SlideShare a Scribd company logo
1 of 19
Project Planning – Developing the Project Plan and Determining
Critical Path
1. Using the District4WarehouseMove WBS.xls provided, create
a Microsoft project plan for the District 4 Warehouse Move
project. Use the PDF document, Project Plan Check –
District4Move, to check your work to be sure you have created
your starting project plan correctly. Microsoft Project is
required for this task. Please follow directions on
MGT402_OpenProj_Directions.docx to download Microsoft
Project.
Note: you will need to insert a column to include your WBS
codes, then you will need to sequence the tasks to show tasks by
work package. It may help to review the Microsoft tutorial,
Sequencing tasks in a project: http://www.project-
open.org/en/project_tutorial
2. Based upon the details in the WBS and the project case,
determine which tasks need to be completed first and which
tasks are dependent upon other tasks to be completed prior to
starting. Using this information identify predecessors in your
project plan’s predecessor column. Complete the predecessor
column by entering the line number of tasks that must be
completed in order for each task to start. This will create your
project timeline.
Note: This is a critical step in the process to developing your
critical path. It may help to review the Microsoft tutorial,
Creating relationships between tasks:
http://www.slideshare.net/dmdk12/creating-the-network-
diagram-and-gantt-with-openproj
3. Using the View Network Diagram functionality within MS
Project, determine the critical path for this project. In a MS
Word document, list the activities that are on the critical path.
Considering the risks identified in the risk table below, identify
which risks would be most likely to increase your project
timeline. Justify your responses.
4. Submit both your completed project plan and your MS Word
document.
District 4 Production Warehouse Move Project - Risk Table
1
Permits are not received per the schedule
2
Finish work contractors walk off the job half way through
3
Framing and drywall contractors are running behind schedule
and can only produce half their crew as scheduled
4
Work benches are poor quality and 1/3 will have to be rebuilt
Assignment 2 Grading Criteria
Maximum Points
Correctly developed a project plan from the WBS provided
60
Completed the predecessor column correctly in the project plan
based upon information in the case.
40
Correctly identified critical path activities
16
Correctly identified risks that would impact the project schedule
40
Used proper writing components such as, correct grammar,
spelling, and word choice and cited all sources using correct
APA style, etc..
44
Total:
200
Unsatisfactory
Emerging
Proficient
Exemplary
Assignment Components
Correctly developed a project plan from the WBS provided.
(CO2, CO3)
The project plan was incorrectly developed.
The project plan had some significant errors.
The project plan was adequate to meet the required elements of
the assignment.
The project plan was correctly developed with additional
elements that added value and meaning.
Completed the predecessor column correctly in the project plan
based upon information in the case. (CO2)
The predecessor column was incorrect in almost all aspects.
The predecessor column was mostly correct; however, some
significant information and/or aspects were missing.
The predecessor column was adequately completed.
The predecessor column was completed correctly and included
additional aspects that set it apart from the ordinary.
Correctly identified critical path activities. (CO2, CO3)
Critical path activities were mostly missing and/or incorrectly
identified.
The critical path activities were mostly identified with some
significant omissions.
The critical paths were adequately identified.
The critical paths were not only identified, but also additional
insights raised the response to a professional level.
Correctly identified risks that would impact the project
schedule.
(CO1, CO4)
Risks that would impact the project schedule were either
incorrectly identified or missed entirely.
Only some risks that would impact the project schedule were
identified with some significant omissions.
Risks that would impact the project schedule were correctly and
adequately identified.
Risks that would impact the project schedule were correctly
identified along with adding additional information that
enhanced the information to a professional level.
Writing Components
Organization
Introduction
Thesis
Transitions
Conclusion
Introduction is limited or missing entirely.
The paper lacks a thesis statement.
Transitions are infrequent, illogical, or missing entirely.
Conclusion is limited or missing entirely.
Introduction is present but incomplete or underdeveloped.
The paper is loosely organized around a thesis that may have to
be inferred.
Transitions are sporadic.
Conclusion is present but incomplete or underdeveloped.
Introduction has a clear opening, provides background
information, and states the topic.
The paper is organized around an arguable, clearly stated thesis
statement.
Transitions are appropriate and help the flow of ideas.
Conclusion summarizes main argument and has a clear ending.
Introduction catches the reader’s attention, provides compelling
and appropriate background info, and clearly states the topic.
The paper is well organized around an arguable, focused thesis.
Thoughtful transitions clearly show how ideas relate.
Conclusion leaves the reader with a sense of closure and
provides concluding insights.
Usage and Mechanics
Grammar
Spelling
Sentence structure
Writing contains numerous errors in spelling, grammar, and/or
sentence structure that severely interferes with readability and
comprehension.
Errors in spelling and grammar exist that somewhat interfere
with readability and/or comprehension.
Writing follows conventions of spelling and grammar
throughout. Errors are infrequent and do not interfere with
readability or comprehension.
The paper is basically error free in terms of mechanics.
Grammar and mechanics help establish a clear idea and aid the
reader in following the writer’s logic.
APA Elements
Attribution
Paraphrasing
Quotations
No attempt at APA format.
APA format is attempted to paraphrase, quote, and cite, but
errors are significant.
Using APA format, accurately paraphrased, quoted, and cited in
many spots throughout when appropriate or called for. Errors
present are somewhat minor.
