SlideShare a Scribd company logo
THE INTERNSHIP REPORT
TEAM MEMBERS
1. MUHAMMAD ZUBAIR SHABBIR
2. WAQAR ULLAH SHAH
3. MUHAMMAD FAHEEM ALI
DEPARTMENT: BE ELECTRICAL
ADVISER: SYED SAJJAD ALI (MAINTENANCE)
ABSTRACT
We have given the task to observe the current situation of power systemand power factor unit
and take out all the necessary readings which help the maintenance department to manage
their plant power consumptions.
INTRODUCTION
Atlas Honda Limited (AHL) is a joint venture between the Atlas Group and Honda Motor Co.
Ltd., Japan. The company was created by the merger of Panjdarya Limited and Atlas Autos Ltd.
in 1988. Both these motorcycle manufacturing concerns were established by the Atlas Group.
AHL is playing a pioneering role in creating conditions for easy and confident use of motorcycles
all over the country. A vast and growing network of over 1600 sales service and spare parts
dealers has been established
KARACHI PLANT
Company mother plant is based in the city of lights and provincial capital of Sindh , The Karachi
city. It is located at F-36, Estate Avenue, S.I.T.E. Karachi. Atlas Group signed technical
agreement with Honda in 1963 and plant started commercial production subsequently. Plant
spread over an area of 5 acres. In 1964, production began with 7 motorcycles per day. Now
plant production has reached to 300 units in a day. Plant manufactures CD 70 only.
SHEIKHUPURAPLANT
Another plant is situated in Sheikhupura city, Punjab. It is located at 26-27 KM Lahore-
Sheikhupura Road Sheikhupura. The plant was built in 1981 and spread over an area of 27 acres
with the establishment of modern and synchronized 500K plant in 2006. The plant
manufactures all four models i.e. CD 70, Pridor, CG 125 and CG 125 Deluxe.
Annual ProductionCapacity AuthorizedCapital Paid Up Capital
750,000 1.5 Billion (Rupees) Rs. 1,034.066 Million
MAINTENANCE DEPARTMENT
The maintenance department is responsible to maintain working of all types of machine and
supply electricity to all departments, compress air to all pneumatic and hydraulic machines and
steam to buffing shop.
EXISTING SYSTEM AND OPERATION
HT Room
K-Electric supply of two 11KV lines F36 and F10. Both HT lines connected with energy meter
and then connected main vacuum circuit breaker. F36 split into two F36A and F36B both
connected with separate VCB and OCB respectively then supply goes to transformer.
Transformer Room
F36 A is connected with 1500 KVA transformer Siemens.
F36B is connected with 1500 KVA transformer Siemens.
F10 is connected with 1000 KVA transformer Johnson and Philips.
Transformer temperature is maintained at 45oC.
And then supply goes to LT Room.
LT Room
All 3 LT supply is connected with separate PFI controller (Technologic Reactive Power Controller
650).
F36A PFI unit has 6 capacitive banks of 50 KVAR ratings. All six are automatic.
F36B PFI unit has 6 capacitive banks 50 KVAR ratings. One manual and 5 automatic.
F10 PFI unit has 12 capacitive banks 50 KVAR rating. Two manual, 4 off and 6 automatic.
Distribution
F36A is fixed for welding shop, press shop and compressor.
Rest of all load can be connected with either F36B or F10.
The temperature of main supply cable is 37OC, 38OC.
Load Management:
The maximum load according to our observation on (2-8-2016) PEAK WORKING TIME.
TRANSFORMER CURRENT VOLTAGE P.F
F36A 800 TO 1200 A 440V 0.96
F36B 500 TO 550 A 440V 0.94
F10 480 TO 520 A 440V 0.96
Calculation
F 36A
VA = 3 × 1200 × 440/√3 = 914 kVA
W = 914 × .96 = 877 kW
𝑉𝐴𝑅 = √914𝐾𝑉𝐴2 − 877𝐾𝑊^2 = 260𝐾𝑉𝐴𝑅
F36B
𝑉𝐴 = 3 × 550 ×
440
√3
= 419𝐾𝑉𝐴
𝑊 = 419𝑘 × 0.94 = 393𝐾𝑊
𝑉𝐴𝑅 = √419𝐾2 − 393𝐾2 = 150𝐾𝑉𝐴𝑅
F10
𝑉𝐴 = 3 × 520 ×
440
√3
= 396𝐾𝑉𝐴
𝑊 = 396𝐾 × 0.96 = 380𝐾𝑊
𝑉𝐴𝑅 = √396𝐾2 − 380𝐾2 = 112.46𝐾𝑉𝐴𝑅
