SlideShare a Scribd company logo
Integrate Early…
Integrate Often!
Success for a LEED Platinum Public Building
Judi Cooper
Deputy Executive Secretary
Administrative Services Manager
judi.cooper@iub.iowa.gov
Shanna Olson
LC
Senior Lighting Designer
olsonsl@kjww.com
Scott Bowman
PE, LEED AP BD+C
Retired Principal and Sustainability Advisor
bowmansc@kjww.com
scottb@ideabuildworks.com
Carey Nagle
AIA, LEED AP BD+C
Associate Principal
cnagle@bnim.com
Fellow
COMMUNICATION
Time to get engaged!
LEARNING OBJECTIVES
…learn how integrated design communication must be
established and nurtured.
…understand how integrated design with early analysis and goal
setting can greatly affect the performance of a building.
…engage and share with peers on the benefits and challenges of
integrated design, and have fun in the process.
…see actual examples of projects which achieved exemplary
performance as a result of integrative design.
Participants will . . .
WHY?
• Energy codes are advancing…
• Sustainability standards are advancing…
• Design constraints are increasing…
• Owners budgets are constrained…
• Owners expectations are higher…
• Buildings and systems are more complex…
• Communication tools have exploded…
• Integrated Design is the way to address all these
issues and more!
© 2 0 1 2
B N I M
A PROCESS FOR HIGH PERFORMANCE
B++
© 2 0 1 2
B N I M
SIMPLE IDEAS
AND PROCESS
FOR ANY:
ACHIEVABLE +
REPLICABLE
TRANSFORM THE FUTURE
© 2 0 1 2
B N I M
Owners
© 2 0 1 2
B N I M
Design
Professionals
Government
EVERY BUILDING
Owner
Consultants
Iowa Energy Center
Utility Companies
State Legislature
INTEGRATE
=
UNITE
COLLABORATION + INTEGRATED DESIGN PROCESS
INTEGRATED DESIGN
As defined by LEED v4
INTEGRATIVE
PROCESS
IP CREDIT 102 INTEGRATIVE PROCESS
New Credit – In HC too!
Early “simple box” energy analysis
Lists parametric options reviewed
Includes water performance
Requires cost analysis and bundling
Reward for doing goal setting and analysis early!
LEED 2009
Didn’t Exist
LEED v4
IP102: Integrative Process
CREDIT POINTS
1
OWNERS PROJECT
REQUIREMENTS
The lowly, miss-understood OPR…
OPR ACCORDING TO LEED
• LEED v2009 – EAp1
– The owner must document the owner’s project
requirements. The design team must develop the
basis of design. The CxA must review these
documents for clarity and completeness. The
owner and design team must be responsible for
updates to their respective documents.
OPR ACCORDING TO LEED
• LEED v2009 – EAp1 – Reference Guide
– The owner’s project requirements should detail
the functional requirements of a project and the
expectations of the building’s use and operation
as they relate to the systems being commissioned.
OPR ACCORDING TO LEED
• LEED v2009 – EAp1 – Reference Guide
– The owner’s project requirements should detail
the functional requirements of a project and the
expectations of the building’s use and operation
as they relate to the systems being
commissioned.
OPR ACCORDING TO LEED
• LEED v2009 – EAp1 – Reference Guide
– Owner and User Requirements
– Environmental and Sustainability Goals
– Energy Efficiency Goals
– Indoor Environmental Goals
– Equipment and System Expectations
– Building Occupant and O&M Requirements
OPR ACCORDING TO LEED
• LEED v4 – Integrative Process and Cx
– Early Energy and Water analysis must be
documented in OPR and BOD
– More Requirements of documents:
• Building and Site Program
• Building Form and Geometry
• Building Envelope and Façade
• Other Systems
WHAT IS THE BIG DEAL?
• The OPR is the most under valued and under
used document in the design process
• Design teams MUST be on the same page and
understand the Owners expectations
• Integration starts with communication, but
must include documentation and approval
• Something other than meeting minutes needs
to reflect objectives, goals and decisions
OPR AS DESIGN TOOL
• Embrace Integrated Design and Process
• Create OPR as a collaboration of initial
building and sustainability charettes
• Focus on Owners goals and expectations
• Expand way beyond energy and systems
• Define required research or future decisions
• Revise and update – living document!
WHAT DOES THE OWNER WANT?
• Meet an aggressive energy usage goal;
• A replicable model building;
• A comfortable, productive environment for
staff/guests;
• Viewed as a positive addition to the Iowa
Capitol Complex;
• A tour destination point; and
• Stay on budget
COMMUNICATION REPORT
BACK
What do you think INTEGRATED DESIGN means?
HIGH PERFORMANCE
PROCESS
What is the right and proper way to reach high goals?
LAYERS OF DESIGN
Use Less
• Reduce Loads
• Passive
• Envelope
Use
Efficiently
• System
Selection
• High
Efficiency
Make On
Site
• Renewable
Energy
• Portal to
Future
Total EUI :
28.0
kBtu/sf/yr
% Reduction from
code base EUI
60%
Model for other
government & private
sector entities
LEED
Platinum
VISIONARY GOALS
Building Area
44,640
GSF
Cost
$204
Per GSF
MODEST BUDGET
PROJECT COMPLETION DATE
Jan. 17, 2011
LOT SIZE
6.06 acres
BUILDING GROSS FLOOR AREA
44,640 sf
BUILDING FOOTPRINT AREA
20,003 sf
HOURS OF OPERATION
6:00 A – 5:30 P.M.
BUILDING OCCUPANCY
Permanent 90 x 44 Hours
Visitors 20 Per Week x 4Hours
TOTAL PROJECT COST
$10,140,768 (Construction Costs)
GENERAL PROJECT
INFORMATION
GROUND FLOOR PLAN
1 lobby
2 open office
3 enclosed office
4 meeting room
5 copy/work room
6 records information
7 hearing room
8 break room
9 receiving
10 files/storage
11 server room
UPPER FLOOR PLAN
1 lobby
2 open office
3 enclosed office
4 meeting room
5 copy/work room
6 records information
7 hearing room
8 break room
9 receiving
10 files/storage
11 server room
“The team saw that the impact of their work