Using APA format, accurately paraphrased, quoted, and cited
throughout the presentation when appropriate or called for.
Only a few minor errors present.
Style
Audience
Word Choice
Writing often slips into first and/or second person.
Word choice is consistently inaccurate, unclear, or
inappropriate for the audience.
Writing sometimes slips into first and/or second person.
Word choice is sometimes inaccurate, unclear, or inappropriate
for the audience.
Writing remains in third person throughout writing.
Word choice is accurate, clear and appropriate for the audience
Writing remains professional in third person throughout writing.
Word choice is precise, appropriate for the audience, and
memorable.
Directions for Downloading and Installing OpenProj
MGT 402_Project Management
MGT 402_Downloading and Installing OpenProj Project
Management Software
Step 1: Enter OpenProj.org into the address bar of your web
browser
· Note: It is important to enter Openproj.org, only, Not
openproject.org as these are two separate and distinct programs.
Step 2: You will be redirected to
Sourceforge.net/projects/openproj
Click on the green Download button
Step 3: You will receive a message counting down the seconds
to your download. * Note, if your download does not begin
automatically, click on directlink .
Step 4: Allow your program to fully download
Step 5: When the program has fully downloaded, place your
cursor on the arrow, select Open
Step 6: Click Run
Step 7: Click Next to begin setup wizard
Step 8: Click Next to deliver OpenProj to the appropriate
directory on your computer
Step 9: ClickInstall to begin program installation
Step 10: Installation has begun
Step 11: Click Finish to conclude Open Proj download
Step 12: Congratulations, you have successfully downloaded
Open Proj and are ready to begin entering project details.
MGT 402- Directions for Downloading and Installing Open
Proj6 | Page
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11
2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager and A
6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11
7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project
Manager and W
9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11
Project Manager
10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11
12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11
Mon 1/3/11 Project Manager
15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11
Mon 1/3/11
16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and E
17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and S
18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11
Project Manager and W
20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon
1/3/11 Project Manager and S
21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
Sparks Electrical PM
23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11
26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11
East Side Framing & D
27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11
28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side
Framing & D
30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11
33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Sparks Electrical PM
34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks
Electrical
35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11
38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed
1/5/11 Waterworks Plumbing
39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11
Waterworks Plumbing
Project Manager
Project Manager
Project Manager
Project Manager and Attend
Project Manager
Project Manager and
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager and East S
Project Manager and Spark
Project Manager and Water
Project Manager and Wood
Project Manager and Stude
Sparks Electrical P
Waterworks Plumbi
East Side Framing
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Sparks Electrical PM
Sparks Electrical
City & County
Project Manager
Waterworks Plumbing PM
Waterworks Plumbi
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: District4Move.mpp
Date: Sat 1/8/11
ID WBS Task Name Duration Start Finish Predecessors
Resource Names
40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City
& County
41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11
43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
East Side Framing & D
44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East
Side Framing & D
45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11
48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11
Woodcraft Carpentry P
49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11
Woodcraft Carpentry
50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City &
County
51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11
53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue
1/4/11 Student Workers Mana
54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11
Student Workers
55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue
1/4/11 Project Manager
56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon
1/3/11 Project Manager
57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11
58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue
1/4/11 City Equipment Mover
60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
61 15 Move 3 days Mon 1/3/11 Wed 1/5/11
62 15.1 Move production equipment 3 days Mon 1/3/11 Wed
1/5/11 Express Moving Comp
63 15.2 Move non-production equipment 3 days Mon 1/3/11
Wed 1/5/11 Express Moving Comp
64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11
66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11
Project Manager
68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11
70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project
Manager
71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11
Project Manager
72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project
Manager
City & County
Project Manager
East Side Framing & Dryw
East Side Fra
City & County
Project Manager
Woodcraft Carpentry PM
Woodcraft Car
City & County
Project Manager
Student Workers Manager
Student Worke
Project Manager
Project Manager
City Equipment Movers PM
City Equipment Movers
Project Manager
Express Moving Company
Express Moving Company
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6
January Februar
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: District4Move.mpp
Date: Sat 1/8/11
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3

More Related Content

Similar to Project Planning – Developing the Project Plan and Determining Cri.docx

A project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxA project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxblondellchancy
 
Hard News Article.docx
Hard News Article.docxHard News Article.docx
Hard News Article.docxwrite4
 
Project proposalguidelines
Project proposalguidelinesProject proposalguidelines
Project proposalguidelinesSamuddra Dilhani
 
Professional project writing
Professional project writingProfessional project writing
Professional project writingjkmaster
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Nzar Braim
 
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...PhD Assistance
 
Project management.docx communiction
Project management.docx communictionProject management.docx communiction
Project management.docx communictionberhanu taye
 
Introduction to the U.S. Legal System Précis AssignmentAlterna.docx
Introduction to the U.S. Legal System Précis AssignmentAlterna.docxIntroduction to the U.S. Legal System Précis AssignmentAlterna.docx
Introduction to the U.S. Legal System Précis AssignmentAlterna.docxvrickens
 
Project Manual
Project ManualProject Manual
Project ManualJoe Lynn
 
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docxENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docxpoulterbarbara
 
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
 ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docxShiraPrater50
 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxmary772
 
Project management.docx communictionLecture notes Training for Trainers in Ge...
Project management.docx communictionLecture notes Training for Trainers in Ge...Project management.docx communictionLecture notes Training for Trainers in Ge...
Project management.docx communictionLecture notes Training for Trainers in Ge...berhanu taye
 
ENGL 151 Research EssayAssignment DetailsValue 25 (additio
ENGL 151 Research EssayAssignment DetailsValue 25 (additioENGL 151 Research EssayAssignment DetailsValue 25 (additio
ENGL 151 Research EssayAssignment DetailsValue 25 (additioeleanorabarrington
 
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docx
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docxENGL 151 Research EssayAssignment DetailsValue 25 (additio.docx
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docxbudabrooks46239
 
Planning and writing your documents - Software documentation
Planning and writing your documents - Software documentationPlanning and writing your documents - Software documentation
Planning and writing your documents - Software documentationRa'Fat Al-Msie'deen
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1Juwad AlOmari
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part bSiep Littooij
 
Project planning and Management training for Amoud University MSc. in Constr...
Project planning and Management training for Amoud University  MSc. in Constr...Project planning and Management training for Amoud University  MSc. in Constr...
Project planning and Management training for Amoud University MSc. in Constr...werku koshe
 

Similar to Project Planning – Developing the Project Plan and Determining Cri.docx (20)

A project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxA project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docx
 
Hard News Article.docx
Hard News Article.docxHard News Article.docx
Hard News Article.docx
 
Project proposalguidelines
Project proposalguidelinesProject proposalguidelines
Project proposalguidelines
 
Professional project writing
Professional project writingProfessional project writing
Professional project writing
 
Project management
Project managementProject management
Project management
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management
 
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...
Guideline for Preparing PhD Course Work Synopsis on Engineering Technology - ...
 
Project management.docx communiction
Project management.docx communictionProject management.docx communiction
Project management.docx communiction
 
Introduction to the U.S. Legal System Précis AssignmentAlterna.docx
Introduction to the U.S. Legal System Précis AssignmentAlterna.docxIntroduction to the U.S. Legal System Précis AssignmentAlterna.docx
Introduction to the U.S. Legal System Précis AssignmentAlterna.docx
 
Project Manual
Project ManualProject Manual
Project Manual
 
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docxENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
 
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
 ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx ENG 510 Module Nine Journal Guidelines and Rubric  Ov.docx
ENG 510 Module Nine Journal Guidelines and Rubric Ov.docx
 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
 
Project management.docx communictionLecture notes Training for Trainers in Ge...
Project management.docx communictionLecture notes Training for Trainers in Ge...Project management.docx communictionLecture notes Training for Trainers in Ge...
Project management.docx communictionLecture notes Training for Trainers in Ge...
 
ENGL 151 Research EssayAssignment DetailsValue 25 (additio
ENGL 151 Research EssayAssignment DetailsValue 25 (additioENGL 151 Research EssayAssignment DetailsValue 25 (additio
ENGL 151 Research EssayAssignment DetailsValue 25 (additio
 
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docx
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docxENGL 151 Research EssayAssignment DetailsValue 25 (additio.docx
ENGL 151 Research EssayAssignment DetailsValue 25 (additio.docx
 
Planning and writing your documents - Software documentation
Planning and writing your documents - Software documentationPlanning and writing your documents - Software documentation
Planning and writing your documents - Software documentation
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part b
 
Project planning and Management training for Amoud University MSc. in Constr...
Project planning and Management training for Amoud University  MSc. in Constr...Project planning and Management training for Amoud University  MSc. in Constr...
Project planning and Management training for Amoud University MSc. in Constr...
 

More from wkyra78

Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docx
Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docxMelissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docx
Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docxwkyra78
 
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docx
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docxMelissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docx
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docxwkyra78
 
Meiner, S. E., & Yeager, J. J. (2019). Chapter 17Chap.docx
Meiner, S. E., & Yeager, J. J. (2019).    Chapter 17Chap.docxMeiner, S. E., & Yeager, J. J. (2019).    Chapter 17Chap.docx
Meiner, S. E., & Yeager, J. J. (2019). Chapter 17Chap.docxwkyra78
 
member is a security software architect in a cloud service provider .docx
member is a security software architect in a cloud service provider .docxmember is a security software architect in a cloud service provider .docx
member is a security software architect in a cloud service provider .docxwkyra78
 
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docx
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docxMelissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docx
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docxwkyra78
 
Melissa is a 15-year-old high school student. Over the last week.docx
Melissa is a 15-year-old high school student. Over the last week.docxMelissa is a 15-year-old high school student. Over the last week.docx
Melissa is a 15-year-old high school student. Over the last week.docxwkyra78
 
Measurement  of  the  angle  θ          .docx
Measurement  of  the  angle  θ          .docxMeasurement  of  the  angle  θ          .docx
Measurement  of  the  angle  θ          .docxwkyra78
 
Measurement of the angle θ For better understanding .docx
Measurement of the angle θ     For better understanding .docxMeasurement of the angle θ     For better understanding .docx
Measurement of the angle θ For better understanding .docxwkyra78
 
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docx
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docxMeaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docx
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docxwkyra78
 
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docx
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docxMBA6231 - 1.1 - project charter.docxProject Charter Pr.docx
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docxwkyra78
 
Medication Errors Led to Disastrous Outcomes1. Search th.docx
Medication Errors Led to Disastrous Outcomes1. Search th.docxMedication Errors Led to Disastrous Outcomes1. Search th.docx
Medication Errors Led to Disastrous Outcomes1. Search th.docxwkyra78
 
Meet, call, Skype or Zoom with a retired athlete and interview himh.docx
Meet, call, Skype or Zoom with a retired athlete and interview himh.docxMeet, call, Skype or Zoom with a retired athlete and interview himh.docx
Meet, call, Skype or Zoom with a retired athlete and interview himh.docxwkyra78
 
Medication Administration Make a list of the most common med.docx
Medication Administration Make a list of the most common med.docxMedication Administration Make a list of the most common med.docx
Medication Administration Make a list of the most common med.docxwkyra78
 
media portfolio”about chapter 1 to 15 from the book  Ci.docx
media portfolio”about chapter 1 to 15 from the book  Ci.docxmedia portfolio”about chapter 1 to 15 from the book  Ci.docx
media portfolio”about chapter 1 to 15 from the book  Ci.docxwkyra78
 
MediationNameAMUDate.docx
MediationNameAMUDate.docxMediationNameAMUDate.docx
MediationNameAMUDate.docxwkyra78
 
Media coverage influences the publics perception of the crimina.docx
Media coverage influences the publics perception of the crimina.docxMedia coverage influences the publics perception of the crimina.docx
Media coverage influences the publics perception of the crimina.docxwkyra78
 
Media Content AnalysisPurpose Evaluate the quality and value of.docx
Media Content AnalysisPurpose Evaluate the quality and value of.docxMedia Content AnalysisPurpose Evaluate the quality and value of.docx
Media Content AnalysisPurpose Evaluate the quality and value of.docxwkyra78
 
Mayan gods and goddesses are very much a part of this text.  Their i.docx
Mayan gods and goddesses are very much a part of this text.  Their i.docxMayan gods and goddesses are very much a part of this text.  Their i.docx
Mayan gods and goddesses are very much a part of this text.  Their i.docxwkyra78
 
Media and SocietyIn 1,100 words, complete the followingAn.docx
Media and SocietyIn 1,100 words, complete the followingAn.docxMedia and SocietyIn 1,100 words, complete the followingAn.docx
Media and SocietyIn 1,100 words, complete the followingAn.docxwkyra78
 
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docx
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docxMBA 5110 – Business Organization and ManagementMidterm ExamAns.docx
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docxwkyra78
 

More from wkyra78 (20)

Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docx
Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docxMelissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docx
Melissa HinkhouseWeek 3-Original PostNURS 6050 Policy and A.docx
 
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docx
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docxMelissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docx
Melissa HinkhouseAdvanced Pharmacology NURS-6521N-43Professo.docx
 
Meiner, S. E., & Yeager, J. J. (2019). Chapter 17Chap.docx
Meiner, S. E., & Yeager, J. J. (2019).    Chapter 17Chap.docxMeiner, S. E., & Yeager, J. J. (2019).    Chapter 17Chap.docx
Meiner, S. E., & Yeager, J. J. (2019). Chapter 17Chap.docx
 
member is a security software architect in a cloud service provider .docx
member is a security software architect in a cloud service provider .docxmember is a security software architect in a cloud service provider .docx
member is a security software architect in a cloud service provider .docx
 
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docx
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docxMelissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docx
Melissa ShortridgeWeek 6COLLAPSEMy own attitude has ch.docx
 
Melissa is a 15-year-old high school student. Over the last week.docx
Melissa is a 15-year-old high school student. Over the last week.docxMelissa is a 15-year-old high school student. Over the last week.docx
Melissa is a 15-year-old high school student. Over the last week.docx
 
Measurement  of  the  angle  θ          .docx
Measurement  of  the  angle  θ          .docxMeasurement  of  the  angle  θ          .docx
Measurement  of  the  angle  θ          .docx
 
