SlideShare a Scribd company logo
Technical Bulletin



H            IGH DENSITY POLYETHYLENE PIPE
                  HDPE Pipe Installation Practice

LANE corrugated high density polyethylene               Classes IA, IB, and II are preferred over Class III
(HDPE) pipe, appropriate backfill material and          when available because they are stiffer materials,
proper installation practice all work together to       limit pipe deflection and permit greater fill heights.
result in a dependable drainage installation. HDPE      Also, construction may be faster because less
pipe, like all flexible pipes, depends on soil-pipe     compactive effort is generally required. Class III
interaction to develop its strength. Thus, proper       material should not be used where water
installation and backfilling are essential to           conditions in a trench can cause instability.
successful performance. This technical bulletin
addresses typical installations in trench and
embankment conditions. Unusual conditions may
                                                             BACKFILL MATERIAL SIZE
require additional investigations, including the            Pipe Diameter (ID)            Max. Particle Size
recommendations of a qualified geotechnical or              in.           mm               in.            mm
soils engineer. More detailed information on                6             150              3/8            10
installation and backfill may be found in ASTM
D2321, " Standard Practice for Underground                  8-15          200-375          5/8            15
Installation of Thermoplastic Pipe for Sewers and           18-48         450-1200         1 1/2          40
Other Gravity-Flow Applications."

Installation practices must always comply               Cement slurry and controlled low strength material
with local, state and federal codes and                 (CLSM) are excellent backfill material provided
                                                        they yield adequate compressive strength and the
safety regulations.
                                                        pipe is restrained to avoid flotation during
                                                        installation.
Material for Foundation,
Bedding and Backfill                                    Foundation and Bedding
The pipe must be surrounded by compacted
material to distribute vertical loads uniformly to      A good foundation and bedding are critical to pipe
the pipe and to provide passive resistance to pipe      performance and service life. They are essential to
deflection. Material selection depends on               help maintain proper pipe elevation, eliminate
availability and cost. Granular materials with little   undesirable stresses in the pipe and ensure good
or no plasticity are preferred. Frozen lumps,           hydraulic performance.
chunks of clay, organic matter and large rock are
unacceptable. Acceptable materials are                  The foundation material beneath the pipe must
summarized in Table 1 by their ASTM Class and           provide a uniform resistance to the loads on the
Soil Group designation.                                 pipe.




                               www.lane-enterprises.com
Sharp longitudinal and lateral variations      However, if special equipment is available
in the foundation must be avoided. If          to provide a quality installation with a
rock is encountered, excavate and replace      narrow trench, the minimum width can be
with gravel or lightly compacted material.     reduced. If material such as CLSM is
Such cushion should have a depth of            used that requires no compaction, the
approximately ½ in. per ft. (42 mm/m) of       trench width can be as little as the pipe
the planned fill depth over the pipe           outside diameter, plus 6 in. (150 mm).
(6 in.-150 mm minimum, 24 in.-600 mm
maximum). If soft foundation material is       The trench must be filled with material,
encountered that must be removed to            placed and compacted in layers to form a
maintain grade, remove the material for a      "structural backfill" surrounding the pipe.
depth of about 2 ft. (0.6 m) and replace       The backfill must be compacted to a
with suitable compacted material. The          minimum of 90 percent of maximum
width of this material should be 2.5 diam-     density as determined by ASTM D698 or
eters on either side of the pipe for pipe 12   AASHTO T99. The envelope should
in. (300 mm) diameter or less. For larger      extend to 12 in. (300 mm) above the top
pipe, the width should be established by       of the pipe before the remainder of the fill
the engineer.                                  is placed in the trench. The trench wall is
                                               assumed to have a stiffness at least that of
The upper 4 in. (100 mm) of the bedding        the compacted backfill. If soft trench
should be relatively loose material so the     walls are encountered, additional
corrugations can be seated. Frozen             excavation may be required.
lumps, chunks of clay, organic matter and
large rock are unacceptable. The pipe
may be installed by shaping the bedding
surface to conform to the pipe
for a width of about one-half
the diameter. A second method
is to place the pipe directly on
the bedding, in which case
particular care must be taken
to compact the backfill under
the haunches of the pipe to
provide uniform support.