was bigger than just the building. It was to set
an example for other government buildings.”
JURY MEMBER
2012 AIA COTE TOP TEN PROJECTS SELECTION COMMITTEE
“The reason we exceeded our [performance] goal is
because the occupants understood what we were
trying to do from the top down [O] we walked in the
door with a set of protocols that we all helped to
develop and understood. We don’t plug in superfluous
loads. We function with daylight. With the systems that
are there— the geothermal, the photovoltaics — there
are times when the building is producing more than we
are using and sending it back to the State Capital
Complex.”
JUDI COOPER
DEPUTY EXECUTIVE SECRETARY | IUB-OCA
“Young people are aware of [this building] and excited by
it. I’ve taken unsolicited phone calls from high school
students saying, I see your new building on the Capital
complex. Can I come and see it? And I say, Of course
you can! I take them on a tour. I’ve taken teachers,
architecture students, people from around the world.
They are aware of it, and I am excited by what they will
do when they are the ones out there designing like this.”
JUDI COOPER
DEPUTY EXECUTIVE SECRETARY | IUB-OCA
WATER STRATEGIES
1 rain garden
2 sediment basin
3 water infiltration basin
4 pervious pavement
5 offsite storm diverter
6 bioswale
7 on-street parking
(minimizes impervious surface)
ENVELOPE
How do we keep the outside out, and the inside in?
REPLICATION INNOVATION
• Good Thermal Envelope
• Cost Effective Precast
• Thermal Bridging Mitigation
• Non-Conductive Precast System
• Material Duality
ENVELOPE
1 continuous thermal and air barriers at construction interfaces
2 thermomass precast concrete wall system
3 zinc cladding
4 cool roof
5 Daylight harvesting sunscreen
6 green wall
REPLICATION INNOVATION
• Operable Windows • Weather Station
• Building Automation System Alert
• Systems Tie-In
• Cost Effective
NATURAL VENTILATION
1 operable exterior windows
2 weather sensor measuring temperature, humidity, wind speed, and direction
3 weather station alerts occupants to open and close windows
4 mechanical system shuts down when windows are open
Material Duality, structural systems
as finish systems
Agrifiber, a rapidly renewable and
regionally sourced material, was
used for the door cores
Furniture achieves Cradle-to-Cradle
certification or equivalent standard
Low V.O.C. materials used
throughout
All furniture within the project is
Greenguard certified at a minimum
35%
of total material content was recycled
67%of materials were regionally extracted,
harvested and fabricated
96%
of wood used was Forestry Stewardship
Council certified, hence responsibly
harvested
89%
of construction waste was recycled
HEATING VENTILATION AND
AIR CONDITIONING
The physiological manifestation of well being…comfort!
Courtesy PNNL
ASHRAE 90.1-2013
ASHRAE 90-1975 ASHRAE 90A-1980
ASHRAE 90.1-1999
ASHRAE 90.1-2001
ASHRAE 90.1-2007
ASHRAE 90.1-2004
ASHRAE 90.1-1989
ASHRAE 90.1-2010
Improvement in ASHRAE Standard 90.1 (Year 1975 – 2010)EnergyUseIndex(1975Use=100)
Year
1970 1975 1980 1985 1990
50
1995 20152000 20102005
110
100
90
80
70
60
ENERGY MODELING
• Key to High Performance
• Important to understand interaction
• Many approximations – manage expectations
• Know limits of software
• Understand gross assumptions!
• Move from isolated evaluations to bundling
• Set early goals – Measure against them
often!
Energy Use Basis
Baseline – 72.5 kBtu/sf
23%
Heating
Cooling
Fan/Pump
Lights
Plug Load
DHW
44%
Data Courtesy of The Weidt Group
Energy Use Basis
Design – 27.3 kBtu/sf
Heating
Cooling
Fan/Pump
Lights
Plug Load
DHW
Data Courtesy of The Weidt Group
15%
21%42%
Actual – 21.2 kBtu/sf
Energy Use Basis
Heating
Cooling
Fan/Pump
Lights
Plug Load
DHW
Data Courtesy of The Weidt Group
18%
HEATING
11%
COOLING
24%
FAN/PUMP
20%
LIGHTS
26%
PLUG
LOAD
Energy Use Basis
Heating
Cooling
Fan/Pump
Lights
Plug Load
DHW
Data Courtesy of The Weidt Group
18%
HEATING
11%
COOLING
Actual – 16.7 kBtu/sf
24%
FAN/PUMP
20%
LIGHTS
26%
PLUG
LOAD
with Renewable (PV)
Why kBtu/sf?
• ASHRAE currently uses energy cost
• Dollars reflect some local energy utilization and
market conditions
• Suppressed sources can obscure signals
– Natural Gas
– Renewable Energy (Wind or Solar)
• Need to measure true performance
• Location, Location, Location
– 28 kBtu/sf means something in Iowa
– What about Portland?
REPLICATION INNOVATION
• Passive Strategies
• Geothermal
• Energy Recovery
• Occupancy Sensors Per Workstation
• Demand Controlled Ventilation
• Building Automation System
• Photovoltaic Panels
ENERGY STRATEGIES
1 geothermal system
2 photovoltaic roof panels
3 occupancy sensors for lighting and plug load reduction at each work station and office
4 stormwater filtered and infiltrated on site
5 continuous monitoring of all systems
6 perimeter radiant heating
19.1%
of Building Energy Use
RENEWABLE ENERGY
DAYLIGHTING AND LIGHTING
What do you mean gas lamps are good anymore?
DAYLIGHT HARVESTING
GOALS
Create a balance between potential energy reduction
through enhanced daylight and reduced heat gain
Sunscreen Conditions
summer winter
1 diffuse northern daylight
2 light tubes
3 daylight harvesting sunscreen
4 light sensors
5 daylight responsive artificial lighting
6 interior glazing transmits daylight
7 exterior view throughout
DAYLIGHTING STRATEGIES
• Feel of the
space
• Energy goals
• Energy code
• LEED
• Light levels
• Comfort
with
technology
• Initial
• Simple
payback
• Life cycle
cost
Budget
User’s
needs
AestheticsEnergy
LIGHTING DESIGN PROGRAMMTIC GOALS
IUB/OCA – LIGHTING DESIGN
Mix of design techniques and lamp sources
IUB/OCA – LIGHTING DESIGN
Mix of design techniques and lamp sources
IUB/OCA – LIGHTING DESIGN
Mix of design techniques and lamp sources
EVOLUTION IN LIGHTING
Linear LED Linear Fluorescent
Life 50-100,000 hrs + 24-87,000 hrs
Efficacy/ Efficiency Varies widely Varies widely
Standard control Typically 0-10v standard Typically switching
standard
Optical qualities Point source/ lenses used
to create ambient optics,
quality ranges
Ambient source
CCT/ CRI 2700-6500/65-90 2700-5000/ 75-90
Cost 1.1-3 1
SDCM/ MacAdam’s step 7 step min 4 step min
Replacement cost and
availability
Unknown Known & varies by lamp
LED V. FLUORESCENT
WHITE LIGHT EFFICACY PROJECTIONS
Who will determine when
LED’s need to be replaced?
How much will it cost to
replace?
IMAGE SOURCE: maxlite.com
Will the replacement parts
provide the same lumen
output and color quality?
IES LM-80 & TM-21 have
been adopted to define LED
life and lumen maintenance
APPLICATION CONSIDERATIONS
What does end of life mean for an LED?
APPLICATION
CONSIDERATIONS
How does it really compare?
TRADITIONAL
SOURCES
SOLID STATE INITIAL COST
LAMP LIFE
DIFFERENCE
LINEAR FL EVERY
FEW FEET’
(SEVERAL
HUNDRED WATTS)
6 TO 10
FIXTURES
300 TO 500
WATTS
UNKNOWN . 24-87,000HRS
TO 50,000HR
126/270/
480 WATTS
DEPENDING ON
SCALE
100/180/350
WATTS
DEPENDING ON
SCALE
MINIMAL
COST
DIFFERENCE
12,000HRS TO
50,000HRS
COMPARISON
APPLICATION
CONSIDERATIONS
What is white light and why does it matter?
IUB/OCA
OUTDOOR LIGHTING
Use of LED for all sources
IUB/OCA
OUTDOOR LIGHTING
LED Parking Lighting
APPLICATION
CONSIDERATIONS
How do exterior lamp source options compare today?
LAMP TYPE
WATTS PER
SQ FOOT
COST
DIFFERENCE
LIFE CONTROL
CMH
37800 NOM
77% EFFICIENCY
29080DELIVERED
338 WATTS
.292 WATTS
PER SQ FT AT
ABOUT 18FC
~ 30,000 HRS 0-10V DIMMING
LED 412w
30,000 LUMEN
.311 WATTS
PER SQ FT AT
ABOUT 18FC
ABOUT 15%
MORE
L90 AT
60,000 HRS
BI-LEVEL OR
0-10V DIMMING
W/ OCCUPANCY
SENSOR
CURRENT EXTERIOR LAMP SOURCE OPTIONS
• Feel of the
space
• Energy goals
• Energy code
• LEED
• Functionality
requirements
• Comfort with
technology
• Initial
• Simple
payback
• Life cycle
cost
Budget
User’s
needs
AestheticsEnergy
CONTROLS PROGRAMMTIC GOALS
CURRENT AND PROJECTED
CODE STATUS PER STATE
IUB/OCA LIGHTING
CONTROLS INTEGRATION
Networked 0-10v & switching protocols with Daylight Harvesting
0-10V DIMMING CONTROL
Daylight Harvesting
TYPICAL LIGHTING CONTROL ZONES
NETWORK CONTROL
SYSTEMS
Digital Addressable Lighting Interface (DALI)
Typically Saves the Most Energy
in the Long Run
Typically Requires More
Knowledge to Maintain
Maximizes Controllability Typically More Expensive
Convergence
Requires Greater Coordination in
Design and Construction
Long Term Flexibility
Two Way Communication
Pro’s Con’s
DIGITAL ADDRESSABLE LIGHTING INTERFACE
DALI PROTOCOLS
CONVERGENCE
How do we bring things together?
CONTROL INTEGRATION
• Integrated control
systems
– Lighting
– AV
– Shades
– HVAC
– Security
– Receptacle
AMBIENT TASK CONTROL
• 50% of all receptacles shall have automatic shutoff in:
Open offices
Private offices
Computer classrooms
• Accomplished in one of three ways
Ceiling or wall vacancy sensor
Relay panel with time clock
Plug in occupancy sensor
MAY NOT BE ALLOWED BY AHJ
ASHRAE 2010
RECEPTACLE CONTROL
PLUG LOAD CONTROL
Data Courtesy of The Weidt Group
Model = 0.90 w/sf
Metered = 0.25 w/sf
OPERATIONS
Now I get to run what you designed…but my reality has shifted!
PROTOCOLS
• Iowa’s Green Government Initiative
• Ensure importance of goal is communicated
• Solicit buy in – “All In”
• Have clear behavioral expectations
• Automated building features make is easy
• Live it out – No superfluous load
Lay the Groundwork
BYOB
POST-OCCUPANCY + KNOWLEDGE SHARING
$54,000 Annual Savings
Includes PV
75%
98%
Includes PV
75%
98%
Energy Monitoring
LEED Measurement &
Verification
Electrical Circuits Monitored
• Lighting
• Plug Loads
• Mechanical Equipment
• General Building Loads
• IT Equipment
Geothermal Loop
Data Collected by Capitol
Complex Energy Management
System
Energy Star = 100
MEASUREMENT AND VERIFICATION
Second Year M&V Results:
• Design Estimated Model EUI – with PV 28.1
• Monitored EUI – with PV 16.7
• Monitored EUI – without PV 21.2
Conclusions:
• Model over predicted pumping energy
• Model slightly over predicted lighting savings
• Plug loads are significantly lower than expectations
• Corrected energy model tracks actual use well
COMMUNICATION FOLLOW-UP
Now what do you think?
TAKEAWAYS
• Integrative Design leads to High Performance
• Use the OPR as a design tool
• Collaboration of envelope to lighting is key
• Energy modeling should be early and often
• Measure against goals for key decisions
• Plug load management is new horizon
Important concepts we wanted to emphasize…
QUESTIONS
…understand how integrated design communication must be
established and nurtured.
…realize integrated design with early analysis and goal
setting can greatly affect the performance of a building.
…have seen the benefits and challenges of integrated
design, and had some fun in the process.
…know of actual examples of projects which achieved
exemplary performance as a result of integrative design.
Learning objectives you should…
AWARDS AND RECOGNITIONS
• AIA Committee On The Environment
Top 10 Green Building Award 2012
Top 10 Plus in 2014
• ASHRAE Technology Award
Second Place in 2014
• AIA Central States Region Merit Award
• AIA Iowa Merit Award
• Des Moines’ Environmental Impact Awards
Built Environment Award
http://bt.e-ditionsbyfry.com/publication/?i=200800&p=38
COMMUNICATION REPORT BACK
What did we learn?
Integrate Early…
Integrate Often!
Success for a LEED Platinum Public Building