Measurement of the angle θ For better understanding .docx
Measurement of the angle θ     For better understanding .docxMeasurement of the angle θ     For better understanding .docx
Measurement of the angle θ For better understanding .docx
 
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docx
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docxMeaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docx
Meaning-Making Forum 2 (Week 5)Meaning-Making Forums 1-4 are thi.docx
 
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docx
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docxMBA6231 - 1.1 - project charter.docxProject Charter Pr.docx
MBA6231 - 1.1 - project charter.docxProject Charter Pr.docx
 
Medication Errors Led to Disastrous Outcomes1. Search th.docx
Medication Errors Led to Disastrous Outcomes1. Search th.docxMedication Errors Led to Disastrous Outcomes1. Search th.docx
Medication Errors Led to Disastrous Outcomes1. Search th.docx
 
Meet, call, Skype or Zoom with a retired athlete and interview himh.docx
Meet, call, Skype or Zoom with a retired athlete and interview himh.docxMeet, call, Skype or Zoom with a retired athlete and interview himh.docx
Meet, call, Skype or Zoom with a retired athlete and interview himh.docx
 
Medication Administration Make a list of the most common med.docx
Medication Administration Make a list of the most common med.docxMedication Administration Make a list of the most common med.docx
Medication Administration Make a list of the most common med.docx
 
media portfolio”about chapter 1 to 15 from the book  Ci.docx
media portfolio”about chapter 1 to 15 from the book  Ci.docxmedia portfolio”about chapter 1 to 15 from the book  Ci.docx
media portfolio”about chapter 1 to 15 from the book  Ci.docx
 
MediationNameAMUDate.docx
MediationNameAMUDate.docxMediationNameAMUDate.docx
MediationNameAMUDate.docx
 
Media coverage influences the publics perception of the crimina.docx
Media coverage influences the publics perception of the crimina.docxMedia coverage influences the publics perception of the crimina.docx
Media coverage influences the publics perception of the crimina.docx
 
Media Content AnalysisPurpose Evaluate the quality and value of.docx
Media Content AnalysisPurpose Evaluate the quality and value of.docxMedia Content AnalysisPurpose Evaluate the quality and value of.docx
Media Content AnalysisPurpose Evaluate the quality and value of.docx
 
Mayan gods and goddesses are very much a part of this text.  Their i.docx
Mayan gods and goddesses are very much a part of this text.  Their i.docxMayan gods and goddesses are very much a part of this text.  Their i.docx
Mayan gods and goddesses are very much a part of this text.  Their i.docx
 
Media and SocietyIn 1,100 words, complete the followingAn.docx
Media and SocietyIn 1,100 words, complete the followingAn.docxMedia and SocietyIn 1,100 words, complete the followingAn.docx
Media and SocietyIn 1,100 words, complete the followingAn.docx
 
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docx
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docxMBA 5110 – Business Organization and ManagementMidterm ExamAns.docx
MBA 5110 – Business Organization and ManagementMidterm ExamAns.docx
 

Recently uploaded

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 

Recently uploaded (20)