Trench
Construction
The trench should be wide
enough for placement and
compaction of backfill, especially the         Excavate trenches to ensure the trench
material placed beside the pipe and that in    walls are stable under all conditions.
the haunch area below the spring line.         Slope the walls or provide support in
Generally, the minimum trench width            conformance with safety standards. All
should not be less than the greater of (1)     appropriate safety practices and
the pipe outside diameter plus 16 in. (400     regulations must be followed to avoid
mm), or (2) the pipe outside diameter          trench collapse. If high ground water is
times 1.25, plus 12 in. (300 mm).              encountered, dewatering may be required
                                               to achieve a safe installation that meets
                                               requirements.
Embankment Construction                                         Backfill Placement
In embankment construction, the compacted                       In either trench or embankment construction, the
envelope of "structural backfill" must surround the             backfill material must be placed in layers and
pipe with a width adequate to resist forces caused              compacted to a minimum of 90 percent of
by construction equipment. The width of this zone               maximum density as determined by ASTM D698
on each side of the pipe should be one diameter,                or ASSHTO T99. The maximum thickness of the
with a minimum of 12 in. (300 mm) and a                         layers or lifts should not exceed 6 in. (150 mm).
maximum of 24 in. (600 mm). The envelope                        The lift thickness, placement technique and
should extend to 12 in. (300 mm) above the top of               compaction method must be such that compaction
the pipe before normal embankment material is                   under the haunches is obtained.
placed.
                                                                                              continued on next page >
                                 TABLE 1
                       Recommended Backfill Materials
 ASTM                                             ASTM                                                         Similar
 D2321                     Type                  D2487                    Description                         AASHTO
 Class                                          Soil Group                                                      Type
                                                             Angular, crushed stone or rock, crushed
   IA        Manufactured Aggregates;                        gravel, broken coral, crushed slag, cinders
             open-graded, clean.                             or shells; large void content, contain little
                                                             or no fines.
             Manufactured Processed                          Angular, crushed stone (or other Class 1A
   IB                                                        materials) and stone/sand mixtures with
             Aggregates; dense-graded,
             clean.                                          gradations selected to minimize migration
                                                             of adjacent soils; contain little or no fines.
                                                  GW         Well-graded gravels and gravel/sand                A1,
   II        Coarse-Grained Soils; clean.
                                                             mixtures, little or no fines.                      A3
                                                   GP        Poorly graded gravels and gravel/sand
                                                             mixtures, little or no fines.
                                                  SW         Well-graded sands and gravelly sands,
                                                             little or no fines.
                                                   SP        Poorly-graded sands and gravelly sands,
                                                             little or no fines.
             Coarse-Grained Soils; borderline     e.g.       Sands which are borderline between
             clean to with fines.                 GW         clean and with fines.
                                                  GC
                                                  SP
                                                  SM
   III       Coarse-Grained Soils with Fines.     GM         Silty gravels, gravel-sand-silt mixtures.          A2


                                                  GC         Clayey gravels, gravel-sand-clay mixtures.
                                                  SM         Silty sands, sand-clay mixtures
                                                  SC         Clayey sands, sand/clay mixtures.

         Note: Compact backfill material to minimum of 90% of maximum density per ASTM D698 or AASHTO T99.
         Table adapted from ASTM D2321.
Each layer must be compacted before the next lift is placed. Backfill
must proceed evenly on each side of the pipe. Care must be taken to
avoid pipe distortion or excessive local or general deflection. Such
unacceptable deformations can result from either excessive or inadequate
compaction or from construction equipment. Do not allow compaction
or other equipment to contact and damage the pipe. Compaction
techniques must be compatible with the backfill materials used, and the
width of the area being compacted.

Mechanical compaction is generally used. However, water consolidation
methods can be used on free-draining backfill material if care is taken to
prevent flotation. Conditions must be controlled and approved by the
engineer.

