SlideShare a Scribd company logo
REPAIR AND RETROFITTING OF
   MASONRY STRUCTURES




             EFFORTS BY:
             ABHISHEK BHATT      (0506)
             ANTARA MASHRUWALA   (1706)
             DISHITA SHAH        (3006)
             RAVI SONI           (5207)
Objective:
        To study different repair materials and techniques to be
adopted in various situation to repair defective structures of brick
and stone masonry.

Repairs: Process to replace or correct deteriorated/damaged
materials and components of a building.

Retrofitting: Upgrading of structural and non-structural systems to
provide a higher level of resistance than existed before .
HOW DAMAGE OCCURS IN BRICK-MASONRY STRUCTURES:

Effect of Aging on Brick-Work:

  Rain Exposure
  Temperature
  Moisture Absorption
  Chemical Alteration
  Continuous Exposure to Chemicals

 Construction   Error:

  Eccentrically Loaded Walls gives overturning effect (Decorative Panels on one
  side, Support of Working platforms on one side)

  Usage of Poor quality of materials

  Error due to saving in economy
Maintenance:

Common maintenance to brick is to white wash or to paint them at regular
intervals, preferably every 2 years.

To maintain all sanitary installation in a good condition, any leakage notice
anywhere should be intended to immediately, since a small leakage from nani-
trap would lead to a major damage in due course.

Any cracking wherever noticed should be attended immediately either by
sealing the joints with cement mortar or by strengthening the cracks with
reinforced bands.
TYPES OF CRACKS IN MASONRY STRUCTURES:
1.Vertical cracks in sidewalls at corner
2.Vertical cracks around balconies
3.Vertical cracks below the openings in line with the window jambs.
4.Vertical cracks at the junction of RCC column and masonry wall.
5. Vertical cracks in the top most stories at corners of structures having RCC slab.
6.Horizontal cracks at window lintel or sill level in the top most story.
7.Horizontal cracks in the top most story below the RCC slab level.
8. Horizontal cracks at eaves level in the buildings having pitched roof with wooden
joists and purlins.
9. Random cracks in all directions involving both external and internal walls.
10. Diagonal cracks over RCC lintels spanning large openings.
11. Shrinkage cracks.
TYPES OF CRACKS IN MASONRY STRUCTURES:




 Typical Earthquake       Typical Earthquake     Wall Cracking above the
Damage - Wall Corner     Damage: In-Plane Wall    Door Opening (1993
 Failure (1993 Killari         Cracking            Killari Earthquake)
     Earthquake)
GENERAL CAUSES TO DEVELOP THE CRACKS:
Poor quality of bricks.
For masonry work,use the porous stones.
Absence of grading in before the use of fine aggregate fine mortar.
If percentage of clay and silt in fine aggregate exceed 3 percent.
Due to the excessive amount of soluble sulphate.
Plumb alignment.
The position of the element in the structure.
Differential loading.
Weak mortar.
Insufficient bond.
Improper curing.
Entered dampness from ground, roof and exterior faces.
High daily temperature variations.
Atmospheric pollutions.
Lack of strength at corner and at junction of walls.
Improper binding of thick walls.
REPAIR TECHNIQUES

Sand / Cement Mortar:
It is the most simplest and basic repair method. It is highly reliable but may fail
under severe drying conditions.
Thus cracks will appear as a result of shrinkage in the plastic state of mortar.
Due to this shrinkage, debonding and delaminating frequently occurs.
Due to high water cement, ratio strength decreases.
High density of pores and capillaries allow water and acidic vapours to more easily
penetrate the repair and attack to the reinforcement bars.

Polymer modified cementations mortars:
Polymer modified cementitious mortars are factory controlled blend of specially
graded fillers, cement and admixtures to control strength development in set time. To
reduce the shrinkage they contain polymers to improve the low permeability, quality
and to enhance adhesion.
The thermal expansion properties are similar to normal concrete.
Heat development is low so much larger volume repairs can be undertaken.
Low impermeability can prevent ingress chlorides.
Epoxy resin mortars:

Epoxy technology is based on the mixing of two liquid resins which
react together to form a hard solid if aggregates are added the resin system
acts to bind them together to create mortar.
Achieves compressive strength of 60-80 N/mm2 and very heavy high
flexural strength.
Due to good adhesion repair will never fail along correctly prepared
bond line.
More strength gain occurs in one day in normal atmospheric conditions.
Properly compact mortar is impermeable to water.
Most epoxy mortar requires primer.
Epoxy injection:


Narrow     cracks of 0.05 mm cracks are repaired by this method.

High     strength, highly viscous material can be achieved.

In   this, holes are drilled at closer interval repairs are done under external force
through pumps or greasing guns.

Normal     pressure should be of 1 kg/cm2.We should not apply too much
pressure which propagates the cracks.

High     degree of skills and executions are required to repair these types of
cracks.
Crack stitching:

This method involves drilling holes on both sides of crack and grouting in

stitching dogs.

Stitching may be used when the tensile strength must be re-established

across major cracks.

Stitching a crack tends to stiffen the structure, causing the concrete to

crack elsewhere. therefore it may be necessary to strengthen the adjacent

section with external reinforcement.
METHOD FOR ADVANCE RETROFIT TECHNIQUE WITH
HELICAL REINFORCEMENT

     Firstly slots are cut with cutter machine of length 500 mm on each side of crack.
1.
     The depth of slot is 10 mm but it also depends on the plaster surfaces.




     Clear loose detritus from slots ensuring exposed brick surfaces are cleaned of
2.
     mortar and flush thoroughly with water, or treated with a suitable primer.




3.   Now fill the slot with grout with pressure.



     Push Helical 6mm reinforcement crack stitching tie into grout to approximately
4.
     two thirds of slot depth.


