The document outlines the intern's training report over an 8 week period at Clement Wong Architecture. During this time, the intern worked on several projects including mix developments, residential properties, and a large scale international trade center. The intern gained experience with CAD software, 3D modeling, drafting, and construction documentation through hands-on work under the supervision of senior architects.
PPT contain the study of the business process management of IT industry , It mainly deals with the customer and billing system . To avoid the time of serving the customer
PPT contain the study of the business process management of IT industry , It mainly deals with the customer and billing system . To avoid the time of serving the customer
MMU INTERNSHIP REPORT JAAYNE JEEVITA A / P RONALD ALFREDJaayneWilliam
JAAYNE JEEVITA A / P RONALD ALFRED TRIMESTER 3 2020 / 2021. This internship report serves the purpose to record the details of my industrial training which was conducted in Influasia SDN.BHD
MMU INTERNSHIP REPORT JAAYNE JEEVITA A / P RONALD ALFREDJaayneWilliam
JAAYNE JEEVITA A / P RONALD ALFRED TRIMESTER 3 2020 / 2021. This internship report serves the purpose to record the details of my industrial training which was conducted in Influasia SDN.BHD
Super-Structural Construction Work of a Six Storied Residential BuildingShariful Haque Robin
The internship report in broad-spectrum contains ten chapters in which I try to explain my
three-month experience in my hosting company. The content of all chapters is broadly
explained and it is constructed from the practical basis of the site work ended all months
ContentsTeam Work Schedule3Team Task Assignment3Project .docxbobbywlane695641
Contents
Team Work Schedule 3
Team Task Assignment 3
Project Plan 4
Step 1: Define the Problem 4
Step 2: Create a Plan 4
Step 3: Execute 4
Step 4: Check Work 6
Step 5: Learn and Generalize 6
House of Quality (HOQ) for Theia’s Smart Glasses 7
Step 1: Define the Problem 7
Step 2: Create a Plan 7
Step 3: Execute 8
Step 4: Check Work 14
Step 5: Learn and Generalize 14
Aggregate Project Plan 15
Step 1: Define the Problem 15
Step 2: Create a Plan 15
Step 3: Execute 16
Step 4: Check Work 22
Step 5: Learn and Generalize 22
I was able to use the APP skills from the midterm and apply it to our actual project. We learned that project #2 yields the highest EMV so that will be the industry we will be focusing on. 22
Theia’s Conceptual Design Process 23
Step 1: Define the Problem 23
Step 2: Create a Plan 23
Step 3: Execute 24
Concept 1 27
Concept 2 28
Concept 3 29
Concept 4 30
Concept 5 31
Concept 6 32
Step 4: Check Work 34
Step 5: Learn and Generalize 34
Phase Ⅱ Reportca 36
Step 1: Define the Problem 36
Step 2: Create a Plan 36
Step 3: Execute 36
Project Planning 36
House of Quality 37
Aggregate Project Plan 37
Reverse Engineering (includes FAST analysis + diagram) 38
Conceptual Design 38
Step 4: Check Work 38
Step 5: Learn and Generalize 39
Team Work Schedule
Date
Task
10/24
Homework assigned, touch bases with team to decide weekend plans.
10/25
Read handout and HOQ example. Everyone assigned to do individual research about AR Glasses.
10/26
Read handout and HOQ example. Everyone assigned to do individual research about AR Glasses.
10/27
Meet at a cafe downtown, due to the power outage. Meeting time is 1 hour.
10/28
Everyone working remotely. Also everyone is working on Phase I/II at the moment. HOQ problem is postponed for a while as we are working on Phase I/II.
10/29
Meet at TBD. Meeting time is 1 hour.
10/30
Revise our work.
10/31
Final revisions. Turn in homework.