Construction Loads
It is important to protect the pipe from equipment loads during
construction. Heavy equipment must not be allowed close to or over
buried pipe unless provisions are made to accommodate the resultant
loads. Depending on the size of the equipment and class of fill material,
a minimum cover from 2 ft. (0.6 m) to 4 ft. (1.2 m), or more for
exceptional loads, may be required. (see table 2) For shallow
installations, it may be necessary to mound and compact material over
the pipe to provide the minimum cover. The mound can be removed and
final grade established after construction.
                                             TABLE 2
                   COVER FOR CONSTRUCTION LOADS
                                  Minimum Cover, in., for indicated Axle Loads, kips
  Nominal Pipe                                                                                                                    Drain with Lane
  Diameter, ft              18.0-50.0             50.0-75.0            75.0-110.0               110.0-150.0
                                                                                                                                    Lane Enterprises, Inc.
  2.0-3.0                      24.0                  30.0                  36.0                      36.0                      3905 Hartzdale Drive, Suite 514
                                                                                                                                   Camp Hill, PA 17011
  3.5-4.0                      36.0                  36.0                  42.0                      48.0                     717-761-8175 Fax 717-761-5055
  4.5-5.0                      36.0                  36.0                  42.0                      48.0
                                                                                                                                          New York
 Minimum cover shall be measured from the top of the pipe to the
                                                                                                                                Ballston Spa 518-885-4385
 top of the maintained construction roadway surface. If unpaved,                                                                    Bath 607-776-3366
 the surface shall be maintained.
                                                                                                                                       North Carolina
Multiple Pipes                                                                                                                   Statesville 704-872-2471

When two or more pipes are installed in adjacent parallel lines, sufficient                                                             Pennsylvania
space must be provided between the pipes to provide for adequate                                                                  Bedford 814-623-1191
compaction of the structural backfill. One rule-of-thumb is to use a                                                              Carlisle 717-249-8342
spacing between pipes equal to 12 in. (300 mm), or one-half the nominal                                                        King of Prussia 610-272-4531
pipe diameter, whichever is greater. This can be increased if necessary to                                                        Pulaski 412-652-7747
accommodate compaction.
                                                                                                                                          Virginia
                                                                                                                                  Bealeton 540-439-3201
 The information contained in this technical bulletin is general in nature and is intended for use in conjunction with
 competent engineering advice as to its suitability for any specific application. Nothing in this bulletin is intended as a        Dublin 540-674-4645
 representative or warranty that such data is suitable for any particular application or purpose.
                                                                                                                                www.lane-enterprises.com

More Related Content

What's hot

Fairscreed r
Fairscreed rFairscreed r
Stonecraft installation instructions
Stonecraft installation instructionsStonecraft installation instructions
Stonecraft installation instructions
Tri County Exteriors LLC
 
Micro Piles Soil Nails
Micro Piles Soil NailsMicro Piles Soil Nails
Micro Piles Soil Nails
jamieram
 
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
Dan Brown and Associates, PC
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
Prabhat chhirolya
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
RAMPRASAD KUMAWAT
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
brijlata sharma
 
Basalt Rebar
Basalt RebarBasalt Rebar
Basalt Rebar
abhi4her
 
Industrial training ppt bitm
Industrial training ppt bitmIndustrial training ppt bitm
Industrial training ppt bitm
Saikat Nandy
 
Structural excavation and backfill
Structural excavation and backfillStructural excavation and backfill
Structural excavation and backfill
mamilli
 
reinforced gabions
reinforced gabions reinforced gabions
reinforced gabions
EVERSENDAI ENGINEERING (L.L.C.)
 
Sanchit
SanchitSanchit
Sanchit
sanchit475
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
BonaganiSarthika
 
soil nailing technique using gfrp
soil nailing technique using gfrpsoil nailing technique using gfrp
soil nailing technique using gfrp
tp jayamohan
 
Basalt rock fibre
Basalt   rock   fibreBasalt   rock   fibre
Basalt rock fibre
AHMED NADIM JILANI
 
Basalt
BasaltBasalt
A seminar on Basalt fiber
A seminar on Basalt fiberA seminar on Basalt fiber
A seminar on Basalt fiber
Avin Ganapathi
 
Seminar basalt fiber rebars
Seminar basalt fiber rebarsSeminar basalt fiber rebars
Seminar basalt fiber rebars
ATHUL ASOK
 
