SlideShare a Scribd company logo
1 of 51
1
10/02/2012 Slide 1
Fundamentals of Transformer-
Rated Field Meter Testing and
Site Verification
Prepared by Rob Reese, TESCO
The Eastern Specialty Company
For NREA ā€“ Nebraska Rural Electric Association
February 10, 2021
2
Site Verification
ā€¢ Why is Site Verification Important?
ā€¢ More than Meter Testing
ā€¢ Testing and Inspecting the Entire Service
ā€¢ Overview of Transformer-Rated Meter Installations
ā€¢ Transformer-Rated Meter Installation Verifications
ā€¢ What to Inspect and Test
ā€¢ Detailed Testing Theory and Equipment
ā€¢ Meter Accuracy
ā€¢ CT Burden, Ratio, Admittance
ā€¢ Vectors and Harmonics
ā€¢ Hot Socket
3
What is Site Verification?
Testing and inspection of more than just the
meter accuracy.
99.975% Registration
4
Premise
ā€¢ Over much of the 20th century, utilities, regulators and customers each
relied upon lab and field meter testing efforts which were primarily focused
upon the accuracy of the watt-hour meter and demand register.
ā€¢ This focus is now changing with the deployment of electronic AMR and
AMI meters to the majority of the 155 Million connected customers in North
America.
ā€¢ The focus has now shifted from just the accuracy of the meter to also
checking other features of the meter (e.g. communication and disconnect
devices), the firmware versions and settings of the meter, and the overall
meter installations for both residential and C&I customers.
ā€¢ Incorrect or miscalculated site information or undetected problems can
lead to an improperly metered customer not related to the meters accuracy
and could also lead to potential safety issues.
5
Field Testing
Common Features and Common Sources of Concern
Electro Mechanical meters were
subject to registration errors caused
by mechanical issues with moving
parts resulting in either the loss of
revenue to the utility or over billing
for the customer. Some of the more
common problems were:
ā€¢ Friction wear
ā€¢ Gear mesh misalignment
ā€¢ Retarding magnet failure
ā€¢ Timing motors
6
Electronic Meters ā€“ new failure modes require
new testing and inspection methods
Electronic meters fail as do electromechanical meters
but differently
ā€¢ Their overall life expectancy is not nearly the same
ā€¢ Failure modes include drift (unexpected)
ā€¢ Failure modes include catastrophic (expected)
ā€¢ Power supply damage due to lightning surges or other
causes
ā€¢ LCD Display failures making a visual read impossible
when required
ā€¢ AMR/AMI communications module failures requiring a field visit to repair or replace meter/AMI
module and get a read for billing purposes
ā€¢ Failure modes include non-catastrophic but significant measurement error modes sometimes
attributed to improper meter programming and in some cases meter firmware issues.
ā€¢ Failure modes can include non-measurement issues which render the meter ineffective or
inaccurate for billing purposes
ā€¢ Clerical errors such as incorrect multipliers can do more damage than even the most catastrophic
equipment failure in the field.
7
Best Practices
ā€¢ Residential vs Commercial
ā€¢ Self-Contained vs Transformer Rated
ā€¢ Follow the money and be as proactive as possible
8
ā€¢ A meter test may not catch intermittent errors or identify errors with
other equipment at the site, e.g. CTā€™s & PTā€™s
ā€¢ A discrepancy between what is thought to be at a given site and
what is actually at that site can cause a major billing error (either
over or under billed)
Why Site Verifications are a
Valuable Utility Tool
ā€¢ It is important to remember that with
current systems it is not just the meter
that can cause a major error in the
measurement of a given service
ā€¢ A meter test that indicates a meter is
within the required accuracy
parameters does not mean your service
is being measured and billed accurately
9
ā€¢ While these numbers will vary from
utility to utility the basic premise
should be the same for all utilities
regarding where Meter Services
should focus their efforts ā€“
follow the money.
Why C&I and what should we invest our
limited meter service resources here?
ā€¢ Easy Answer: Money.