Team Task Assignment
Task
Phase 1 - Missing Info + Tech Strategy
Phase 1 - Missing Functional Maps
Project Planning
House of Quality for Product
Aggregate Project Plan
Reverse Engineering
Conceptual Design
Phase II ReportProject PlanStep 1: Define the Problem
We need to clearly determine the tasks required of this project and develop a systematic plan of action to tackle these tasks.Step 2: Create a Plan
Framework for Project Planning:
1. Clearly state the intent of the Project
2. Determine the Design/Development sub-tasks and activities Comment by Christopher Chiang: Develop OS
Develop Display technology
Develop glasses framework
Audio Output
Develop Bluetooth compatibility
Battery development
Charge development
Environment sensing capability
3. Create a design/development activity matrix
4. Create a schedule for each subtask using a GANTT Chart
5. Identify the Critical Path for the Project
6. Assign Clear Roles and Responsibilities & track progressStep 3: Execute
1. Clearly state the intent of the Project
a. Develop smart glasses wearable technology prototype within a 1 year timesp.
The idea of this case study is to give real example of using scrum methodology on PMO daily operations in the construction industry and how we can benefit from this methodology flexibility.
We tried to focus on daily operations since using such methodologies will incredibly affect on consumed efforts and time.
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
The waterfall technique is also called the traditional method of project management. Learn about the 5 key takeaways and how you can implement the techniques in your project.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...Levi Shapiro
Letter from the Congress of the United States regarding Anti-Semitism sent June 3rd to MIT President Sally Kornbluth, MIT Corp Chair, Mark Gorenberg
Dear Dr. Kornbluth and Mr. Gorenberg,
The US House of Representatives is deeply concerned by ongoing and pervasive acts of antisemitic
harassment and intimidation at the Massachusetts Institute of Technology (MIT). Failing to act decisively to ensure a safe learning environment for all students would be a grave dereliction of your responsibilities as President of MIT and Chair of the MIT Corporation.
This Congress will not stand idly by and allow an environment hostile to Jewish students to persist. The House believes that your institution is in violation of Title VI of the Civil Rights Act, and the inability or
unwillingness to rectify this violation through action requires accountability.
Postsecondary education is a unique opportunity for students to learn and have their ideas and beliefs challenged. However, universities receiving hundreds of millions of federal funds annually have denied
students that opportunity and have been hijacked to become venues for the promotion of terrorism, antisemitic harassment and intimidation, unlawful encampments, and in some cases, assaults and riots.
The House of Representatives will not countenance the use of federal funds to indoctrinate students into hateful, antisemitic, anti-American supporters of terrorism. Investigations into campus antisemitism by the Committee on Education and the Workforce and the Committee on Ways and Means have been expanded into a Congress-wide probe across all relevant jurisdictions to address this national crisis. The undersigned Committees will conduct oversight into the use of federal funds at MIT and its learning environment under authorities granted to each Committee.
• The Committee on Education and the Workforce has been investigating your institution since December 7, 2023. The Committee has broad jurisdiction over postsecondary education, including its compliance with Title VI of the Civil Rights Act, campus safety concerns over disruptions to the learning environment, and the awarding of federal student aid under the Higher Education Act.
• The Committee on Oversight and Accountability is investigating the sources of funding and other support flowing to groups espousing pro-Hamas propaganda and engaged in antisemitic harassment and intimidation of students. The Committee on Oversight and Accountability is the principal oversight committee of the US House of Representatives and has broad authority to investigate “any matter” at “any time” under House Rule X.
• The Committee on Ways and Means has been investigating several universities since November 15, 2023, when the Committee held a hearing entitled From Ivory Towers to Dark Corners: Investigating the Nexus Between Antisemitism, Tax-Exempt Universities, and Terror Financing. The Committee followed the hearing with letters to those institutions on January 10, 202
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
Acetabularia Information For Class 9 .docxvaibhavrinwa19
Acetabularia acetabulum is a single-celled green alga that in its vegetative state is morphologically differentiated into a basal rhizoid and an axially elongated stalk, which bears whorls of branching hairs. The single diploid nucleus resides in the rhizoid.
Francesca Gottschalk - How can education support child empowerment.pptxEduSkills OECD
Francesca Gottschalk from the OECD’s Centre for Educational Research and Innovation presents at the Ask an Expert Webinar: How can education support child empowerment?