Work check list
Work check listWork check list

What's hot (19)

Fairscreed r
Fairscreed rFairscreed r
Fairscreed r
 
Stonecraft installation instructions
Stonecraft installation instructionsStonecraft installation instructions
Stonecraft installation instructions
 
Micro Piles Soil Nails
Micro Piles Soil NailsMicro Piles Soil Nails
Micro Piles Soil Nails
 
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
 
Basalt Rebar
Basalt RebarBasalt Rebar
Basalt Rebar
 
Industrial training ppt bitm
Industrial training ppt bitmIndustrial training ppt bitm
Industrial training ppt bitm
 
Structural excavation and backfill
Structural excavation and backfillStructural excavation and backfill
Structural excavation and backfill
 
reinforced gabions
reinforced gabions reinforced gabions
reinforced gabions
 
Sanchit
SanchitSanchit
Sanchit
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
 
soil nailing technique using gfrp
soil nailing technique using gfrpsoil nailing technique using gfrp
soil nailing technique using gfrp
 
Basalt rock fibre
Basalt   rock   fibreBasalt   rock   fibre
Basalt rock fibre
 
Basalt
BasaltBasalt
Basalt
 
A seminar on Basalt fiber
A seminar on Basalt fiberA seminar on Basalt fiber
A seminar on Basalt fiber
 
Seminar basalt fiber rebars
Seminar basalt fiber rebarsSeminar basalt fiber rebars
Seminar basalt fiber rebars
 
Work check list
Work check listWork check list
Work check list
 

Similar to Hdpe installation practice

02_siteworks.ppt
02_siteworks.ppt02_siteworks.ppt
02_siteworks.ppt
bambang819101
 
Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826
ram saran
 
Construction of flexible pavement in brief
Construction of flexible pavement in briefConstruction of flexible pavement in brief
Construction of flexible pavement in brief
AJINKYA THAKRE
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
AJINKYA THAKRE
 
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET Journal
 
Dams and control works
Dams and control worksDams and control works
Dams and control works
julian21323
 
3873
38733873
7873
78737873
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNITA presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
Riteshmani Tripathi
 
Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1
Onondaga County Save the Rain
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
cathexis123
 
Geotech and Pavement Design Information
Geotech and Pavement Design InformationGeotech and Pavement Design Information
Geotech and Pavement Design Information
J C
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
cathexis123
 
Strength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste MaterialsStrength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste Materials
IRJET Journal
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
pokjak80
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.ppt
mosesnhidza
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and Practice
Senthamizhan M
 
pile wall
pile wallpile wall
pile wall
SALEM MOHAMMED
 
Research in Geotechnical Engineering
Research in Geotechnical EngineeringResearch in Geotechnical Engineering
Research in Geotechnical Engineering
Abhineet Godayal CE
 
Bubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptxBubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptx
Sudhanshu Baigra
 

Similar to Hdpe installation practice (20)

02_siteworks.ppt
02_siteworks.ppt02_siteworks.ppt
02_siteworks.ppt
 
Aggrigatemortor 170209141826
Aggrigatemortor 170209141826Aggrigatemortor 170209141826
Aggrigatemortor 170209141826
 
Construction of flexible pavement in brief
Construction of flexible pavement in briefConstruction of flexible pavement in brief
Construction of flexible pavement in brief
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
 
Dams and control works
Dams and control worksDams and control works
Dams and control works
 
3873
38733873
3873
 
7873
78737873
7873
 
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNITA presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
A presentation(12 btceng040) ON SUMMER INTERNSHIP from MNNIT
 
Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
 
Geotech and Pavement Design Information
Geotech and Pavement Design InformationGeotech and Pavement Design Information
Geotech and Pavement Design Information
 
Geotech and pavement design information
Geotech and pavement design informationGeotech and pavement design information
Geotech and pavement design information
 
Strength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste MaterialsStrength Improvement in the Soil Using Waste Materials
Strength Improvement in the Soil Using Waste Materials
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
 