ā€¢ These customers represent a disproportionately large
amount of the overall revenue for every utility in North
America.
ā€¢ For some utilities the ten percent of their customers
who have transformer rated metering services can
represent over 70% of their overall revenue.
10
ā€¢ Most Utilities do not have a comprehensive and
complete list of every instrument transformer on
their system that is involved in providing the billing
for the largest 10 to 20% of any utilities revenue.
ā€¢ Most Utilities do not visit, document and verify
these same services on any regular basis.
ā€¢ Best practices call for the on-site verification of a
Utilities ā€œlargestā€ customers on a periodic basis.
ā€“ There is no definition of what this verification
should entail
ā€“ There is no definition of what ā€œlargestā€ means
ā€“ There is no agreement on the frequency of this
ā€œperiodicā€ inspection
What are the opportunities that can be found in
this work and what are our industryā€™s ā€œBest
Practicesā€ for this type of work?
11
ā€¢ A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if
an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over
a two year period). Does this mean that $10,000 per month or more defines large?
Define ā€œLargestā€ and what this may represent
ā€¢ Largest should be defined by revenue.
ā€¢ Lost metering revenue is no longer
ā€œrecovered in the next rate caseā€, nor is
recovered metering revenue necessarily
ā€œgiven backā€ in the next rate case.
ā€¢ Utility Commissions are having less
tolerance for new rate cases.
ā€¢ Over billing of any customer has always
been a public relations nightmare.
12
ā€¢ A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if
an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over
a two year period). Does this mean that $10,000 per month or more defines large?
ā€“ I would argue that this size customer is universally a ā€œLarge customerā€ and that from here
each utility should decide how much smaller they should go in their definition of ā€œLargeā€.
Define ā€œLargestā€ and what this may represent
ā€¢ Largest should be defined by revenue.
ā€¢ Lost metering revenue is no longer
ā€œrecovered in the next rate caseā€, nor is
recovered metering revenue necessarily
ā€œgiven backā€ in the next rate case.
ā€¢ Utility Commissions are having less
tolerance for new rate cases.
ā€¢ Over billing of any customer has always
been a public relations nightmare.
13
ā€¢ If changes in usage, equipment failures in the metering service,
external damage to the service, or energy diversion at a single
ā€œlargeā€ customer can pay for a single meter tech in just two or three
years, and a single meter tech can handle several of these
inspections in a single day, then there is ample cost justification for
inspecting these services at least once every year.
Define ā€œPeriodicallyā€ and how
frequent this may be
14
Self-Contained vs. Transformer-Rated
Self Contained
(direct)
Transformer-Rated
(indirect)
15
Self-Contained Metering
Relatively Low Current
Example: 100A
Primarily Residential
(1S, 2S, 12S)
16
Self-Contained Metering
Primarily Residential
(1S, 2S, 12S)
17
Transformer-Rated Metering
Relatively High Current
Example: 400A
Primarily Commercial/Industrial
(9S, 16S)
18
Transformer-Rated Metering
Primarily Commercial/Industrial
(9S, 16S)
19
Transformer-Rated Metering
Typical Components of an Installation
20
Transformer-Rated Metering Verification
Potential list of tasks to be completed:
Double check the meter number, the location the test result and the
meter record
Perform a visual safety inspection of the site. This includes utility and
customer equipment. Things to look for include intact down ground on
pole, properly attached enclosure, unwanted voltage on enclosure,
proper trimming and site tidiness (absence of discarded seals, etc.)
Visually inspect for energy diversions (intentional and not). This includes
broken or missing wires, jumpers, open test switch, unconnected wires
and foreign objects on meters or other metering equipment. Broken or
missing wires can seriously cause the under measurement of energy. A
simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the
registration on either 3 element or 2 element metering, respectively.
Visually check lightning arrestors and transformers for damage or leaks.
Check for proper grounding and bonding of metering equipment. Poor
grounding and bonding practices may result in inaccurate measurements
that go undetected for long periods of time. Implementing a single point
ground policy and practice can reduce or eliminate this type of issue.
Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
21
Transformer-Rated Metering Verification
Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
Verify service voltage. Stuck regulator or seasonal capacitor can
impact service voltage.
Verify condition of metering control wire. This includes looking for
cracks in insulation, broken wires, loose connections, etc.
Compare the test switch wiring with the wiring at the CTs and VTs.
Verify CTs and VTs not cross wired. Be sure CTs are grounded in
one location (test switch) only.
Check for bad test switch by examining voltage at the top and
bottom of the switch. Also verify amps using amp probe on both
sides of the test switch. Verify neutral connection to cabinet
(voltage).
Check rotation by closing in one phase at a time at the test switch
and observing the phase meter for forward rotation. If forward
rotation is not observed measurements may be significantly
impacted as the phases are most likely cancelling each other out.
Test meter for accuracy. Verify demand if applicable with observed
load. If meter is performing compensation (line and/or transformer
losses) the compensation should be verified either through direct
testing at the site or by examining recorded pulse data.
22
Transformer-Rated Metering Verification
Verify metering vectors. Traditionally this has been done using
instruments such as a circuit analyzer. Many solid state meters
today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many
of these desired values are programmed into the meters
Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in
determining if unbalanced loads are present and if CTs are sized
properly. The vendor software generally has the ability to capture
both diagnostic and vector information electronically. These
electronic records should be kept in the meter shop for future
comparisons.
If metering is providing pulses/EOI pulse to customers, SCADA
systems or other meters for totalization they also should be verified
vs. the known load on the meter. If present test/inspect isolation
relays/pulse splitters for things like blown fuses to ensure they are
operating properly.
Verify meter information including meter multiplier (rework it), serial
number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in
this type of information can also cause a adverse impact on
measured/reported values.
23
Transformer-Rated Metering Verification
Verify CT shunts are all opened.
Look for signs of excessive heat on the meter base e.g.
melted plastic or discoloration related to heat
24
Testing Theory and Equipment
Most Important Tools You Have!
25
Testing Theory and Equipment
Meter Accuracy Testing ā€“ A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
26
Testing Theory and Equipment
Meter Accuracy Testing ā€“ A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Watthour Meter
- Measures Electrical Energy (kWh)
Potential (V) * Current (I) = Power (W)
Power Over Time = Energy (kWh)
27
Testing Theory and Equipment
Meter Accuracy Testing ā€“ A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Energy Reference Standard
- Measures Electrical Energy (kWh)
- Higher Accuracy Class
- Traceability to SI
28
Testing Theory and Equipment
Meter Accuracy Testing ā€“ A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
- Apply the Same Voltage and Current to the Standard and Meter for a Defined Period of Time
- Standard and Meter Should Measure the Same Energy
- The Difference is the Error of the Meter
29
Testing Theory and Equipment
Meter Accuracy Testing ā€“ A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Example:
Standard Registers 100kWh / Meter Registers 101.38
Then the Error of the Meter is 1.38%
30
CT Testing
Ratio, Burden, and Admittance
31
Example Application
9S Meter
Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
32
Faceplate Specifications
33
Faceplate Specifications
Ratio
34
CTs Ratio
For instance, a CT with a 400:5 ratio will
produce 5A on the secondary, when 400A
are applied to the primary.
35
Faceplate Specifications
Burden
Rating
36
Burden Rating
The burden range, present in the secondary
circuit, that the manufacturer will guarantee
their CTā€™s will still accurately function, in
regards to the ratio specification.
37
Ratio Testing
Ratio of Primary Current to Secondary Current
5A
PHASE A
SOURCE LOAD
400A
400A
400A
5A
5A
Calculate
Ratio
38
Burden Testing
Functionality with Burden Present on the Secondary Loop
PHASE A
Some burden will always be
present ā€“ junctions, meter coils,
test switches, cables, etc.
CTā€™s must be able to maintain
an accurate ratio with burden on
the secondary.
39
Burden Testing
Functionality with Burden Present on the
Secondary Loop
PHASE A
Some burden will always be
present ā€“ junctions, meter coils,
test switches, cables, etc.
CTā€™s must be able to maintain
an accurate ratio with burden on
the secondary.
40
Burden Testing
Functionality with Burden Present on the Secondary Loop
Example Burden Spec:
0.3% @ B0.1, B0.2, B0.5
or
There should be less than the 0.3%
change in secondary current from initial
(ā€œ0ā€ burden) reading, when up to
0.5Ohms of burden is applied
41
Burden Testing
Functionality with Burden Present on the Secondary Loop
ANSI Burden Values
0.1 Ohms
0.2 Ohms
0.5 Ohms
1 Ohms
2 Ohms
4 Ohms
8 Ohms
42
Burden Testing
Functionality with Burden Present on the
Secondary Loop
PHASE A
.1 Ohm
43
Burden Testing
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A ā€“ 0.015 = 4.985A
44
Burden Testing
4.9500
4.9600
4.9700
4.9800
4.9900
5.0000
5.0100
5.0200
5.0300
5.0400
5.0500
0 0.2 0.4 0.6 0.8 1
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A ā€“ 0.015 = 4.985A
At 0.5Ohms of Burden
the secondary current is still at
4.990A ā€“ Less than 0.3% change ā€“
Good CT!
45
Admittance Testing
ā€¢ What is Admittance?
ā€¢ Admittance testing measures the
overall ā€œhealthā€ of the secondary
loop of the CT.
ā€¢ Measured in units of MiliSiemens
(mS)
ā€¢ Admittance is the inverse of
impedance.
ā€¢ Impedance is the opposition to
current.
ā€¢ Therefore, admittance testing
measures the overall ā€œhealthā€ of
the secondary loop of the CT.
46
Admittance Testing
ā€¢ Admittance testing devices inject an audio sine
wave signal into the secondary loop of the CT.
ā€¢ The resulting current is measured.
ā€¢ The voltage of the initial signal is known.
ā€¢ From these two parameters, the impedance,
and thus the admittance can be calculated.
47
Admittance Testing
ā€¢ Admittance test results are not immediately
intuitive.
ā€¢ Some analysis and interpretation is need.
ā€¢ What do all these mS values mean?
48
Admittance Testing
Three phase process is recommended.
1.Test each CT individually
2.Test the matched sets
3.Test over time
49
Hot Socket Checks
50
References and Citations
1. http://www.texasmeter.com/
2. https://home.howstuffworks.com/home-improvement/repair/how-to-do-home-electrical-repairs.htm
3. https://www.youtube.com/watch?v=SeyojxVonrk
4. https://www.tescometering.com/product/tesco-transockets/
5. http://www.gecdurham.com/
6. https://www.radianresearch.com/
7. http://www.brooksutility.com/products/122
51
Questions and Discussion
Rob Reese
TESCO ā€“ The Eastern Specialty Company
Bristol, PA
215-310-8809 (cell)
This presentation can also be found under Meter
Conferences and Schools on the TESCO website:
www.tescometering.com

More Related Content

What's hot

What's hot (14)

Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
Ā 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
Ā 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
Ā 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
Ā 
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two ChargersCertifying DC Electric Vehicle Chargers and AC Level Two Chargers
Certifying DC Electric Vehicle Chargers and AC Level Two Chargers
Ā 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
Ā 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
Ā 
TESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the FieldTESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the Field
Ā 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing ā€“ Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing ā€“ Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing ā€“ Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing ā€“ Part II
Ā 
Simulating Real World Metering Conditions
Simulating Real World Metering ConditionsSimulating Real World Metering Conditions
Simulating Real World Metering Conditions
Ā 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
Ā 
Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability
Ā 
Power Quality & Power Quality Problems
Power Quality & Power Quality ProblemsPower Quality & Power Quality Problems
Power Quality & Power Quality Problems
Ā 
Meter Forms: Wiring and Uses
Meter Forms: Wiring and UsesMeter Forms: Wiring and Uses
Meter Forms: Wiring and Uses
Ā 

Similar to Fundamentals of Transformer-Rated Field Meter Testing and Site Verification

Similar to Fundamentals of Transformer-Rated Field Meter Testing and Site Verification (20)

Site Verification for Newer Employees
Site Verification for Newer EmployeesSite Verification for Newer Employees
Site Verification for Newer Employees
Ā 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
Ā 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
Ā 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
Ā 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Ā 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
Ā 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
Ā 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Ā 
Single Phase Meter Testing Overview
Single Phase Meter Testing OverviewSingle Phase Meter Testing Overview
Single Phase Meter Testing Overview
Ā 
Field Testing
Field TestingField Testing
Field Testing
Ā 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
Ā 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Ā 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Ā 
Field Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair KitsField Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair Kits
Ā 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Ā 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
Ā 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
Ā 
Self-Contained Fundamentals
Self-Contained FundamentalsSelf-Contained Fundamentals
Self-Contained Fundamentals
Ā 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Ā 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
Ā 

Recently uploaded

Recently uploaded (20)

Top 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development CompaniesTop 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development Companies
Ā 
Design and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data ScienceDesign and Development of a Provenance Capture Platform for Data Science
Design and Development of a Provenance Capture Platform for Data Science
Ā 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptx
Ā 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
Ā 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps Productivity
Ā 
Decarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceDecarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational Performance
Ā 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
Ā 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
Ā 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
Ā 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Ā 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Ā 
Less Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data PlatformLess Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Less Is More: Utilizing Ballerina to Architect a Cloud Data Platform
Ā 
The Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and InsightThe Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and Insight
Ā 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Ā 
Ų§Ł„Ų£Ł…Ł† Ų§Ł„Ų³ŁŠŲØŲ±Ų§Ł†ŁŠ - Ł…Ų§ Ł„Ų§ ŁŠŲ³Ų¹ Ł„Ł„Ł…Ų³ŲŖŲ®ŲÆŁ… Ų¬Ł‡Ł„Ł‡
Ų§Ł„Ų£Ł…Ł† Ų§Ł„Ų³ŁŠŲØŲ±Ų§Ł†ŁŠ - Ł…Ų§ Ł„Ų§ ŁŠŲ³Ų¹ Ł„Ł„Ł…Ų³ŲŖŲ®ŲÆŁ… Ų¬Ł‡Ł„Ł‡Ų§Ł„Ų£Ł…Ł† Ų§Ł„Ų³ŁŠŲØŲ±Ų§Ł†ŁŠ - Ł…Ų§ Ł„Ų§ ŁŠŲ³Ų¹ Ł„Ł„Ł…Ų³ŲŖŲ®ŲÆŁ… Ų¬Ł‡Ł„Ł‡
Ų§Ł„Ų£Ł…Ł† Ų§Ł„Ų³ŁŠŲØŲ±Ų§Ł†ŁŠ - Ł…Ų§ Ł„Ų§ ŁŠŲ³Ų¹ Ł„Ł„Ł…Ų³ŲŖŲ®ŲÆŁ… Ų¬Ł‡Ł„Ł‡
Ā 
Simplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxSimplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptx
Ā 
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Ā 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
Ā 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
Ā 
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
Ā 

Fundamentals of Transformer-Rated Field Meter Testing and Site Verification

  • 1. 1 10/02/2012 Slide 1 Fundamentals of Transformer- Rated Field Meter Testing and Site Verification Prepared by Rob Reese, TESCO The Eastern Specialty Company For NREA ā€“ Nebraska Rural Electric Association February 10, 2021
  • 2. 2 Site Verification ā€¢ Why is Site Verification Important? ā€¢ More than Meter Testing ā€¢ Testing and Inspecting the Entire Service ā€¢ Overview of Transformer-Rated Meter Installations ā€¢ Transformer-Rated Meter Installation Verifications ā€¢ What to Inspect and Test ā€¢ Detailed Testing Theory and Equipment ā€¢ Meter Accuracy ā€¢ CT Burden, Ratio, Admittance ā€¢ Vectors and Harmonics ā€¢ Hot Socket
  • 3. 3 What is Site Verification? Testing and inspection of more than just the meter accuracy. 99.975% Registration
  • 4. 4 Premise ā€¢ Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. ā€¢ This focus is now changing with the deployment of electronic AMR and AMI meters to the majority of the 155 Million connected customers in North America. ā€¢ The focus has now shifted from just the accuracy of the meter to also checking other features of the meter (e.g. communication and disconnect devices), the firmware versions and settings of the meter, and the overall meter installations for both residential and C&I customers. ā€¢ Incorrect or miscalculated site information or undetected problems can lead to an improperly metered customer not related to the meters accuracy and could also lead to potential safety issues.