More Related Content

What's hot

LEED-EB O&M Basics
LEED-EB O&M BasicsLEED-EB O&M Basics
LEED-EB O&M Basics
Lida_Lewis
 
How CFD & Daylight Modelling Can Support Successful UK Planning Applications
How CFD & Daylight Modelling Can Support Successful UK Planning ApplicationsHow CFD & Daylight Modelling Can Support Successful UK Planning Applications
How CFD & Daylight Modelling Can Support Successful UK Planning Applications
IES VE
 
Hero to Zero: Understand and meet Vancouver's new energy and emission require...
Hero to Zero: Understand and meet Vancouver's new energy and emission require...Hero to Zero: Understand and meet Vancouver's new energy and emission require...
Hero to Zero: Understand and meet Vancouver's new energy and emission require...
Lauren-Lee Camp
 
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
Rod Yeoh
 
Cowhorn Vineyard + Garden Tasting Room
Cowhorn Vineyard + Garden Tasting RoomCowhorn Vineyard + Garden Tasting Room
Cowhorn Vineyard + Garden Tasting Room
melanie_bissonnette
 
Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...
Michael Taranto
 
Leed for SWE WE 14
Leed for SWE WE 14Leed for SWE WE 14
Energy and comfort modeling for the net zero rocky mountain institute headqua...
Energy and comfort modeling for the net zero rocky mountain institute headqua...Energy and comfort modeling for the net zero rocky mountain institute headqua...
Energy and comfort modeling for the net zero rocky mountain institute headqua...
energytrustor
 
Allies for efficiency training chemeketa final locked
Allies for efficiency training   chemeketa final lockedAllies for efficiency training   chemeketa final locked
Allies for efficiency training chemeketa final locked
energytrustor
 
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
IES VE
 
LEED-EB Presentation
LEED-EB PresentationLEED-EB Presentation
LEED-EB Presentation
Kevin Sneed
 
Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010
smilerneil
 
Optimizing Building Operations and Maintenance Practices
Optimizing Building Operations and Maintenance PracticesOptimizing Building Operations and Maintenance Practices
Optimizing Building Operations and Maintenance Practices
Green Initiatives 绿色倡议
 
Energy in Schools by John Dolan
Energy in Schools by John DolanEnergy in Schools by John Dolan
Energy in Schools by John Dolan
SustainableEnergyAut
 
LEED Canada - Existing Building Commissioning_Mar1st
LEED Canada - Existing Building Commissioning_Mar1stLEED Canada - Existing Building Commissioning_Mar1st
LEED Canada - Existing Building Commissioning_Mar1stMichael Clarke
 
LEED v4 Transformation
LEED v4 TransformationLEED v4 Transformation
LEED v4 Transformation
OC_Composites
 
GRIHA RATING SYSTEM
GRIHA RATING SYSTEMGRIHA RATING SYSTEM
GRIHA RATING SYSTEM
Krina Vesuwala
 
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume SystemsEnergy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
melanie_bissonnette
 

What's hot (20)

LEED-EB O&M Basics
LEED-EB O&M BasicsLEED-EB O&M Basics
LEED-EB O&M Basics
 
How CFD & Daylight Modelling Can Support Successful UK Planning Applications
How CFD & Daylight Modelling Can Support Successful UK Planning ApplicationsHow CFD & Daylight Modelling Can Support Successful UK Planning Applications
How CFD & Daylight Modelling Can Support Successful UK Planning Applications
 
Hero to Zero: Understand and meet Vancouver's new energy and emission require...
Hero to Zero: Understand and meet Vancouver's new energy and emission require...Hero to Zero: Understand and meet Vancouver's new energy and emission require...
Hero to Zero: Understand and meet Vancouver's new energy and emission require...
 
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
Hero to Zero, Vancouver's New Rezoning Policy - Buildex Vancouver 2017
 
Cowhorn Vineyard + Garden Tasting Room
Cowhorn Vineyard + Garden Tasting RoomCowhorn Vineyard + Garden Tasting Room
Cowhorn Vineyard + Garden Tasting Room
 
Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...
 
Leed for SWE WE 14
Leed for SWE WE 14Leed for SWE WE 14
Leed for SWE WE 14
 
Energy and comfort modeling for the net zero rocky mountain institute headqua...
Energy and comfort modeling for the net zero rocky mountain institute headqua...Energy and comfort modeling for the net zero rocky mountain institute headqua...
Energy and comfort modeling for the net zero rocky mountain institute headqua...
 
Allies for efficiency training chemeketa final locked
Allies for efficiency training   chemeketa final lockedAllies for efficiency training   chemeketa final locked
Allies for efficiency training chemeketa final locked
 
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
 
LEED-EB Presentation
LEED-EB PresentationLEED-EB Presentation
LEED-EB Presentation
 
Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010
 
Optimizing Building Operations and Maintenance Practices
Optimizing Building Operations and Maintenance PracticesOptimizing Building Operations and Maintenance Practices
Optimizing Building Operations and Maintenance Practices
 
Energy in Schools by John Dolan
Energy in Schools by John DolanEnergy in Schools by John Dolan
Energy in Schools by John Dolan
 
LEED Canada - Existing Building Commissioning_Mar1st
LEED Canada - Existing Building Commissioning_Mar1stLEED Canada - Existing Building Commissioning_Mar1st
LEED Canada - Existing Building Commissioning_Mar1st
 
LEED Presentation
LEED PresentationLEED Presentation
LEED Presentation
 
LEED v4 Transformation
LEED v4 TransformationLEED v4 Transformation
LEED v4 Transformation
 
GRIHA RATING SYSTEM
GRIHA RATING SYSTEMGRIHA RATING SYSTEM
GRIHA RATING SYSTEM
 
LEED
LEEDLEED
LEED
 
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume SystemsEnergy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
 

Viewers also liked

أهمية الحاسب 1
أهمية الحاسب 1أهمية الحاسب 1
أهمية الحاسب 1
Younes Orabi
 
شبكات الإتصال والإنترنت
شبكات الإتصال والإنترنتشبكات الإتصال والإنترنت
شبكات الإتصال والإنترنت
s7xs7
 
Network Implementation and Support Lesson 10 Server Administration - Eric V...
Network Implementation and Support Lesson 10   Server Administration - Eric V...Network Implementation and Support Lesson 10   Server Administration - Eric V...
Network Implementation and Support Lesson 10 Server Administration - Eric V...
Eric Vanderburg
 
مكونات شبكات الحاسب الآلي Www.algeria pedia.info
مكونات شبكات الحاسب الآلي  Www.algeria pedia.infoمكونات شبكات الحاسب الآلي  Www.algeria pedia.info
مكونات شبكات الحاسب الآلي Www.algeria pedia.info
Marketing matic Seo Brand
 
اقصاد المعرقة..
اقصاد المعرقة..اقصاد المعرقة..
اقصاد المعرقة..
m elelwa
 
الشبكات
الشبكاتالشبكات
الشبكات
m_gemy86
 
شبكات الحاسب
شبكات الحاسبشبكات الحاسب
شبكات الحاسبSALEH ALBHADAL
 
شرح شبكات الحاسب
شرح شبكات الحاسبشرح شبكات الحاسب
شرح شبكات الحاسب
طاهر صميلي
 
بوربونت الشبكات
بوربونت الشبكاتبوربونت الشبكات
بوربونت الشبكاتlames10
 
شبكات و أمن المعلومات 2
شبكات و أمن المعلومات 2شبكات و أمن المعلومات 2
شبكات و أمن المعلومات 2
emad tawfeek
 