     Finish the surface and repair the crack on the wall with appropriate filler /grout
5.
     chemical.
Tuck pointing:

 Defective joints can usually be repaired by tuck-pointing with Portland cement
  mortar, with the help of skilled stonemason
 In this method, all joints, vertical and horizontal, in the face of the wall should be
  tuck-pointed.
 This procedure requires removing and replacing all mortar to a depth of at least
  16mm throughout every joint. each joint is raked to a depth not greater than
  26mm unless the old mortar is so defective then it is necessary to remove the
  mortar up to greater depth.
 The depth of old mortar is removed first so that sound mortar acts as a base for
  new mortar.
 All dust and dirt within the raked joints should be washed out.
 The mortar is mixed at least 1 hour prior to use to ensure pre-hydration which
  stabilizes the plasticity and workability of mortar and minimizes any tendency to
  shrink after insertion into the joint opening.
 The sand/cement ratio should be about 3 to 1 by volume.
TUCK POINTING
Grouting (cement mortar):

Masonry structures can be sealed effectively with less cost by using grout
provided the cement-base stabilizing mixture contains an intrusion aid.
The consistency of intrusion mixture is that of smooth slurry.
Before the intrusion, grout is pumped, the holes are tested by pumping
water to see the drilling is adequate and to determine correct consistency
for the slurry repairs.
Firstly plaster is removed near the cracks from inside and outside of
walls and clean the cracks thoroughly with airjet and water.
Wet the cracks ,if dry ,by sprinkling water.
This mixture is pumped into holes previously drilled at various interval
to various depths without damaging the integrity of structure.

Pumping the grout simultaneously into multiple series of drill holes
ensures good penetration into any fissures within the structure and for
making masonry structures watertight.
Grouting (chemical):

 Chemical grouts consist of solution of two or more chemicals (such as
  urethanes, sodium silicate) that react to form a gel. This grout opposed
  to cement grouts that consist of suspension of solid particles in a fluid.

 Advantages of chemical grout include applicability in moist
  environment and their ability to be applied in very fine facture.

 Disadvantage is high degree of skill needed for satisfactory use and their
  lack of strength.

 Crack as narrow as 0.05 mm can been filled with chemical grout.
Polymer coating:

 Polymer coating is use for the job condition and can be an
  effective protective coating if properly applied.

 Polymer coating should be selected from the material specifically
  for the intended application.

 Some formulation will adhere to damp surfaces and even under
  water but may required a completely dry surface.

 Mixing and applying polymers below 16 degree and above 32
  degree Celsius will require special caution and procedure.

 Moisture passing through the sub grade backfill or from
  rainwater can accumulate under the coating, which will be
  interrupted by freezing and thawing.
REPAIR MATERIALS
Epoxy resins
    Epoxy resins are excellent binding agents with high tensile strength. The
     epoxy components are mixed just prior to application. The product is of low
     vis­cosity and can be injected in small cracks too.
    The higher viscosity epoxy resin can be used for surface coating or filling
     larger cracks or holes.
Epoxy mortar
    Epoxy resins when combined, with sand aggregate it forms epoxy mortar.
     Epoxy mortar mixture has higher compressive strength, higher tensile
     strength and a lower modulus of elasticity than Portland cement concrete.
Quick-setting cement mortar
    It is a non-hydrous magnesium phosphate cement with two components, a
     liquid and a dry, which can be mixed in a manner similar to portland cement
     concrete.
Gypsum cement mortar
    It has lowest strength at fail­ure among these three materials. So it is used in
     minor repair works in structural application.
Mechanical anchors
    Mechanical anchors provide both shear and ten­sion resistance. Such anchors
     are manu­factured to give sufficient strength.
RETROFIT:
         Post earthquake improvement of the seismic resistance of
 a structure including repair of damage . Upgrading of structural
 and non-structural systems to provide a higher level of resistance
 than existed before the earthquake.



SURFACE TREATMENT:

Surface treatment is a common method, which has largely
developed through experience.

Surface treatment incorporates different techniques such as
ferrocement, reinforced plaster, and shotcrete.
FERROCEMENT:

Ferrocement consists of closely spaced multiple layers of hardware
mesh of fine rods
(Figure 1 (a)) with reinforcement ratio of 3-8% completely embedded
in a high strength (15-30 MPa) cement mortar layer (10- 50 mm
thickness).
The mortar is troweled on through the mesh with covering thickness
of 1-5 mm.
Typical mortar mix consists of 1 part cement: 1.5-3 parts sand with
approximately 0.4 w/c ratio.
REINFORCED PLASTER:

A thin layer of cement plaster applied over high strength steel reinforcement
can be used for retrofitting.

The steel can be arranged as diagonal bars or as a vertical and horizontal
mesh.

