EXECUTION PLAN REVISION HISTORY
Version #
Implemented by
Revision Date
Approved by
Approval Date
Reason
Table of Contents
1. PROJECT OVERVIEW
1.1 Purpose, Scope and Objectives, and Business Case
1.1.1 Scope
1.1.2 Statement of Work (SOW)
1.1.3 Business Case
1.2 Project Deliverables
1.3 Project Organization
1.4 Work Breakdown Structure (WBS)
1.4.1 Task description documentation
1.4.2 Organization Breakdown Structure (OBS)
1.5 Responsibility Assignment Matrix (RAM)
1.6 Work Authorization
1.7 Project Charter
2. RISK ASSESSMENT
2.1 Risk Identification
2.2 Assessment of Probability and Consequence (Qualitative)
2.3 Assessment of Probability and Consequence (Quantitative)
2.4 Mitigation Strategies
3. PROJECT SCHEDULE
3.1 Activity Duration Estimates
3.2 Gantt Chart
3.3 Activity Network
4. PROJECT BUDGET
4.1 Project Resources
4.2 Other costs
4.3 Cost estimates
4.4 Time-phased budget
5. COMMUNICATIONS MANAGEMENT
6. TRACKING AND STATUS UPDATES
6.1 Tracking method
6.2 Notification record
6.3 Control systems
7. PROJECT CLOSE-OUT
7.1 Close cost accounts
7.2 Lessons Learned
Project Overview—This section is intended to provide a brief background description of the project, including motivation, goals and objectives, success criteria by which it will be evaluated, major project deliverables, and identified constraints. See Chapter 5 for development of project scope.
1.1Purpose, Scope and Objectives, and Business Case—Describe the purpose of the project here. What are the key deliverables, that is, the major items to be delivered to the customer, other stakeholders, suppliers, or other parties?
1.1.1Scope—Describe the project scope in general terms. Include a problem statement, detailed steps in requirements gathering (who was consulted, when?), information gathering (critical features uncovered from investigation), project constraints, alternatives analysis, and business case documentation.
1.1.2Statement of Work (SOW)—Include a detailed SOW for the project. Include:
1. Key milestones
2. Resource requirements
3. Risks and concerns
4. Acceptance criteria
1.1.3Business Case—Insert the project Business Case here. You can find an explanation of the business case in Chapter 5. Briefly identify the business needs to be satisfied, the feasibility of the project, a description of internal and external forces likely to affect the project, a comparative analysis of the costs and benefits of this project over alternative solutions, and time estimates to return on investment. Identify how the satisfaction of business needs will be determined.
1.2Project Deliverables—List the major items or project features to be delivered to the client. Include sign-off documentation from client to demonstrate their concurrence with the deliverable set.
1.3Project Organization—Indicate all project team members, their specific roles, and project organization hierarchy. Where appropriate, indicate joint responsibility between project m ...
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
1. EXECUTION PLAN REVISION HISTORY
Version #
Implemented by
Revision Date
Approved by
Approval Date
Reason
Table of Contents
1. PROJECT OVERVIEW
1.1 Purpose, Scope and Objectives, and Business Case
1.1.1 Scope
1.1.2 Statement of Work (SOW)
1.1.3 Business Case
1.2 Project Deliverables
1.3 Project Organization
1.4 Work Breakdown Structure (WBS)
1.4.1 Task description documentation
1.4.2 Organization Breakdown -Structure (OBS)
2. 1.5 Responsibility Assignment Matrix (RAM)
1.6 Work Authorization
1.7 Project Charter
2. RISK ASSESSMENT
2.1 Risk Identification
2.2 Assessment of Probability and -Consequence (Qualitative)
2.3 Assessment of Probability and -Consequence (Quantitative)
2.4 Mitigation Strategies
3. PROJECT SCHEDULE
3.1 Activity Duration Estimates
3.2 Gantt Chart
3.3 Activity Network
4. PROJECT BUDGET
4.1 Project Resources
4.2 Other costs
4.3 Cost estimates
4.4 Time-phased budget
5. COMMUNICATIONS MANAGEMENT
3. 6. TRACKING AND STATUS UPDATES
6.1 Tracking method
6.2 Notification record
6.3 Control systems
7. PROJECT CLOSE-OUT
7.1 Close cost accounts
7.2 Lessons Learned
Project Overview—This section is intended to provide a brief
background description of the project, including motivation,
goals and objectives, success criteria by which it will be
evaluated, major project deliverables, and identified constraints.
See Chapter 5 for development of project scope.
1.1Purpose, Scope and Objectives, and Business Case—
Describe the purpose of the project here. What are the key
deliverables, that is, the major items to be delivered to the
customer, other stakeholders, suppliers, or other parties?
1.1.1Scope—Describe the project scope in general terms.