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
2. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
1 | P a g e
Table of Content
1.0 ACKNOWLEDGEMENT……………………………………………………. 1
2.0 INTRODUCTION………………………………………………………… 2 - 3
2.1 Module Objective……………………………………………………….. 2
2.2 Intern-Working Environment………………………………………....... 3
3.0 General Scope of Training…………………………………………………. 4
4.0 Project 5…………………………………………………………………. 5 - 41
4.1 Mix-Development on lot 3065 & 3085……………………..……… 5 - 8
4.1.1 Learning Outcome……………………………………………….. 9
4.2 D’Marina International Trade Center…………………………… 10 - 19
4.2.1 Jewel of East Coast Malaysia……………………………. 10 – 11
4.2.2 Beachfront Villa…………………………………………………. 12
4.2.3 Semenyik…………………………………………………………. 13
4.2.4 Road and Pedestrian walkway…………………………………. 14
4.2.5 Parcel 3…………………………………………………………… 15
4.2.6 Parcel 1 – 11…………………………………………………….. 16
4.2.7 Render………………………………………………………. 17 – 18
4.2.8 Learning Outcome……………………………………………….. 19
4.3 Lutheran Church…………………………………………………… 20 - 34
4.3.1 Gate Design Proposal 1……………………………………. 20 - 23
4.3.2 Gate Design Proposal 2……………………………………. 24 - 27
4.3.3 Gate Design Proposal 3……………………………………. 28 - 30
4.3.4 Gate Design Proposal 4……………………………………. 31 - 33
4.3.5 Learning Outcome……………………………………………….. 34
4.4 Mix-Development on PT7258 ( Johnny Ong )……………………35 - 37
4.4.1 Emergency Lighting and Fire Wall………….…………….. 35 - 37
4.4.2 Learning Outcome……………………………………………….. 37
4.5 Jason Tan’s Bungalow……………………….…………………….38 - 41
4.5.1 Window Schedule, Bathroom detail………………………. 38 – 41
4.5.2 Learning Outcome…………………………………...…………… 41
5.0 Site Visitation……………………………………………………………. 42 - 47
5.1 Lot 495, 41 Units 3 Storey Terrace House………………………….. 42
5.1.1 Site Photoes………………………………………………… 42 – 43
5.1.2 Client Consultant Meeting and Site Meeting…………….. 44 – 46
5.1.3 Construction Documents………………………………………… 47
5.1.4 Learning Outcome………………………………………………... 47
6.0 Conclusion…………………………………………………………………… 48
3. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
2 | P a g e
1.0 ACKNOWLEDGEMENT
I would like to express my sincerest gratitude to my colleagues at Clement Wong
Architecture for guiding me throughout the duration of my entire internship, which was 8
weeks. Their constant guidance & support had taught me as well as allowed me to
experience the working environment of what I would call it as, “The architecture life”.
During my time interning here, I was definitely given a lot of opportunities and chances
to learn and develop new talents at professional skills. Our seniors were also always
there to answer our questions & help us along the way. “AS LONG AS WE ASK” to
what we want to do and learn, our seniors will try their best to guide us. They also like
giving us the more difficult tasks, though we might have complained, we now are
thankful for the things we’ve learnt and for the experiences we have gotten from
completing the tasks. Thanks to their guidance and mentorship, they were able to
encourage me to be professional during the entire internship programme.
Sincerely,
Hern-Hymn Devinchi Ng
4. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
3 | P a g e
2.0 INTRODUCTION
2.1 Module Objective
This internship is aimed at introducing students to the requirements, activities and
operations involved in working in architectural / construction practices. The purpose is to
facilitate the involvement of students in professional attachments to architectural
practices in order to develop an understanding of the general nature, principles and
procedure of law and legislation as applied to architectural drawings, especially the
Building by laws. Students will also be exposed to the process of authority submission
for various drawings from an architectural practice and the range of contract
documentation produced to support these drawings. Via a full-time internship
attachment, students will further appreciate the documentation and report writing skill
required of an employee in an architect’s firm.
5. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
4 | P a g e
2.2 Intern-Working Environment
2.2.1. Company Background
Company
Name
Clement Wong Architecture
Address 56D & 57D, Jalan Desa Bakti, Taman Desa, 58100 Kuala Lumpur
Email Cwarch.hr@gmail.com / clementwongarch@gmail.com
Contact
Number
+603 7984 0128
Clement Wong started his own practice called Clement Wong Architecture in
2009 registered under the Board of Architect, Malaysia. His current work
include Eco-tech Vertical Farming in China; REHDA new headquarter in PJ;
several housing estate development and bungalows around Klang Valley
which emphasis on “green features” and sustainable designs including his own
home office retrofit. Clement Wong is also a Green Building Facilitator under
the newly formed Green Building Index rating tool specific for Malaysian
buildings.
2.2.2 Period of Training
The total required training period is 8 weeks, from January 3rd 2016 to March
3rd 2016, however I ended my training period at March 6th 2016.
2.2.3 Working Hours
Monday to Friday
9am to 6pm
*( Lunch Hour: 1pm to 2pm)*
6. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
5 | P a g e
3.0 General Scope of Training
Overall Task and Practices
1. Design Sketch, Drafting.
2. AutoCAD Drawing, 3D modeling.
3. Comment, Modifications & Amendments of Architectural Drawings.
4. Preparation of presentation slides.
5. Observed and assessed regulatory context with Building By – Laws, Set Back,
and Fire Escape.
6. Prepared architectural drawing with regard to location, building elements,
finishes, and fittings.
7. Establish requirements for co-ordinate, consultants and product suppliers.
8. Preparation for tender documents and participated in the process
Software Applications
1. Autodesk AutoCAD
2. SketchUp
3. Rhino 5
4. Photoshop
5. Lumion 6 Pro
6. Adobe
7. Microsoft ( Word, and PowerPoint )
8. Google Chrome
Training Program Schedule
We are to do the projects that are given or requires upon our self and expected to be
self-discipline and to multitask our given task and to be completed on time without
procrastinating. Our given task didn’t have a rushing due date, but when one of our
colleague give us another task, we have to complete that new given task first, because
it’s near to dead line. That is why we have a lot of stuff to do and learn coming from it.
7. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
6 | P a g e
4.0 Project
4.1 Mix-Development on lot 3065 & 3085
Overview
Project: Mix-Development on lot 3065 & 3085
Site location: Sungai Penchala, Mukim, Kuala Lumpur, Malaysia
Specification: Mix-used, Shopping Complex, Residential, Office, Public Gathering
Supervisor: Oilver Tan
Task: Technical drawing of fire-staircase ( Tender Drawing )
Mix-Development on lot 3065 &3085 is a project that is consisting of 500 units of
residential, 5 floor of basement carpark, and 2 floor of shopping complex. This high rise
features greenery and double volume of some units. This Mix-Development area of land
ranging from 3800𝑚2
to 3900𝑚2
of boundary line. The estimated prince to complete
building this high rise, cost round RM80,000,000. This project to scheduled to be
completed by the end of 2018. The current stage of his project is on the pile foundation,
and it already costed RM20,000,000. The total of number fire-escape/ staircase of this
building in the building are 8, and I have completed 5 of the drawing, thankful for my
colleague Winnie Ang ( Taylor’s intern ) for completed her first task fast, and her second
task for to assist me on this Technical drawing of fire-staircase. If it wasn’t for her, I think
that I will stuck on drawing this my whole intern. Our supervisor Oilver Tan was in-
charge of this project, and he taught us a lot. By drawing it so that the person who will
read it next understand it well. The gird-line way so, that if people want to look back the
staircase, they can just see back where the grid-line at. Most-important that is the stair-
case must basic on UBBL. So each step maximum of 180mm per rises.
On Day 1, that is what I did (Figure
4.1.1 ) and completed on the next day,
but later we found a problem that is each
rises are only 155mm that is very
following according to the floor plan step.
So that my supervisor told me to
decrease the number of step, and as
long as the match back the floor level,
then is fine. So, we decided to decrease
the number of step, and my new task to
make sure the floor plan step is correct
with the technical section. The below
image of staircase is I draw.
Figure 4.1.1
8. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
7 | P a g e
This is my first product work in my internship program. ( figure 4.1.2 ) This staircase is
staircase number 2. My supervisor told me to start from complicated one first so that the
next one will be more easily for me.
This is staircase number 3. ( Figure 4.1.3)
Figure 4.1.2
Figure 4.1.3
9. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
8 | P a g e
This is staircase number 6 ( figure 4.1.4 )
This is staircase number 7 ( figure 4.1.5 )
Figure 4.1.4
Figure 4.1.5
10. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
9 | P a g e
This is staircase number 8. ( Figure 4.1.6 )
Figure 4.1.6
Figure 4.1.7
This is the floor plan, and the location of staircase. ( Figure 4.1.7 ) The red box is the one I
draw, and the blue box is Winnie Ang who draw it.
#2 #3 #6 #7 #8
11. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
10 | P a g e
4.1.1 Learning Outcome:
After Completing this technical drawing of fire-escape staircase, given from my
supervisor Oilver Tan, I now managed to enhance my knowledge of the Fire-escape
staircase, and the UBBL of fire-escape staircase. Furthermore, now I have a better
understanding of how to do a technical drawing, basic on the UBBL step and railing.
12. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
11 | P a g e
4.2 D’Marina International Trade Center
For this project, it’s split into many part, due to it’s 500 acres. And all the work still on
proposal stage. And the total estimate development cost RM10,006,507,578.
4.2.1 Jewel of East Coast Malaysia
Overview
Project: Jewel of East Coast Malaysia
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Bovi
Task: Update the slide to 2017 version
For this task, I was assign to update the slide at latest as possible, due to some info are
out to date and some have new info regarding of it. This PowerPoint slide are mainly to
intro the bullet train from China to Malaysia, the distance and timing of it. And mainly it
informs the contractor to understand more and update why this location we planning to
built is the suitable spot.
13. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
12 | P a g e
This is the total slide of it, ( figure 4.2.1.1 ) and I tried my best to update it as update as
possible.
Figure 4.2.1.1
14. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
13 | P a g e
4.2.2 Beachfront Villa
Overview
Project: Beachfront Villa
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Saidu
Task: 3d modeling
For this task, I was assign built the 3d model, repaint to other material, and make the 3d
model as simple as possible. So, that when we are doing the perspective view for the
master planning render. The building wouldn’t effect it. So that we can focus on what we
want too. This Beachfront Villa consist of 3 different style and design of the bungalow.
That is the 3d model I did, and make it as simple as possible. ( Figure 4.2.2.1 )
Figure 4.2.2.1
15. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
14 | P a g e
4.2.3 Semenyik
Overview
Project: Semenyik
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Saidu
Task: 3d modeling
For this task, I was assign built the 3d model, repaint to other material, and make the 3d
model as simple as possible. So, that when we are doing the perspective view for the
master planning render. The building wouldn’t effect it. So that we can focus on what we
want too. This is the 4 storey of Semi-D housing.
The front perspective view ( figure 4.2.3.1 ) and, the back view ( figure 4.2.3.2 )
Figure 4.2.3.1 Figure 4.2.3.2
16. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
15 | P a g e
4.2.4 Road and Pedestrian walkway
Overview
Project: Road and Pedestrian walkway
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Saidu
Task: 3d modeling
For this task, I was assign built the 3d model, repaint to other material, and make the 3d
model as simple as possible. So, that when we are doing the perspective view for the
master planning render. The building wouldn’t effect it. So that we can focus on what we
want to render. This is the road and pedestrian walkway for D’Marina.
For this task, I overnight to complete it during the Chinese new year break. Cause I was
informed that it’s very in rush. ( figure 4.2.4.2 )
Figure 4.2.4.1 Figure 4.2.4.2
17. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
16 | P a g e
4.2.5 Parcel 3
Overview
Project: Parcel 3
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Clive
Task: Photoshop
For this task, I was assign to Cad the drawing and Photoshop Parcel 3, and color it in
red. So that it’s easier for the supervisor to present and the highlight of the area.
Figure 4.2.5.1
18. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
17 | P a g e
4.2.6 Parcel 1 - 11
Overview
Project: Parcel 1 - 11
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Saidu
Task: Update the slide to 2017 version
For this task, I was assign to update the slide at latest as possible, due to some info are
out to date and some have new info regarding of it. This PowerPoint slide are mainly to
about the Parcel 1 to 11, where to intro each and every parcel unique design and idea.