In diagonal tension test and static cyclic tests, the technique was able to
improve the improvement in strength depends on the strengthening layer
thickness, the cement mortar strength, the reinforcement quantity and the
means of its bonding with the retrofitted wall, and the degree of masonry
damage.
SHOTCRETE:
 Shotcrete overlays are sprayed onto the surface of a masonry wall over a mesh
  of reinforcing bars.
 In shotcrete the size of coarse aggregate is limited to 6mm.
 With thorough mixing of aggregates and adjustment of pressure at the nozzle
  should be controlled otherwise a large proportion of coarse aggregate is lost in
  rebound.
 Due to greater wear of nozzles during shotcrete there is a tendency to reduce the
  proportion or even eliminate coarse aggregates.
 Certain additives are available which can reduce wear and tear of nozzles.
 After shotcreting proper curing is essential.
 In situation where heavy construction machinery can not be moved or is not
  economically viable, manual shotcreting can also be resorted too.
 In manual method layers of concrete can not exceed 35-40 mm in thickness
  when laid.
 Mason should be trained properly to move the trowel applying vibrations and
  simultaneously for compacting effect on each layer.
 Non destructive testing of shotcrete repair work should be carried out.
GROUT AND EPOXY INJECTION:
 PROCESS :
 The crack or joint should be widen wherever the injection work is to be carried out
  (approximately 15 mm wide x 15 mm depth)
 Drill holes of about 13 mm dia upto 150 mm deep at 500 mm @ c/c.
 Use compressed air to clean the hole, as well as crack to remove dust, dirt, loose
  materials etc.
 Use 12 mm dia specially threaded injection nipples and fix them into the holes
  provided. Seal the entire surface around the nipple with putty.
 Seal the surface of the crack with putty so as to ensure that the injected grout does
  not leak from the gaps & from cracked surface.
 The surface now is ready for injection.
 Prepare the injection grout and load it into the injection gun.
EXTERNAL REINFORCEMENT:

A steel plates or tubes can be used as external reinforcement for existing
Unreinforced Masonry(URM) buildings.

Steel system is attached directly to the existing diaphragm or wall.

Two vertical members (via pin connections), which are placed next to the
existing wall (i.e. creating in-fill panel) can be used.
CONFINING URM USING R.C. COLUMNS:
 Confined masonry with R.C., weak frame represents one of the most widely
  used masonry construction system in Asia and Latin America.
 In China, they used such confinement in new masonry buildings as well as it is
  used as retrofitting for existing URM buildings.
 The basic feature of confined masonry structures is the vertical R.C. or
  reinforced masonry tie columns, which confine the walls at all corners and wall
  intersections as well as the vertical borders of doors and windows openings.
 In order to be effective, tie columns should connect with a tie beam along the
  walls at floors levels.
POST TENSIONING:
Post-tensioning involves a compressive force applied to masonry wall; this force
counteracts the tensile stresses resulting from lateral loads.

There has been little application of this technique; post-tensioning is mainly used
to retrofit structures characterized as monuments.

This is due in part to lack of knowledge about the behavior of post-tensioning
masonry.

In addition, the codification of post-tensioning masonry has only begun recently.
(Contd…..)POST TENSIONING:
Post-tensioning tendons are usually in the form of alloy steel thread bars.

Bars typically show higher relaxation losses (2-3 times strand losses) and much
lower strength/weight ratio (VSL 1990); in addition, a major drawback for using of
steel bars is corrosion. Fiber reinforced plastic presents a promising solution for this
problem

Tendons are placed inside steel tube (duct) either within holes drilled along the
midplane of the wall or along groves symmetrically cut on both surfaces of the wall.

Holes are cement grouted and external grooves are filled with shotcrete.
GROUT OR EPOXY INJECTION IN
CRACKS

1 - Plaster removed

2 - Cracks sealed after cleaning

3 - Grout ports




Strengthening of existing
masonry

1 - Brick or block wall

2 - Injection holes

3 - Grout mixture
STRENGTHENING WITH WIRE MESH AND MORTAR
STRENGTHENING WITH WIRE MESH
Two steel meshes (welded wire fabric with an elementary mesh of approximately 50 x 50 mm)
are placed on the two sides of the wall, they are connected by passing steel each 500 to 750 mm
apart, A 20 to 40 mm thick cement mortar or micro concrete layer is then applied on the two
networks thus giving rise to two interconnected vertical plates. This system can also be used to
improve connection of orthogonal walls.

                                                       1 - Welded wire mesh - 50 mm x 50 mm

                                                       2 - Mortar or micro-concrete rendering

                                                       3 - Concrete roof band

                                                       4 - Cross ties at 500 to 750 mm apart

                                                       5 - Corner bar diameter 8 mm
              3




       CORNER REINFORCEMENT
For Large cracks and crushed concrete
             For cracks wider than about 6 mm or for regions in which the concrete or masonry has crushed, a
treatment other than injection is indicated. The following procedure may be adopted.
The loose material is removed and replaced with any of the materials mentioned earlier, i.e., expansive
cement mortar, quick setting cement or gypsum cement mortar.




                                                                     Strengthening of existing
                                                                     masonry
                                                                     1 - Wire mesh on front face

                                                                     2 – Clamps

                                                                     3 - Wire mesh on back face

                                                                     4 - Cement plaster

                                                                     5 - Crack in wall
Splint and bandage strengthening technique

                                  The technique of covering
                                  the wall with steel mesh
                                  and mortar or micro-
                                  concrete may be used only
                                  on the outside surface of
                                  external walls but
                                  maintaining continuity of
                                  steel at the corners. This
                                  would strengthen the walls
                                  as well as bind them
                                  together. As a variation and
                                  for economy in the use of
                                  materials, the covering
                                  may be in the form of
                                  vertical splints between
                                  openings and horizontal
                                  bandages over spandrel
                                  walls at suitable number of
                                  points.
Splint and bandage strengthening technique
NEGLIGENCE AFTER REPAIRS AND RETROFITTING

 No.          Negligence                             Reasons
  1    Hair cracks are found on lack of curing after 4 hours from the application
       the all ready strengthened               of cement mortar.
         brick masonry walls.



  2    Weld mesh are soon on the     improper thickness of the cement mortar
        brick masonry walls after
              finishing coat.

  3    Uneven plaster surface are   works are going on without preparing proper
          found on the wall.                       level markers.

