SlideShare a Scribd company logo
1 of 11
In the journal article by McCormick and White (Fall 2000)
about the roles and competencies required for the success of
organization development practitioners, compare and contrast
the relative advantages and disadvantages of being an outside
consultant or an internal process/program improvement leader.
Focus your analysis on the consultant or leader’s ability to
effectively diagnose and facilitate change initiatives within an
organization. Evaluate differences in the ethical and values-
driven considerations of the two types of organization
development practitioners, as well as the different ways each
type of practitioner might deal with ethical dilemmas.
No paper format needed. 300 wrods.
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11
2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager and A
6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11
7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project
Manager and W
9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11
12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11
Mon 1/3/11 Project Manager
15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11
Mon 1/3/11
16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and E
17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and S
18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and S
21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
Sparks Electrical PM
23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11
26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11
East Side Framing & D
27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11
28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side
Framing & D
30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11
33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Sparks Electrical PM
34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks
Electrical
35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11
38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed
1/5/11 Waterworks Plumbing
39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
Project Manager
Project Manager
Project Manager
Project Manager and Attend
Project Manager
Project Manager and
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager and East S
Project Manager and Spark
Project Manager and Water
Project Manager and Wood
Project Manager and Stude
Sparks Electrical P
Waterworks Plumbi
East Side Framing
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Sparks Electrical PM
Sparks Electrical
City & County
Project Manager
Waterworks Plumbing PM
Waterworks Plumbi
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: District4Move.mpp
Date: Sat 1/8/11
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City
& County
41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11
43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East
Side Framing & D
45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11
48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Woodcraft Carpentry P
49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11
Woodcraft Carpentry
50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11
53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue
1/4/11 Student Workers Mana
54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11
Student Workers
55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11
58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
61 15 Move 3 days Mon 1/3/11 Wed 1/5/11
62 15.1 Move production equipment 3 days Mon 1/3/11 Wed
1/5/11 Express Moving Comp
63 15.2 Move non-production equipment 3 days Mon 1/3/11
Wed 1/5/11 Express Moving Comp
64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11
66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11
70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project
Manager
71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
City & County
Project Manager
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Woodcraft Carpentry PM
Woodcraft Car
City & County
Project Manager
Student Workers Manager
Student Worke
Project Manager
Project Manager
City Equipment Movers PM
City Equipment Movers
Project Manager
Express Moving Company
Express Moving Company
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: District4Move.mpp
Date: Sat 1/8/11
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3

More Related Content

Similar to In the journal article by McCormick and White (Fall 2000) about th.docx

ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docxACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
annetnash8266
 
Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides
SlideTeam
 
Bai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du anBai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du an
Doan Tran Ngocvu
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
Deborah Obasogie
 
Project Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docxProject Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docx
briancrawford30935
 
SHC Family Practice Plan-Project Plan
SHC Family Practice Plan-Project PlanSHC Family Practice Plan-Project Plan
SHC Family Practice Plan-Project Plan
Ron Crawford, PMP
 
Project Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docxProject Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docx
wkyra78
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docx
joyjonna282
 

Similar to In the journal article by McCormick and White (Fall 2000) about th.docx (20)

NJ_RFP_Project-Schedule_v2_cfc_03-02-13
NJ_RFP_Project-Schedule_v2_cfc_03-02-13NJ_RFP_Project-Schedule_v2_cfc_03-02-13
NJ_RFP_Project-Schedule_v2_cfc_03-02-13
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...
 
Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides
 
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docxACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
 
Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides Project Brief Summary PowerPoint Presentation Slides
Project Brief Summary PowerPoint Presentation Slides
 
Standard Competition 12 Months
Standard Competition 12 MonthsStandard Competition 12 Months
Standard Competition 12 Months
 
Bai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du anBai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du an
 
PMBOK Planning Process Group
PMBOK Planning Process GroupPMBOK Planning Process Group
PMBOK Planning Process Group
 
UMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group PresentationUMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group Presentation
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Project Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docxProject Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docx
 
SHC Family Practice Plan-Project Plan
SHC Family Practice Plan-Project PlanSHC Family Practice Plan-Project Plan
SHC Family Practice Plan-Project Plan
 
Project Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docxProject Planning – Developing the Project Plan and Determining Cri.docx
Project Planning – Developing the Project Plan and Determining Cri.docx
 
Project charter j
Project charter jProject charter j
Project charter j
 
Project Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation SlidesProject Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation Slides
 
Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
Internship report
Internship reportInternship report
Internship report
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 