POWER FACTOR CORRECTION
Powerfactorcorrection isthe termgiventoa technologythathasbeenusedsince the turnof the 20th
centuryto restore the powerfactorto as close to unityas iseconomicallyviable.Thisisnormally
achievedbythe additionof capacitorstothe electrical networkwhichcompensate forthe reactive
powerdemandof the inductive loadandthusreduce the burdenonthe supply.There shouldbe no
effectonthe operationof the equipment.Toreduce lossesinthe distributionsystem,andtoreduce the
electricitybill,powerfactorcorrection,usuallyinthe formof capacitors,isaddedtoneutralize asmuch
of the magnetizingcurrentaspossible.Capacitorscontainedinmostpowerfactorcorrectionequipment
draw currentthat leadsthe voltage,thusproducingaleadingpowerfactor. If capacitorsare connected
to a circuit thatoperatesat a nominallylaggingpowerfactor,the extentthatthe circuitlagsisreduced
proportionately.Typicallythe correctedpowerfactorwill be 0.92 to 0.95. Some powerdistributorsoffer
incentivesforoperatingwithapowerfactorof betterthan 0.9, for example,andsome penalize
consumerswithapoor powerfactor.There are manyways thatthisis meteredbutthe netresultisthat
inorder to reduce wastedenergyinthe distributionsystem,the consumerisencouragedtoapplypower
factor correction.MostNetworkOperatingcompaniesnow penalize forpowerfactorsbelow 0.95 or 0.9.
KVAR
KVA
KW
WHY IMPROVE POWER FACTOR ?
The benefitsthatcanbe achievedbyapplyingthe correctpowerfactorcorrectionare:
 Environmental benefit.Reductionof powerconsumptiondue toimprovedenergyefficiency.
Reducedpowerconsumptionmeanslessgreenhouse gasemissionsandfossil fueldepletionbypower
stations.
 Reductionof electricitybills
 Extra KVA available fromthe existingsupply
 Reductionof I^2 R lossesintransformersanddistributionequipment
 Reductionsof voltage dropinlongcables.
 Extendedequipmentlife–Reducedelectrical burdenoncablesandelectrical components.
HOW TO IMPROVE POWER FACTOR
Powerfactorcorrectionisachievedbythe additionof capacitorsinparallel withthe connectedmotoror
lightingcircuitsandcan be appliedatthe equipment,distributionboardorat the originof the
installation.Staticpowerfactorcorrectioncanbe appliedateachindividual motorbyconnectingthe
correctioncapacitorsto the motor starter.A disadvantage canoccur whenthe loadonthe motor
changesand can resultinunderor overcorrection.Staticpowerfactorcorrectionmustnot be appliedat
the outputof a variable speeddrive,solidstate softstarterorinverterasthe capacitorscan cause
seriousdamage tothe electroniccomponents.Over-correctionshouldnotoccurif the powerfactor
correctioniscorrectlysized.Typicallythe powerfactorcorrectionforan individualmotorisbasedonthe
nonload (magnetizing) powersince the reactiveloadof amotor iscomparativelyconstantcomparedto
actual kW loadovercompensationshouldbe avoided.Care shouldbe takenwhenapplyingpowerfactor
correctionstar/deltatype control sothat the capacitorsare not subjectedtorapidon-off-onconditions.
Typicallythe correctionwouldbe placedoneitherthe Mainor Deltacontactor circuits.Powerfactor
correctionappliedatthe originof the installation consistsof acontrollermonitoringthe VAr’sandthis
controllerswitchescapacitorsinoroutto maintainthe powerfactorbetterthana presetlimit(typically
0.95). Where ‘bulk’powerfactorcorrectionisinstalled,otherloadscanintheorybe connected
anywhere onthe network.
VACUUM CIRCUITBREAKER
Circuitbreakersmustmake andbreakall currentswithinthe scope of theirratings,fromsmall inductive
and capacitive loadcurrentsupto the short-circuitcurrent,andthisunderall faultconditions inthe
powersupplysystemsuchasearthfaults,phase oppositionandsoon.
CONCLUSION
We have concluded thatexistingpowersystemandpowerfactorunitmeets the currentrequirementof
the whole plantandworkingefficiently.

