supply. The Kolar capacity (i.e. a part of the water stored in p l a n t w a s f u l l y c o m p l e t e d a n d some hydro-reservoirs is also meant for commissioned on 27 December 2009 (see irrigation), (b) unforeseen outages Figure1). Later, two more plants with the (necessitating a spinning reserve), and (c) same capacity were constructed in Belgaum maintenance protection reserve. Also, in and Raichur (seeTable1 and Figure2). years of poor rainfall, the contribution of hydel plants to annual electricity generation India has an ambitious plan to build largedecreases further [1]. One of the main grid-connected solar power plants, with areasons for the power crisis in 2008-09 was cumulative installed capacity of 20,000 MWPthe failure of the monsoon, which reduced by 2020, under the National Solar Mission.the reservoir levels in the major hydel Hence, it is essential to document thereservoirs (viz., Linganamakki, Supa and performance of the first large-scaleMani) by 26% compared to 2007-08 and this grid-connected solar power plant installedled to a reduction of 29.51% (2261 MU) in in Karnataka. This report contains thehydro generation [2]. All of these are leading analysis of the performance of theto an increased dependence on thermal photovoltaic solar power plant in Kolarplants, whose GHG emissions are high and during 2010.pollute the environment more compared to 1 1. Introduction 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 10. Figure 1 : Photovoltaic Solar Power Plant at Yalesandra, Kolar, Karnataka Table 1 : Mega Watt scale Solar PV Plants in Karnataka State (all are under KPCL) Place Yalesandra Kolar Itnal, Chikkodi Belgaum Yapaldinni Raichur Shivanasamudra Mandya Cost per Mega Watt (Approximate figures) Rs. 20 crore Rs. 20 crore Rs. 14.5 crore - Total Nominal Capacity (MW) 3 3 3 5 Contractor Titan Energy Systems Ltd. Photon Energy Systems Ltd. BHEL (yet to be commissioned) - 2 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 11. Figure 2 : Karnataka map showing the locations of all the three 3MW Solar PV Power Plants 3 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 12. 2. Site details The Yalesandra plant installation site has a room, substation and other ancillary steep slope with a level difference of about structures. The general information 15 m and there are rock outcrops in the site. regarding the climatic conditions of Kolar The structures for the Power Plant district and description of the Plant are given comprises Solar Arrays, PCUs, control in theTables 2 and 3. Table 2 : General Climatic conditions of Kolar district [3] Height above sea level Ambient Air Temperature Relative Humidity Rainfall 882 m o Maximum: 40 C Minimum: 18o C Maximum: 99.1% (during monsoon) Minimum: 18.3% Annual average: 1549 mm Period: 4 months Table 3 : General description of Yalesandra PV Plant Place of Installation Near Yalesandra Village, Kolar, Karnataka, India Latitude & Longitude of the place 12 0 53’ & 78 0 09’ Allotted Land Area 15 acres (10.3 acres effectively used) Nominal Capacity of the PV Plant 3 MW Date of Commission 27th December 2009 Owner Karnataka Power Corporation Limited (KPCL) Installed by (Contractor) Titan Energy Systems Ltd., Secunderabad Modules Titan S6-60 series SCADA for diagnosing and monitoring Yes PCU (Inverters) 250 kW (12 Nos) HT Transformer and switchgear for 1.25 MVA for each MW evacuation 4 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 13. 2.1 Technical details Segments The 3 MW Plant is divided into three single Inverter, and each array consists of 24 independent segments of one MW each. modules connected in series. The power Each segment is equipped with four generated from 3 MW PV Plant at 0.415 kVp Inverters of 250 kW each and grouped is stepped up to 11 kV with the help of three together to form one LT panel. Depending on step-up transformers and connected to the mix of 225 & 240 Wp modules, 45 to 46 existing 11 kV lines. The simple block PVArrays are connected in parallel to each diagram of the Plant is shown in Figure 3. Figure 3 : Simple block diagram of the PV Plant LT PANEL 3 z = z = z = z = z = z = z = z = z = z = z = z = HT METERING CUBICLE LT PANEL 2 PV Arrays PCUs MCBs TRANSFORMER 2 LT PANEL 1 TO SCADA TO SCADA TO SCADA SPARE 11 kV KPTCL lines 11 kV HT PANELTRANSFORMER 1 TRANSFORMER 3 5 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 14. Tables 4 and 5 give the general technical details and the module specifications of the Plant. Table 4 : Technical data of Solar PV 225 W & 240 Wp pTwo type of S6- 60 series modules are used 13,368 [10,152 - 225 W ;p 3216 – 240 Wp ] Total number of modules Mono-Crystalline SiliconSolar