More from jaggernaoma

Attached Files News Analysis Sample.docxNews Analysis Sam.docx
Attached Files News Analysis Sample.docxNews Analysis Sam.docxAttached Files News Analysis Sample.docxNews Analysis Sam.docx
Attached Files News Analysis Sample.docxNews Analysis Sam.docx
jaggernaoma
 
Attached Files  SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
Attached Files     SOC-220_SOCIAL PROBLEMS PRESENTATION.docxAttached Files     SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
Attached Files  SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
jaggernaoma
 
Attached are the instructions and rubric! Research Paper #2.docx
Attached are the instructions and rubric! Research Paper #2.docxAttached are the instructions and rubric! Research Paper #2.docx
Attached are the instructions and rubric! Research Paper #2.docx
jaggernaoma
 
Attached are the guidelines for the Expertise Sharing Project. M.docx
Attached are the guidelines for the Expertise Sharing Project. M.docxAttached are the guidelines for the Expertise Sharing Project. M.docx
Attached are the guidelines for the Expertise Sharing Project. M.docx
jaggernaoma
 
Atomic models are useful because they allow us to picture what is in.docx
Atomic models are useful because they allow us to picture what is in.docxAtomic models are useful because they allow us to picture what is in.docx
Atomic models are useful because they allow us to picture what is in.docx
jaggernaoma
 
Atoms and Electrons AssignmentLook at these websites to he.docx
Atoms and Electrons AssignmentLook at these websites to he.docxAtoms and Electrons AssignmentLook at these websites to he.docx
Atoms and Electrons AssignmentLook at these websites to he.docx
jaggernaoma
 

More from jaggernaoma (20)

Attached is a joint letter to Capitol Hill to advocate for increased.docx
Attached is a joint letter to Capitol Hill to advocate for increased.docxAttached is a joint letter to Capitol Hill to advocate for increased.docx
Attached is a joint letter to Capitol Hill to advocate for increased.docx
 
Attached is a copy of an interview done with a Tribal member regardi.docx
Attached is a copy of an interview done with a Tribal member regardi.docxAttached is a copy of an interview done with a Tribal member regardi.docx
Attached is a copy of an interview done with a Tribal member regardi.docx
 
Attached Files Week 5 - trace IP Physical Location.rtf (38..docx
Attached Files Week 5 - trace IP Physical Location.rtf (38..docxAttached Files Week 5 - trace IP Physical Location.rtf (38..docx
Attached Files Week 5 - trace IP Physical Location.rtf (38..docx
 
Attached here is a psychology article I need to be summarized. Pleas.docx
Attached here is a psychology article I need to be summarized. Pleas.docxAttached here is a psychology article I need to be summarized. Pleas.docx
Attached here is a psychology article I need to be summarized. Pleas.docx
 
Attached Files News Analysis Sample.docxNews Analysis Sam.docx
Attached Files News Analysis Sample.docxNews Analysis Sam.docxAttached Files News Analysis Sample.docxNews Analysis Sam.docx
Attached Files News Analysis Sample.docxNews Analysis Sam.docx
 
Attached Files  SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
Attached Files     SOC-220_SOCIAL PROBLEMS PRESENTATION.docxAttached Files     SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
Attached Files  SOC-220_SOCIAL PROBLEMS PRESENTATION.docx
 
Attached below you will find the series of 4 questions. This assignm.docx
Attached below you will find the series of 4 questions. This assignm.docxAttached below you will find the series of 4 questions. This assignm.docx
Attached below you will find the series of 4 questions. This assignm.docx
 
Attached below isWEEK 4 As always, include references. As alwa.docx
Attached below isWEEK 4 As always, include references. As alwa.docxAttached below isWEEK 4 As always, include references. As alwa.docx
Attached below isWEEK 4 As always, include references. As alwa.docx
 
Attached are two articles in one document. Write thoughtful resp.docx
Attached are two articles in one document. Write thoughtful resp.docxAttached are two articles in one document. Write thoughtful resp.docx
Attached are two articles in one document. Write thoughtful resp.docx
 
Attached are the instructions to the assignment.Written Assign.docx
Attached are the instructions to the assignment.Written Assign.docxAttached are the instructions to the assignment.Written Assign.docx
Attached are the instructions to the assignment.Written Assign.docx
 
Attached are the instructions and rubric! Research Paper #2.docx
Attached are the instructions and rubric! Research Paper #2.docxAttached are the instructions and rubric! Research Paper #2.docx
Attached are the instructions and rubric! Research Paper #2.docx
 
Attached are the guidelines for the Expertise Sharing Project. M.docx
Attached are the guidelines for the Expertise Sharing Project. M.docxAttached are the guidelines for the Expertise Sharing Project. M.docx
Attached are the guidelines for the Expertise Sharing Project. M.docx
 