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 

Project Planning – Developing the Project Plan and Determining Cri.docx

  • 1. Project Planning – Developing the Project Plan and Determining Critical Path 1. Using the District4WarehouseMove WBS.xls provided, create a Microsoft project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check – District4Move, to check your work to be sure you have created your starting project plan correctly. Microsoft Project is required for this task. Please follow directions on MGT402_OpenProj_Directions.docx to download Microsoft Project. Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package. It may help to review the Microsoft tutorial, Sequencing tasks in a project: http://www.project- open.org/en/project_tutorial 2. Based upon the details in the WBS and the project case, determine which tasks need to be completed first and which tasks are dependent upon other tasks to be completed prior to starting. Using this information identify predecessors in your project plan’s predecessor column. Complete the predecessor column by entering the line number of tasks that must be completed in order for each task to start. This will create your project timeline. Note: This is a critical step in the process to developing your critical path. It may help to review the Microsoft tutorial, Creating relationships between tasks: http://www.slideshare.net/dmdk12/creating-the-network- diagram-and-gantt-with-openproj 3. Using the View Network Diagram functionality within MS
  • 2. Project, determine the critical path for this project. In a MS Word document, list the activities that are on the critical path. Considering the risks identified in the risk table below, identify which risks would be most likely to increase your project timeline. Justify your responses. 4. Submit both your completed project plan and your MS Word document. District 4 Production Warehouse Move Project - Risk Table 1 Permits are not received per the schedule 2 Finish work contractors walk off the job half way through 3 Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled 4 Work benches are poor quality and 1/3 will have to be rebuilt Assignment 2 Grading Criteria Maximum Points Correctly developed a project plan from the WBS provided 60 Completed the predecessor column correctly in the project plan based upon information in the case. 40 Correctly identified critical path activities 16 Correctly identified risks that would impact the project schedule 40 Used proper writing components such as, correct grammar, spelling, and word choice and cited all sources using correct
  • 3. APA style, etc.. 44 Total: 200 Unsatisfactory Emerging Proficient Exemplary Assignment Components Correctly developed a project plan from the WBS provided. (CO2, CO3) The project plan was incorrectly developed. The project plan had some significant errors. The project plan was adequate to meet the required elements of the assignment. The project plan was correctly developed with additional elements that added value and meaning. Completed the predecessor column correctly in the project plan based upon information in the case. (CO2) The predecessor column was incorrect in almost all aspects. The predecessor column was mostly correct; however, some significant information and/or aspects were missing. The predecessor column was adequately completed. The predecessor column was completed correctly and included
  • 4. additional aspects that set it apart from the ordinary. Correctly identified critical path activities. (CO2, CO3) Critical path activities were mostly missing and/or incorrectly identified. The critical path activities were mostly identified with some significant omissions. The critical paths were adequately identified. The critical paths were not only identified, but also additional insights raised the response to a professional level. Correctly identified risks that would impact the project schedule. (CO1, CO4) Risks that would impact the project schedule were either incorrectly identified or missed entirely. Only some risks that would impact the project schedule were identified with some significant omissions. Risks that would impact the project schedule were correctly and adequately identified. Risks that would impact the project schedule were correctly identified along with adding additional information that enhanced the information to a professional level. Writing Components Organization Introduction Thesis Transitions Conclusion Introduction is limited or missing entirely.
  • 5. The paper lacks a thesis statement. Transitions are infrequent, illogical, or missing entirely. Conclusion is limited or missing entirely. Introduction is present but incomplete or underdeveloped. The paper is loosely organized around a thesis that may have to be inferred. Transitions are sporadic. Conclusion is present but incomplete or underdeveloped. Introduction has a clear opening, provides background information, and states the topic. The paper is organized around an arguable, clearly stated thesis statement. Transitions are appropriate and help the flow of ideas. Conclusion summarizes main argument and has a clear ending. Introduction catches the reader’s attention, provides compelling and appropriate background info, and clearly states the topic. The paper is well organized around an arguable, focused thesis. Thoughtful transitions clearly show how ideas relate. Conclusion leaves the reader with a sense of closure and
  • 6. provides concluding insights. Usage and Mechanics Grammar Spelling Sentence structure Writing contains numerous errors in spelling, grammar, and/or sentence structure that severely interferes with readability and comprehension. Errors in spelling and grammar exist that somewhat interfere with readability and/or comprehension. Writing follows conventions of spelling and grammar throughout. Errors are infrequent and do not interfere with readability or comprehension. The paper is basically error free in terms of mechanics. Grammar and mechanics help establish a clear idea and aid the reader in following the writer’s logic. APA Elements Attribution Paraphrasing Quotations No attempt at APA format. APA format is attempted to paraphrase, quote, and cite, but errors are significant. Using APA format, accurately paraphrased, quoted, and cited in many spots throughout when appropriate or called for. Errors