مفاهيم حول الشبكات
مفاهيم حول الشبكاتمفاهيم حول الشبكات
مفاهيم حول الشبكات
issa alsumri
 
الدرس الأول: مفهوم الشبكات
الدرس الأول: مفهوم الشبكاتالدرس الأول: مفهوم الشبكات
الدرس الأول: مفهوم الشبكاتalwardi68709
 
شبكات و أمن المعلومات 1
شبكات و أمن المعلومات 1شبكات و أمن المعلومات 1
شبكات و أمن المعلومات 1
emad tawfeek
 
عالم الشبكات
عالم الشبكاتعالم الشبكات
عالم الشبكات
T. Fatma Esa
 
أساسيات أمن المعلومات
أساسيات أمن المعلوماتأساسيات أمن المعلومات
أساسيات أمن المعلومات
Mohammed Almeshekah
 
An Introduction to the LEED Rating Systems
An Introduction to the LEED Rating SystemsAn Introduction to the LEED Rating Systems
An Introduction to the LEED Rating Systems
Allison Beer
 
مقدمة في الشبكات
مقدمة في الشبكاتمقدمة في الشبكات
مقدمة في الشبكات
Mostafa Gawdat
 
BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS Kak Yong
 

Viewers also liked (18)

أهمية الحاسب 1
أهمية الحاسب 1أهمية الحاسب 1
أهمية الحاسب 1
 
شبكات الإتصال والإنترنت
شبكات الإتصال والإنترنتشبكات الإتصال والإنترنت
شبكات الإتصال والإنترنت
 
Network Implementation and Support Lesson 10 Server Administration - Eric V...
Network Implementation and Support Lesson 10   Server Administration - Eric V...Network Implementation and Support Lesson 10   Server Administration - Eric V...
Network Implementation and Support Lesson 10 Server Administration - Eric V...
 
مكونات شبكات الحاسب الآلي Www.algeria pedia.info
مكونات شبكات الحاسب الآلي  Www.algeria pedia.infoمكونات شبكات الحاسب الآلي  Www.algeria pedia.info
مكونات شبكات الحاسب الآلي Www.algeria pedia.info
 
اقصاد المعرقة..
اقصاد المعرقة..اقصاد المعرقة..
اقصاد المعرقة..
 
الشبكات
الشبكاتالشبكات
الشبكات
 
شبكات الحاسب
شبكات الحاسبشبكات الحاسب
شبكات الحاسب
 
شرح شبكات الحاسب
شرح شبكات الحاسبشرح شبكات الحاسب
شرح شبكات الحاسب
 
بوربونت الشبكات
بوربونت الشبكاتبوربونت الشبكات
بوربونت الشبكات
 
شبكات و أمن المعلومات 2
شبكات و أمن المعلومات 2شبكات و أمن المعلومات 2
شبكات و أمن المعلومات 2
 
مفاهيم حول الشبكات
مفاهيم حول الشبكاتمفاهيم حول الشبكات
مفاهيم حول الشبكات
 
الدرس الأول: مفهوم الشبكات
الدرس الأول: مفهوم الشبكاتالدرس الأول: مفهوم الشبكات
الدرس الأول: مفهوم الشبكات
 
شبكات و أمن المعلومات 1
شبكات و أمن المعلومات 1شبكات و أمن المعلومات 1
شبكات و أمن المعلومات 1
 
عالم الشبكات
عالم الشبكاتعالم الشبكات
عالم الشبكات
 
أساسيات أمن المعلومات
أساسيات أمن المعلوماتأساسيات أمن المعلومات
أساسيات أمن المعلومات
 
An Introduction to the LEED Rating Systems
An Introduction to the LEED Rating SystemsAn Introduction to the LEED Rating Systems
An Introduction to the LEED Rating Systems
 
مقدمة في الشبكات
مقدمة في الشبكاتمقدمة في الشبكات
مقدمة في الشبكات
 
BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS
 

Similar to Integrate Early; Integrate Often

High Performance Building Design Workshop
High Performance Building Design WorkshopHigh Performance Building Design Workshop
High Performance Building Design Workshop
Jerry Yudelson
 
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Shanti Pless
 
Commercial Building Science - Comfortable Environments Through Sustainable De...
Commercial Building Science - Comfortable Environments Through Sustainable De...Commercial Building Science - Comfortable Environments Through Sustainable De...
Commercial Building Science - Comfortable Environments Through Sustainable De...
Safe Rise
 
Leadership in Energy and Environmental Design
Leadership in Energy and Environmental DesignLeadership in Energy and Environmental Design
Leadership in Energy and Environmental Design
Society of Women Engineers
 
Controlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build processControlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build process
Shanti Pless
 
Green Building 101 For Contractors
Green Building 101 For ContractorsGreen Building 101 For Contractors
Green Building 101 For Contractors
Sustainable Performance Institute
 
Cli Grp
Cli GrpCli Grp
The Green Buiding Debate
The Green Buiding DebateThe Green Buiding Debate
The Green Buiding Debate
Diaa El-Masry - PMP, LEED AP, GSAS CGP
 
Saving the Environment One Building at a Time
Saving the Environment One Building at a TimeSaving the Environment One Building at a Time
Saving the Environment One Building at a Time
Society of Women Engineers
 
Presentation green construction
Presentation   green constructionPresentation   green construction
Presentation green construction
Mukhtar Malik
 
Leed.2018
Leed.2018Leed.2018
Leed.2018
smithcindyk
 
Paths to Net-Zero Energy Sustainable Homes
Paths to Net-Zero Energy Sustainable HomesPaths to Net-Zero Energy Sustainable Homes
Paths to Net-Zero Energy Sustainable Homes
Derek Satnik
 
Green
GreenGreen
Trends in Green Kitchens and Green Buildings
Trends in Green Kitchens and Green BuildingsTrends in Green Kitchens and Green Buildings
Trends in Green Kitchens and Green Buildings
Derek Satnik
 
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in SustainabilityNewport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
American Society of Civil Engineers, Orange County Branch
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovations
saif hasan
 
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
the Environment Centre (tEC)
 

Similar to Integrate Early; Integrate Often (20)

High Performance Building Design Workshop
High Performance Building Design WorkshopHigh Performance Building Design Workshop
High Performance Building Design Workshop
 
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
 
Commercial Building Science - Comfortable Environments Through Sustainable De...
Commercial Building Science - Comfortable Environments Through Sustainable De...Commercial Building Science - Comfortable Environments Through Sustainable De...
Commercial Building Science - Comfortable Environments Through Sustainable De...
 