More Related Content

What's hot

A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
Ishank Ranjan
 
ppt of summer traning nwr jaipur
ppt of summer traning nwr jaipurppt of summer traning nwr jaipur
ppt of summer traning nwr jaipur
7597861730
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments
Anuj Gupta
 
Internship Report
Internship Report Internship Report
Internship Report
Muhammad Usman Rafiq
 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 
LANNET Backup Power Supplies
LANNET Backup Power SuppliesLANNET Backup Power Supplies
LANNET Backup Power Supplies
Ronald Bartels
 
Rj final ppt
Rj final pptRj final ppt
Rj final ppt
RAJ KUMAR MEENA
 
Mnzeet kota railway electrical ppt
Mnzeet kota railway electrical pptMnzeet kota railway electrical ppt
Mnzeet kota railway electrical ppt
MANJEET SINGH
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
CHANDER G MENGHANI MENGHANI
 
Bses powerpoint presentation
Bses powerpoint presentationBses powerpoint presentation
Bses powerpoint presentation
Anuj Gupta
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
Aneel-k Suthar
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
student
 
A multilevel medium voltage inverter
A multilevel medium voltage inverterA multilevel medium voltage inverter
A multilevel medium voltage inverter
saif ulla baig
 
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Dharmpal Yadav
 
Summer Internship Presentation on Manufacturing and testing of locomotive e...
Summer Internship  Presentation on Manufacturing and testing  of locomotive e...Summer Internship  Presentation on Manufacturing and testing  of locomotive e...
Summer Internship Presentation on Manufacturing and testing of locomotive e...
Aman Jaiswal
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
shivashankar307
 
variable frequency drive and its energy saving by MD FARYAD ALAM
variable frequency drive and its energy saving by MD FARYAD ALAMvariable frequency drive and its energy saving by MD FARYAD ALAM
variable frequency drive and its energy saving by MD FARYAD ALAM
MDFARYADALAM
 
IRJET- Phase Conversion of VFD based Induction Motor
IRJET- Phase Conversion of VFD based Induction MotorIRJET- Phase Conversion of VFD based Induction Motor
IRJET- Phase Conversion of VFD based Induction Motor
IRJET Journal
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
kishankky
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
Ankur Mahajan
 

What's hot (20)

A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
 
ppt of summer traning nwr jaipur
ppt of summer traning nwr jaipurppt of summer traning nwr jaipur
ppt of summer traning nwr jaipur
 
BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments BSES - Maintaince of EHV Equipments
BSES - Maintaince of EHV Equipments
 
Internship Report
Internship Report Internship Report
Internship Report
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
LANNET Backup Power Supplies
LANNET Backup Power SuppliesLANNET Backup Power Supplies
LANNET Backup Power Supplies
 
Rj final ppt
Rj final pptRj final ppt
Rj final ppt
 
Mnzeet kota railway electrical ppt
Mnzeet kota railway electrical pptMnzeet kota railway electrical ppt
Mnzeet kota railway electrical ppt
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
 
Bses powerpoint presentation
Bses powerpoint presentationBses powerpoint presentation
Bses powerpoint presentation
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 
A multilevel medium voltage inverter
A multilevel medium voltage inverterA multilevel medium voltage inverter
A multilevel medium voltage inverter
 
Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)Ppt of PGCIL by d.p.yadav( 91 8432379261)
Ppt of PGCIL by d.p.yadav( 91 8432379261)
 
Summer Internship Presentation on Manufacturing and testing of locomotive e...
Summer Internship  Presentation on Manufacturing and testing  of locomotive e...Summer Internship  Presentation on Manufacturing and testing  of locomotive e...
Summer Internship Presentation on Manufacturing and testing of locomotive e...
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
variable frequency drive and its energy saving by MD FARYAD ALAM
variable frequency drive and its energy saving by MD FARYAD ALAMvariable frequency drive and its energy saving by MD FARYAD ALAM
variable frequency drive and its energy saving by MD FARYAD ALAM
 