  • 5. 5 Field Testing Common Features and Common Sources of Concern Electro Mechanical meters were subject to registration errors caused by mechanical issues with moving parts resulting in either the loss of revenue to the utility or over billing for the customer. Some of the more common problems were: ā€¢ Friction wear ā€¢ Gear mesh misalignment ā€¢ Retarding magnet failure ā€¢ Timing motors
  • 6. 6 Electronic Meters ā€“ new failure modes require new testing and inspection methods Electronic meters fail as do electromechanical meters but differently ā€¢ Their overall life expectancy is not nearly the same ā€¢ Failure modes include drift (unexpected) ā€¢ Failure modes include catastrophic (expected) ā€¢ Power supply damage due to lightning surges or other causes ā€¢ LCD Display failures making a visual read impossible when required ā€¢ AMR/AMI communications module failures requiring a field visit to repair or replace meter/AMI module and get a read for billing purposes ā€¢ Failure modes include non-catastrophic but significant measurement error modes sometimes attributed to improper meter programming and in some cases meter firmware issues. ā€¢ Failure modes can include non-measurement issues which render the meter ineffective or inaccurate for billing purposes ā€¢ Clerical errors such as incorrect multipliers can do more damage than even the most catastrophic equipment failure in the field.
  • 7. 7 Best Practices ā€¢ Residential vs Commercial ā€¢ Self-Contained vs Transformer Rated ā€¢ Follow the money and be as proactive as possible
  • 8. 8 ā€¢ A meter test may not catch intermittent errors or identify errors with other equipment at the site, e.g. CTā€™s & PTā€™s ā€¢ A discrepancy between what is thought to be at a given site and what is actually at that site can cause a major billing error (either over or under billed) Why Site Verifications are a Valuable Utility Tool ā€¢ It is important to remember that with current systems it is not just the meter that can cause a major error in the measurement of a given service ā€¢ A meter test that indicates a meter is within the required accuracy parameters does not mean your service is being measured and billed accurately
  • 9. 9 ā€¢ While these numbers will vary from utility to utility the basic premise should be the same for all utilities regarding where Meter Services should focus their efforts ā€“ follow the money. Why C&I and what should we invest our limited meter service resources here? ā€¢ Easy Answer: Money. ā€¢ These customers represent a disproportionately large amount of the overall revenue for every utility in North America. ā€¢ For some utilities the ten percent of their customers who have transformer rated metering services can represent over 70% of their overall revenue.
  • 10. 10 ā€¢ Most Utilities do not have a comprehensive and complete list of every instrument transformer on their system that is involved in providing the billing for the largest 10 to 20% of any utilities revenue. ā€¢ Most Utilities do not visit, document and verify these same services on any regular basis. ā€¢ Best practices call for the on-site verification of a Utilities ā€œlargestā€ customers on a periodic basis. ā€“ There is no definition of what this verification should entail ā€“ There is no definition of what ā€œlargestā€ means ā€“ There is no agreement on the frequency of this ā€œperiodicā€ inspection What are the opportunities that can be found in this work and what are our industryā€™s ā€œBest Practicesā€ for this type of work?
  • 11. 11 ā€¢ A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over a two year period). Does this mean that $10,000 per month or more defines large? Define ā€œLargestā€ and what this may represent ā€¢ Largest should be defined by revenue. ā€¢ Lost metering revenue is no longer ā€œrecovered in the next rate caseā€, nor is recovered metering revenue necessarily ā€œgiven backā€ in the next rate case. ā€¢ Utility Commissions are having less tolerance for new rate cases. ā€¢ Over billing of any customer has always been a public relations nightmare.
  • 12. 12 ā€¢ A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over a two year period). Does this mean that $10,000 per month or more defines large? ā€“ I would argue that this size customer is universally a ā€œLarge customerā€ and that from here each utility should decide how much smaller they should go in their definition of ā€œLargeā€. Define ā€œLargestā€ and what this may represent ā€¢ Largest should be defined by revenue. ā€¢ Lost metering revenue is no longer ā€œrecovered in the next rate caseā€, nor is recovered metering revenue necessarily ā€œgiven backā€ in the next rate case. ā€¢ Utility Commissions are having less tolerance for new rate cases. ā€¢ Over billing of any customer has always been a public relations nightmare.
  • 13. 13 ā€¢ If changes in usage, equipment failures in the metering service, external damage to the service, or energy diversion at a single ā€œlargeā€ customer can pay for a single meter tech in just two or three years, and a single meter tech can handle several of these inspections in a single day, then there is ample cost justification for inspecting these services at least once every year. Define ā€œPeriodicallyā€ and how frequent this may be
  • 14. 14 Self-Contained vs. Transformer-Rated Self Contained (direct) Transformer-Rated (indirect)
  • 15. 15 Self-Contained Metering Relatively Low Current Example: 100A Primarily Residential (1S, 2S, 12S)
  • 17. 17 Transformer-Rated Metering Relatively High Current Example: 400A Primarily Commercial/Industrial (9S, 16S)
  • 20. 20 Transformer-Rated Metering Verification Potential list of tasks to be completed: Double check the meter number, the location the test result and the meter record Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. Visually check lightning arrestors and transformers for damage or leaks. Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
  • 21. 21 Transformer-Rated Metering Verification Burden, Ratio, and/or Admittance test CTs and voltage check PTs. Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage. Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross wired. Be sure CTs are grounded in one location (test switch) only. Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data.
  • 22. 22 Transformer-Rated Metering Verification Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. If present test/inspect isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly. Verify meter information including meter multiplier (rework it), serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values.
  • 23. 23 Transformer-Rated Metering Verification Verify CT shunts are all opened. Look for signs of excessive heat on the meter base e.g. melted plastic or discoloration related to heat
  • 24. 24 Testing Theory and Equipment Most Important Tools You Have!
  • 25. 25 Testing Theory and Equipment Meter Accuracy Testing ā€“ A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX
  • 26. 26 Testing Theory and Equipment Meter Accuracy Testing ā€“ A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Watthour Meter - Measures Electrical Energy (kWh) Potential (V) * Current (I) = Power (W) Power Over Time = Energy (kWh)
  • 27. 27 Testing Theory and Equipment Meter Accuracy Testing ā€“ A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Energy Reference Standard - Measures Electrical Energy (kWh) - Higher Accuracy Class - Traceability to SI
  • 28. 28 Testing Theory and Equipment Meter Accuracy Testing ā€“ A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX - Apply the Same Voltage and Current to the Standard and Meter for a Defined Period of Time - Standard and Meter Should Measure the Same Energy - The Difference is the Error of the Meter
  • 29. 29 Testing Theory and Equipment Meter Accuracy Testing ā€“ A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Example: Standard Registers 100kWh / Meter Registers 101.38 Then the Error of the Meter is 1.38%
  • 31. 31 Example Application 9S Meter Installation 5A PHASE A SOURCE PHASE C PHASE B LOAD 400A 400A 400A 5A 5A
  • 34. 34 CTs Ratio For instance, a CT with a 400:5 ratio will produce 5A on the secondary, when 400A are applied to the primary.