Leadership in Energy and Environmental Design
Leadership in Energy and Environmental DesignLeadership in Energy and Environmental Design
Leadership in Energy and Environmental Design
 
Controlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build processControlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build process
 
Green Building 101 For Contractors
Green Building 101 For ContractorsGreen Building 101 For Contractors
Green Building 101 For Contractors
 
USGBC LEED sheet Watertown 040411
USGBC LEED sheet Watertown 040411USGBC LEED sheet Watertown 040411
USGBC LEED sheet Watertown 040411
 
Cli Grp
Cli GrpCli Grp
Cli Grp
 
The Green Buiding Debate
The Green Buiding DebateThe Green Buiding Debate
The Green Buiding Debate
 
Saving the Environment One Building at a Time
Saving the Environment One Building at a TimeSaving the Environment One Building at a Time
Saving the Environment One Building at a Time
 
Presentation green construction
Presentation   green constructionPresentation   green construction
Presentation green construction
 
Leed.2018
Leed.2018Leed.2018
Leed.2018
 
Usgbc intro
Usgbc introUsgbc intro
Usgbc intro
 
Paths to Net-Zero Energy Sustainable Homes
Paths to Net-Zero Energy Sustainable HomesPaths to Net-Zero Energy Sustainable Homes
Paths to Net-Zero Energy Sustainable Homes
 
Green
GreenGreen
Green
 
Trends in Green Kitchens and Green Buildings
Trends in Green Kitchens and Green BuildingsTrends in Green Kitchens and Green Buildings
Trends in Green Kitchens and Green Buildings
 
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in SustainabilityNewport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
 
Julian_Carroll resume 2015 link
Julian_Carroll resume 2015 linkJulian_Carroll resume 2015 link
Julian_Carroll resume 2015 link
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovations
 
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
 

Recently uploaded

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 

Recently uploaded (20)