Include a problem statement, detailed steps in requirements
gathering (who was consulted, when?), information gathering
(critical features uncovered from investigation), project
constraints, alternatives analysis, and business case
documentation.
1.1.2Statement of Work (SOW)—Include a detailed SOW for
the project. Include:
1. Key milestones
4. 2. Resource requirements
3. Risks and concerns
4. Acceptance criteria
1.1.3Business Case—Insert the project Business Case here. You
can find an explanation of the business case in Chapter 5.
Briefly identify the business needs to be satisfied, the
feasibility of the project, a description of internal and external
forces likely to affect the project, a comparative analysis of the
costs and benefits of this project over alternative solutions, and
time estimates to return on investment. Identify how the
satisfaction of business needs will be determined.
1.2Project Deliverables—List the major items or project
features to be delivered to the client. Include sign-off
documentation from client to demonstrate their concurrence
with the deliverable set.
1.3Project Organization—Indicate all project team members,
their specific roles, and -project organization hierarchy. Where
appropriate, indicate joint responsibility between project
manager and functional manager. Develop project team
reporting structure and include sponsor and/or executive team
sign-off. See Chapter 3 for examples of project -organization
types.
1.4Work Breakdown Structure (WBS)—Insert a WBS for the
project, including all key -deliverables and work packages.
Include sign-off from project stakeholders on WBS.
1.4.1Include project task description documentation
If appropriate, complete project task description data sheets (for
5. an example, see Figure 5.5 from Chapter 5 .
1.4.2Include an organization breakdown structure (OBS) if
needed. Identify all cost accounts across cooperating
departments in the organization. See Figure 5.7 from Chapter 5 .
1.5Responsibility Assignment Matrix—Include a copy of a
RAM for the project identifying all team members by WBS task
code, including tasks for which they assume responsibility,
notification, support, or approval upon completion. See Figure
5.10 from Chapter 5 .
1.6Work Authorization—Include a copy of the contract or
specific mention of contract terms and conditions. Include all
penalty clauses and specific events that will trigger execution of
penalties. Include all notification information, including
members of the organization to be notified of changes in
contract terms.
1.7Project Charter—Include a copy of the project charter here.
Include the formal sanction of the project and authorization to
apply organizational resources to the project’s execution. See an
example in the Appendix to Chapter 5.
Risk Assessment—This section requires evidence of project risk
assessment. The section is divided into subsections on
identification of risks, analysis (assessment of risk probability
and consequences), and mitigation strategies. See Chapter 7 for
methods for risk management.
2.1Risk Identification—Identify all relevant risk variables for
the project, including a brief description of the risk variable and
the ways in which it is likely to affect the project.
2.2Assessment of Probability and Consequence (Qualitative) —
Insert a qualitative risk assessment matrix in this space. Give
6. evidence of how you arrived at this assessment, including sign-
offs from key project stakeholders participating in the risk
assessment exercise.
Sample Qualitative Risk Assessment Matrix
Low Consequences
High Consequences
Low Likelihood
Low Priority
Medium Priority
High Likelihood
Medium Priority
High Priority
2.3Assessment of Probability and Consequence (Quantitative) —
Insert a quantitative -assessment of probability and
consequences, clearly identifying the criteria used for
-determining both probability of failure and consequence of
failure. Insert this analysis here.
2.4Mitigation Strategies—Identify individual mitigation
strategies for each high priority risk factor. Briefly describe the
strategy as either: Accept, Minimize, Transfer, or Share and
specify actions to be taken in order to accomplish the strategy.
Project Schedule—This section addresses the duration estimates
for all project activities, their activity networks, project critical
path, and estimated project duration. A copy of the approved
project schedule, including both activity network and Gantt
7. chart, should be inserted in this section of the execution plan.
See Chapters 9 and 11 for methods for project schedule
development.
3.1Activity Duration Estimates—Insert table with all activity
duration estimates shown. Indicate if each estimate was derived
stochastically (through PERT probability estimates) or
deterministically. Add sign-off documentation from key
organization members, -including the project sponsor, that
supports these duration estimates.
3.2Gantt Chart—Insert copy of project Gantt chart from MS
Project output file. On the chart, make sure to identify the
project critical path, estimated time to completion, and resource
assignments. Indicate all activity precedence relationships,
including any lag requirements. Show all milestones and other
significant mid-project stages, including scheduled supplier
delivery dates (where appropriate).
3.3Activity Network—Provide activity-on-node (AON) project
network from MS Project output file.
Project Budget—This section includes activity cost estimation
and the project budget. All direct and indirect costs should be
included as well as the method used to develop fully loaded
costs for all project resources. See Chapters 8 and 12 for
examples of methods for cost estimation, fully loaded resource
charges, time-phased budgeting, and resource leveling.