  4    Different shades are found     Improper mixing of cement with other
          on plastered surface.          materials and improper curing
CASE STUDY : JABALPUR EARTHQUAKE


• PHOTOGRAPHS OF DAMAGE DUE TO EARTHQUAKE

• STRENGTHNING OF EXISTING CONSTRUCTION

• STRENGTHNING OF NEW CONSTRUCTION

• PHOTOGRAPHS OF NEW CONSTRUCTION AFTER
  EARTHQUAKE
JABALPUR EARTHQUAKE DAMAGED NUILDINGS




Partial Building Collapse in the   Faillure of Brick Masonry Walls in
1997 Jabalpur Earthquake           the 1997 Jabalpur Earthquake
STRENGTHENING OF EXISTING CONSTRUCTION

                                                     Description of Seismic Strengthening provisions
                  Seismic Deficiency
                                                                          used
Lack of integrity (box-type action)                Installation of seismic belt (bandage) at the lintel level; it
                                                   consists of welded wire mesh installed above the lintel
                                                   level and anchored to the wall. The mesh is covered with
                                                   a thin cement plaster overlay (see Figure a) 

Cracks in the walls                                In case of small cracks, pressure injection of epoxy
                                                   grout; in case of large cracks, filling the gaps with
                                                   cement grout and jacketing with reinforced cement
                                                   overlay.
Inadequate wall resistance (shear and tensile)     Reinforced concrete jacketing. Difficult to find skilled
                                                   labor and materials for welded wire mesh in rural areas 

Flexible floor/roof diaphragm (Corrugated metal    Installation of RC roof band (bond beam). Provision of
sheets/timber)                                     roof band is expected to enhance the overall intergrity
                                                   and improve torsional resistance of building 
Cracking/damage of wall corners (due to improper   Corner strengthening of wall corners - installation of
interlocking of cross walls)                       welded wire mesh anchored to the walls with steel
                                                   dowels and covered with a thin cement plaster overlay ,
                                                   see Figure b. 
FIGURE A   FIGURE B
STRENGTHENING OF NEW CONSTRUCTION


                                 Description of Seismic
   Seismic Deficiency
                             Strengthening provisions used
                        Reinforced concrete roof band; provision of roof band
          Roof 
                        results in an improved overall integrity and torsional
                        resistance of the building. 


                        RCC lintel band; very effective, however skilled labour
          Wall 
                        and materials may not be available, see Figures 7D, 7E
                        and 7F 

                        Improved quality of masonry (bricks and mortar) use of
          Wall 
                        better quality bricks will drastically improve the wall
                        seismic resistance; use or richer cement/sand mortar will
                        improve wall shear resistance. 


                        Provision of vertical reinforcement at wall corners and
          Wall 
                        intersections, see Figure 7G (Source: IAEE 1986) 
7D-An Example of New Construction with                7E-Construction of RC lintel
  Seismic Features (note RC lintel band)                        band




                      7F-Construction of RC Lintel Band - Pouring of
                                   Concrete Completed
7G-Provision of Vertical
Reinforcement at Wall
Corners and
Intersections
CONCLUSION



 Cost   effective and safer approach will be to carry out appropriate repair and
  retrofitting of the building.

 It   will offer the advantage of carrying out the work part by part or room by room
  so that the occupants may continue to live in the building during the repair and
  retrofitting work .

 By   doing so the cost of repair and retrofitting came to only 8 % of the estimated
  cost of reconstruction.
REFERENCES:

   Civil Engineering & Construction Review (Vol.14 Dec.2001)
   Structural Consolidation & Strengthening of masonry (Department of
    Civil Engineering, Belgium)
   13th International Brick & Block masonry Conference
   Deterioration & Damages in Buildings, Department of Civil
    Engineering, IIT, Kharagpur
   Jabalpur & Killari earthquake Damage reports & Retrofitting Method,
    Department of Civil engineering, IIT, Kanpur
QUESTION FROM OUR PRESENTATION

   Why cracks or deteriorations occurs in brick masonry
    structures? State any 6 techniques by which it can be
    repaired? Explain any one in detail with neat sketches.
Group 2 brick masonry- 0506,1706,3006,5207

More Related Content

What's hot

Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
Madan Mohan Jana
 
Precast construction
Precast constructionPrecast construction
Precast construction
Divya Vishnoi
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
padamatikona swapnika
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
toshi gupta
 
cladding
claddingcladding
cladding
Barsha
 
Ferrocement
FerrocementFerrocement
Ferrocement
Prabhat chhirolya
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
Abhishek Gupta
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall system
bee_by
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
ANKITAARORA85
 
Cladding
CladdingCladding
Cladding
AyeshaBukhari11
 
Construction defects
Construction defectsConstruction defects
Construction defects
shivam tomar
 
FALSE CEILING
FALSE CEILINGFALSE CEILING
FALSE CEILING
Shashikant Jadhav
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
Grace Henry
 
Partition walls
Partition wallsPartition walls
Partition walls
Momina Ghayas
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
abidha karthu
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
JenilPatel22
 
STAIRS 1
 STAIRS 1 STAIRS 1
STAIRS 1
Abhishek Mewada
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
Shailja km
 
Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
Saurav Chaudhary
 

What's hot (20)

Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
 
cladding
claddingcladding
cladding
 
Ferrocement
FerrocementFerrocement
Ferrocement
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall system
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Cladding
CladdingCladding
Cladding
 
Construction defects
Construction defectsConstruction defects
Construction defects
 
FALSE CEILING
FALSE CEILINGFALSE CEILING
FALSE CEILING
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
Timber floor
Timber floorTimber floor
Timber floor
 
Partition walls
Partition wallsPartition walls
Partition walls
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
STAIRS 1
 STAIRS 1 STAIRS 1
STAIRS 1
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 
Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
 

Similar to Group 2 brick masonry- 0506,1706,3006,5207

Repairing of masonry structures
Repairing of masonry structuresRepairing of masonry structures
Repairing of masonry structures
Dhaval Jalalpara
 
type of Cracks in building and its repair
type of Cracks in building and its repairtype of Cracks in building and its repair
type of Cracks in building and its repair
basilesho2
 
