SlideShare a Scribd company logo
Guide Banks (or Guide Bunds)
Rivers in flood plains submerge very large area
during flood periods.
When some structure is to be constructed across
such a river (e.g. bridge, weir, etc) it is very
expensive to construct the work spanning the
whole width of the river.
Therefore, guide banks are constructed to
imprison(send down) the flow of the water within a
reasonable waterway.
They extend both upstream and downstream of the
abutments of the structure.
They are generally provided in pairs (couple)
symmetrical in plan.
The main parts of a guide bank are:
1. Upstream curved head
2. Downstream head
3. Shank or straight portion which joins the two curved
heads
4. Slope protection and launching apron
Con…
 where P = Lacey’s Regime perimeter (m),
Q = maximum discharge (m³/s)
Generally, L≈ 1.1 to 1.25 P.
River Training Structures
Design Criteria for Guide Banks
a. Length of Clear Waterway:
to be provided between the guide banks or the abutments of
the work
P  4.75 Q
1
2
Con…
b. Length of Guide Bank:
According to Spring, length of guide banks on the upstream
side from the axis of the work should be equal to 1.1L and
downstream side from the axis of the work 0.1L to 0.2L.
Other formulas (e.g. Gales) depending on the discharge are
also recommended:
Upstream of axis of work:-
1.25 L ------------------for Qmax up to 20,000 m³/s
1.25L – 1.5L ---------for 21,000<Qmax<42,000 m³/s
1.5L--------------------- for Qmax >42,000 m³/s
Downstream of axis of work:
0.25L------------------- for all sizes of rivers.
Con…
c. Radius of Curved Heads:
Upstream curved heads – sweep angle of 120° to 145°;
R = 0.45L
Downstream curved heads – sweep angle of 45° to 60°
and half radius of upstream curved head;
R1 = ½ R
d. Cross section of Guide Banks:
Top width not less than 3 m
Constructed of locally available material, usually sand
(earthen, soil)
Side slopes not steeper than 2:1 (H:V)
Free board of 1.25 to 1.5 m above anticipated flood level
Con…
e. Slope Protection for Guide Banks:
Water face protected by stone pitching (each stone weighing
T = thickness of stone pitching (m)
Q = maximum discharge (m³/s)
Con…
3
40 to 50 kg
Rear face slope provided with vegetal cover to protect it
against wind & rain erosion
At both curved ends the pitching is done on both front and
rear faces
The pitching as recommended by
Inglis is given by
1
T  0 . 0 6 Q 
where
f. Launching apron:
The slope of the guide bank may be damaged due to
scour, which may occur at the toe of the bank with
consequent undermining and collapse of the stone
pitching.
In order to protect the slope against such damage a stone
cover known as launching apron is laid from the toe of the
bank on the horizontal river bed
Slope of scoured face is assumed to be 2:1 (H:V).
Thus if D is the depth of scour below the bed of the river
then the length of the scour face will be= (√5) D.
Depth of scour below high flood level (H.F.L.) = K Rs
Con….
f = silt factor
d = mean size of bed material (mm)
The thickness of the apron in launched position is
assumed to be 1.25T.
Thus, the quantity of stone required per meter length
of the launching apron will be
(√5) D x 1.25T = 2.80 TD
Width of launching apron = 1.5D (usually).
River Training Structures
 Lacey´s regime scour depth (m)
 
Q = maximum discharge (m³/s)
3
1
 Q 
Rs  0.47
f

f  1.75 d
Inglis and Joglekar gave the following
values for maximum scour depth:-
1


 f
 Q  3
D s  1 . 9 
1


 f
 Q  3
D s  0 . 9 5 
1
 
 Q  3
D s  1 .3 
f

•Maximum scour depth downstream of bridge:
Maximum scour depth around bridge piers:
•Maximum scour depth at nose of guide banks of a large radius:
River Training Structures

More Related Content

What's hot

River training method
River training methodRiver training method
River training method
Muhammad Bilal
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
pradeepkumawat4142
 
Spillways
SpillwaysSpillways
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channel
Mir Zafarullah
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
Binu Karki
 