4.1Project Resources—Identify all project resources. Include
employment status (full-time, part-time, exemption status, etc.).
Develop fully loaded cost table for all project resources.
4.2Other costs—Identify all significant costs for materials,
equipment, overhead, expediting, etc.
8. 4.3Cost estimates—Submit ballpark, comparative, and
feasibility estimates. Show all information gathered to support
these estimates. Identify who participated in the cost estimate
exercise. Provide final, definitive estimate with sponsor sign-
off for final project budget.
4.4Time-phased Budget—Submit time-phased budget with
estimated expenses costed by project duration increments
(weeks, months, quarters, etc.).
Communications Management—This section identifies all
critical communication channels for project stakeholders,
frequency of communications, types of information to be
communicated, and project status tracking plan. Where
appropriate, include electronic media used for collaborative
purposes (e.g., Google Docs, Yammer, Facebook, etc.). Also, in
cases of geographically dispersed project teams, indicate
methods for regular communication. See discussion from
Chapter 6 on team communication methods. An example of a
communication management protocol is shown below.
Purpose of communication
Schedule frequency
Media or mechanism used
Called by:
Participants
Status updates
Weekly
Meeting and/or -teleconference
9. Project manager
Full project team
Exception/variance reports
As needed
Meeting and/or -teleconference
Project manager or technical lead
Impacted team -members and client
Project reviews
Monthly or at milestone
Meeting and/or -teleconference
Project manager
Full project team, -sponsor
Configuration changes
As changes are -approved
Meeting for impacted parties; e-mail for team
Project manager, sponsor or technical lead
Impacted team -members and client
Supplier coordination
10. As needed prior to and post deliveries
Phone call
Supply chain lead
Project manager and supply chain lead
Emergency or critical events
As needed
Face to face
Any team member
Full project team
Tracking and Status Updates—This section of the plan indicates
the methods the project team will use to regularly update the
project status, including methods for tracking project progress,
and which organizational stakeholders receive notification of
the project status. See Chapter 13 for examples of tracking and
status updating methods.
6.1Tracking method—Show the method used to track project
status (S-curve, earned value, milestones, etc.). Indicate the
regularity of these assessments (i.e., monthly, as needed, upon
completion of major deliverables, etc.). For earned value
assessments, indicate how you will provide updated cost
performance index (CPI) and schedule performance index (SPI)
data in a sample format as shown below.
Date
11. CPI
Trend
SPI
Trend
Month 1
Month 2
Month 3
6.2Notification record—Maintain record of project status update
communications. Indicate who received project updates and
show sign-off by key stakeholders upon their receipt of status
updates.
6.3Control systems—Indicate the forms of project control that
will be used for the project, including configuration control,
design control, quality control, document control, and trend
monitoring. Develop control documentation for each form of
control you intend to use, including a list of key organizational
stakeholders who will be copied on all control documents and
status updates.
Project Close-out—In this section, all necessary project close-
out documentation and sign-offs must be included. Work
completed or soon-to-be-complete must be identified, and
configuration management changes, all sign-off documentation,
warranties, notices of completion, supplier contracts, and
charges for or against suppliers must be recorded and formally
documented. Include copies of client sign-off, including
satisfaction of contracted terms and conditions. See Chapter 14
for examples of steps in project close-out.
12. 7.1Close cost-accounts—Complete and close all project cost-
accounts and other financial closeouts.
7.2Lessons Learned—Complete a Lessons Learned assessment
that identifies all exceptions and other problems, mitigation
strategies employed, success of the strategies, and suggestions
for the future, and include sign-off documentation that key
project team members participated in Lessons Learned
meetings. Develop and embed an action plan for future projects
in the Lessons Learned documentation.
Part One Course Project
Starting Your Project Plan
In Unit I, you were required to develop and submit a project
idea. Your instructor should have provided you with either the
okay to proceed with your idea or some feedback so that you
can make changes. Once you have this feedback, you will be
able to make any needed modifications to your project idea, and
then you may start putting together your project plan.
Also in Unit I, you were provided with an outline for your final
project plan. For the assignment in this unit, refer to your unit
lesson and required unit resources to begin to draft your project
plan, which should include the components listed below.
1. Project Overview: This section should include a brief
background description of the project, including motivation,
goals
and objectives, success criteria, major project deliverables, and
identified constraints.
1.1 Purpose, Scope and Objectives, and Business Case (In these
sections, be sure to include how you will
measure project success.)
1.1.1 Scope: The project scope may be described in general
13. terms. Include a problem statement, detailed
steps in requirements gathering, information gathering, project
constraints, alternatives analysis, and business
case documentation. Be sure to describe the techniques used to
derive the requirements for this project.
1.1.2 Statement of Work (SOW): Include key milestones,
resource requirements, risks and concerns, and
acceptance criteria.
1.1.3 Business Case: Include the business needs to be satisfie d,
the feasibility of the project, a description of
internal and external forces likely to affect the project, a
comparative analysis of the costs and benefits of this
project over alternative solutions, and time estimates to return
on investment. Identify how the satisfaction of
business needs will be determined.
1.2 Project Deliverables: List the major items or project
features to be delivered to the client.
1.3 Project Organization: List all project team members, their
specific roles, and the project organization hierarchy.
Where appropriate, indicate joint responsibilities between the
project manager and functional manager. Develop a
project team reporting structure.
This assignment should be a minimum of two pages in length,
not counting the title page and reference page. Be sure to
use proper APA formatting. Citations are not required; however,
if outside sources are used, make certain to provide in-text
citations and references in APA format.
For more elaboration on what you should include in your project
plan, refer to pp.
539–542 in your textbook
Part Two
Wrapping up the Project Overview
14. In Unit II, you were required to complete components 1.1–1.3 in
the Project Overview section. As you receive feedback from
your professor, be sure to make improvements to your project
plan.
In Unit III, you are required to complete the rest of the Project
Overview section (components 1.4–1.7) from your project
plan. For this assignment, refer to your unit lesson and required
unit resources to advance your project plan. You should now
have the components from Unit II already developed (see
below).
1. Project Overview (due in Unit II)
1.1 Purpose, Scope and Objectives, and Business Case (due in
Unit II)
1.1.1 Scope (due in Unit II)
1.1.2 Statement of Work (SOW) (due in Unit II)
1.1.3 Business Case (due in Unit II)
1.2 Project Deliverables (due in Unit II)
1.3 Project Organization (due in Unit II)
For this assignment, continue this section by completing the
components listed below.
1.4 Work Breakdown Structure (WBS): Provide a WBS for the
project, including all key deliverables and work
packages.
1.4.1 Task Description Documentation
1.4.2 Organization Breakdown Structure (OBS): Include all cost
accounts across cooperating departments in the
organization.
1.5 Responsibility Assignment Matrix (RAM): Include a copy of
a RAM for the project that identifies all team members
by WBS task code, including tasks for which they assume
responsibility, notification, support, or approval upon
completion.
1.6 Work Authorization: Describe contract terms and
15. conditions. Include all penalty clauses and specific events that
will trigger execution of penalties. Include all notification
information, including members of the organization to be
notified of changes in contract terms.
1.7 Project Charter
This assignment should be a minimum of two pages in length,
not counting the title page and reference page. Be sure to
use proper APA formatting. Citations are not required; however,
if outside sources are used, make certain to provide in-text
citations and references in APA format. For more elaboration on
what you should include in your project plan, refer to pp.
539–542 in your textbook.
Zen Enchantments Yoga Studio Renovation Project
Zen Enchantments Yoga Studio is extending their
cooperation and would like to offer more services to their
cliental. The company has decided to make renovations to one
of their existing yoga studios located in Mansfield, TX. Zen
Enchantments Inc. currently only offers one yoga practice in
their studio. The company has recently expended their
partnership and is now able to offer five yoga practices
including Bikram, Hatha, Vinyasa, Kundalini and Anusara yoga.
The title of this project will be Zen Enchantment Yoga Studio
Renovation.
Project Description
The project description will provide an abbreviated scope of the
project. This project will include renovations for both cold and
heated yoga studios. The project will include multiple class
session studio renovations. The studio is currently operating
session from one large open area in the studio. The project will
included the break down of different rooms types for classes.
The project also includes the structure of a dinning operations
that will be used to store cold and dry food and process a
minimum amount of food products. The project objective is to
construct high quality renovations within two months at cost not
16. exceeding $375,000.
Project Timeline
The project timeline for the Zen Enchantment yoga studio is two
months induration from start to finish. The project timeline will
provide a detail breakdown of the task and activities that will
take place during the project. The task and activities will be
ranked in chronological order for the entire project. Although, it
may be challenging at time the project team will need to
communicate details and any timeline updates.
Project Involvement
The project involvement will include a Chief Executive Officer,
Studio Administrator, Instructors, Accountant, and Client
Service Executive. The Chief Executive Officer who services as
one of the highest decision makers with the company that will
communicate the concept of the project to the corporate
operations. The Studio Administrator will provide insight and
feedback for studio requirements. The instructors will also
provide feedback with dynamic of the requirements. The
accountant will closely monitor and review the project budgets
and ensure that expenses are being reported and tracked. The
Client Services Executive will provide feedback from surveys
that were taken prior to the start date of the project that the
company has decided to include with their renovations.
17. References
Pinto, J. K. (2019). Project management: Achieving competitive
advantage (5th ed.). Pearson.