  • 7. present are somewhat minor. Using APA format, accurately paraphrased, quoted, and cited throughout the presentation when appropriate or called for. Only a few minor errors present. Style Audience Word Choice Writing often slips into first and/or second person. Word choice is consistently inaccurate, unclear, or inappropriate for the audience. Writing sometimes slips into first and/or second person. Word choice is sometimes inaccurate, unclear, or inappropriate for the audience. Writing remains in third person throughout writing. Word choice is accurate, clear and appropriate for the audience Writing remains professional in third person throughout writing. Word choice is precise, appropriate for the audience, and memorable. Directions for Downloading and Installing OpenProj MGT 402_Project Management
  • 8. MGT 402_Downloading and Installing OpenProj Project Management Software Step 1: Enter OpenProj.org into the address bar of your web browser · Note: It is important to enter Openproj.org, only, Not openproject.org as these are two separate and distinct programs. Step 2: You will be redirected to Sourceforge.net/projects/openproj Click on the green Download button Step 3: You will receive a message counting down the seconds to your download. * Note, if your download does not begin automatically, click on directlink . Step 4: Allow your program to fully download Step 5: When the program has fully downloaded, place your cursor on the arrow, select Open Step 6: Click Run
  • 9. Step 7: Click Next to begin setup wizard Step 8: Click Next to deliver OpenProj to the appropriate directory on your computer Step 9: ClickInstall to begin program installation Step 10: Installation has begun Step 11: Click Finish to conclude Open Proj download Step 12: Congratulations, you have successfully downloaded Open Proj and are ready to begin entering project details. MGT 402- Directions for Downloading and Installing Open Proj6 | Page ID WBS Task Name Duration Start Finish Predecessors Resource Names 1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11 2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager
  • 10. 3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and A 6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11 7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project Manager and W 9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11 12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11 Mon 1/3/11 16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and E 17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W 20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S 21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11
  • 11. 22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical PM 23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing 25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11 26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11 East Side Framing & D 27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11 28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D 30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11 33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Sparks Electrical PM 34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical 35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11 38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Waterworks Plumbing 39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing Project Manager Project Manager Project Manager Project Manager and Attend
  • 12. Project Manager Project Manager and Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager and East S Project Manager and Spark Project Manager and Water Project Manager and Wood Project Manager and Stude Sparks Electrical P Waterworks Plumbi East Side Framing East Side Framing & Dryw East Side Fra City & County Project Manager Sparks Electrical PM Sparks Electrical City & County Project Manager Waterworks Plumbing PM
  • 13. Waterworks Plumbi 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Page 1 Project: District4Move.mpp Date: Sat 1/8/11 ID WBS Task Name Duration Start Finish Predecessors Resource Names 40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon
  • 14. 1/3/11 Project Manager 42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11 43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D 44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D 45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11 48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Woodcraft Carpentry P 49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11 Woodcraft Carpentry 50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County 51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11 53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue 1/4/11 Student Workers Mana 54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11 Student Workers 55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue 1/4/11 Project Manager 56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11 58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover 60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 61 15 Move 3 days Mon 1/3/11 Wed 1/5/11
  • 15. 62 15.1 Move production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 63 15.2 Move non-production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp 64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11 66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager 69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11 70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11 Project Manager 72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project Manager City & County Project Manager East Side Framing & Dryw East Side Fra City & County Project Manager Woodcraft Carpentry PM Woodcraft Car City & County Project Manager
  • 16. Student Workers Manager Student Worke Project Manager Project Manager City Equipment Movers PM City Equipment Movers Project Manager Express Moving Company Express Moving Company Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager 2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6 January Februar Task Split Progress Milestone
  • 17. Summary Project Summary External Tasks External Milestone Deadline Page 2 Project: District4Move.mpp Date: Sat 1/8/11 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject
  • 18. Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers Manger15Electrical Permits105.1Obtain Electrical PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing & Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches-
  • 19. BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject Manager1 Sheet2 Sheet3