Cell material 24 Modules1 Array 45-46 (Total 557 Arrays with 12 Inverters)No. of Arrays per Inverter(250 kW) 1st MW – 181 2nd & 3rd MW– 188 per MW Arrays per MW 5.4 acreTotal SolarCells area 15 degreeInclination of Modules Table 5 : Module Specifications [4] Type S6-60 series Maximum Power, Pmp (W) 225 240 Maximum Power Voltage (Vmp) 28.63 V 29.62 V Maximum Power Current (Imp) 7.93 A 8.12A Open Circuit Voltage (Voc) 37.50 V 37.62 V Short Circuit Current (Isc) 8.52 A 8.55A Module dimensions (mm) 1657 x 987 x 42 Number, type and arrangement of cells 60, Mono-Crystalline, 6 x 10 Matrix Cell Size 156 x 156 (mm) Nominal Operating Cell Temp (°C)NOCT– 45 Weight (Kg) 19 Glass Type and Thickness 3.2mm Thick, Low iron, Tempered 6 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 15. Power Conditioning Units (PCUs) Transformers All the twelve PCUs are identical and are The full load rating of the Transformers is supplied by the single manufacturer 1.25 MVA. All the three oil - cooled BONFIGLIOLI (VECTRON, RPS 450 type). Transformers are supplied by the The MPPT device is in-built in the control manufacturer Pan Electro Technic system which allows operating at constant Enterprises Pvt. Ltd. The efficiency is voltage. The efficiency of the PCUs is 98.91% at rated voltage and 99.3% at around 96% at nominal load. The rated maximum flux density. capacity of the PCU is 250 kW. Mounting structure Type 6 x 4 Module Array (24 modules per )Structure Material Mild Steel Overall dimensions (mm) 6780x 6030 Coating Galvanized Wind rating 160 km per hour Tilt angle 150 Foundation PCC Fixing type Nut Bolts Timelines Foundation was laid on 9th January 2009 30th September 2009, 2 MW on 12th and the site handed over to TITAN on 28th November and 3 MW on 27th December May 2009. 1MW was completed onp 2009. p p 7 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 16. 2.2 Cost details Table 6 : Cost breakup of 3 MWp Yalesandra PV power plant [3] [5] The total cost of installing the Power Plant The detailed Cost breakup of 3 MW Kolar PV including the maintenance charges for first plant is given inTable 6. three years is approximately Rs. 60 crores. Item SPV Arrays totaling to 3 MWp PCUs Mounting structures Cables & Hardware Junction box & distribution boxes Lightning Arrester, Earthing kit PVC pipes & accessories Spares for 3 years SCADA system Taxes, CST/KVAT, etc. Design, engineering, quality surveillance, testing, transportation, insurance coverage, etc. Total Supply of Equipments (for 3 MW) Erection & Commissioning 10 kW additional solar PV system with Battery support Cost (in Rupees) 43,50,00,000 5,40,00,000 3,00,00,000 50,00,000 9,00,000 12,00,000 3,00,000 5,00,000 20,00,000 1,05,78,000 1,80,99,400 55,75,77,400 2,98,00,000 31,00,000 Note: Miscellaneous expenses have not been taken into account 2.3 Plant Maintenance & Operation In addition to 3 MW , one more 10 kW PV regularly to meet the water requirements of the Plant. The other two pump sets remainplant has been installed on the rooftop of idle most of the time.office building to take care of domestic lighting and cooling loads of the Plant, Cleaning of PV Modules: including the load of exhaust fans. At Generally, the modules are cleaned by present, the plant is maintained by 13 spraying water with the help of extendable workers which includes 2 technical persons hosepipes. Occasionally, wipers are used to who look after data collection and remove the accumulated dirt and bird monitoring. droppings, say once in a month. On an Three bore - wells have been installed at average, each module is cleaned once in a the site with pump-set capacities of 2 HP, week on rotational basis. 5 HP and 10 HP. The 2 HP pump set is used p 8 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 17. 3. Performance analysis The total Energy produced by 3 MW Plant generation during 2010. Since Segment-3 was not performing satisfactorily for a fewduring the year 2010 was 3,347,480 units. months, which is evident from the figure, weOut of this, 3,303,200 units were sold to the will restrict our analysis to the first twogrid. Figure 4 shows the contribution of all Segments only.the three Segments in the total power p Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month 450000 400000 350000 300000 250000 200000 150000 100000 50000 0 MonthlyEnergyGeneration(kWh) Energy generated by 3 MW Plant - 2010 Segment-3 Segment-2 Segment-1 Figure 4 : Contribution of all the three segments in the total power generation during 2010 9 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 18. The performance of the first two segments mean output of 6655.4 kWh per day. The and their cumulative production over the capacity factor for this 2 MW plant was year 2010 is shown in Figures 5 and 6 around 14.52% at the generation end respectively. The total cumulative Energy (impact of grid-off times and maintenance generated by both the Segments together down times are not included). for the year 2010 was 2,429,219.6 kWh with 3.1 Segment-1 and Segment-2 Figure 5 : Daily Performance of Segment 1 & 2 during 2010 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 1000 2000 3000 4000 5000 6000 EnergyGeneratedperday[kWh/day] Time [Daily] Segment-1 Segment-2 10 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 19. Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 500000 1000000 1500000 2000000 2500000 Energyproduced[kWh] Time [Daily] 2,429,219.6 kWh Figure 6 : Cumulative Energy Produced by Segment 1 & 2 for the year 2010 The highest power generation achieved was temperature and Plant efficiency of 6663 o 11812.4 kWh on 5th February 2010, with the Wh/sqm/day, 42 C and 12.24% respectively. recorded insolation, average module 11 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 20. The decline in energy generation during number of cloudy days during that period August to November period in Figure 7 was (see Figures 8 and 9). The declination can mainly due to the improper functioning of be seen more clearly in Fig. 11 which shows four Inverters (two in Segment-1 and the the variation of daily efficiency for the 2 MW other two in Segment-2), and partially plant during the year 2010. because of higher plant downtime and more Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 2000 4000 6000 8000 10000 12000 EnergyProduced[kWh] Time [Daily] Figure 7: Daily energy production of 2MW Plant [Seg.1 & 2] 12 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 21. Figure 8: Daily performance of all the 8 inverters Figure 8 shows the daily performance of all 2, 3, 5 and 7 (which are shown in red) were the inverters, first four come under malfunctioning during the period August to Segment-1 and the next four under November, as compared with the remaining Segment-2. It can be seen that the Inverters four inverters. Inverter 6 Inverter 3 Jan Mar May Jul Sep Nov Inverter 6 Date 0.0 200.0k 400.0k 600.0k 800.0k 1.0M 1.2M 1.4M 1.6M Inverter 4 EnergyGen(wh/day) Inverter 1 0.0 200.0k 400.0k 600.0k 800.0k 1.0M 1.2M 1.4M 1.6M EnergyGen(wh/day) Jan Mar May Jul Sep Nov 0.0 200.0k 400.0k 600.0k 800.0k 1.0M 1.2M 1.4M 1.6M Inverter 7 EnergyGen(wh/day) Date Inverter 5 Inverter 2 Inverter 8 Jan Mar May Jul Sep Nov Date 13 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 22. Figure 9: Monthly Plant down-time in hours-2010 Grid-off times: Figure 9 shows the was observed that the grid-offs occurred cumulative monthly grid-off times during the mainly during the peak hours (11.30 am – year 2010. Out of the 357 days of the Plant's 2 pm), that is, when the availability of solar operation, there were 75 days on which the insolation is maximal. grid was off for less than an hour and 57 days The Plant was shut down for 8 days during with grid-offs more than one hour. Totally the November for repairing the faulty cables and grid was off for about 201.4 hours. Also, it Inverters. Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 20 40 60 80 100 Downtime(Hours) Month Plant Shut Down Grid-Off Times 14 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 23. The Plant is equipped with a Pyranometer mid May to mid June, due to some problem o in the Pyranometer. The highest recordedinstalled at an angle of 15 , equal to the daily insolation was 7199 Wh/sqm on 2ndinclination of the Modules. The Solar March 2010. The yearly average insolationInsolation recorded at the site is shown in on the panels was about 4789 Wh/sqm/day.Figure 10. The Insolation data is not available for about 44 days, especially from Solar Insolation o Figure 10: Daily Solar Insolation at the site - 2010 [@15 . inclination] Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1000 2000 3000 4000 5000 6000 7000 8000 Time [Daily] 15 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1 Insolation[15Wh/m2] o
  • 24. Efficiency The 2-MW plant efficiency is the combined insolation of 2561 Wh/sqm and an average 0 efficiencies of segments 1 and 2 after the module temperature of 28.63 C. The daily dc-ac conversion by inverters to 415 Volts efficiency of the 2MW plant ranged from 5% and just before stepping up to 11 kV ac. So, to 13.41% depending on the performance of this should not to be confused with the arrays, inverters, average module overall plant efficiency. temperature and the solar insolation. The yearly average daily efficiency of the plant Figure 11 shows the efficiency of the 2 MW was about 10.14%, considering the days plant, that is combined efficiency of which have grid-offs for less than half an segments 1 & 2, over the study period. The hour or no grid-offs. The abnormal drop in highest efficiency achieved was 13.41% on the efficiency during the last few months was 24th July 2010. The total energy generated mainly due to inverter related problems. on that day was 4975.8 kWh with solar Figure 11: Daily Efficiency of 2 MW Plant [Seg.1&2] Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 2 4 6 8 10 12 14 16 PlantEfficiency(%) Time [Daily] 16 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 25. Figure 12: Daily average temperature of PV modules (During day time) – 2010 Figure 12 shows the daily average Although the solar insolation level is more in temperature of PV modules for the year March compared to January, the efficiency 0 during March is low. This may be due to2010. It ranged from a minimum of 24.65 C 0 increase in the daily average temperature of(on 6th Dec) to a maximum of 51.9 C (on PV modules during that month, as seen from23rdApril). the Figure. But this is not very clear because Figure 13 shows the combined plots of plant of too much noise in the data. To reduce the efficiency, daily average modules noise and explore the issue further, we temperature and daily solar insolation with decided to analyze a single inverter which reference to time scale. It appears from the had performed well during the study period. figure that the efficiency is more sensitive to modules temperature than the insolation. 3.2 PV Modules Temperature Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 10 20 30 40 50 60 Temperature[deg.Celsius] DATE 17 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 26. Figure 13: Daily variation of average modules temperature, insolation (in Wh) and efficiency of the 2MW Plant 3.3 Performance of Inverter-1 As the performance of Inverter-1 is good energy generation by Inverter-1 versus the compared to other Inverters (see Figure 8), incident solar insolation on that day for the we chose this Inverter for more in-depth year 2010. The energy generation increases study. Figure 14 shows the plot of daily linearly with the increase in solar insolation. 18 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 27. Inverter-1 0 1000 2000 3000 4000 5000 6000 7000 8000 0 200 400 600 800 1000 1200 1400 1600 EnergyGenerated(kWh) Solar Insolation (Wh/m 2 /day) Figure 14: Annual plot of daily energy generated by Inverter-1 versus solar insolation 3.3.1 Effect of temperature on efficiency Figure 15 shows the variation in energy This is mainly because of increase in the generation of solar modules with insolation temperature of modules, which negatively and the effect of module temperature on impacts the efficiency more during that time their efficiency. The plots are made using the [see Figure 15(B)]. Figure 16 shows the 5 minutes average values from 10 am to variation in efficiency of the modules with 3 pm on 21st January, 2010. variation in temperature of modules, along with color mapped values for average solar Even though the energy generation shows irradiance. The efficiency of the modules direct dependency on the incident solar o decreases from 14.5% at 30 C to 11.5% at insolation [see Figure 15(A)] and reaches o 55 C. It is also clear from the Figure that thethe maximum during peak insolation hours, temperature of modules increases with thethe efficiency of the modules decreases and increase in solar insolation and reaches thereaches the minimum during peak hours. 19 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 28. 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 11.2 12.0 12.8 Efficiency Temperature Time, 21-Jan Efficiency(%) 42 49 56 Temperature( o C) maximum during peak insolation hours, values) for the year 2010. Due to lots of leading to reduced conversion efficiency. noise below 20 , the temperature values 0 0 Thus, the Plant's capacity to produce were binned between 20 C and 55 C. Then maximum power is retarded during peak the efficiency values were binned between insolation hours, when the availability of 10% and 15% choosing only the maximum incident solar radiation is highest, because points. The plot shows linear decrease in the of increase in modules temperature. daily efficiency of modules from 14.5% to 11.5% with increase in the daily averagedFigure 17 shows the annual plot of daily o o modules temperature from 25 C to 50 C.efficiency of modules in Inverter-1 versus daily averaged module temperature (binned 0 C 3.3.2 Performance of Inverter-1 on good days – Daily plots Figure 18 shows the daily performance plots efficiency of Inverter-1 with modules of Inverter-1 on 24th March, 11th May, 18th temperature. The values of solar insolation, June, 24th July and 20th September. The modules temperature and efficiency are plots on the left side show the variation of averaged for every 5 minute interval. The energy generation with solar insolation and energy generation values are the cumulative the right side plots show the variation in figures generated for the same time period. Figure A: Insolation and Energy Generation (of Invereter-1) Figure B: Efficiency and Temperature of Modules (of Invereter-1) Figure15: Plots of insolation, & temperature of Inverter-1 modules on January 21 energy generation, efficiency 09:00 10:00 11:00 12:00 13:00 14:00 15:00 650 700 750 800 850 900 950 1000 1050 1100 1150 1200 Insolation Energy Generated Time, Jan 21 Insolation(W) 12000 13000 14000 15000 16000 17000 EnergyGenerated(Wh) 20 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 29. 25 30 35 40 45 50 55 60 11.0 11.5 12.0 12.5 13.0 13.5 14.0 14.5 15.0 5 Min Avg. Efficiency Efficiency(%) 0 Temperature ( C) 20.00 100.0 200.0 300.0 400.0 500.0 600.0 700.0 800.0 900.0 1000 SCALE FOR AVG SOL IRR (W/m2) Figure 16: Efficiency v/s Temperature of modules of Inverter-1 on January 21, 2010 (Color scale : Average Solar Irradiance) (5 min average values) Figure 17: Plot of daily maximum efficiency versus temperature of modules in Inverter-1 for 2010 11.0 11.5 12.0 12.5 13.0 13.5 14.0 14.5 25 30 35 40 45 50 55 Temperature ( )0 C MaximumEfficiency(%) Maximum Efficiency Linear Fit of Maximum Efficiency Plot Maximum Efficiency vs Temperature of Modules in Inverter 1 21 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 30. Figure 18: (Left) Daily plots showing variation of energy generation with insolation; (Right) Daily plots showing variation of efficiency with modules temperature 09:36 10:48 12:00 13:12 14:24 15:36 16:48 20 30 40 50 60 70 Time (July-24) TempMod(DegC) 6 7 8 9 10 11 12 13 14 15 Efficiency(%) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 100 200 300 400 500 600 700 800 900 1000 1100 1200 Time (July-24) SolarInsolation(W/m 2 ) 2000 4000 6000 8000 10000 12000 14000 16000 18000 EnergyGeneration(Wh) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 100 200 300 400 500 600 700 800 900 1000 1100 1200 Time (March-24) SolarInsolation(W/m 2 ) 2000 4000 6000 8000 10000 12000 14000 16000 18000 EnergyGeneration(Wh) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 20 30 40 50 60 70 Time (March-24) TempMod(Deg.C) 6 7 8 9 10 11 12 13 14 15 Efficiency(%) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 100 200 300 400 500 600 700 800 900 1000 1100 1200 Time (Sept-20) SolarInsolation(W/m 2 ) 2000 4000 6000 8000 10000 12000 14000 16000 18000 EnergyGeneration(Wh) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 20 30 40 50 60 70 Time (Sept-20) TempMod(DegC) 6 8 10 12 14 Efficiency(%) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 100 200 300 400 500 600 700 800 900 1000 1100 1200 Time (June-18) SolarInsolation(W/m 2 ) 2000 4000 6000 8000 10000 12000 14000 16000 18000 EnergyGeneration(Wh) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 20 30 40 50 60 70 Time (June-18) TempMod(Deg.C) 6 7 8 9 10 11 12 13 14 15 Efficiency(%) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 100 200 300 400 500 600 700 800 900 1000 1100 1200 Time (May-11) SolarInsolation(W/m 2 ) 2000 4000 6000 8000 10000 12000 14000 16000 18000 EnergyGeneration(Wh) 09:36 10:48 12:00 13:12 14:24 15:36 16:48 20 30 40 50 60 70 Time (May-11) TempMod(Deg.C) 6 7 8 9 10 11 12 13 14 15 Efficiency(%) Solar Insolation Energy Generation Temp Mod Efficiency 22 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 31. 4. Technical and maintenance related problems Some of the major technical & maintenance ?Presently the modules are cleaned by related problems faced by the plant spraying water. But the dust operators are as follows: accumulated on the modules turns into paste form once the modules are water ?The power of the PV plant cannot be fed sprayed, making it difficult to remove. to the grid if the power supply from the Also, the height of the modules grid stops. Due to this, the power from mounting structures (see Figure 19) the PV Plant is not available when it is makes it impossible to remove the dirt needed most and the capacity of the completely with wipers while standing Plant to work effectively has been on the ground. This has led inevitably, to retarded. the option of cleaning the modules by climbing on top of them (and then using?There is no tracking mechanism to wipers!). This will weaken the strengthlocate the modules if they fail. If a of solar modules as well as mountingmodule fails, it is very tiresome to structures in the long run and also affectidentify it because no sensors have the power production. Hence, it is feltbeen installed for this purpose. The only that there is a need to address this issuesolution presently available is to wait till by developing alternate method/the peak time to identify the Inverter technology for cleaning the PV(from which the output is lower). Then modules.the Inverter has to be isolated and all the 45-46 arrays connected to this ?Recently, some of the modules have inverter should be checked. Once the shown change in color (see Figure 20). faulty array is located, all the connected It is yet to be ascertained whether this modules need to be checked to identify color change in the modules has any the faulty one. negative impact on their performance. 0 Figure 19: Photo of PV Plant showing the modules mounting structures inclined at 15 . 23 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 32. Figure 20: Visual color change of the photovoltaic modules 24 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 33. 5. Conclusion The performance of the 3 MW Yalesandra afternoon. The daily efficiency of modulesp varied from 14.5% to 11.5% with thesolar photovoltaic power plant has been variation in the daily averaged modulesanalyzed for the year 2010. The total o o temperature from 25 C to 50 C. Hence,electrical energy generated by the cooling of the solar modules may beYalesandra power plant during 2010 was desirable to increase the efficiency. There is3.34 million kWh and 3.30 million units were a need to evaluate if the additional energysold to the grid. Based on the performance of required for cooling the solar modules will bethe first two segments we estimate the mean less than the additional energy generatedoutput to be 6655 kWh per day. This is lower due to higher efficiency.than expected for a solar power plant and is on account of teething trouble associated with inverters and the grid-encountered in The daily plots showing the variation ofthe first year of the operation of the plant. It efficiency with modules temperature and thewas found that failure in inverters were the variation of energy generation with solarmost frequent incidents. This is mostly insolation have been plotted for five differentcaused by lack of experience in the initial days of the year. Also, some of the presentproduction stage and some unexplained maintenance and technical problems facedinverter failures might be caused by by plant operators, including the colordisturbance from the grid and other change in PV modules and cleaning issues,interconnected issues [6]. have been discussed. The impact of temperature variation (of It is also suggested that more measuringmodules) on the performance of instruments such as Pyrheliometer, Rainphotovoltaic mono-crystalline silicon Gauge, Thermocouple (Thermometer) formodules was studied both on daily and measuring ambient temperature, to beyearly basis (daily average values). It is installed in the plant and the existingobserved that the efficiency of modules is instruments to be calibrated for greatermore sensitive to temperature than the solar accuracy. This will enable further technicalinsolation. The normal daily trend is that the analysis of India’s first 3MW scale plant andefficiency of Plant is high during morning help KPCL in their future solar power planthours but low during the middle of the day projects.and again starts increasing from late 25 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 34. 6. References 1.AntonetteD'SaandK.V.NarasimhaMurthy,Karnataka'sPowerSector&SuggestedWays Forward,InternationalEnergyInitiative,discussionpaper,2002. 2.K.Jairaj,EnergyscenarioinKarnataka,powerpointpresentation,EnergyDepartment, GovernmentofKarnataka. 3.SolarPVPowerPlants,contractagreementforsupplyofequipments,CE(EI&TA)/SPV, KPCLandTitanEnergySystemsLtd.,Secunderabad. 4.Operationmanual,TitanEnergySystemsLtd.,Secunderabad. 5.ContractagreementforErection,testingandcommissioningof3MWSolarPVpowerplant, KPCLandTitanEnergySystemsLtd.,Secunderabad. 6.MohamedA.EltawilandZhengmingZhao,Grid-connectedphotovoltaicpowersystems: Technicalandpotentialproblems-Areview,RenewableandSustainableEnergyReviews, 14,2010,112–129. 26 3-MWscalegrid-connectedsolarphotovoltaicpowerplantatKolar,Karnataka ReportIISc-DCCC11RE1
  • 36.
  • 37. Satellite image of the 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka
  • 38. DIVECHA CENTRE FOR CLIMATE CHANGE INDIAN INSTITUTE OF SCIENCE Bangalore REPORT IISc-DCCC 11 RE 1 AUGUST 2011