IRJET- Phase Conversion of VFD based Induction Motor
IRJET- Phase Conversion of VFD based Induction MotorIRJET- Phase Conversion of VFD based Induction Motor
IRJET- Phase Conversion of VFD based Induction Motor
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 

Similar to Internship report

sub-station training report
sub-station training reportsub-station training report
sub-station training report
sitesh95074
 
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Devendra Kumar
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)
99sunilkumar
 
Sks
SksSks
Ppt on Kharagpur railway
Ppt on Kharagpur railwayPpt on Kharagpur railway
Ppt on Kharagpur railway
SURAJBHAKTA4
 
Ijetr012032
Ijetr012032Ijetr012032
Ijetr012032
ER Publication.org
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandey
shubhangpandey5
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electrical
Piyush Dwivedi
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
Yogesh Jadoun
 
Single phase compensated motor
Single phase compensated motorSingle phase compensated motor
Single phase compensated motor
SayanSarkar55
 
Solar ppt
Solar pptSolar ppt
Training report of Electric Loco Shed
Training report of Electric Loco ShedTraining report of Electric Loco Shed
Training report of Electric Loco Shed
Aarti Ojha
 
Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover
IJSRED
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
Gyanendra Prakash
 
Projectreportonvocational 141120000656-conversion-gate02
Projectreportonvocational 141120000656-conversion-gate02Projectreportonvocational 141120000656-conversion-gate02
Projectreportonvocational 141120000656-conversion-gate02
*noT yeT workinG! !M stilL studyinG*
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital Circuits
IRJET Journal
 
Energy & safety audit of rice mill for husk based power plant for finance, ...
Energy & safety audit of rice mill for husk based power plant   for finance, ...Energy & safety audit of rice mill for husk based power plant   for finance, ...
Energy & safety audit of rice mill for husk based power plant for finance, ...
Radha Krishna Sahoo
 
IRJET- Load Sharing of Transformer using Microcontroller
IRJET- Load Sharing of Transformer using MicrocontrollerIRJET- Load Sharing of Transformer using Microcontroller
IRJET- Load Sharing of Transformer using Microcontroller
IRJET Journal
 

Similar to Internship report (20)

sub-station training report
sub-station training reportsub-station training report
sub-station training report
 
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)
 
Sks
SksSks
Sks
 
Ppt on Kharagpur railway
Ppt on Kharagpur railwayPpt on Kharagpur railway
Ppt on Kharagpur railway
 
Ijetr012032
Ijetr012032Ijetr012032
Ijetr012032
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandey
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electrical
 
PPT PROJECT
PPT PROJECTPPT PROJECT
PPT PROJECT
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
 
Single phase compensated motor
Single phase compensated motorSingle phase compensated motor
Single phase compensated motor
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
Training report of Electric Loco Shed
Training report of Electric Loco ShedTraining report of Electric Loco Shed
Training report of Electric Loco Shed
 
Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 
Projectreportonvocational 141120000656-conversion-gate02
Projectreportonvocational 141120000656-conversion-gate02Projectreportonvocational 141120000656-conversion-gate02
Projectreportonvocational 141120000656-conversion-gate02
 
Multi-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital CircuitsMulti-power rail FLR configurable for Digital Circuits
Multi-power rail FLR configurable for Digital Circuits
 
Energy & safety audit of rice mill for husk based power plant for finance, ...
Energy & safety audit of rice mill for husk based power plant   for finance, ...Energy & safety audit of rice mill for husk based power plant   for finance, ...
Energy & safety audit of rice mill for husk based power plant for finance, ...
 