Force acting on gravity dam
Force acting on gravity damForce acting on gravity dam
Force acting on gravity dam
Divya Vishnoi
 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipators
Rahul Gupta
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure
Kiran Jadhav
 
Spillways
SpillwaysSpillways
Spillways
Divya Vishnoi
 
Dams and spillways
Dams and spillwaysDams and spillways
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
Satish Taji
 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance system
marif tahayy
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
GAURAV. H .TANDON
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
Divya Vishnoi
 
Gravity dams
Gravity damsGravity dams
Gravity dams
MitaliShelke
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Jimit Shah
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G
 
Stilling basin
Stilling basinStilling basin
Irrigation canals
Irrigation canalsIrrigation canals
Irrigation canals
Anirudhan K M
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
Malla Reddy University
 

What's hot (20)

River training method
River training methodRiver training method
River training method
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
 
Spillways
SpillwaysSpillways
Spillways
 
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channel
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
 
Force acting on gravity dam
Force acting on gravity damForce acting on gravity dam
Force acting on gravity dam
 
Energy dissipators
Energy dissipatorsEnergy dissipators
Energy dissipators
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure
 
Spillways
SpillwaysSpillways
Spillways
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance system
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 
Gravity dams
Gravity damsGravity dams
Gravity dams
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Stilling basin
Stilling basinStilling basin
Stilling basin
 
Irrigation canals
Irrigation canalsIrrigation canals
Irrigation canals
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 

Similar to guide banks.pptx

Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
SAGAR RAUT
 
Canal drop notch type -design steps
Canal drop notch type -design stepsCanal drop notch type -design steps
Canal drop notch type -design steps
Nirmala Krrishnan
 
Control Seepage Thought Earth Dams
Control Seepage Thought Earth DamsControl Seepage Thought Earth Dams
Control Seepage Thought Earth Dams
Ahmed Mansor
 
Flexible lining for flood channels 100509
Flexible lining for flood channels 100509Flexible lining for flood channels 100509
Flexible lining for flood channels 100509
AHMED NADIM JILANI
 
Flexible lining for flood channels 100509
Flexible lining for flood channels 100509Flexible lining for flood channels 100509
Flexible lining for flood channels 100509
AHMED NADIM JILANI
 
FINAL-COPY.-channel-slope-and-freeboard-1.pptx
FINAL-COPY.-channel-slope-and-freeboard-1.pptxFINAL-COPY.-channel-slope-and-freeboard-1.pptx
FINAL-COPY.-channel-slope-and-freeboard-1.pptx
JhetBonode
 
1Bridges.ppt
1Bridges.ppt1Bridges.ppt
1Bridges.ppt
ssuser95bbb81
 
Chapter two
Chapter twoChapter two
Chapter two
Tewelde Gtsadkan
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
Vishal Jolaniya
 
Presentation on notches and weirs
Presentation on notches and weirsPresentation on notches and weirs
Presentation on notches and weirs
sush_vyas
 
Dr Mujahid sb Presentation 2.pptx
Dr Mujahid sb Presentation 2.pptxDr Mujahid sb Presentation 2.pptx
Dr Mujahid sb Presentation 2.pptx
habibahmadjan
 
Open channel design
Open channel designOpen channel design
Open channel design
Mohsin Siddique
 
Canal design
Canal designCanal design
Canal design
brijlata sharma
 
Wave Transmission on Submerged Breakwater with Interlocking D-Block Armor
Wave Transmission on Submerged Breakwater with Interlocking D-Block ArmorWave Transmission on Submerged Breakwater with Interlocking D-Block Armor
Wave Transmission on Submerged Breakwater with Interlocking D-Block Armor
irjes
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
saibabu48
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
Ramanuj Jaldhari
 
lecture-2.pdf
lecture-2.pdflecture-2.pdf
lecture-2.pdf
ShahidAli465
 
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONSLAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
Namitha M R
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
Latif Hyder Wadho
 
Ce 3205-lecture-08-spillways
Ce 3205-lecture-08-spillwaysCe 3205-lecture-08-spillways
Ce 3205-lecture-08-spillways
saibabu48
 