B-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.pptB-Tech Construction Material Presentaion.ppt
B-Tech Construction Material Presentaion.ppt
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and Practice
 
pile wall
pile wallpile wall
pile wall
 
Research in Geotechnical Engineering
Research in Geotechnical EngineeringResearch in Geotechnical Engineering
Research in Geotechnical Engineering
 
Bubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptxBubble Deck Slab PPT.pptx
Bubble Deck Slab PPT.pptx
 

More from TADSA1

CATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSACATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSA
TADSA1
 
FICHA TÉCNICA LANE
FICHA TÉCNICA LANEFICHA TÉCNICA LANE
FICHA TÉCNICA LANE
TADSA1
 
GUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓNGUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓN
TADSA1
 
HDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍAHDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍATADSA1
 
Manual de instalacion
Manual de instalacionManual de instalacion
Manual de instalacion
TADSA1
 
Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2
TADSA1
 
Hdpe installation practice
Hdpe installation practiceHdpe installation practice
Hdpe installation practice
TADSA1
 
Hdpe perforation guide
Hdpe perforation guideHdpe perforation guide
Hdpe perforation guide
TADSA1
 
Ficha tecnica lane
Ficha tecnica laneFicha tecnica lane
Ficha tecnica lane
TADSA1
 

More from TADSA1 (9)

CATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSACATÁLOGO DE PRODUCTOS TADSA
CATÁLOGO DE PRODUCTOS TADSA
 
FICHA TÉCNICA LANE
FICHA TÉCNICA LANEFICHA TÉCNICA LANE
FICHA TÉCNICA LANE
 
GUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓNGUÍA DE PERFORACIÓN
GUÍA DE PERFORACIÓN
 
HDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍAHDPE ROLLOS DE TUBERÍA
HDPE ROLLOS DE TUBERÍA
 
Manual de instalacion
Manual de instalacionManual de instalacion
Manual de instalacion
 
Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2Hdpe coil-pipe-brochure2
Hdpe coil-pipe-brochure2
 
Hdpe installation practice
Hdpe installation practiceHdpe installation practice
Hdpe installation practice
 
Hdpe perforation guide
Hdpe perforation guideHdpe perforation guide
Hdpe perforation guide
 
Ficha tecnica lane
Ficha tecnica laneFicha tecnica lane
Ficha tecnica lane
 

Recently uploaded

Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStrDeep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
saastr
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
fredae14
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
Tomaz Bratanic
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Alpen-Adria-Universität
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
Tatiana Kojar
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
Postman
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Safe Software
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Wask
 
Trusted Execution Environment for Decentralized Process Mining
Trusted Execution Environment for Decentralized Process MiningTrusted Execution Environment for Decentralized Process Mining
Trusted Execution Environment for Decentralized Process Mining
LucaBarbaro3
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
HarisZaheer8
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
Chart Kalyan
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
Dinusha Kumarasiri
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
GDSC PJATK
 
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
Jeffrey Haguewood
 

Recently uploaded (20)

Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStrDeep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
 
Trusted Execution Environment for Decentralized Process Mining
Trusted Execution Environment for Decentralized Process MiningTrusted Execution Environment for Decentralized Process Mining
Trusted Execution Environment for Decentralized Process Mining
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
 
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
Letter and Document Automation for Bonterra Impact Management (fka Social Sol...
 