Figure 4.2.6.1
19. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
18 | P a g e
4.2.7 Render
Overview
Project: Render
Site location: Kuantan, Pahang, Malaysia
Specification: 500 acres
Supervisor: Saidu
Task: Adding human figure and trees
For this task, I told my colleague I was free, so that I can help him to do it, when he was
doing it himself, and rushing for another work.
Figure 4.2.7.1
20. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
19 | P a g e
For theses are the human figure and tree on the render view that I did. for
( figure 4.2.7.1, figure 4.2.7.2 , figure 4.2.7.3 )
Figure 4.2.7.2
Figure 4.2.7.3
21. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
20 | P a g e
4.2.8 Learning Outcome
After Completing so many stuff for D’Marina project, I have learned how to do a
proposal PowerPoint slide better, and how does it attract the attention of the human.
Making 3D-model as simple as possible so that it can the master perspective view won’t
not look so irritating. And that Photoshop the image so that it will look better and to be
more presentable. Furthermore, now I have a better understanding of how to do a
Multitask better and to work in very efficiently way.
22. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
21 | P a g e
4.3 Lutheran Church
4.3.1 Gate Design Proposal 1
Overview
Project: Lutheran Church
Site location: Mont Kiara, Kuala Lumpur, Malaysia
Specification: Church
Supervisor: Sunil
Task: Designing Gate
Lutheran Church is a project that is a public space for private realm. This Mix-
Development area of land ranging from 3155𝑚2
of boundary line. The estimated prince
to complete building this high rise, cost round RM8,000,000. But they reduce the cost to
RM6,000,000 so that the design of the building didn’t look as nice as what we had
present in the beginning. This project to scheduled to be completed by the end of
September 2017. For this is the first during my internship, I took a measurement tape,
and measure the site. So that our gate proposal can be basic on the site drawing. For
this Task, I was to do sketches, AutoCAD, SketchUP, and Photoshop.
This is the Site picture that I took. ( Figure 4.3.1.1 )
Figure 4.3.1.1
23. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
22 | P a g e
Figure 4.3.1.2
Figure 4.3.1.3
24. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
23 | P a g e
Figure 4.3.1.4
Figure 4.3.1.5
25. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
24 | P a g e
This is the Full set of the gate design proposal 1 from ( Figure 4.3.1.1 to Figure 4.3.1.6 )
Figure 4.3.1.6
26. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
25 | P a g e
4.3 Lutheran Church
4.3.2 Gate Design Proposal 2
Overview
Project: Lutheran Church
Site location: Mont Kiara, Kuala Lumpur, Malaysia
Specification: Church
Supervisor: Sunil
Task: Designing Gate
Lutheran Church is a project that is a public space for private realm. This Mix-
Development area of land ranging from 3155𝑚2
of boundary line. The estimated prince
to complete building this high rise, cost round RM8,000,000. But they reduce the cost to
RM6,000,000 so that the design of the building didn’t look as nice as what we had
present in the beginning. This project to scheduled to be completed by the end of
September 2017. For this Task, I was to do sketches, AutoCAD, SketchUP, and
Photoshop. Proposal 2 include with the refuses compartment, and the letter box. Went
to revisit site again to measure the refuse compartment area.
Figure 4.3.2.1
27. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
26 | P a g e
Figure 4.3.2.2
Figure 4.3.2.3
28. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
27 | P a g e
Figure 4.3.2.4
Figure 4.3.2.5
29. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
28 | P a g e
This is the Full set of the gate design proposal 2 from ( Figure 4.3.2.1 to Figure 4.3.2.6 )
Figure 4.3.2.6
30. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
29 | P a g e
4.3 Lutheran Church
4.3.3Gate Design Proposal 3
Overview
Project: Lutheran Church
Site location: Mont Kiara, Kuala Lumpur, Malaysia
Specification: Church
Supervisor: Sunil
Task: Designing Gate
Lutheran Church is a project that is a public space for private realm. This Mix-
Development area of land ranging from 3155𝑚2
of boundary line. The estimated prince
to complete building this high rise, cost round RM8,000,000. But they reduce the cost to
RM6,000,000 so that the design of the building didn’t look as nice as what we had
present in the beginning. This project to scheduled to be completed by the end of
September 2017. For this Task, I was to do sketches, AutoCAD, SketchUP, and
Photoshop. Proposal 3, after knowing the gate is over-weight, and Clement told us to
change the design to a simpler one. Which is more cost saving.
Figure 4.3.3.1
31. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
30 | P a g e
Figure 4.3.3.2
Figure 4.3.3.3
32. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
31 | P a g e
This is the Full set of the gate design proposal 2 from ( Figure 4.3.3.1 to Figure 4.3.3.5 )
Figure 4.3.3.4
Figure 4.3.3.5
33. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
32 | P a g e
4.3 Lutheran Church
4.3.4Gate Design Proposal 4
Overview
Project: Lutheran Church
Site location: Mont Kiara, Kuala Lumpur, Malaysia
Specification: Church
Supervisor: Sunil
Task: Designing Gate
Lutheran Church is a project that is a public space for private realm. This Mix-
Development area of land ranging from 3155𝑚2
of boundary line. The estimated prince
to complete building this high rise, cost round RM8,000,000. But they reduce the cost to
RM6,000,000 so that the design of the building didn’t look as nice as what we had
present in the beginning. This project to scheduled to be completed by the end of
September 2017. For this Task, I was to do sketches, AutoCAD, SketchUP, and
Photoshop. Proposal 4, because they have no budget now, they are reducing a lot of
stuff, and it’s back to follow the first tender set.
Figure 4.3.4.1
34. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
33 | P a g e
Figure 4.3.4.2
Figure 4.3.4.3
35. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
34 | P a g e
Figure 4.3.4.4
Figure 4.3.4.5
36. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
35 | P a g e
4.3.5 Learning Outcome:
After Completing so many different gate design proposals for Lutheran Church, I have
learned that how to do a better work in a proposals drawing, as in once we having a
meeting on site, a drawing and dimension must state it very clear so that people don’t
have to flip thru out the page just to find that single dimension, and working drawing that
is suppose to be more efficiently so that it will look more neat. Furthermore, now I have
a better understanding of how to a tender drawing that has to be properly organized.
37. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
36 | P a g e
4.4 Mix-Development on PT7258 ( Johnny Ong )
4.4.1 Emergency Lighting and Fire Wall
Overview
Project: Mix-Development on PT7258 ( Johnny Ong )
Site location: Country Homes, Mukim Rawang, Selangor, Malaysia
Specification: Shopping Complex
Supervisor: Sunil
Task: Emergency Lighting and Fire Wall
Mix-Development on PT7258 ( Johnny Ong ) is a project that is developing a shopping
complex. This Mix-Development area of land ranging from 12150𝑚2
of boundary line.
The estimated prince to complete building this high rise, cost round RM5,000,000. This
project to scheduled to be completed by the end of August 2017. Since it’s a Bomba
drawing, for this task I had to do is to know the UBBL fire wall, and Emergency Lighting
Figure 4.4.1.1
38. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
37 | P a g e
Figure 4.4.1.2
Figure 4.4.1.3
39. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
38 | P a g e
Figure 4.4.1.1 to figure 4.4.1.4 are the image of fire wall and emergency lighting.
4.4.2 Learning Outcome:
After Completing so this task, it helped me to understand more of a bomba drawing.
Furthermore, now I have a better understanding of how to a bomba drawing that has to
be properly organized.
Figure 4.4.1.4
40. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
39 | P a g e
4.5 Jason Tan’s Bungalow
4.5.1 Window schedule, bathroom detail.
Overview
Project: Jason Tan’s Bungalow
Site location: Klang, Selangor, Malaysia
Specification: Bungalow
Supervisor: Sunil
Task: Update floor plan, elevation, 3d model, and washroom detail.
Jason Tan’s Bungalow is a project that is building a Private Bungalow. This Mix-
Development area of land ranging from 9250𝑚2
of boundary line. The estimated cost to
complete this bungalow round RM4,000,000. This project to scheduled to be completed
by the end of end of June 2018. The current stage it’s on now is pre-casting the
skeleton structure. For this task, I was assign to update the window schedule to the
elevation, and than update the 3d model, and after than update the washroom detail line
weight isn’t correct I was told to do that too.
Figure 4.5.1.1
41. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
40 | P a g e
Figure 4.5.1.1 and figure 4.5.1.2 are the updated elevation, and the figure 4.5.1.3 are
the update 3d model of the window.
Figure 4.5.1.2
Figure 4.5.1.3
42. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
41 | P a g e
Figure 4.5.1.4
Figure 4.5.1.5
43. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
42 | P a g e
These are the bathroom detail and finishes figure 4.5.1.4 to figure 4.5.1.6
4.5.2 Learning Outcome:
After Completing so this task, as an intern, this is my first bathroom detail I did. and I
learned that once we update an drawing we must highlight it so the following next
person will know about it, and pay more attention to it.
Figure 4.5.1.6
44. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
43 | P a g e
5.0 Site Visitation
5.1 Lot 495, 41 Units 3 Storey Terrace House
5.1.1 Site Photos
Overview
Project: Lot 495, 41 Units 3 Storey Terrace House
Site location: Jalan Gombak, Setapak, Kuala Lumpur Malaysia
Specification: Terrace House
Supervisor: Ling Siang
Task: Going to site, and taking picture,
Lot 495, 41 Units 3 Storey Terrace House is a project that are developing a Terrace
Houses. The estimated cost to complete this bungalow round RM8,000,000. This
project to scheduled to be completed by the end of end of this year. For this task, I was
assign to go to site with my colleague, as she is also my supervisor for site visit. My
main job is the go and understand the feeling of having a meeting on site, and taking
picture as backup. Once we are back to the office, I will also try my best to do Client
Consultant Meeting (ccm), and Site Meeting (sm), even thought I know my
understanding is not as well as my supervisor, she is still willing to learn me do it, and
than teach me later about me.
Figure 5.1.1.1
On site meeting
Figure 5.1.1.2
Terrace Houses
45. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
44 | P a g e
Figure 5.1.1.1 to Figure 5.1.1.6 are all on site photo.
Figure 5.1.1.3
Conctractor sketch on finihes titles.
Figure 5.1.1.4
.
Figure 5.1.1.5
.
Figure 5.1.1.6
.
46. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
45 | P a g e
5.1.2 Client Consultant Meeting (ccm), and Site Meeting (sm),
Overview
Project: Lot 495, 41 Units 3 Storey Terrace House
Site location: Jalan Gombak, Setapak, Kuala Lumpur Malaysia
Specification: Terrace House
Supervisor: Ling Siang
Task: typing the Client Consultant Meeting (ccm), and Site Meeting (sm)
Figure 5.1.2.1 and figure 5.1.2.2 are the image of the CCM minutes.
Figure 5.1.2.2
Febuary 23th 2017
Figure 5.1.2.1
January 19th2017
.
47. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
46 | P a g e
Figure 5.1.2.3
January 19th2017
.
Figure 5.1.2.4
February 10th2017
.
48. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
47 | P a g e
Figure 5.1.2.5
February 24th2017
.
49. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
48 | P a g e
5.1.3 Construction Documents
Overview
Project: Lot 495, 41 Units 3 Storey Terrace House
Site location: Jalan Gombak, Setapak, Kuala Lumpur Malaysia
Specification: Terrace House
Supervisor: Ling Siang
Task: Plotting Construction Documents for Contractor
5.1.4 Learning Outcome:
After Going to site, and typing out CCM, and SM, I know that going site is easy, bur
typing CCM and SM are hard because there are still a lot of element that I still didn’t
know off.
Figure 5.1.3.1
.
50. [AR2615] INTERSHIP TRAINNING AND REPORT
NAME: HERN-HYMN DEVINCHI NG ( 0320526 )
49 | P a g e
6.0 Conclusion
For the past 8 Week I have learned a lot that I couldn’t had learn in education, would
like to thank you Clement Wong Architecture colleague again, and thank ms, balkish for
spending your time to come visit us during your busy day.