Good construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACCGood construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACC
Keto Diet Active
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
jay Rathod
 
presentation on retro fit and repair methods
presentation on retro fit and repair methodspresentation on retro fit and repair methods
presentation on retro fit and repair methods
KumarS250747
 
Various methods for repair and rehabilitation for concrete structure failure
Various methods for repair and rehabilitation for concrete structure failureVarious methods for repair and rehabilitation for concrete structure failure
Various methods for repair and rehabilitation for concrete structure failure
Constrofacilitator
 
Retrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structureRetrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structure
KumarS250747
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
Kiran Hadiya
 
Types of crack-Amit Payal
Types of crack-Amit PayalTypes of crack-Amit Payal
Types of crack-Amit Payal
AMIT PAYAL
 
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptxREPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
BasineniUdaykumar
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding material
Constrofacilitator
 
Rebuild
RebuildRebuild
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketing
Aditya Sanyal
 
Building crack,types,causes & its repairing
Building crack,types,causes & its repairingBuilding crack,types,causes & its repairing
Building crack,types,causes & its repairing
GAUTAMSWALA
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
Ishwar Chauhan
 
cracks.pptx
cracks.pptxcracks.pptx
cracks.pptx
BinnySidhu
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structures
KumarS250747
 
Litterature study on building failures
Litterature study on building failures Litterature study on building failures
Litterature study on building failures
Ar v chiru
 
Cavity Walling
Cavity WallingCavity Walling
Cavity WallingDjCurrie
 

Similar to Group 2 brick masonry- 0506,1706,3006,5207 (20)

Repairing of masonry structures
Repairing of masonry structuresRepairing of masonry structures
Repairing of masonry structures
 
type of Cracks in building and its repair
type of Cracks in building and its repairtype of Cracks in building and its repair
type of Cracks in building and its repair
 
Good construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACCGood construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACC
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
 
presentation on retro fit and repair methods
presentation on retro fit and repair methodspresentation on retro fit and repair methods
presentation on retro fit and repair methods
 
Various methods for repair and rehabilitation for concrete structure failure
Various methods for repair and rehabilitation for concrete structure failureVarious methods for repair and rehabilitation for concrete structure failure
Various methods for repair and rehabilitation for concrete structure failure
 
Retrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structureRetrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structure
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
 
Types of crack-Amit Payal
Types of crack-Amit PayalTypes of crack-Amit Payal
Types of crack-Amit Payal
 
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptxREPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding material
 
Rebuild
RebuildRebuild
Rebuild
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketing
 
Building crack,types,causes & its repairing
Building crack,types,causes & its repairingBuilding crack,types,causes & its repairing
Building crack,types,causes & its repairing
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
 
cracks.pptx
cracks.pptxcracks.pptx
cracks.pptx
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structures
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Litterature study on building failures
Litterature study on building failures Litterature study on building failures
Litterature study on building failures
 
Cavity Walling
Cavity WallingCavity Walling
Cavity Walling
 

Recently uploaded

India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 

Recently uploaded (20)

India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 

Group 2 brick masonry- 0506,1706,3006,5207

  • 1. REPAIR AND RETROFITTING OF MASONRY STRUCTURES EFFORTS BY: ABHISHEK BHATT (0506) ANTARA MASHRUWALA (1706) DISHITA SHAH (3006) RAVI SONI (5207)
  • 2. Objective: To study different repair materials and techniques to be adopted in various situation to repair defective structures of brick and stone masonry. Repairs: Process to replace or correct deteriorated/damaged materials and components of a building. Retrofitting: Upgrading of structural and non-structural systems to provide a higher level of resistance than existed before .
  • 3. HOW DAMAGE OCCURS IN BRICK-MASONRY STRUCTURES: Effect of Aging on Brick-Work: Rain Exposure Temperature Moisture Absorption Chemical Alteration Continuous Exposure to Chemicals  Construction Error: Eccentrically Loaded Walls gives overturning effect (Decorative Panels on one side, Support of Working platforms on one side) Usage of Poor quality of materials Error due to saving in economy
  • 4. Maintenance: Common maintenance to brick is to white wash or to paint them at regular intervals, preferably every 2 years. To maintain all sanitary installation in a good condition, any leakage notice anywhere should be intended to immediately, since a small leakage from nani- trap would lead to a major damage in due course. Any cracking wherever noticed should be attended immediately either by sealing the joints with cement mortar or by strengthening the cracks with reinforced bands.
  • 5. TYPES OF CRACKS IN MASONRY STRUCTURES: 1.Vertical cracks in sidewalls at corner 2.Vertical cracks around balconies 3.Vertical cracks below the openings in line with the window jambs. 4.Vertical cracks at the junction of RCC column and masonry wall. 5. Vertical cracks in the top most stories at corners of structures having RCC slab. 6.Horizontal cracks at window lintel or sill level in the top most story. 7.Horizontal cracks in the top most story below the RCC slab level. 8. Horizontal cracks at eaves level in the buildings having pitched roof with wooden joists and purlins. 9. Random cracks in all directions involving both external and internal walls. 10. Diagonal cracks over RCC lintels spanning large openings. 11. Shrinkage cracks.
  • 6. TYPES OF CRACKS IN MASONRY STRUCTURES: Typical Earthquake Typical Earthquake Wall Cracking above the Damage - Wall Corner Damage: In-Plane Wall Door Opening (1993 Failure (1993 Killari Cracking Killari Earthquake) Earthquake)
  • 7. GENERAL CAUSES TO DEVELOP THE CRACKS: Poor quality of bricks. For masonry work,use the porous stones. Absence of grading in before the use of fine aggregate fine mortar. If percentage of clay and silt in fine aggregate exceed 3 percent. Due to the excessive amount of soluble sulphate. Plumb alignment. The position of the element in the structure. Differential loading. Weak mortar. Insufficient bond. Improper curing. Entered dampness from ground, roof and exterior faces. High daily temperature variations. Atmospheric pollutions. Lack of strength at corner and at junction of walls. Improper binding of thick walls.
  • 8. REPAIR TECHNIQUES Sand / Cement Mortar: It is the most simplest and basic repair method. It is highly reliable but may fail under severe drying conditions. Thus cracks will appear as a result of shrinkage in the plastic state of mortar. Due to this shrinkage, debonding and delaminating frequently occurs. Due to high water cement, ratio strength decreases. High density of pores and capillaries allow water and acidic vapours to more easily penetrate the repair and attack to the reinforcement bars. Polymer modified cementations mortars: Polymer modified cementitious mortars are factory controlled blend of specially graded fillers, cement and admixtures to control strength development in set time. To reduce the shrinkage they contain polymers to improve the low permeability, quality and to enhance adhesion. The thermal expansion properties are similar to normal concrete. Heat development is low so much larger volume repairs can be undertaken. Low impermeability can prevent ingress chlorides.
  • 9. Epoxy resin mortars: Epoxy technology is based on the mixing of two liquid resins which react together to form a hard solid if aggregates are added the resin system acts to bind them together to create mortar. Achieves compressive strength of 60-80 N/mm2 and very heavy high flexural strength. Due to good adhesion repair will never fail along correctly prepared bond line. More strength gain occurs in one day in normal atmospheric conditions. Properly compact mortar is impermeable to water. Most epoxy mortar requires primer.
  • 10. Epoxy injection: Narrow cracks of 0.05 mm cracks are repaired by this method. High strength, highly viscous material can be achieved. In this, holes are drilled at closer interval repairs are done under external force through pumps or greasing guns. Normal pressure should be of 1 kg/cm2.We should not apply too much pressure which propagates the cracks. High degree of skills and executions are required to repair these types of cracks.
  • 11. Crack stitching: This method involves drilling holes on both sides of crack and grouting in stitching dogs. Stitching may be used when the tensile strength must be re-established across major cracks. Stitching a crack tends to stiffen the structure, causing the concrete to crack elsewhere. therefore it may be necessary to strengthen the adjacent section with external reinforcement.
  • 12. METHOD FOR ADVANCE RETROFIT TECHNIQUE WITH HELICAL REINFORCEMENT Firstly slots are cut with cutter machine of length 500 mm on each side of crack. 1. The depth of slot is 10 mm but it also depends on the plaster surfaces. Clear loose detritus from slots ensuring exposed brick surfaces are cleaned of 2. mortar and flush thoroughly with water, or treated with a suitable primer. 3. Now fill the slot with grout with pressure. Push Helical 6mm reinforcement crack stitching tie into grout to approximately 4. two thirds of slot depth. Finish the surface and repair the crack on the wall with appropriate filler /grout 5. chemical.
  • 13. Tuck pointing:  Defective joints can usually be repaired by tuck-pointing with Portland cement mortar, with the help of skilled stonemason  In this method, all joints, vertical and horizontal, in the face of the wall should be tuck-pointed.  This procedure requires removing and replacing all mortar to a depth of at least 16mm throughout every joint. each joint is raked to a depth not greater than 26mm unless the old mortar is so defective then it is necessary to remove the mortar up to greater depth.  The depth of old mortar is removed first so that sound mortar acts as a base for new mortar.  All dust and dirt within the raked joints should be washed out.  The mortar is mixed at least 1 hour prior to use to ensure pre-hydration which stabilizes the plasticity and workability of mortar and minimizes any tendency to shrink after insertion into the joint opening.  The sand/cement ratio should be about 3 to 1 by volume.
  • 15. Grouting (cement mortar): Masonry structures can be sealed effectively with less cost by using grout provided the cement-base stabilizing mixture contains an intrusion aid. The consistency of intrusion mixture is that of smooth slurry. Before the intrusion, grout is pumped, the holes are tested by pumping water to see the drilling is adequate and to determine correct consistency for the slurry repairs. Firstly plaster is removed near the cracks from inside and outside of walls and clean the cracks thoroughly with airjet and water. Wet the cracks ,if dry ,by sprinkling water. This mixture is pumped into holes previously drilled at various interval to various depths without damaging the integrity of structure. Pumping the grout simultaneously into multiple series of drill holes ensures good penetration into any fissures within the structure and for making masonry structures watertight.
  • 16. Grouting (chemical):  Chemical grouts consist of solution of two or more chemicals (such as urethanes, sodium silicate) that react to form a gel. This grout opposed to cement grouts that consist of suspension of solid particles in a fluid.  Advantages of chemical grout include applicability in moist environment and their ability to be applied in very fine facture.  Disadvantage is high degree of skill needed for satisfactory use and their lack of strength.  Crack as narrow as 0.05 mm can been filled with chemical grout.
  • 17. Polymer coating:  Polymer coating is use for the job condition and can be an effective protective coating if properly applied.  Polymer coating should be selected from the material specifically for the intended application.  Some formulation will adhere to damp surfaces and even under water but may required a completely dry surface.  Mixing and applying polymers below 16 degree and above 32 degree Celsius will require special caution and procedure.  Moisture passing through the sub grade backfill or from rainwater can accumulate under the coating, which will be interrupted by freezing and thawing.
  • 18. REPAIR MATERIALS Epoxy resins  Epoxy resins are excellent binding agents with high tensile strength. The epoxy components are mixed just prior to application. The product is of low vis­cosity and can be injected in small cracks too.  The higher viscosity epoxy resin can be used for surface coating or filling larger cracks or holes. Epoxy mortar  Epoxy resins when combined, with sand aggregate it forms epoxy mortar. Epoxy mortar mixture has higher compressive strength, higher tensile strength and a lower modulus of elasticity than Portland cement concrete. Quick-setting cement mortar  It is a non-hydrous magnesium phosphate cement with two components, a liquid and a dry, which can be mixed in a manner similar to portland cement concrete. Gypsum cement mortar  It has lowest strength at fail­ure among these three materials. So it is used in minor repair works in structural application. Mechanical anchors  Mechanical anchors provide both shear and ten­sion resistance. Such anchors are manu­factured to give sufficient strength.
  • 19.
  • 20. RETROFIT: Post earthquake improvement of the seismic resistance of a structure including repair of damage . Upgrading of structural and non-structural systems to provide a higher level of resistance than existed before the earthquake. SURFACE TREATMENT: Surface treatment is a common method, which has largely developed through experience. Surface treatment incorporates different techniques such as ferrocement, reinforced plaster, and shotcrete.
  • 21. FERROCEMENT: Ferrocement consists of closely spaced multiple layers of hardware mesh of fine rods (Figure 1 (a)) with reinforcement ratio of 3-8% completely embedded in a high strength (15-30 MPa) cement mortar layer (10- 50 mm thickness). The mortar is troweled on through the mesh with covering thickness of 1-5 mm. Typical mortar mix consists of 1 part cement: 1.5-3 parts sand with approximately 0.4 w/c ratio.
  • 22. REINFORCED PLASTER: A thin layer of cement plaster applied over high strength steel reinforcement can be used for retrofitting. The steel can be arranged as diagonal bars or as a vertical and horizontal mesh. In diagonal tension test and static cyclic tests, the technique was able to improve the improvement in strength depends on the strengthening layer thickness, the cement mortar strength, the reinforcement quantity and the means of its bonding with the retrofitted wall, and the degree of masonry damage.
  • 23. SHOTCRETE:  Shotcrete overlays are sprayed onto the surface of a masonry wall over a mesh of reinforcing bars.  In shotcrete the size of coarse aggregate is limited to 6mm.  With thorough mixing of aggregates and adjustment of pressure at the nozzle should be controlled otherwise a large proportion of coarse aggregate is lost in rebound.  Due to greater wear of nozzles during shotcrete there is a tendency to reduce the proportion or even eliminate coarse aggregates.  Certain additives are available which can reduce wear and tear of nozzles.  After shotcreting proper curing is essential.  In situation where heavy construction machinery can not be moved or is not economically viable, manual shotcreting can also be resorted too.  In manual method layers of concrete can not exceed 35-40 mm in thickness when laid.  Mason should be trained properly to move the trowel applying vibrations and simultaneously for compacting effect on each layer.  Non destructive testing of shotcrete repair work should be carried out.
  • 24. GROUT AND EPOXY INJECTION:  PROCESS :  The crack or joint should be widen wherever the injection work is to be carried out (approximately 15 mm wide x 15 mm depth)  Drill holes of about 13 mm dia upto 150 mm deep at 500 mm @ c/c.  Use compressed air to clean the hole, as well as crack to remove dust, dirt, loose materials etc.  Use 12 mm dia specially threaded injection nipples and fix them into the holes provided. Seal the entire surface around the nipple with putty.  Seal the surface of the crack with putty so as to ensure that the injected grout does not leak from the gaps & from cracked surface.  The surface now is ready for injection.  Prepare the injection grout and load it into the injection gun.
  • 25. EXTERNAL REINFORCEMENT: A steel plates or tubes can be used as external reinforcement for existing Unreinforced Masonry(URM) buildings. Steel system is attached directly to the existing diaphragm or wall. Two vertical members (via pin connections), which are placed next to the existing wall (i.e. creating in-fill panel) can be used.
  • 26. CONFINING URM USING R.C. COLUMNS:  Confined masonry with R.C., weak frame represents one of the most widely used masonry construction system in Asia and Latin America.  In China, they used such confinement in new masonry buildings as well as it is used as retrofitting for existing URM buildings.  The basic feature of confined masonry structures is the vertical R.C. or reinforced masonry tie columns, which confine the walls at all corners and wall intersections as well as the vertical borders of doors and windows openings.  In order to be effective, tie columns should connect with a tie beam along the walls at floors levels.
  • 27. POST TENSIONING: Post-tensioning involves a compressive force applied to masonry wall; this force counteracts the tensile stresses resulting from lateral loads. There has been little application of this technique; post-tensioning is mainly used to retrofit structures characterized as monuments. This is due in part to lack of knowledge about the behavior of post-tensioning masonry. In addition, the codification of post-tensioning masonry has only begun recently.
  • 28. (Contd…..)POST TENSIONING: Post-tensioning tendons are usually in the form of alloy steel thread bars. Bars typically show higher relaxation losses (2-3 times strand losses) and much lower strength/weight ratio (VSL 1990); in addition, a major drawback for using of steel bars is corrosion. Fiber reinforced plastic presents a promising solution for this problem Tendons are placed inside steel tube (duct) either within holes drilled along the midplane of the wall or along groves symmetrically cut on both surfaces of the wall. Holes are cement grouted and external grooves are filled with shotcrete.
  • 29. GROUT OR EPOXY INJECTION IN CRACKS 1 - Plaster removed 2 - Cracks sealed after cleaning 3 - Grout ports Strengthening of existing masonry 1 - Brick or block wall 2 - Injection holes 3 - Grout mixture
  • 30. STRENGTHENING WITH WIRE MESH AND MORTAR STRENGTHENING WITH WIRE MESH Two steel meshes (welded wire fabric with an elementary mesh of approximately 50 x 50 mm) are placed on the two sides of the wall, they are connected by passing steel each 500 to 750 mm apart, A 20 to 40 mm thick cement mortar or micro concrete layer is then applied on the two networks thus giving rise to two interconnected vertical plates. This system can also be used to improve connection of orthogonal walls. 1 - Welded wire mesh - 50 mm x 50 mm 2 - Mortar or micro-concrete rendering 3 - Concrete roof band 4 - Cross ties at 500 to 750 mm apart 5 - Corner bar diameter 8 mm 3 CORNER REINFORCEMENT
  • 31. For Large cracks and crushed concrete For cracks wider than about 6 mm or for regions in which the concrete or masonry has crushed, a treatment other than injection is indicated. The following procedure may be adopted. The loose material is removed and replaced with any of the materials mentioned earlier, i.e., expansive cement mortar, quick setting cement or gypsum cement mortar. Strengthening of existing masonry 1 - Wire mesh on front face 2 – Clamps 3 - Wire mesh on back face 4 - Cement plaster 5 - Crack in wall
  • 32. Splint and bandage strengthening technique The technique of covering the wall with steel mesh and mortar or micro- concrete may be used only on the outside surface of external walls but maintaining continuity of steel at the corners. This would strengthen the walls as well as bind them together. As a variation and for economy in the use of materials, the covering may be in the form of vertical splints between openings and horizontal bandages over spandrel walls at suitable number of points.
  • 33. Splint and bandage strengthening technique
  • 34. NEGLIGENCE AFTER REPAIRS AND RETROFITTING No. Negligence Reasons 1 Hair cracks are found on lack of curing after 4 hours from the application the all ready strengthened of cement mortar. brick masonry walls. 2 Weld mesh are soon on the improper thickness of the cement mortar brick masonry walls after finishing coat. 3 Uneven plaster surface are works are going on without preparing proper found on the wall. level markers. 4 Different shades are found Improper mixing of cement with other on plastered surface. materials and improper curing
  • 35. CASE STUDY : JABALPUR EARTHQUAKE • PHOTOGRAPHS OF DAMAGE DUE TO EARTHQUAKE • STRENGTHNING OF EXISTING CONSTRUCTION • STRENGTHNING OF NEW CONSTRUCTION • PHOTOGRAPHS OF NEW CONSTRUCTION AFTER EARTHQUAKE
  • 36. JABALPUR EARTHQUAKE DAMAGED NUILDINGS Partial Building Collapse in the Faillure of Brick Masonry Walls in 1997 Jabalpur Earthquake the 1997 Jabalpur Earthquake
  • 37. STRENGTHENING OF EXISTING CONSTRUCTION Description of Seismic Strengthening provisions Seismic Deficiency used Lack of integrity (box-type action)  Installation of seismic belt (bandage) at the lintel level; it consists of welded wire mesh installed above the lintel level and anchored to the wall. The mesh is covered with a thin cement plaster overlay (see Figure a)  Cracks in the walls  In case of small cracks, pressure injection of epoxy grout; in case of large cracks, filling the gaps with cement grout and jacketing with reinforced cement overlay. Inadequate wall resistance (shear and tensile)  Reinforced concrete jacketing. Difficult to find skilled labor and materials for welded wire mesh in rural areas  Flexible floor/roof diaphragm (Corrugated metal Installation of RC roof band (bond beam). Provision of sheets/timber)  roof band is expected to enhance the overall intergrity and improve torsional resistance of building  Cracking/damage of wall corners (due to improper Corner strengthening of wall corners - installation of interlocking of cross walls)  welded wire mesh anchored to the walls with steel dowels and covered with a thin cement plaster overlay , see Figure b. 
  • 38. FIGURE A FIGURE B
  • 39. STRENGTHENING OF NEW CONSTRUCTION Description of Seismic Seismic Deficiency Strengthening provisions used Reinforced concrete roof band; provision of roof band Roof  results in an improved overall integrity and torsional resistance of the building.  RCC lintel band; very effective, however skilled labour Wall  and materials may not be available, see Figures 7D, 7E and 7F  Improved quality of masonry (bricks and mortar) use of Wall  better quality bricks will drastically improve the wall seismic resistance; use or richer cement/sand mortar will improve wall shear resistance.  Provision of vertical reinforcement at wall corners and Wall  intersections, see Figure 7G (Source: IAEE 1986) 
  • 40. 7D-An Example of New Construction with 7E-Construction of RC lintel Seismic Features (note RC lintel band) band 7F-Construction of RC Lintel Band - Pouring of Concrete Completed
  • 41. 7G-Provision of Vertical Reinforcement at Wall Corners and Intersections
  • 42. CONCLUSION  Cost effective and safer approach will be to carry out appropriate repair and retrofitting of the building.  It will offer the advantage of carrying out the work part by part or room by room so that the occupants may continue to live in the building during the repair and retrofitting work .  By doing so the cost of repair and retrofitting came to only 8 % of the estimated cost of reconstruction.
  • 43. REFERENCES:  Civil Engineering & Construction Review (Vol.14 Dec.2001)  Structural Consolidation & Strengthening of masonry (Department of Civil Engineering, Belgium)  13th International Brick & Block masonry Conference  Deterioration & Damages in Buildings, Department of Civil Engineering, IIT, Kharagpur  Jabalpur & Killari earthquake Damage reports & Retrofitting Method, Department of Civil engineering, IIT, Kanpur
  • 44. QUESTION FROM OUR PRESENTATION  Why cracks or deteriorations occurs in brick masonry structures? State any 6 techniques by which it can be repaired? Explain any one in detail with neat sketches.