IRJET- Load Sharing of Transformer using Microcontroller
IRJET- Load Sharing of Transformer using MicrocontrollerIRJET- Load Sharing of Transformer using Microcontroller
IRJET- Load Sharing of Transformer using Microcontroller
 

Internship report

  • 1. THE INTERNSHIP REPORT TEAM MEMBERS 1. MUHAMMAD ZUBAIR SHABBIR 2. WAQAR ULLAH SHAH 3. MUHAMMAD FAHEEM ALI DEPARTMENT: BE ELECTRICAL ADVISER: SYED SAJJAD ALI (MAINTENANCE)
  • 2. ABSTRACT We have given the task to observe the current situation of power systemand power factor unit and take out all the necessary readings which help the maintenance department to manage their plant power consumptions. INTRODUCTION Atlas Honda Limited (AHL) is a joint venture between the Atlas Group and Honda Motor Co. Ltd., Japan. The company was created by the merger of Panjdarya Limited and Atlas Autos Ltd. in 1988. Both these motorcycle manufacturing concerns were established by the Atlas Group. AHL is playing a pioneering role in creating conditions for easy and confident use of motorcycles all over the country. A vast and growing network of over 1600 sales service and spare parts dealers has been established KARACHI PLANT Company mother plant is based in the city of lights and provincial capital of Sindh , The Karachi city. It is located at F-36, Estate Avenue, S.I.T.E. Karachi. Atlas Group signed technical agreement with Honda in 1963 and plant started commercial production subsequently. Plant spread over an area of 5 acres. In 1964, production began with 7 motorcycles per day. Now plant production has reached to 300 units in a day. Plant manufactures CD 70 only. SHEIKHUPURAPLANT Another plant is situated in Sheikhupura city, Punjab. It is located at 26-27 KM Lahore- Sheikhupura Road Sheikhupura. The plant was built in 1981 and spread over an area of 27 acres with the establishment of modern and synchronized 500K plant in 2006. The plant manufactures all four models i.e. CD 70, Pridor, CG 125 and CG 125 Deluxe. Annual ProductionCapacity AuthorizedCapital Paid Up Capital 750,000 1.5 Billion (Rupees) Rs. 1,034.066 Million
  • 3. MAINTENANCE DEPARTMENT The maintenance department is responsible to maintain working of all types of machine and supply electricity to all departments, compress air to all pneumatic and hydraulic machines and steam to buffing shop. EXISTING SYSTEM AND OPERATION HT Room K-Electric supply of two 11KV lines F36 and F10. Both HT lines connected with energy meter and then connected main vacuum circuit breaker. F36 split into two F36A and F36B both connected with separate VCB and OCB respectively then supply goes to transformer. Transformer Room F36 A is connected with 1500 KVA transformer Siemens. F36B is connected with 1500 KVA transformer Siemens. F10 is connected with 1000 KVA transformer Johnson and Philips. Transformer temperature is maintained at 45oC. And then supply goes to LT Room. LT Room All 3 LT supply is connected with separate PFI controller (Technologic Reactive Power Controller 650). F36A PFI unit has 6 capacitive banks of 50 KVAR ratings. All six are automatic. F36B PFI unit has 6 capacitive banks 50 KVAR ratings. One manual and 5 automatic. F10 PFI unit has 12 capacitive banks 50 KVAR rating. Two manual, 4 off and 6 automatic. Distribution F36A is fixed for welding shop, press shop and compressor. Rest of all load can be connected with either F36B or F10. The temperature of main supply cable is 37OC, 38OC. Load Management: The maximum load according to our observation on (2-8-2016) PEAK WORKING TIME. TRANSFORMER CURRENT VOLTAGE P.F F36A 800 TO 1200 A 440V 0.96 F36B 500 TO 550 A 440V 0.94 F10 480 TO 520 A 440V 0.96