  • 36. 36 Burden Rating The burden range, present in the secondary circuit, that the manufacturer will guarantee their CTā€™s will still accurately function, in regards to the ratio specification.
  • 37. 37 Ratio Testing Ratio of Primary Current to Secondary Current 5A PHASE A SOURCE LOAD 400A 400A 400A 5A 5A Calculate Ratio
  • 38. 38 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A Some burden will always be present ā€“ junctions, meter coils, test switches, cables, etc. CTā€™s must be able to maintain an accurate ratio with burden on the secondary.
  • 39. 39 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A Some burden will always be present ā€“ junctions, meter coils, test switches, cables, etc. CTā€™s must be able to maintain an accurate ratio with burden on the secondary.
  • 40. 40 Burden Testing Functionality with Burden Present on the Secondary Loop Example Burden Spec: 0.3% @ B0.1, B0.2, B0.5 or There should be less than the 0.3% change in secondary current from initial (ā€œ0ā€ burden) reading, when up to 0.5Ohms of burden is applied
  • 41. 41 Burden Testing Functionality with Burden Present on the Secondary Loop ANSI Burden Values 0.1 Ohms 0.2 Ohms 0.5 Ohms 1 Ohms 2 Ohms 4 Ohms 8 Ohms
  • 42. 42 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A .1 Ohm
  • 43. 43 Burden Testing 0.0000 1.0000 2.0000 3.0000 4.0000 5.0000 6.0000 0 2 4 6 8 Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000 0.3% @ B0.1, B0.2, B0.5 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A ā€“ 0.015 = 4.985A
  • 44. 44 Burden Testing 4.9500 4.9600 4.9700 4.9800 4.9900 5.0000 5.0100 5.0200 5.0300 5.0400 5.0500 0 0.2 0.4 0.6 0.8 1 Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000 0.3% @ B0.1, B0.2, B0.5 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A ā€“ 0.015 = 4.985A At 0.5Ohms of Burden the secondary current is still at 4.990A ā€“ Less than 0.3% change ā€“ Good CT!
  • 45. 45 Admittance Testing ā€¢ What is Admittance? ā€¢ Admittance testing measures the overall ā€œhealthā€ of the secondary loop of the CT. ā€¢ Measured in units of MiliSiemens (mS) ā€¢ Admittance is the inverse of impedance. ā€¢ Impedance is the opposition to current. ā€¢ Therefore, admittance testing measures the overall ā€œhealthā€ of the secondary loop of the CT.
  • 46. 46 Admittance Testing ā€¢ Admittance testing devices inject an audio sine wave signal into the secondary loop of the CT. ā€¢ The resulting current is measured. ā€¢ The voltage of the initial signal is known. ā€¢ From these two parameters, the impedance, and thus the admittance can be calculated.
  • 47. 47 Admittance Testing ā€¢ Admittance test results are not immediately intuitive. ā€¢ Some analysis and interpretation is need. ā€¢ What do all these mS values mean?
  • 48. 48 Admittance Testing Three phase process is recommended. 1.Test each CT individually 2.Test the matched sets 3.Test over time
  • 50. 50 References and Citations 1. http://www.texasmeter.com/ 2. https://home.howstuffworks.com/home-improvement/repair/how-to-do-home-electrical-repairs.htm 3. https://www.youtube.com/watch?v=SeyojxVonrk 4. https://www.tescometering.com/product/tesco-transockets/ 5. http://www.gecdurham.com/ 6. https://www.radianresearch.com/ 7. http://www.brooksutility.com/products/122
  • 51. 51 Questions and Discussion Rob Reese TESCO ā€“ The Eastern Specialty Company Bristol, PA 215-310-8809 (cell) This presentation can also be found under Meter Conferences and Schools on the TESCO website: www.tescometering.com