Hdpe installation practice

  • 1. Technical Bulletin H IGH DENSITY POLYETHYLENE PIPE HDPE Pipe Installation Practice LANE corrugated high density polyethylene Classes IA, IB, and II are preferred over Class III (HDPE) pipe, appropriate backfill material and when available because they are stiffer materials, proper installation practice all work together to limit pipe deflection and permit greater fill heights. result in a dependable drainage installation. HDPE Also, construction may be faster because less pipe, like all flexible pipes, depends on soil-pipe compactive effort is generally required. Class III interaction to develop its strength. Thus, proper material should not be used where water installation and backfilling are essential to conditions in a trench can cause instability. successful performance. This technical bulletin addresses typical installations in trench and embankment conditions. Unusual conditions may BACKFILL MATERIAL SIZE require additional investigations, including the Pipe Diameter (ID) Max. Particle Size recommendations of a qualified geotechnical or in. mm in. mm soils engineer. More detailed information on 6 150 3/8 10 installation and backfill may be found in ASTM D2321, " Standard Practice for Underground 8-15 200-375 5/8 15 Installation of Thermoplastic Pipe for Sewers and 18-48 450-1200 1 1/2 40 Other Gravity-Flow Applications." Installation practices must always comply Cement slurry and controlled low strength material with local, state and federal codes and (CLSM) are excellent backfill material provided they yield adequate compressive strength and the safety regulations. pipe is restrained to avoid flotation during installation. Material for Foundation, Bedding and Backfill Foundation and Bedding The pipe must be surrounded by compacted material to distribute vertical loads uniformly to A good foundation and bedding are critical to pipe the pipe and to provide passive resistance to pipe performance and service life. They are essential to deflection. Material selection depends on help maintain proper pipe elevation, eliminate availability and cost. Granular materials with little undesirable stresses in the pipe and ensure good or no plasticity are preferred. Frozen lumps, hydraulic performance. chunks of clay, organic matter and large rock are unacceptable. Acceptable materials are The foundation material beneath the pipe must summarized in Table 1 by their ASTM Class and provide a uniform resistance to the loads on the Soil Group designation. pipe. www.lane-enterprises.com
  • 2. Sharp longitudinal and lateral variations However, if special equipment is available in the foundation must be avoided. If to provide a quality installation with a rock is encountered, excavate and replace narrow trench, the minimum width can be with gravel or lightly compacted material. reduced. If material such as CLSM is Such cushion should have a depth of used that requires no compaction, the approximately ½ in. per ft. (42 mm/m) of trench width can be as little as the pipe the planned fill depth over the pipe outside diameter, plus 6 in. (150 mm). (6 in.-150 mm minimum, 24 in.-600 mm maximum). If soft foundation material is The trench must be filled with material, encountered that must be removed to placed and compacted in layers to form a maintain grade, remove the material for a "structural backfill" surrounding the pipe. depth of about 2 ft. (0.6 m) and replace The backfill must be compacted to a with suitable compacted material. The minimum of 90 percent of maximum width of this material should be 2.5 diam- density as determined by ASTM D698 or eters on either side of the pipe for pipe 12 AASHTO T99. The envelope should in. (300 mm) diameter or less. For larger extend to 12 in. (300 mm) above the top pipe, the width should be established by of the pipe before the remainder of the fill the engineer. is placed in the trench. The trench wall is assumed to have a stiffness at least that of The upper 4 in. (100 mm) of the bedding the compacted backfill. If soft trench should be relatively loose material so the walls are encountered, additional corrugations can be seated. Frozen excavation may be required. lumps, chunks of clay, organic matter and large rock are unacceptable. The pipe may be installed by shaping the bedding surface to conform to the pipe for a width of about one-half the diameter. A second method is to place the pipe directly on the bedding, in which case particular care must be taken to compact the backfill under the haunches of the pipe to provide uniform support. Trench Construction The trench should be wide enough for placement and compaction of backfill, especially the Excavate trenches to ensure the trench material placed beside the pipe and that in walls are stable under all conditions. the haunch area below the spring line. Slope the walls or provide support in Generally, the minimum trench width conformance with safety standards. All should not be less than the greater of (1) appropriate safety practices and the pipe outside diameter plus 16 in. (400 regulations must be followed to avoid mm), or (2) the pipe outside diameter trench collapse. If high ground water is times 1.25, plus 12 in. (300 mm). encountered, dewatering may be required to achieve a safe installation that meets requirements.
  • 3. Embankment Construction Backfill Placement In embankment construction, the compacted In either trench or embankment construction, the envelope of "structural backfill" must surround the backfill material must be placed in layers and pipe with a width adequate to resist forces caused compacted to a minimum of 90 percent of by construction equipment. The width of this zone maximum density as determined by ASTM D698 on each side of the pipe should be one diameter, or ASSHTO T99. The maximum thickness of the with a minimum of 12 in. (300 mm) and a layers or lifts should not exceed 6 in. (150 mm). maximum of 24 in. (600 mm). The envelope The lift thickness, placement technique and should extend to 12 in. (300 mm) above the top of compaction method must be such that compaction the pipe before normal embankment material is under the haunches is obtained. placed. continued on next page > TABLE 1 Recommended Backfill Materials ASTM ASTM Similar D2321 Type D2487 Description AASHTO Class Soil Group Type Angular, crushed stone or rock, crushed IA Manufactured Aggregates; gravel, broken coral, crushed slag, cinders open-graded, clean. or shells; large void content, contain little or no fines. Manufactured Processed Angular, crushed stone (or other Class 1A IB materials) and stone/sand mixtures with Aggregates; dense-graded, clean. gradations selected to minimize migration of adjacent soils; contain little or no fines. GW Well-graded gravels and gravel/sand A1, II Coarse-Grained Soils; clean. mixtures, little or no fines. A3 GP Poorly graded gravels and gravel/sand mixtures, little or no fines. SW Well-graded sands and gravelly sands, little or no fines. SP Poorly-graded sands and gravelly sands, little or no fines. Coarse-Grained Soils; borderline e.g. Sands which are borderline between clean to with fines. GW clean and with fines. GC SP SM III Coarse-Grained Soils with Fines. GM Silty gravels, gravel-sand-silt mixtures. A2 GC Clayey gravels, gravel-sand-clay mixtures. SM Silty sands, sand-clay mixtures SC Clayey sands, sand/clay mixtures. Note: Compact backfill material to minimum of 90% of maximum density per ASTM D698 or AASHTO T99. Table adapted from ASTM D2321.
  • 4. Each layer must be compacted before the next lift is placed. Backfill must proceed evenly on each side of the pipe. Care must be taken to avoid pipe distortion or excessive local or general deflection. Such unacceptable deformations can result from either excessive or inadequate compaction or from construction equipment. Do not allow compaction or other equipment to contact and damage the pipe. Compaction techniques must be compatible with the backfill materials used, and the width of the area being compacted. Mechanical compaction is generally used. However, water consolidation methods can be used on free-draining backfill material if care is taken to prevent flotation. Conditions must be controlled and approved by the engineer. Construction Loads It is important to protect the pipe from equipment loads during construction. Heavy equipment must not be allowed close to or over buried pipe unless provisions are made to accommodate the resultant loads. Depending on the size of the equipment and class of fill material, a minimum cover from 2 ft. (0.6 m) to 4 ft. (1.2 m), or more for exceptional loads, may be required. (see table 2) For shallow installations, it may be necessary to mound and compact material over the pipe to provide the minimum cover. The mound can be removed and final grade established after construction. TABLE 2 COVER FOR CONSTRUCTION LOADS Minimum Cover, in., for indicated Axle Loads, kips Nominal Pipe Drain with Lane Diameter, ft 18.0-50.0 50.0-75.0 75.0-110.0 110.0-150.0 Lane Enterprises, Inc. 2.0-3.0 24.0 30.0 36.0 36.0 3905 Hartzdale Drive, Suite 514 Camp Hill, PA 17011 3.5-4.0 36.0 36.0 42.0 48.0 717-761-8175 Fax 717-761-5055 4.5-5.0 36.0 36.0 42.0 48.0 New York Minimum cover shall be measured from the top of the pipe to the Ballston Spa 518-885-4385 top of the maintained construction roadway surface. If unpaved, Bath 607-776-3366 the surface shall be maintained. North Carolina Multiple Pipes Statesville 704-872-2471 When two or more pipes are installed in adjacent parallel lines, sufficient Pennsylvania space must be provided between the pipes to provide for adequate Bedford 814-623-1191 compaction of the structural backfill. One rule-of-thumb is to use a Carlisle 717-249-8342 spacing between pipes equal to 12 in. (300 mm), or one-half the nominal King of Prussia 610-272-4531 pipe diameter, whichever is greater. This can be increased if necessary to Pulaski 412-652-7747 accommodate compaction. Virginia Bealeton 540-439-3201 The information contained in this technical bulletin is general in nature and is intended for use in conjunction with competent engineering advice as to its suitability for any specific application. Nothing in this bulletin is intended as a Dublin 540-674-4645 representative or warranty that such data is suitable for any particular application or purpose. www.lane-enterprises.com