  • 4. Calculation F 36A VA = 3 × 1200 × 440/√3 = 914 kVA W = 914 × .96 = 877 kW 𝑉𝐴𝑅 = √914𝐾𝑉𝐴2 − 877𝐾𝑊^2 = 260𝐾𝑉𝐴𝑅 F36B 𝑉𝐴 = 3 × 550 × 440 √3 = 419𝐾𝑉𝐴 𝑊 = 419𝑘 × 0.94 = 393𝐾𝑊 𝑉𝐴𝑅 = √419𝐾2 − 393𝐾2 = 150𝐾𝑉𝐴𝑅 F10 𝑉𝐴 = 3 × 520 × 440 √3 = 396𝐾𝑉𝐴 𝑊 = 396𝐾 × 0.96 = 380𝐾𝑊 𝑉𝐴𝑅 = √396𝐾2 − 380𝐾2 = 112.46𝐾𝑉𝐴𝑅 POWER FACTOR CORRECTION Powerfactorcorrection isthe termgiventoa technologythathasbeenusedsince the turnof the 20th centuryto restore the powerfactorto as close to unityas iseconomicallyviable.Thisisnormally achievedbythe additionof capacitorstothe electrical networkwhichcompensate forthe reactive powerdemandof the inductive loadandthusreduce the burdenonthe supply.There shouldbe no effectonthe operationof the equipment.Toreduce lossesinthe distributionsystem,andtoreduce the electricitybill,powerfactorcorrection,usuallyinthe formof capacitors,isaddedtoneutralize asmuch of the magnetizingcurrentaspossible.Capacitorscontainedinmostpowerfactorcorrectionequipment draw currentthat leadsthe voltage,thusproducingaleadingpowerfactor. If capacitorsare connected to a circuit thatoperatesat a nominallylaggingpowerfactor,the extentthatthe circuitlagsisreduced proportionately.Typicallythe correctedpowerfactorwill be 0.92 to 0.95. Some powerdistributorsoffer incentivesforoperatingwithapowerfactorof betterthan 0.9, for example,andsome penalize consumerswithapoor powerfactor.There are manyways thatthisis meteredbutthe netresultisthat inorder to reduce wastedenergyinthe distributionsystem,the consumerisencouragedtoapplypower factor correction.MostNetworkOperatingcompaniesnow penalize forpowerfactorsbelow 0.95 or 0.9. KVAR KVA KW
  • 5. WHY IMPROVE POWER FACTOR ? The benefitsthatcanbe achievedbyapplyingthe correctpowerfactorcorrectionare:  Environmental benefit.Reductionof powerconsumptiondue toimprovedenergyefficiency. Reducedpowerconsumptionmeanslessgreenhouse gasemissionsandfossil fueldepletionbypower stations.  Reductionof electricitybills  Extra KVA available fromthe existingsupply  Reductionof I^2 R lossesintransformersanddistributionequipment  Reductionsof voltage dropinlongcables.  Extendedequipmentlife–Reducedelectrical burdenoncablesandelectrical components. HOW TO IMPROVE POWER FACTOR Powerfactorcorrectionisachievedbythe additionof capacitorsinparallel withthe connectedmotoror lightingcircuitsandcan be appliedatthe equipment,distributionboardorat the originof the installation.Staticpowerfactorcorrectioncanbe appliedateachindividual motorbyconnectingthe correctioncapacitorsto the motor starter.A disadvantage canoccur whenthe loadonthe motor changesand can resultinunderor overcorrection.Staticpowerfactorcorrectionmustnot be appliedat the outputof a variable speeddrive,solidstate softstarterorinverterasthe capacitorscan cause seriousdamage tothe electroniccomponents.Over-correctionshouldnotoccurif the powerfactor correctioniscorrectlysized.Typicallythe powerfactorcorrectionforan individualmotorisbasedonthe nonload (magnetizing) powersince the reactiveloadof amotor iscomparativelyconstantcomparedto actual kW loadovercompensationshouldbe avoided.Care shouldbe takenwhenapplyingpowerfactor correctionstar/deltatype control sothat the capacitorsare not subjectedtorapidon-off-onconditions. Typicallythe correctionwouldbe placedoneitherthe Mainor Deltacontactor circuits.Powerfactor correctionappliedatthe originof the installation consistsof acontrollermonitoringthe VAr’sandthis controllerswitchescapacitorsinoroutto maintainthe powerfactorbetterthana presetlimit(typically 0.95). Where ‘bulk’powerfactorcorrectionisinstalled,otherloadscanintheorybe connected anywhere onthe network. VACUUM CIRCUITBREAKER Circuitbreakersmustmake andbreakall currentswithinthe scope of theirratings,fromsmall inductive and capacitive loadcurrentsupto the short-circuitcurrent,andthisunderall faultconditions inthe powersupplysystemsuchasearthfaults,phase oppositionandsoon. CONCLUSION We have concluded thatexistingpowersystemandpowerfactorunitmeets the currentrequirementof the whole plantandworkingefficiently.