Similar to guide banks.pptx (20)

Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Canal drop notch type -design steps
Canal drop notch type -design stepsCanal drop notch type -design steps
Canal drop notch type -design steps
 
Control Seepage Thought Earth Dams
Control Seepage Thought Earth DamsControl Seepage Thought Earth Dams
Control Seepage Thought Earth Dams
 
Flexible lining for flood channels 100509
Flexible lining for flood channels 100509Flexible lining for flood channels 100509
Flexible lining for flood channels 100509
 
Flexible lining for flood channels 100509
Flexible lining for flood channels 100509Flexible lining for flood channels 100509
Flexible lining for flood channels 100509
 
FINAL-COPY.-channel-slope-and-freeboard-1.pptx
FINAL-COPY.-channel-slope-and-freeboard-1.pptxFINAL-COPY.-channel-slope-and-freeboard-1.pptx
FINAL-COPY.-channel-slope-and-freeboard-1.pptx
 
1Bridges.ppt
1Bridges.ppt1Bridges.ppt
1Bridges.ppt
 
Chapter two
Chapter twoChapter two
Chapter two
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
Presentation on notches and weirs
Presentation on notches and weirsPresentation on notches and weirs
Presentation on notches and weirs
 
Dr Mujahid sb Presentation 2.pptx
Dr Mujahid sb Presentation 2.pptxDr Mujahid sb Presentation 2.pptx
Dr Mujahid sb Presentation 2.pptx
 
Open channel design
Open channel designOpen channel design
Open channel design
 
Canal design
Canal designCanal design
Canal design
 
Wave Transmission on Submerged Breakwater with Interlocking D-Block Armor
Wave Transmission on Submerged Breakwater with Interlocking D-Block ArmorWave Transmission on Submerged Breakwater with Interlocking D-Block Armor
Wave Transmission on Submerged Breakwater with Interlocking D-Block Armor
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
 
lecture-2.pdf
lecture-2.pdflecture-2.pdf
lecture-2.pdf
 
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONSLAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
LAND DRAINAGE- CLASSIFICATIONS, STEADY AND UNSTEADY STATE EQUATIONS
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
 
Ce 3205-lecture-08-spillways
Ce 3205-lecture-08-spillwaysCe 3205-lecture-08-spillways
Ce 3205-lecture-08-spillways
 

More from tameneaDemissie

Climate change and hydrological modeling.pptx
Climate change and hydrological modeling.pptxClimate change and hydrological modeling.pptx
Climate change and hydrological modeling.pptx
tameneaDemissie
 
shaft.pptx
shaft.pptxshaft.pptx
shaft.pptx
tameneaDemissie
 
Chapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdfChapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdf
tameneaDemissie
 
Draft PPT for panel Discussion.pptx
Draft PPT for panel Discussion.pptxDraft PPT for panel Discussion.pptx
Draft PPT for panel Discussion.pptx
tameneaDemissie
 
Chapter 2.pdf
Chapter 2.pdfChapter 2.pdf
Chapter 2.pdf
tameneaDemissie
 
Presentation_final.pptx
Presentation_final.pptxPresentation_final.pptx
Presentation_final.pptx
tameneaDemissie
 
LUCST walkthrough v1.2.pdf
LUCST walkthrough v1.2.pdfLUCST walkthrough v1.2.pdf
LUCST walkthrough v1.2.pdf
tameneaDemissie
 
cdo.pdf
cdo.pdfcdo.pdf

More from tameneaDemissie (8)

Climate change and hydrological modeling.pptx
Climate change and hydrological modeling.pptxClimate change and hydrological modeling.pptx
Climate change and hydrological modeling.pptx
 
shaft.pptx
shaft.pptxshaft.pptx
shaft.pptx
 
Chapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdfChapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdf
 
Draft PPT for panel Discussion.pptx
Draft PPT for panel Discussion.pptxDraft PPT for panel Discussion.pptx
Draft PPT for panel Discussion.pptx
 
Chapter 2.pdf
Chapter 2.pdfChapter 2.pdf
Chapter 2.pdf
 
Presentation_final.pptx
Presentation_final.pptxPresentation_final.pptx
Presentation_final.pptx
 