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 

Integrate Early; Integrate Often

  • 1.
  • 2. Integrate Early… Integrate Often! Success for a LEED Platinum Public Building
  • 3. Judi Cooper Deputy Executive Secretary Administrative Services Manager judi.cooper@iub.iowa.gov Shanna Olson LC Senior Lighting Designer olsonsl@kjww.com
  • 4. Scott Bowman PE, LEED AP BD+C Retired Principal and Sustainability Advisor bowmansc@kjww.com scottb@ideabuildworks.com Carey Nagle AIA, LEED AP BD+C Associate Principal cnagle@bnim.com Fellow
  • 6. LEARNING OBJECTIVES …learn how integrated design communication must be established and nurtured. …understand how integrated design with early analysis and goal setting can greatly affect the performance of a building. …engage and share with peers on the benefits and challenges of integrated design, and have fun in the process. …see actual examples of projects which achieved exemplary performance as a result of integrative design. Participants will . . .
  • 7. WHY? • Energy codes are advancing… • Sustainability standards are advancing… • Design constraints are increasing… • Owners budgets are constrained… • Owners expectations are higher… • Buildings and systems are more complex… • Communication tools have exploded… • Integrated Design is the way to address all these issues and more!
  • 8.
  • 9. © 2 0 1 2 B N I M
  • 10. A PROCESS FOR HIGH PERFORMANCE B++
  • 11. © 2 0 1 2 B N I M SIMPLE IDEAS AND PROCESS FOR ANY:
  • 13.
  • 14. © 2 0 1 2 B N I M
  • 15. Owners © 2 0 1 2 B N I M Design Professionals Government EVERY BUILDING
  • 16. Owner Consultants Iowa Energy Center Utility Companies State Legislature INTEGRATE = UNITE COLLABORATION + INTEGRATED DESIGN PROCESS
  • 19. IP CREDIT 102 INTEGRATIVE PROCESS New Credit – In HC too! Early “simple box” energy analysis Lists parametric options reviewed Includes water performance Requires cost analysis and bundling Reward for doing goal setting and analysis early! LEED 2009 Didn’t Exist LEED v4 IP102: Integrative Process CREDIT POINTS 1
  • 20.
  • 21.
  • 22. OWNERS PROJECT REQUIREMENTS The lowly, miss-understood OPR…
  • 23. OPR ACCORDING TO LEED • LEED v2009 – EAp1 – The owner must document the owner’s project requirements. The design team must develop the basis of design. The CxA must review these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
  • 24. OPR ACCORDING TO LEED • LEED v2009 – EAp1 – Reference Guide – The owner’s project requirements should detail the functional requirements of a project and the expectations of the building’s use and operation as they relate to the systems being commissioned.
  • 25. OPR ACCORDING TO LEED • LEED v2009 – EAp1 – Reference Guide – The owner’s project requirements should detail the functional requirements of a project and the expectations of the building’s use and operation as they relate to the systems being commissioned.
  • 26. OPR ACCORDING TO LEED • LEED v2009 – EAp1 – Reference Guide – Owner and User Requirements – Environmental and Sustainability Goals – Energy Efficiency Goals – Indoor Environmental Goals – Equipment and System Expectations – Building Occupant and O&M Requirements
  • 27. OPR ACCORDING TO LEED • LEED v4 – Integrative Process and Cx – Early Energy and Water analysis must be documented in OPR and BOD – More Requirements of documents: • Building and Site Program • Building Form and Geometry • Building Envelope and Façade • Other Systems
  • 28. WHAT IS THE BIG DEAL? • The OPR is the most under valued and under used document in the design process • Design teams MUST be on the same page and understand the Owners expectations • Integration starts with communication, but must include documentation and approval • Something other than meeting minutes needs to reflect objectives, goals and decisions
  • 29. OPR AS DESIGN TOOL • Embrace Integrated Design and Process • Create OPR as a collaboration of initial building and sustainability charettes • Focus on Owners goals and expectations • Expand way beyond energy and systems • Define required research or future decisions • Revise and update – living document!
  • 30. WHAT DOES THE OWNER WANT? • Meet an aggressive energy usage goal; • A replicable model building; • A comfortable, productive environment for staff/guests; • Viewed as a positive addition to the Iowa Capitol Complex; • A tour destination point; and • Stay on budget
  • 31.
  • 32. COMMUNICATION REPORT BACK What do you think INTEGRATED DESIGN means?
  • 33. HIGH PERFORMANCE PROCESS What is the right and proper way to reach high goals?
  • 34.
  • 36. Use Less • Reduce Loads • Passive • Envelope Use Efficiently • System Selection • High Efficiency Make On Site • Renewable Energy • Portal to Future
  • 37. Total EUI : 28.0 kBtu/sf/yr % Reduction from code base EUI 60% Model for other government & private sector entities LEED Platinum VISIONARY GOALS
  • 39.
  • 40. PROJECT COMPLETION DATE Jan. 17, 2011 LOT SIZE 6.06 acres BUILDING GROSS FLOOR AREA 44,640 sf BUILDING FOOTPRINT AREA 20,003 sf HOURS OF OPERATION 6:00 A – 5:30 P.M. BUILDING OCCUPANCY Permanent 90 x 44 Hours Visitors 20 Per Week x 4Hours TOTAL PROJECT COST $10,140,768 (Construction Costs) GENERAL PROJECT INFORMATION
  • 41. GROUND FLOOR PLAN 1 lobby 2 open office 3 enclosed office 4 meeting room 5 copy/work room 6 records information 7 hearing room 8 break room 9 receiving 10 files/storage 11 server room
  • 42. UPPER FLOOR PLAN 1 lobby 2 open office 3 enclosed office 4 meeting room 5 copy/work room 6 records information 7 hearing room 8 break room 9 receiving 10 files/storage 11 server room
  • 43.
  • 44. “The team saw that the impact of their work was bigger than just the building. It was to set an example for other government buildings.” JURY MEMBER 2012 AIA COTE TOP TEN PROJECTS SELECTION COMMITTEE
  • 45.
  • 46.
  • 47.
  • 48.
  • 49. “The reason we exceeded our [performance] goal is because the occupants understood what we were trying to do from the top down [O] we walked in the door with a set of protocols that we all helped to develop and understood. We don’t plug in superfluous loads. We function with daylight. With the systems that are there— the geothermal, the photovoltaics — there are times when the building is producing more than we are using and sending it back to the State Capital Complex.” JUDI COOPER DEPUTY EXECUTIVE SECRETARY | IUB-OCA
  • 50.
  • 51.
  • 52.
  • 53. “Young people are aware of [this building] and excited by it. I’ve taken unsolicited phone calls from high school students saying, I see your new building on the Capital complex. Can I come and see it? And I say, Of course you can! I take them on a tour. I’ve taken teachers, architecture students, people from around the world. They are aware of it, and I am excited by what they will do when they are the ones out there designing like this.” JUDI COOPER DEPUTY EXECUTIVE SECRETARY | IUB-OCA
  • 54.
  • 55.
  • 56. WATER STRATEGIES 1 rain garden 2 sediment basin 3 water infiltration basin 4 pervious pavement 5 offsite storm diverter 6 bioswale 7 on-street parking (minimizes impervious surface)
  • 57.
  • 58.
  • 59. ENVELOPE How do we keep the outside out, and the inside in?
  • 60.
  • 61. REPLICATION INNOVATION • Good Thermal Envelope • Cost Effective Precast • Thermal Bridging Mitigation • Non-Conductive Precast System • Material Duality ENVELOPE 1 continuous thermal and air barriers at construction interfaces 2 thermomass precast concrete wall system 3 zinc cladding 4 cool roof 5 Daylight harvesting sunscreen 6 green wall
  • 62. REPLICATION INNOVATION • Operable Windows • Weather Station • Building Automation System Alert • Systems Tie-In • Cost Effective NATURAL VENTILATION 1 operable exterior windows 2 weather sensor measuring temperature, humidity, wind speed, and direction 3 weather station alerts occupants to open and close windows 4 mechanical system shuts down when windows are open
  • 63.
  • 64. Material Duality, structural systems as finish systems Agrifiber, a rapidly renewable and regionally sourced material, was used for the door cores Furniture achieves Cradle-to-Cradle certification or equivalent standard Low V.O.C. materials used throughout All furniture within the project is Greenguard certified at a minimum
  • 65. 35% of total material content was recycled 67%of materials were regionally extracted, harvested and fabricated 96% of wood used was Forestry Stewardship Council certified, hence responsibly harvested 89% of construction waste was recycled