Attached are the documents needed to complete the assignment. The in.docx
Attached are the documents needed to complete the assignment. The in.docxAttached are the documents needed to complete the assignment. The in.docx
Attached are the documents needed to complete the assignment. The in.docx
 
Attached are the 3 documents1. Draft copy submitted2. Sam.docx
Attached are the 3 documents1. Draft copy submitted2. Sam.docxAttached are the 3 documents1. Draft copy submitted2. Sam.docx
Attached are the 3 documents1. Draft copy submitted2. Sam.docx
 
attached are directions needed to complete this essay! Please make s.docx
attached are directions needed to complete this essay! Please make s.docxattached are directions needed to complete this essay! Please make s.docx
attached are directions needed to complete this essay! Please make s.docx
 
Attach is the checklist For this Assignment, write a 3 and half pa.docx
Attach is the checklist For this Assignment, write a 3 and half pa.docxAttach is the checklist For this Assignment, write a 3 and half pa.docx
Attach is the checklist For this Assignment, write a 3 and half pa.docx
 
Attach and submit the final draft of your Narrative Essay. Remember .docx
Attach and submit the final draft of your Narrative Essay. Remember .docxAttach and submit the final draft of your Narrative Essay. Remember .docx
Attach and submit the final draft of your Narrative Essay. Remember .docx
 
Atomic Theory Scientists and Their ContributionsScientist .docx
Atomic Theory Scientists and Their ContributionsScientist .docxAtomic Theory Scientists and Their ContributionsScientist .docx
Atomic Theory Scientists and Their ContributionsScientist .docx
 
Atomic models are useful because they allow us to picture what is in.docx
Atomic models are useful because they allow us to picture what is in.docxAtomic models are useful because they allow us to picture what is in.docx
Atomic models are useful because they allow us to picture what is in.docx
 
Atoms and Electrons AssignmentLook at these websites to he.docx
Atoms and Electrons AssignmentLook at these websites to he.docxAtoms and Electrons AssignmentLook at these websites to he.docx
Atoms and Electrons AssignmentLook at these websites to he.docx
 

Recently uploaded

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 

In the journal article by McCormick and White (Fall 2000) about th.docx

  • 1. In the journal article by McCormick and White (Fall 2000) about the roles and competencies required for the success of organization development practitioners, compare and contrast the relative advantages and disadvantages of being an outside consultant or an internal process/program improvement leader. Focus your analysis on the consultant or leader’s ability to effectively diagnose and facilitate change initiatives within an organization. Evaluate differences in the ethical and values- driven considerations of the two types of organization development practitioners, as well as the different ways each type of practitioner might deal with ethical dilemmas. No paper format needed. 300 wrods. ID WBS Task Name Duration Start Finish Predecessors Resource Names 1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11 2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and A 6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11 7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project Manager and W 9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager
  • 2. 10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11 12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11 Mon 1/3/11 16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and E 17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical PM 23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing 25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11 26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11 East Side Framing & D 27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11 28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D
  • 3. 30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11 33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Sparks Electrical PM 34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical 35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11 38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Waterworks Plumbing 39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing Project Manager Project Manager Project Manager Project Manager and Attend Project Manager Project Manager and Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager and East S Project Manager and Spark
  • 4. Project Manager and Water Project Manager and Wood Project Manager and Stude Sparks Electrical P Waterworks Plumbi East Side Framing East Side Framing & Dryw East Side Fra City & County Project Manager Sparks Electrical PM Sparks Electrical City & County Project Manager Waterworks Plumbing PM Waterworks Plumbi 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone
  • 5. Summary Project Summary External Tasks External Milestone Deadline Page 1 Project: District4Move.mpp Date: Sat 1/8/11 ID WBS Task Name Duration Start Finish Predecessors Resource Names 40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11 43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D 45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11 48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Woodcraft Carpentry P
  • 6. 49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11 Woodcraft Carpentry 50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11 53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue 1/4/11 Student Workers Mana 54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11 Student Workers 55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11 58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 61 15 Move 3 days Mon 1/3/11 Wed 1/5/11 62 15.1 Move production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 63 15.2 Move non-production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11 66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager
  • 7. 69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11 70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project Manager City & County Project Manager East Side Framing & Dryw East Side Fra City & County Project Manager Woodcraft Carpentry PM Woodcraft Car City & County Project Manager Student Workers Manager Student Worke Project Manager Project Manager City Equipment Movers PM City Equipment Movers Project Manager Express Moving Company Express Moving Company
  • 8. Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Page 2 Project: District4Move.mpp
  • 9. Date: Sat 1/8/11 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers
  • 10. Manger15Electrical Permits105.1Obtain Electrical PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing & Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject