SlideShare a Scribd company logo
GREEN CAMPUS CONFERENCE ATGREEN CAMPUS CONFERENCE AT
ECSUECSU
APRIL 19, 2012APRIL 19, 2012
The Latest & Greatest Energy Technology !The Latest & Greatest Energy Technology !
Where we were,Where we were,
Where we are,Where we are,
Where we are headed….Where we are headed….
Presented byPresented by
Rob GagneRob Gagne
CCSU Plant Facilities Engineer IICCSU Plant Facilities Engineer II
gagne@ccsu.edugagne@ccsu.edu
CCSU’S ORIGINAL POWERHOUSECCSU’S ORIGINAL POWERHOUSE
POWERHOUSE
18,500 PPH
BOILERS
• Planning for the Energy Center
commenced in the early 1990s to
respond to problems with the
aging and undersized campus
heating system
• Provides all heating, cooling, hot
water and some electricity for the
campus
• Staffed by CCSU on a 24/7 basis
since the Fall of 2004
• Equipment in the Energy Center
o Three dual fuel Nebraska boilers
o Two 1,250 kW Cummins natural gas
engines
o One 1.5 ton electric centrifugal chiller
o One 1.5 ton steam absorption chiller
o Two heat recovery steam generators
ENERGYENERGY
CENTERCENTER
Energy Center Control Room Energy Center Space
ENERGY CENTER EQUIPMENTENERGY CENTER EQUIPMENT
65,000 PPH ENERGY CENTER BOILER
1,500 TON
ELECTRIC
CHILLER
1,500 TON
STEAM
ABSORPTION
CHILLER
CUMMINS QSV
18 CYLINDER
1,250 KW
GENERATORS
HEAT
RECOVERY
STEAM
GENERATORS
2,000 PPH
300 HP
COOLING
WATER
PUMPS
500 HP
SECONDARY
CHILLED
WATER
PUMPS
UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
UTILITY TUNNEL COMPLETIONUTILITY TUNNEL COMPLETION
UTILITY
TUNNEL
INTERIOR
ENERGY
CENTER
SWITCHGEAR
ROOM
ELECTRICAL PROFILEELECTRICAL PROFILE
FUEL CELLFUEL CELL
• 1,400 kW Direct Fuel Cell power
plant was installed in the Fall 2011
and delivering power by January 1,
2012
• Minimum electrical capacity 1,303
kW . Minimal steam capacity
1,600 lb/hr with three modes of
operation.
• Grid Connected Mode (with or
without existing E.C. generators)
• Grid Independent Mode (without
the utility grid) MICRO GRID
• Island Hot Standby Mode
(powering its own parasitic loads)
FUEL CELLFUEL CELL
FUEL CELLFUEL CELL
FUEL CELLFUEL CELL
• Phase 1 (completed October 2011): Consisted of energy
efficient improvement measures to Copernicus Hall, and
Vance Academic Center. Implementation cost $164,166.00.
Total energy savings $111,592.00 with a 1.5 year payback.
Additional incentive through CEEF, $3,753.50 when project
was closed out.
• Phase 2 (funding request submitted): Energy efficient
improvement measures to the Energy Center.
Implementation cost $270,671.00. Total energy savings
$192,332.00 with a 1.4 year payback. Additional incentive
through CEEF, $54,026.27 when project is closed out.
RETRO-COMMISSIONINGRETRO-COMMISSIONING
• Retrofitting of 500 lamps across the CCSU campus
with energy saving Sylvania DG LED retrofit kits
• Lessen electrical usage without compromising safety
and security
• Bulb life approximately 5 times a traditional lamp
• Annual reduction of 240,900 kWh with an
approximate 41k cost savings
• Reduction of criteria pollutants such as sulfur oxide,
nitrogen and carbon compounds
• Reduction of light pollution in accordance with the
Dark Sky Initiative
LED REPLACEMENT PROJECTLED REPLACEMENT PROJECT
• Copernicus Garage lighting: 700 (150watt HPS)fixtures were
replaced with 100 watt MH
• Welte Garage lighting: 216 (150 watt HPS) fixtures were
replaced with 8 foot 4 lamp fluorescents, approximately 112
watts per fixture
• Combined average savings for two garages is approximately
4,000 kWh per month
• Square D Monitoring: provides the ability to monitor each
buildings electrical load
• Infrared motion sensor lighting controls: Installed in various
portions of campus to include hallways, classrooms, etc.
OTHER CAMPUS WIDE ENERGYOTHER CAMPUS WIDE ENERGY
EFFICIENCY PROJECTSEFFICIENCY PROJECTS
We will continue to:
– Investigate any and all incentive programs available
– Research additional retro-commissioning and continue with
persistent strategies on existing retro-commissioning
projects
– Educate and involve the campus community in energy
conservation and sustainability efforts
– Stay committed to meeting the goals and efforts in the
University’s Climate Action Plan
WHERE ARE WE HEADED?WHERE ARE WE HEADED?
(IN THE RIGHT DIRECTION!)(IN THE RIGHT DIRECTION!)

More Related Content

What's hot

UC Davis Presentation (2012)
UC Davis Presentation (2012)UC Davis Presentation (2012)
UC Davis Presentation (2012)
HEFContest
 
Carnegie BPObjective-Energy
Carnegie BPObjective-EnergyCarnegie BPObjective-Energy
Carnegie BPObjective-Energy
Nick Sloan
 
Case: Hjallerup District Heating
Case: Hjallerup District HeatingCase: Hjallerup District Heating
Case: Hjallerup District Heating
Linka Energy A/S
 
South Lanarkshire College
South Lanarkshire College South Lanarkshire College
South Lanarkshire College
Kingspan Insulated Panels
 
Washington State University Presentation (2012)
Washington State University Presentation (2012)Washington State University Presentation (2012)
Washington State University Presentation (2012)
HEFContest
 
Gas power station (GPS)
Gas power station (GPS)Gas power station (GPS)
Gas power station (GPS)
Kamal Raj
 
SBC Introduction To Co Gen
SBC Introduction To Co GenSBC Introduction To Co Gen
SBC Introduction To Co Gen
Barbara Albert
 
Khi Solar One, Abengoa in South Africa
Khi Solar One, Abengoa in South AfricaKhi Solar One, Abengoa in South Africa
Khi Solar One, Abengoa in South Africa
Abengoa
 
Ipcc srren generic_presentation
Ipcc srren generic_presentationIpcc srren generic_presentation
Ipcc srren generic_presentation
Anvan Tan
 
Solar Power Generation 2011 (Las Vegas, NV)
Solar Power Generation 2011 (Las Vegas, NV)Solar Power Generation 2011 (Las Vegas, NV)
Solar Power Generation 2011 (Las Vegas, NV)
MitchellDong
 
Jaguar Land Rover
Jaguar Land RoverJaguar Land Rover
Jaguar Land Rover
Kingspan Insulated Panels
 
Integrated systems design project
Integrated systems design projectIntegrated systems design project
Integrated systems design project
Alexander Perukarote
 
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
Farming Futures
 
Energy Sector
Energy SectorEnergy Sector
Energy Sector
Pomcert
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel Sanchez
Reenergize
 
001 160718 energy systems for green buildings20160718-2
001 160718 energy systems for green buildings20160718-2001 160718 energy systems for green buildings20160718-2
001 160718 energy systems for green buildings20160718-2
senicsummerschool
 
Investigating the geothermal potential of northern mines and communities
Investigating the geothermal potential of northern mines and communitiesInvestigating the geothermal potential of northern mines and communities
Investigating the geothermal potential of northern mines and communities
Jasmin Raymond
 
University of Maryland Presentation (2012)
University of Maryland Presentation (2012)University of Maryland Presentation (2012)
University of Maryland Presentation (2012)
HEFContest
 
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINALElec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
Suresh Jambunathan
 
Building Integrated Renewables Public
Building Integrated Renewables PublicBuilding Integrated Renewables Public
Building Integrated Renewables Public
Gavin Harper
 

What's hot (20)

UC Davis Presentation (2012)
UC Davis Presentation (2012)UC Davis Presentation (2012)
UC Davis Presentation (2012)
 
Carnegie BPObjective-Energy
Carnegie BPObjective-EnergyCarnegie BPObjective-Energy
Carnegie BPObjective-Energy
 
Case: Hjallerup District Heating
Case: Hjallerup District HeatingCase: Hjallerup District Heating
Case: Hjallerup District Heating
 
South Lanarkshire College
South Lanarkshire College South Lanarkshire College
South Lanarkshire College
 
Washington State University Presentation (2012)
Washington State University Presentation (2012)Washington State University Presentation (2012)
Washington State University Presentation (2012)
 
Gas power station (GPS)
Gas power station (GPS)Gas power station (GPS)
Gas power station (GPS)
 
SBC Introduction To Co Gen
SBC Introduction To Co GenSBC Introduction To Co Gen
SBC Introduction To Co Gen
 
Khi Solar One, Abengoa in South Africa
Khi Solar One, Abengoa in South AfricaKhi Solar One, Abengoa in South Africa
Khi Solar One, Abengoa in South Africa
 
Ipcc srren generic_presentation
Ipcc srren generic_presentationIpcc srren generic_presentation
Ipcc srren generic_presentation
 
Solar Power Generation 2011 (Las Vegas, NV)
Solar Power Generation 2011 (Las Vegas, NV)Solar Power Generation 2011 (Las Vegas, NV)
Solar Power Generation 2011 (Las Vegas, NV)
 
Jaguar Land Rover
Jaguar Land RoverJaguar Land Rover
Jaguar Land Rover
 
Integrated systems design project
Integrated systems design projectIntegrated systems design project
Integrated systems design project
 
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
Introduction to Farm Renewables - Paul Holmes-Ling (Laurence Gould Partnership)
 
Energy Sector
Energy SectorEnergy Sector
Energy Sector
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel Sanchez
 
001 160718 energy systems for green buildings20160718-2
001 160718 energy systems for green buildings20160718-2001 160718 energy systems for green buildings20160718-2
001 160718 energy systems for green buildings20160718-2
 
Investigating the geothermal potential of northern mines and communities
Investigating the geothermal potential of northern mines and communitiesInvestigating the geothermal potential of northern mines and communities
Investigating the geothermal potential of northern mines and communities
 
University of Maryland Presentation (2012)
University of Maryland Presentation (2012)University of Maryland Presentation (2012)
University of Maryland Presentation (2012)
 
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINALElec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
Elec Pwr Conf Baltimore 2012 5-17-2012 SJ FINAL
 
Building Integrated Renewables Public
Building Integrated Renewables PublicBuilding Integrated Renewables Public
Building Integrated Renewables Public
 

Viewers also liked

Designing, Implementing, and Project Managing Campus Green Funds
Designing, Implementing, and Project Managing Campus Green FundsDesigning, Implementing, and Project Managing Campus Green Funds
Designing, Implementing, and Project Managing Campus Green Funds
Mieko Ozeki
 
McClure Productions Internship
McClure Productions InternshipMcClure Productions Internship
McClure Productions Internship
Mieko Ozeki
 
Project Managing and Implementing STARS 2.1 process
Project Managing and Implementing STARS 2.1 processProject Managing and Implementing STARS 2.1 process
Project Managing and Implementing STARS 2.1 process
Mieko Ozeki
 
Designing and Implementing a Robust and Sustainable Campus Green Fund: Recom...
Designing and Implementing a Robust and Sustainable Campus Green Fund:  Recom...Designing and Implementing a Robust and Sustainable Campus Green Fund:  Recom...
Designing and Implementing a Robust and Sustainable Campus Green Fund: Recom...
Mieko Ozeki
 
Apresentação Green Campus - Conferência PCEEE 2012
Apresentação Green Campus - Conferência PCEEE 2012Apresentação Green Campus - Conferência PCEEE 2012
Apresentação Green Campus - Conferência PCEEE 2012
Green Campus
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introduction
tharwat sakr
 
Go Green Initiative for School Leaders
Go Green Initiative for School LeadersGo Green Initiative for School Leaders
Go Green Initiative for School Leaders
Go Green Initiative
 

Viewers also liked (7)

Designing, Implementing, and Project Managing Campus Green Funds
Designing, Implementing, and Project Managing Campus Green FundsDesigning, Implementing, and Project Managing Campus Green Funds
Designing, Implementing, and Project Managing Campus Green Funds
 
McClure Productions Internship
McClure Productions InternshipMcClure Productions Internship
McClure Productions Internship
 
Project Managing and Implementing STARS 2.1 process
Project Managing and Implementing STARS 2.1 processProject Managing and Implementing STARS 2.1 process
Project Managing and Implementing STARS 2.1 process
 
Designing and Implementing a Robust and Sustainable Campus Green Fund: Recom...
Designing and Implementing a Robust and Sustainable Campus Green Fund:  Recom...Designing and Implementing a Robust and Sustainable Campus Green Fund:  Recom...
Designing and Implementing a Robust and Sustainable Campus Green Fund: Recom...
 
Apresentação Green Campus - Conferência PCEEE 2012
Apresentação Green Campus - Conferência PCEEE 2012Apresentação Green Campus - Conferência PCEEE 2012
Apresentação Green Campus - Conferência PCEEE 2012
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introduction
 
Go Green Initiative for School Leaders
Go Green Initiative for School LeadersGo Green Initiative for School Leaders
Go Green Initiative for School Leaders
 

Similar to Green Campus Conference 4-19-2011 R. Gagne

March5 2009-workshop-slides
March5 2009-workshop-slidesMarch5 2009-workshop-slides
March5 2009-workshop-slides
SWITCHOntario
 
Challenges implementing Green Initiatives in Tall Buildings
Challenges implementing Green Initiatives in Tall BuildingsChallenges implementing Green Initiatives in Tall Buildings
Challenges implementing Green Initiatives in Tall Buildings
Tejwant Navalkar
 
2012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
2012 ISCN Symposium - Energy Optimization at Central Michigan University 20122012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
2012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
ISCN_Secretariat
 
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
Invest Northern Ireland
 
Update on Water/ Wastewater Programs at BCC
Update on Water/ Wastewater Programs at BCCUpdate on Water/ Wastewater Programs at BCC
Update on Water/ Wastewater Programs at BCC
Stone Soup Leadership Institute
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slides
SWITCHOntario
 
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul..."Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
Sustainable Business Partnership
 
Net-Zero Energy Case Studies
Net-Zero Energy Case StudiesNet-Zero Energy Case Studies
Net-Zero Energy Case Studies
aiahouston
 
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
UK Carbon Capture and Storage Research Centre
 
Zero Carbon technology
Zero Carbon technologyZero Carbon technology
Zero Carbon technology
Saumya Ranjan Behura
 
Clean energy technology
Clean energy technologyClean energy technology
Clean energy technology
Gargi Asodariya
 
Global Nes P Pt 2009 A Finals Copy[1]
Global Nes P Pt 2009 A Finals   Copy[1]Global Nes P Pt 2009 A Finals   Copy[1]
Global Nes P Pt 2009 A Finals Copy[1]
bethchenoweth
 
Innovating to Tackle Fuel Poverty
Innovating to Tackle Fuel PovertyInnovating to Tackle Fuel Poverty
Innovating to Tackle Fuel Poverty
Susan Lang-Bissell
 
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
Student Energy
 
2015-Commercial-Installations-Brochure
2015-Commercial-Installations-Brochure2015-Commercial-Installations-Brochure
2015-Commercial-Installations-Brochure
Ian Dutton
 
Designing High Performance Schools In New Orleans
Designing High Performance Schools In New OrleansDesigning High Performance Schools In New Orleans
Designing High Performance Schools In New Orleans
iandoebber
 
Passive House: A Primer on High Performance Buildings
Passive House: A Primer on High Performance BuildingsPassive House: A Primer on High Performance Buildings
Passive House: A Primer on High Performance Buildings
Michael Nemeth
 
Energy Modelling comparison project
Energy Modelling comparison projectEnergy Modelling comparison project
Energy Modelling comparison project
Paul Butler
 
Carbon Capture Status & Outlook 2007
Carbon Capture Status & Outlook 2007Carbon Capture Status & Outlook 2007
Carbon Capture Status & Outlook 2007
Anthony Cirillo, PE
 
Renewable sources of energy
Renewable sources of energyRenewable sources of energy
Renewable sources of energy
grantdiecel
 

Similar to Green Campus Conference 4-19-2011 R. Gagne (20)

March5 2009-workshop-slides
March5 2009-workshop-slidesMarch5 2009-workshop-slides
March5 2009-workshop-slides
 
Challenges implementing Green Initiatives in Tall Buildings
Challenges implementing Green Initiatives in Tall BuildingsChallenges implementing Green Initiatives in Tall Buildings
Challenges implementing Green Initiatives in Tall Buildings
 
2012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
2012 ISCN Symposium - Energy Optimization at Central Michigan University 20122012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
2012 ISCN Symposium - Energy Optimization at Central Michigan University 2012
 
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
Donald MacBrayne, Scottish Water Horizons – Commercial Renewable and Energy S...
 
Update on Water/ Wastewater Programs at BCC
Update on Water/ Wastewater Programs at BCCUpdate on Water/ Wastewater Programs at BCC
Update on Water/ Wastewater Programs at BCC
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slides
 
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul..."Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
"Products / Technologies: Lessons Learnt form Radian Retrofit Project" - Paul...
 
Net-Zero Energy Case Studies
Net-Zero Energy Case StudiesNet-Zero Energy Case Studies
Net-Zero Energy Case Studies
 
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
CO2 Capture - Jon Gibbins, UKCCSRC, at the UKCCSRC ECR Winter School 2015
 
Zero Carbon technology
Zero Carbon technologyZero Carbon technology
Zero Carbon technology
 
Clean energy technology
Clean energy technologyClean energy technology
Clean energy technology
 
Global Nes P Pt 2009 A Finals Copy[1]
Global Nes P Pt 2009 A Finals   Copy[1]Global Nes P Pt 2009 A Finals   Copy[1]
Global Nes P Pt 2009 A Finals Copy[1]
 
Innovating to Tackle Fuel Poverty
Innovating to Tackle Fuel PovertyInnovating to Tackle Fuel Poverty
Innovating to Tackle Fuel Poverty
 
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
 
2015-Commercial-Installations-Brochure
2015-Commercial-Installations-Brochure2015-Commercial-Installations-Brochure
2015-Commercial-Installations-Brochure
 
Designing High Performance Schools In New Orleans
Designing High Performance Schools In New OrleansDesigning High Performance Schools In New Orleans
Designing High Performance Schools In New Orleans
 
Passive House: A Primer on High Performance Buildings
Passive House: A Primer on High Performance BuildingsPassive House: A Primer on High Performance Buildings
Passive House: A Primer on High Performance Buildings
 
Energy Modelling comparison project
Energy Modelling comparison projectEnergy Modelling comparison project
Energy Modelling comparison project
 
Carbon Capture Status & Outlook 2007
Carbon Capture Status & Outlook 2007Carbon Capture Status & Outlook 2007
Carbon Capture Status & Outlook 2007
 
Renewable sources of energy
Renewable sources of energyRenewable sources of energy
Renewable sources of energy
 

Green Campus Conference 4-19-2011 R. Gagne

  • 1. GREEN CAMPUS CONFERENCE ATGREEN CAMPUS CONFERENCE AT ECSUECSU APRIL 19, 2012APRIL 19, 2012 The Latest & Greatest Energy Technology !The Latest & Greatest Energy Technology ! Where we were,Where we were, Where we are,Where we are, Where we are headed….Where we are headed…. Presented byPresented by Rob GagneRob Gagne CCSU Plant Facilities Engineer IICCSU Plant Facilities Engineer II gagne@ccsu.edugagne@ccsu.edu
  • 3.
  • 4.
  • 5.
  • 7. • Planning for the Energy Center commenced in the early 1990s to respond to problems with the aging and undersized campus heating system • Provides all heating, cooling, hot water and some electricity for the campus • Staffed by CCSU on a 24/7 basis since the Fall of 2004 • Equipment in the Energy Center o Three dual fuel Nebraska boilers o Two 1,250 kW Cummins natural gas engines o One 1.5 ton electric centrifugal chiller o One 1.5 ton steam absorption chiller o Two heat recovery steam generators ENERGYENERGY CENTERCENTER
  • 8. Energy Center Control Room Energy Center Space ENERGY CENTER EQUIPMENTENERGY CENTER EQUIPMENT
  • 9. 65,000 PPH ENERGY CENTER BOILER
  • 16. UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
  • 17. UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
  • 18. UTILITY TUNNEL COMPLETIONUTILITY TUNNEL COMPLETION
  • 23. • 1,400 kW Direct Fuel Cell power plant was installed in the Fall 2011 and delivering power by January 1, 2012 • Minimum electrical capacity 1,303 kW . Minimal steam capacity 1,600 lb/hr with three modes of operation. • Grid Connected Mode (with or without existing E.C. generators) • Grid Independent Mode (without the utility grid) MICRO GRID • Island Hot Standby Mode (powering its own parasitic loads) FUEL CELLFUEL CELL
  • 26. • Phase 1 (completed October 2011): Consisted of energy efficient improvement measures to Copernicus Hall, and Vance Academic Center. Implementation cost $164,166.00. Total energy savings $111,592.00 with a 1.5 year payback. Additional incentive through CEEF, $3,753.50 when project was closed out. • Phase 2 (funding request submitted): Energy efficient improvement measures to the Energy Center. Implementation cost $270,671.00. Total energy savings $192,332.00 with a 1.4 year payback. Additional incentive through CEEF, $54,026.27 when project is closed out. RETRO-COMMISSIONINGRETRO-COMMISSIONING
  • 27. • Retrofitting of 500 lamps across the CCSU campus with energy saving Sylvania DG LED retrofit kits • Lessen electrical usage without compromising safety and security • Bulb life approximately 5 times a traditional lamp • Annual reduction of 240,900 kWh with an approximate 41k cost savings • Reduction of criteria pollutants such as sulfur oxide, nitrogen and carbon compounds • Reduction of light pollution in accordance with the Dark Sky Initiative LED REPLACEMENT PROJECTLED REPLACEMENT PROJECT
  • 28. • Copernicus Garage lighting: 700 (150watt HPS)fixtures were replaced with 100 watt MH • Welte Garage lighting: 216 (150 watt HPS) fixtures were replaced with 8 foot 4 lamp fluorescents, approximately 112 watts per fixture • Combined average savings for two garages is approximately 4,000 kWh per month • Square D Monitoring: provides the ability to monitor each buildings electrical load • Infrared motion sensor lighting controls: Installed in various portions of campus to include hallways, classrooms, etc. OTHER CAMPUS WIDE ENERGYOTHER CAMPUS WIDE ENERGY EFFICIENCY PROJECTSEFFICIENCY PROJECTS
  • 29. We will continue to: – Investigate any and all incentive programs available – Research additional retro-commissioning and continue with persistent strategies on existing retro-commissioning projects – Educate and involve the campus community in energy conservation and sustainability efforts – Stay committed to meeting the goals and efforts in the University’s Climate Action Plan WHERE ARE WE HEADED?WHERE ARE WE HEADED? (IN THE RIGHT DIRECTION!)(IN THE RIGHT DIRECTION!)

Editor's Notes

  1. PHASE 1 Modify enable control to avoid tertiary pump operation when EC is disabled Static pressure reset based on VAV box dampers. 0.8” and 1.5” W.C. Installation of ultrasonic occupancy sensors in classrooms and lecture halls Convert buildings chilled water system to variable speed PHASE 2 Convert boiler feed pumps to variable flow with VFD’s 50 hp motors Provide VFD’s for boiler forced draft fans 100hp motors Optimize auxiliary ventilation systems. Dampers for boiler using inside air for combustion will prevent 18000 cfm exhaust fans from operating