Jennifer Gonzalez, city planner at the City of Hoboken shines a light on how the city handles stormwater and shows the problem areas during the Learning Lunch on September 19th.
Innovative Approaches to Managing Stormwater: The Hoboken Approach
1. Innovative Approaches to
Managing Stormwater:
Lessons from Rotterdam,
New Jersey and New York
Learning Lunch:
Monday September 19, 2016
City of Hoboken, New Jersey
3. Landmass within Flood Zone (A): 63.85%
Landmass within Flood Zone (V): 7.41%
Landmass within Flood Zone (X): 7.66%
Hoboken NFIP Total Liability: $1,922,187,500
Hoboken NFIP Annual Premiums: $5,984,720
Flood Risk
7. Rebuild by Design Hudson River: ▪ Resist ▪ Delay ▪ Store ▪ Discharge ▪
REBUILD
BY
DESIGN
▪ RESIST ▪ DELAY ▪STORE ▪ DISCHARGE ▪
HUDSON RIVERHOBOKEN WEEHAWKEN JERSEY CITY │ NEW JERSEY
8.
9.
10. Rainfall model depicting a 5-year rainfall
event (high-tide) “No Action Alternative.”
Model estimates future flood (rainfall)
event if Project is not built.
Model assumes Hoboken and NHSA’s
existing on-going initiatives WILL be
built:
• Southwest Park
• H1 and H5 Pump Stations
• Washington Street Rain Garden
• City Hall Green Infrastructure
Washington
Street Rain Gardens
H5 Pump Station
City Hall GI
Project
H1 Pump Station
Southwest Park
Areas that
Flood
21. Baseline Conditions (NAA) Proposed DSD Alternative
Washington
Street Rain
Gardens
H5 Pump
Station
City Hall GI
Project
H1 Pump
Station
Southwest
Park
BASF Site
NJ Transit
Site
Block 10
Site
22. BASF Site
NJ Transit
Site
Block 10
Site
Proposed underground detention facilities
with green/open space on ground surface
with discharge features such as pumps to
manage rainfall runoff volume
ROW Green/Grey Infrastructure Practices
‐ Total of 61 sites to manage street drainage for
approx. 13 acres
NJ Transit site
‐ Manages rainfall runoff for approx. 15
acres
Block 10 site
‐ Manages rainfall runoff for approx. 8
acres
BASF site
‐ Manages rainfall runoff for approx. 55 acres
23.
24.
25.
26.
27. • Integrated flood management
solutions to complement RBD
• Proposed a combined surface and
sub-surface plan to utilize 4
contiguous acres of the 6-acre BASF
site that would include:
• Stormwater detention facility
• Underground parking garage
• Surface park space
• Integrated green infrastructure
Re.Invest
29. • Create an “ecological zone” in part of the H6 and H7 drainage
areas
• Would install new storm sewer infrastructure to separate the
currently combined system
• Stormwater would flow to the BASF site where solids and
floatables would be removed
• Stormwater would be detained under BASF site until the
detention facility is at capacity
• New stormwater pump station on BASF site would pump to a
new outfall in Weehawken Cove
• Engineered wetlands in Cove would filter stormwater
NHSA Eco-Zone
30. Jennifer Gonzalez AICP, ENV SP
Principal Planner
City of Hoboken
jgonzalez@hobokennj.gov
www.hobokennj.gov
https://www.facebook.com/hoboken
https://twitter.com/cityofhoboken
https://www.instagram.com/hobokennj
https://vimeo.com/hobokennj
https://www.flickr.com/photos/hoboken
Thank you!