  • 66. HEATING VENTILATION AND AIR CONDITIONING The physiological manifestation of well being…comfort!
  • 67. Courtesy PNNL ASHRAE 90.1-2013 ASHRAE 90-1975 ASHRAE 90A-1980 ASHRAE 90.1-1999 ASHRAE 90.1-2001 ASHRAE 90.1-2007 ASHRAE 90.1-2004 ASHRAE 90.1-1989 ASHRAE 90.1-2010 Improvement in ASHRAE Standard 90.1 (Year 1975 – 2010)EnergyUseIndex(1975Use=100) Year 1970 1975 1980 1985 1990 50 1995 20152000 20102005 110 100 90 80 70 60
  • 68. ENERGY MODELING • Key to High Performance • Important to understand interaction • Many approximations – manage expectations • Know limits of software • Understand gross assumptions! • Move from isolated evaluations to bundling • Set early goals – Measure against them often!
  • 69. Energy Use Basis Baseline – 72.5 kBtu/sf 23% Heating Cooling Fan/Pump Lights Plug Load DHW 44% Data Courtesy of The Weidt Group
  • 70. Energy Use Basis Design – 27.3 kBtu/sf Heating Cooling Fan/Pump Lights Plug Load DHW Data Courtesy of The Weidt Group 15% 21%42%
  • 71. Actual – 21.2 kBtu/sf Energy Use Basis Heating Cooling Fan/Pump Lights Plug Load DHW Data Courtesy of The Weidt Group 18% HEATING 11% COOLING 24% FAN/PUMP 20% LIGHTS 26% PLUG LOAD
  • 72. Energy Use Basis Heating Cooling Fan/Pump Lights Plug Load DHW Data Courtesy of The Weidt Group 18% HEATING 11% COOLING Actual – 16.7 kBtu/sf 24% FAN/PUMP 20% LIGHTS 26% PLUG LOAD with Renewable (PV)
  • 73. Why kBtu/sf? • ASHRAE currently uses energy cost • Dollars reflect some local energy utilization and market conditions • Suppressed sources can obscure signals – Natural Gas – Renewable Energy (Wind or Solar) • Need to measure true performance • Location, Location, Location – 28 kBtu/sf means something in Iowa – What about Portland?
  • 74. REPLICATION INNOVATION • Passive Strategies • Geothermal • Energy Recovery • Occupancy Sensors Per Workstation • Demand Controlled Ventilation • Building Automation System • Photovoltaic Panels ENERGY STRATEGIES 1 geothermal system 2 photovoltaic roof panels 3 occupancy sensors for lighting and plug load reduction at each work station and office 4 stormwater filtered and infiltrated on site 5 continuous monitoring of all systems 6 perimeter radiant heating
  • 75. 19.1% of Building Energy Use RENEWABLE ENERGY
  • 76.
  • 77. DAYLIGHTING AND LIGHTING What do you mean gas lamps are good anymore?
  • 78. DAYLIGHT HARVESTING GOALS Create a balance between potential energy reduction through enhanced daylight and reduced heat gain
  • 79. Sunscreen Conditions summer winter 1 diffuse northern daylight 2 light tubes 3 daylight harvesting sunscreen 4 light sensors 5 daylight responsive artificial lighting 6 interior glazing transmits daylight 7 exterior view throughout DAYLIGHTING STRATEGIES
  • 80.
  • 81.
  • 82.
  • 83. • Feel of the space • Energy goals • Energy code • LEED • Light levels • Comfort with technology • Initial • Simple payback • Life cycle cost Budget User’s needs AestheticsEnergy LIGHTING DESIGN PROGRAMMTIC GOALS
  • 84. IUB/OCA – LIGHTING DESIGN Mix of design techniques and lamp sources
  • 85. IUB/OCA – LIGHTING DESIGN Mix of design techniques and lamp sources
  • 86. IUB/OCA – LIGHTING DESIGN Mix of design techniques and lamp sources
  • 88. Linear LED Linear Fluorescent Life 50-100,000 hrs + 24-87,000 hrs Efficacy/ Efficiency Varies widely Varies widely Standard control Typically 0-10v standard Typically switching standard Optical qualities Point source/ lenses used to create ambient optics, quality ranges Ambient source CCT/ CRI 2700-6500/65-90 2700-5000/ 75-90 Cost 1.1-3 1 SDCM/ MacAdam’s step 7 step min 4 step min Replacement cost and availability Unknown Known & varies by lamp LED V. FLUORESCENT
  • 89. WHITE LIGHT EFFICACY PROJECTIONS
  • 90. Who will determine when LED’s need to be replaced? How much will it cost to replace? IMAGE SOURCE: maxlite.com Will the replacement parts provide the same lumen output and color quality? IES LM-80 & TM-21 have been adopted to define LED life and lumen maintenance APPLICATION CONSIDERATIONS What does end of life mean for an LED?
  • 92. TRADITIONAL SOURCES SOLID STATE INITIAL COST LAMP LIFE DIFFERENCE LINEAR FL EVERY FEW FEET’ (SEVERAL HUNDRED WATTS) 6 TO 10 FIXTURES 300 TO 500 WATTS UNKNOWN . 24-87,000HRS TO 50,000HR 126/270/ 480 WATTS DEPENDING ON SCALE 100/180/350 WATTS DEPENDING ON SCALE MINIMAL COST DIFFERENCE 12,000HRS TO 50,000HRS COMPARISON
  • 93. APPLICATION CONSIDERATIONS What is white light and why does it matter?
  • 94. IUB/OCA OUTDOOR LIGHTING Use of LED for all sources
  • 96. APPLICATION CONSIDERATIONS How do exterior lamp source options compare today?
  • 97. LAMP TYPE WATTS PER SQ FOOT COST DIFFERENCE LIFE CONTROL CMH 37800 NOM 77% EFFICIENCY 29080DELIVERED 338 WATTS .292 WATTS PER SQ FT AT ABOUT 18FC ~ 30,000 HRS 0-10V DIMMING LED 412w 30,000 LUMEN .311 WATTS PER SQ FT AT ABOUT 18FC ABOUT 15% MORE L90 AT 60,000 HRS BI-LEVEL OR 0-10V DIMMING W/ OCCUPANCY SENSOR CURRENT EXTERIOR LAMP SOURCE OPTIONS
  • 98. • Feel of the space • Energy goals • Energy code • LEED • Functionality requirements • Comfort with technology • Initial • Simple payback • Life cycle cost Budget User’s needs AestheticsEnergy CONTROLS PROGRAMMTIC GOALS
  • 99. CURRENT AND PROJECTED CODE STATUS PER STATE
  • 100. IUB/OCA LIGHTING CONTROLS INTEGRATION Networked 0-10v & switching protocols with Daylight Harvesting
  • 103. NETWORK CONTROL SYSTEMS Digital Addressable Lighting Interface (DALI)
  • 104. Typically Saves the Most Energy in the Long Run Typically Requires More Knowledge to Maintain Maximizes Controllability Typically More Expensive Convergence Requires Greater Coordination in Design and Construction Long Term Flexibility Two Way Communication Pro’s Con’s DIGITAL ADDRESSABLE LIGHTING INTERFACE DALI PROTOCOLS
  • 105. CONVERGENCE How do we bring things together?
  • 106. CONTROL INTEGRATION • Integrated control systems – Lighting – AV – Shades – HVAC – Security – Receptacle
  • 108. • 50% of all receptacles shall have automatic shutoff in: Open offices Private offices Computer classrooms • Accomplished in one of three ways Ceiling or wall vacancy sensor Relay panel with time clock Plug in occupancy sensor MAY NOT BE ALLOWED BY AHJ ASHRAE 2010 RECEPTACLE CONTROL
  • 109. PLUG LOAD CONTROL Data Courtesy of The Weidt Group Model = 0.90 w/sf Metered = 0.25 w/sf
  • 110. OPERATIONS Now I get to run what you designed…but my reality has shifted!
  • 111. PROTOCOLS • Iowa’s Green Government Initiative • Ensure importance of goal is communicated • Solicit buy in – “All In” • Have clear behavioral expectations • Automated building features make is easy • Live it out – No superfluous load Lay the Groundwork
  • 112.
  • 113. BYOB
  • 118. Energy Monitoring LEED Measurement & Verification Electrical Circuits Monitored • Lighting • Plug Loads • Mechanical Equipment • General Building Loads • IT Equipment Geothermal Loop Data Collected by Capitol Complex Energy Management System
  • 119. Energy Star = 100 MEASUREMENT AND VERIFICATION Second Year M&V Results: • Design Estimated Model EUI – with PV 28.1 • Monitored EUI – with PV 16.7 • Monitored EUI – without PV 21.2 Conclusions: • Model over predicted pumping energy • Model slightly over predicted lighting savings • Plug loads are significantly lower than expectations • Corrected energy model tracks actual use well
  • 121. TAKEAWAYS • Integrative Design leads to High Performance • Use the OPR as a design tool • Collaboration of envelope to lighting is key • Energy modeling should be early and often • Measure against goals for key decisions • Plug load management is new horizon Important concepts we wanted to emphasize…
  • 122. QUESTIONS …understand how integrated design communication must be established and nurtured. …realize integrated design with early analysis and goal setting can greatly affect the performance of a building. …have seen the benefits and challenges of integrated design, and had some fun in the process. …know of actual examples of projects which achieved exemplary performance as a result of integrative design. Learning objectives you should…
  • 123. AWARDS AND RECOGNITIONS • AIA Committee On The Environment Top 10 Green Building Award 2012 Top 10 Plus in 2014 • ASHRAE Technology Award Second Place in 2014 • AIA Central States Region Merit Award • AIA Iowa Merit Award • Des Moines’ Environmental Impact Awards Built Environment Award
  • 126. Integrate Early… Integrate Often! Success for a LEED Platinum Public Building