LUCST walkthrough v1.2.pdf
LUCST walkthrough v1.2.pdfLUCST walkthrough v1.2.pdf
LUCST walkthrough v1.2.pdf
 
cdo.pdf
cdo.pdfcdo.pdf
cdo.pdf
 

Recently uploaded

5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 

Recently uploaded (20)

5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 

guide banks.pptx

  • 1. Guide Banks (or Guide Bunds) Rivers in flood plains submerge very large area during flood periods. When some structure is to be constructed across such a river (e.g. bridge, weir, etc) it is very expensive to construct the work spanning the whole width of the river.
  • 2. Therefore, guide banks are constructed to imprison(send down) the flow of the water within a reasonable waterway. They extend both upstream and downstream of the abutments of the structure. They are generally provided in pairs (couple) symmetrical in plan. The main parts of a guide bank are: 1. Upstream curved head 2. Downstream head 3. Shank or straight portion which joins the two curved heads 4. Slope protection and launching apron Con…
  • 3.
  • 4.  where P = Lacey’s Regime perimeter (m), Q = maximum discharge (m³/s) Generally, L≈ 1.1 to 1.25 P. River Training Structures Design Criteria for Guide Banks a. Length of Clear Waterway: to be provided between the guide banks or the abutments of the work P  4.75 Q 1 2
  • 5.
  • 7. b. Length of Guide Bank: According to Spring, length of guide banks on the upstream side from the axis of the work should be equal to 1.1L and downstream side from the axis of the work 0.1L to 0.2L. Other formulas (e.g. Gales) depending on the discharge are also recommended: Upstream of axis of work:- 1.25 L ------------------for Qmax up to 20,000 m³/s 1.25L – 1.5L ---------for 21,000<Qmax<42,000 m³/s 1.5L--------------------- for Qmax >42,000 m³/s Downstream of axis of work: 0.25L------------------- for all sizes of rivers. Con…
  • 8. c. Radius of Curved Heads: Upstream curved heads – sweep angle of 120° to 145°; R = 0.45L Downstream curved heads – sweep angle of 45° to 60° and half radius of upstream curved head; R1 = ½ R d. Cross section of Guide Banks: Top width not less than 3 m Constructed of locally available material, usually sand (earthen, soil) Side slopes not steeper than 2:1 (H:V) Free board of 1.25 to 1.5 m above anticipated flood level Con…
  • 9. e. Slope Protection for Guide Banks: Water face protected by stone pitching (each stone weighing T = thickness of stone pitching (m) Q = maximum discharge (m³/s) Con… 3 40 to 50 kg Rear face slope provided with vegetal cover to protect it against wind & rain erosion At both curved ends the pitching is done on both front and rear faces The pitching as recommended by Inglis is given by 1 T  0 . 0 6 Q  where
  • 10. f. Launching apron: The slope of the guide bank may be damaged due to scour, which may occur at the toe of the bank with consequent undermining and collapse of the stone pitching. In order to protect the slope against such damage a stone cover known as launching apron is laid from the toe of the bank on the horizontal river bed Slope of scoured face is assumed to be 2:1 (H:V). Thus if D is the depth of scour below the bed of the river then the length of the scour face will be= (√5) D. Depth of scour below high flood level (H.F.L.) = K Rs Con….
  • 11. f = silt factor d = mean size of bed material (mm) The thickness of the apron in launched position is assumed to be 1.25T. Thus, the quantity of stone required per meter length of the launching apron will be (√5) D x 1.25T = 2.80 TD Width of launching apron = 1.5D (usually). River Training Structures  Lacey´s regime scour depth (m)   Q = maximum discharge (m³/s) 3 1  Q  Rs  0.47 f  f  1.75 d
  • 12. Inglis and Joglekar gave the following values for maximum scour depth:- 1    f  Q  3 D s  1 . 9  1    f  Q  3 D s  0 . 9 5  1    Q  3 D s  1 .3  f  •Maximum scour depth downstream of bridge: Maximum scour depth around bridge piers: •Maximum scour depth at nose of guide banks of a large radius: