Investment Planning
Meeting Today’s Challenges and Planning for the Future
Challenges to Address in Investment Planning
2
Strategic
Objectives
Delivery
How is the plan updated
when things change?
What is the scope of the
assets within the
project?
3 Stages in which Investment Challenges must be addressed
Translation to Delivery
In-AMP Change
Management
TOTEX Investment Planning Cycle - Stages
Investment required to
deliver corporate and
stakeholder objectives
Informing PR submission
Strategic Business Plan Development Stage
4
Statistical
Analysis
70%?
Bottom-up
Schemes
30%?
Strategic
Business Plan
Outputs support:
• Customer engagement
• Cost and Performance ‘Envelopes’
• Timing for Larger Projects
Translate to Delivery Stage – Structured process in some cases
5
Translate to Delivery Stage – Sometimes unclear
6
Investment Plan
(Delivery)
Strategy/Planning
Investment Plan
(Strategy)
Delivery
?
Programme Delivery Stage
7
--..- Project A
.— Project B
-…- Project C
-.- Project D
..- Project E
--..- Project A
.--..- Project B
-…- Project C
-.- Project D
..- Project E
DeliveryStrategy
? ?
? ?
? ?
Programme Delivery: In-AMP Change Management
8
Forecasts Actuals
Inform Decisions
• Measuring and Managing change in the plan:
• Costs, Risks, Reactive Events and Outcomes
Integrated and Optimised Planning
10
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
Integrated and Optimised Planning
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
Integrated and Optimised Planning
11
• Portfolio Optimisation
• Selected ‘Scenario’ Defines
Strategic Business Plan
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
Integrated and Optimised Planning
12
Strategic Plan
Every 1 to 5 years
Monthly
• Programmes translated to
schemes of work
• ‘Virtual’ projects refined
• Specific Assets and Activities
create Delivery Plan
• Cost Centres for Reactive Work
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
13
• Additional Options imported
• Allowing for changes:
• Reduced Budget or
• Deteriorating Performance
Monthly
Synchronised:
• Costs, Resourcing, Assets, Project Status
• e.g. planned, in-progress, complete
• Predicted vs Actual monitored
• Proactive Annual Plan: Optimised Monthly
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
Risk Capture and Management
14
Everyday Process
• Risks raised from remote work
• Using Risk Management system & app
Strategic 5 Year
Business PlanBottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
Risk Capture and Management
15
Validation of Risks – Options:
1. Rejected
2. Work Request to address Issue
• Existing budget and Cost Centre
3. Raised for CAPEX budget request
Concern
Issues Create
Work Request
Work request accrued
to Cost centre
Risk Raised
Strategic 5 Year
Business Plan
Statistical
Analysis
Bottom-up
Schemes
Web
App
Web
App
Web
App
Risk
Capture
Risk Triage
Annual Integrated
Optimised Plan
Ongoing
Projects
Risk
Management
16
Dashboards
• Communicate and Track:
• Costs & Budgets
• Performance & Risk
• From Different Areas
• To Different Stakeholders
EDA Asset
EDA Portfolio
Strategic AMP
Planning
EDA Portfolio
Named
Schemes
EDA Asset
Strategic Asset
Planning
(Models)
Import
Optionsns
Annual
EDAP
Web App
Advanced
Dashboards
AMP Plan
Integrated and Optimised Planning - Dashboards
17
Forecasts Actuals
Inform Decisions
• Provides Visibility of Changes and their Impacts
• Ensures Decisions are Driven by Organisational Objectives
• Results in Efficiencies and ODI returns
Benefits

Investment Planning: Meeting today's challenges and planning for the future

  • 1.
    Investment Planning Meeting Today’sChallenges and Planning for the Future
  • 2.
    Challenges to Addressin Investment Planning 2 Strategic Objectives Delivery
  • 3.
    How is theplan updated when things change? What is the scope of the assets within the project? 3 Stages in which Investment Challenges must be addressed Translation to Delivery In-AMP Change Management TOTEX Investment Planning Cycle - Stages Investment required to deliver corporate and stakeholder objectives Informing PR submission
  • 4.
    Strategic Business PlanDevelopment Stage 4 Statistical Analysis 70%? Bottom-up Schemes 30%? Strategic Business Plan Outputs support: • Customer engagement • Cost and Performance ‘Envelopes’ • Timing for Larger Projects
  • 5.
    Translate to DeliveryStage – Structured process in some cases 5
  • 6.
    Translate to DeliveryStage – Sometimes unclear 6 Investment Plan (Delivery) Strategy/Planning Investment Plan (Strategy) Delivery ?
  • 7.
    Programme Delivery Stage 7 --..-Project A .— Project B -…- Project C -.- Project D ..- Project E --..- Project A .--..- Project B -…- Project C -.- Project D ..- Project E DeliveryStrategy ? ? ? ? ? ?
  • 8.
    Programme Delivery: In-AMPChange Management 8 Forecasts Actuals Inform Decisions • Measuring and Managing change in the plan: • Costs, Risks, Reactive Events and Outcomes
  • 9.
  • 10.
    10 Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management Integrated and Optimised Planning
  • 11.
    Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management Integrated and Optimised Planning 11 • Portfolio Optimisation • Selected ‘Scenario’ Defines Strategic Business Plan
  • 12.
    Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management Integrated and Optimised Planning 12 Strategic Plan Every 1 to 5 years Monthly • Programmes translated to schemes of work • ‘Virtual’ projects refined • Specific Assets and Activities create Delivery Plan • Cost Centres for Reactive Work
  • 13.
    Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management 13 • Additional Options imported • Allowing for changes: • Reduced Budget or • Deteriorating Performance Monthly Synchronised: • Costs, Resourcing, Assets, Project Status • e.g. planned, in-progress, complete • Predicted vs Actual monitored • Proactive Annual Plan: Optimised Monthly
  • 14.
    Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management Risk Capture and Management 14 Everyday Process • Risks raised from remote work • Using Risk Management system & app
  • 15.
    Strategic 5 Year BusinessPlanBottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management Risk Capture and Management 15 Validation of Risks – Options: 1. Rejected 2. Work Request to address Issue • Existing budget and Cost Centre 3. Raised for CAPEX budget request Concern Issues Create Work Request Work request accrued to Cost centre Risk Raised
  • 16.
    Strategic 5 Year BusinessPlan Statistical Analysis Bottom-up Schemes Web App Web App Web App Risk Capture Risk Triage Annual Integrated Optimised Plan Ongoing Projects Risk Management 16 Dashboards • Communicate and Track: • Costs & Budgets • Performance & Risk • From Different Areas • To Different Stakeholders EDA Asset EDA Portfolio Strategic AMP Planning EDA Portfolio Named Schemes EDA Asset Strategic Asset Planning (Models) Import Optionsns Annual EDAP Web App Advanced Dashboards AMP Plan Integrated and Optimised Planning - Dashboards
  • 17.
    17 Forecasts Actuals Inform Decisions •Provides Visibility of Changes and their Impacts • Ensures Decisions are Driven by Organisational Objectives • Results in Efficiencies and ODI returns Benefits