SlideShare a Scribd company logo
1
10/02/2012 Slide 1
Site Verification for
Newer Employees
Prepared by Rob Reese, TESCO
The Eastern Specialty Company
For NREA – Nebraska Rural Electric Association
February 9, 2021
2
Site Verification
• Why is Site Verification Important?
• More than Meter Testing
• Testing and Inspecting the Entire Service
• Self-Contained vs. Transformer-Rated Meter Installations
• Self-Contained Meter Installation Verifications
• What to Inspect and Test
• Transformer-Rated Meter Installation Verifications
• What to Inspect and Test
• Detailed Testing Theory and Equipment
• Meter Accuracy
• CT Burden, Ratio, Admittance
• Vectors and Harmonics
• Hot Socket
3
What is Site Verification?
Testing and inspection of more than just the
meter accuracy.
99.975% Registration
4
Premise
• Over much of the 20th century, utilities, regulators and customers each
relied upon lab and field meter testing efforts which were primarily focused
upon the accuracy of the watt-hour meter and demand register.
• This focus is now changing with the deployment of electronic AMR and
AMI meters to the majority of the 155 Million connected customers in North
America.
• The focus has now shifted from just the accuracy of the meter to also
checking other features of the meter (e.g. communication and disconnect
devices), the firmware versions and settings of the meter, and the overall
meter installations for both residential and C&I customers.
• Incorrect or miscalculated site information or undetected problems can
lead to an improperly metered customer not related to the meters accuracy
and could also lead to potential safety issues.
5
Field Testing
Common Features and Common Sources of Concern
Electro Mechanical meters were
subject to registration errors caused
by mechanical issues with moving
parts resulting in either the loss of
revenue to the utility or over billing
for the customer. Some of the more
common problems were:
• Friction wear
• Gear mesh misalignment
• Retarding magnet failure
• Timing motors
6
Electronic Meters – new failure modes require
new testing and inspection methods
Electronic meters fail as do electromechanical meters
but differently
• Their overall life expectancy is not nearly the same
• Failure modes include drift (unexpected)
• Failure modes include catastrophic (expected)
• Power supply damage due to lightning surges or other
causes
• LCD Display failures making a visual read impossible
when required
• AMR/AMI communications module failures requiring a field visit to repair or replace meter/AMI
module and get a read for billing purposes
• Failure modes include non-catastrophic but significant measurement error modes sometimes
attributed to improper meter programming and in some cases meter firmware issues.
• Failure modes can include non-measurement issues which render the meter ineffective or
inaccurate for billing purposes
• Clerical errors such as incorrect multipliers can do more damage than even the most catastrophic
equipment failure in the field.
7
Best Practices
• Residential vs Commercial
• Self-Contained vs Transformer Rated
• Follow the money and be as proactive as possible
8
• A meter test may not catch intermittent errors or identify errors with
other equipment at the site, e.g. CT’s & PT’s
• A discrepancy between what is thought to be at a given site and
what is actually at that site can cause a major billing error (either
over or under billed)
Why Site Verifications are a
Valuable Utility Tool
• It is important to remember that with
current systems it is not just the meter
that can cause a major error in the
measurement of a given service
• A meter test that indicates a meter is
within the required accuracy
parameters does not mean your service
is being measured and billed accurately
9
• While these numbers will vary from
utility to utility the basic premise
should be the same for all utilities
regarding where Meter Services
should focus their efforts –
follow the money.
Why C&I and what should we invest our
limited meter service resources here?
• Easy Answer: Money.
• These customers represent a disproportionately large
amount of the overall revenue for every utility in North
America.
• For some utilities the ten percent of their customers
who have transformer rated metering services can
represent over 70% of their overall revenue.
10
• Most Utilities do not have a comprehensive and
complete list of every instrument transformer on
their system that is involved in providing the billing
for the largest 10 to 20% of any utilities revenue.
• Most Utilities do not visit, document and verify
these same services on any regular basis.
• Best practices call for the on-site verification of a
Utilities “largest” customers on a periodic basis.
– There is no definition of what this verification
should entail
– There is no definition of what “largest” means
– There is no agreement on the frequency of this
“periodic” inspection
What are the opportunities that can be found in
this work and what are our industry’s “Best
Practices” for this type of work?
11
• A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if
an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over
a two year period). Does this mean that $10,000 per month or more defines large?
Define “Largest” and what this may represent
• Largest should be defined by revenue.
• Lost metering revenue is no longer
“recovered in the next rate case”, nor is
recovered metering revenue necessarily
“given back” in the next rate case.
• Utility Commissions are having less
tolerance for new rate cases.
• Over billing of any customer has always
been a public relations nightmare.
12
• A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if
an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over
a two year period). Does this mean that $10,000 per month or more defines large?
– I would argue that this size customer is universally a “Large customer” and that from here
each utility should decide how much smaller they should go in their definition of “Large”.
Define “Largest” and what this may represent
• Largest should be defined by revenue.
• Lost metering revenue is no longer
“recovered in the next rate case”, nor is
recovered metering revenue necessarily
“given back” in the next rate case.
• Utility Commissions are having less
tolerance for new rate cases.
• Over billing of any customer has always
been a public relations nightmare.
13
• If changes in usage, equipment failures in the metering service,
external damage to the service, or energy diversion at a single
“large” customer can pay for a single meter tech in just two or three
years, and a single meter tech can handle several of these
inspections in a single day, then there is ample cost justification for
inspecting these services at least once every year.
Define “Periodically” and how
frequent this may be
14
Self-Contained vs. Transformer Rated
Self Contained
(direct)
Transformer-Rated
(indirect)
15
Self-Contained Metering
Relatively Low Current
Example: 100A
Primarily Residential
(1S, 2S, 12S)
16
Self-Contained Metering
Primarily Residential
(1S, 2S, 12S)
17
Transformer-Rated Metering
Relatively High Current
Example: 400A
Primarily Commercial/Industrial
(9S, 16S)
18
Transformer-Rated Metering
Primarily Commercial/Industrial
(9S, 16S)
19
Self-Contained Metering Verification
Potential tasks to be completed:
Double check the meter number, the location the test result
and the meter record
Perform a visual safety inspection of the site. This includes
utility and customer equipment. Things to look for include
intact down ground on pole, properly attached enclosure,
unwanted voltage on enclosure, proper trimming and site
tidiness (absence of discarded seals, etc.)
Visually inspect for energy diversions (intentional and not).
This includes broken or missing wires, jumpers, unconnected
wires and foreign objects on meters or other metering
equipment. Broken or missing wires can seriously cause the
under measurement of energy.
Visually check lightning arrestors for damage.
Check for proper grounding and bonding of metering
equipment. Poor grounding and bonding practices may result
in inaccurate measurements that go undetected for long
periods of time. Implementing a single point ground policy and
practice can reduce or eliminate this type of issue.
20
Self-Contained Metering Verification
Verify service voltage.
Verify condition of metering control wire. This includes looking
for cracks in insulation, broken wires, loose connections, etc.
Test meter for accuracy. Verify demand if applicable with
observed load. If meter is performing compensation (line and/or
transformer losses) the compensation should be verified either
through direct testing at the site or by examining recorded pulse
data.
Look for signs of excessive heat on the meter base - melted
plastic or discoloration related to heat
21
Transformer-Rated Metering Verification
Potential list of tasks to be completed:
Double check the meter number, the location the test result and the
meter record
Perform a visual safety inspection of the site. This includes utility and
customer equipment. Things to look for include intact down ground on
pole, properly attached enclosure, unwanted voltage on enclosure,
proper trimming and site tidiness (absence of discarded seals, etc.)
Visually inspect for energy diversions (intentional and not). This includes
broken or missing wires, jumpers, open test switch, unconnected wires
and foreign objects on meters or other metering equipment. Broken or
missing wires can seriously cause the under measurement of energy. A
simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the
registration on either 3 element or 2 element metering, respectively.
Visually check lightning arrestors and transformers for damage or leaks.
Check for proper grounding and bonding of metering equipment. Poor
grounding and bonding practices may result in inaccurate measurements
that go undetected for long periods of time. Implementing a single point
ground policy and practice can reduce or eliminate this type of issue.
Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
22
Transformer-Rated Metering Verification
Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
Verify service voltage. Stuck regulator or seasonal capacitor can
impact service voltage.
Verify condition of metering control wire. This includes looking for
cracks in insulation, broken wires, loose connections, etc.
Compare the test switch wiring with the wiring at the CTs and VTs.
Verify CTs and VTs not cross wired. Be sure CTs are grounded in
one location (test switch) only.
Check for bad test switch by examining voltage at the top and
bottom of the switch. Also verify amps using amp probe on both
sides of the test switch. Verify neutral connection to cabinet
(voltage).
Check rotation by closing in one phase at a time at the test switch
and observing the phase meter for forward rotation. If forward
rotation is not observed measurements may be significantly
impacted as the phases are most likely cancelling each other out.
Test meter for accuracy. Verify demand if applicable with observed
load. If meter is performing compensation (line and/or transformer
losses) the compensation should be verified either through direct
testing at the site or by examining recorded pulse data.
23
Transformer-Rated Metering Verification
Verify metering vectors. Traditionally this has been done using
instruments such as a circuit analyzer. Many solid state meters
today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many
of these desired values are programmed into the meters
Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in
determining if unbalanced loads are present and if CTs are sized
properly. The vendor software generally has the ability to capture
both diagnostic and vector information electronically. These
electronic records should be kept in the meter shop for future
comparisons.
If metering is providing pulses/EOI pulse to customers, SCADA
systems or other meters for totalization they also should be verified
vs. the known load on the meter. If present test/inspect isolation
relays/pulse splitters for things like blown fuses to ensure they are
operating properly.
Verify meter information including meter multiplier (rework it), serial
number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in
this type of information can also cause a adverse impact on
measured/reported values.
24
Transformer-Rated Metering Verification
Verify CT shunts are all opened.
Look for signs of excessive heat on the meter base e.g.
melted plastic or discoloration related to heat
25
Testing Theory and Equipment
Most Important Tools You Have!
26
Testing Theory and Equipment
Meter Accuracy Testing – A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
27
Testing Theory and Equipment
Meter Accuracy Testing – A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Watthour Meter
- Measures Electrical Energy (kWh)
Potential (V) * Current (I) = Power (W)
Power Over Time = Energy (kWh)
28
Testing Theory and Equipment
Meter Accuracy Testing – A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Energy Reference Standard
- Measures Electrical Energy (kWh)
- Higher Accuracy Class
- Traceability to SI
29
Testing Theory and Equipment
Meter Accuracy Testing – A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
- Apply the Same Voltage and Current to the Standard and Meter for a Defined Period of Time
- Standard and Meter Should Measure the Same Energy
- The Difference is the Error of the Meter
30
Testing Theory and Equipment
Meter Accuracy Testing – A Comparison Test
CURRENT
SOURCE
POTENTIAL
SOURCE
ENERGY
REFERENCE
STANDARD
XXXXXXXXX
Example:
Standard Registers 100kWh / Meter Registers 101.38
Then the Error of the Meter is 1.38%
31
CT Testing
Ratio, Burden, and Admittance
32
Example Application
9S Meter
Installation
5A
PHASE A
SOURCE
PHASE C
PHASE B
LOAD
400A
400A
400A
5A
5A
33
Faceplate Specifications
34
Faceplate Specifications
Ratio
35
CTs Ratio
For instance, a CT with a 400:5 ratio will
produce 5A on the secondary, when 400A
are applied to the primary.
36
Faceplate Specifications
Burden
Rating
37
Burden Rating
The burden range, present in the secondary
circuit, that the manufacturer will guarantee
their CT’s will still accurately function, in
regards to the ratio specification.
38
Ratio Testing
Ratio of Primary Current to Secondary Current
5A
PHASE A
SOURCE LOAD
400A
400A
400A
5A
5A
Calculate
Ratio
39
Burden Testing
Functionality with Burden Present on the Secondary Loop
PHASE A
Some burden will always be
present – junctions, meter coils,
test switches, cables, etc.
CT’s must be able to maintain
an accurate ratio with burden on
the secondary.
40
Burden Testing
Functionality with Burden Present on the
Secondary Loop
PHASE A
Some burden will always be
present – junctions, meter coils,
test switches, cables, etc.
CT’s must be able to maintain
an accurate ratio with burden on
the secondary.
41
Burden Testing
Functionality with Burden Present on the Secondary Loop
Example Burden Spec:
0.3% @ B0.1, B0.2, B0.5
or
There should be less than the 0.3%
change in secondary current from initial
(“0” burden) reading, when up to
0.5Ohms of burden is applied
42
Burden Testing
Functionality with Burden Present on the Secondary Loop
ANSI Burden Values
0.1 Ohms
0.2 Ohms
0.5 Ohms
1 Ohms
2 Ohms
4 Ohms
8 Ohms
43
Burden Testing
Functionality with Burden Present on the
Secondary Loop
PHASE A
.1 Ohm
44
Burden Testing
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
45
Burden Testing
4.9500
4.9600
4.9700
4.9800
4.9900
5.0000
5.0100
5.0200
5.0300
5.0400
5.0500
0 0.2 0.4 0.6 0.8 1
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
0.3% @ B0.1, B0.2, B0.5
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
At 0.5Ohms of Burden
the secondary current is still at
4.990A – Less than 0.3% change –
Good CT!
46
Admittance Testing
• What is Admittance?
• Admittance testing measures the
overall “health” of the secondary
loop of the CT.
• Measured in units of MiliSiemens
(mS)
• Admittance is the inverse of
impedance.
• Impedance is the opposition to
current.
• Therefore, admittance testing
measures the overall “health” of
the secondary loop of the CT.
47
Admittance Testing
• Admittance testing devices inject an audio sine
wave signal into the secondary loop of the CT.
• The resulting current is measured.
• The voltage of the initial signal is known.
• From these two parameters, the impedance,
and thus the admittance can be calculated.
48
Admittance Testing
• Admittance test results are not immediately
intuitive.
• Some analysis and interpretation is need.
• What do all these mS values mean?
49
Admittance Testing
Three phase process is recommended.
1.Test each CT individually
2.Test the matched sets
3.Test over time
50
Hot Socket Checks
51
References and Citations
1. http://www.texasmeter.com/
2. https://home.howstuffworks.com/home-improvement/repair/how-to-do-home-electrical-repairs.htm
3. https://www.youtube.com/watch?v=SeyojxVonrk
4. https://www.tescometering.com/product/tesco-transockets/
5. http://www.gecdurham.com/
6. https://www.radianresearch.com/
7. http://www.brooksutility.com/products/122
52
Questions and Discussion
Rob Reese
TESCO – The Eastern Specialty Company
Bristol, PA
215-310-8809 (cell)
This presentation can also be found under Meter
Conferences and Schools on the TESCO website:
www.tescometering.com

More Related Content

What's hot

Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
TESCO - The Eastern Specialty Company
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
TESCO - The Eastern Specialty Company
 
Simulating Real World Metering Conditions
Simulating Real World Metering ConditionsSimulating Real World Metering Conditions
Simulating Real World Metering Conditions
TESCO - The Eastern Specialty Company
 
Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter Testing
TESCO - The Eastern Specialty Company
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
TESCO - The Eastern Specialty Company
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Communicating to Your Meters
Communicating to Your MetersCommunicating to Your Meters
Communicating to Your Meters
TESCO - The Eastern Specialty Company
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
TESCO - The Eastern Specialty Company
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
TESCO - The Eastern Specialty Company
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
TESCO - The Eastern Specialty Company
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
TESCO - The Eastern Specialty Company
 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
TESCO - The Eastern Specialty Company
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
TESCO - The Eastern Specialty Company
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Metering Configurations
TESCO Tuesday: Metering ConfigurationsTESCO Tuesday: Metering Configurations
TESCO Tuesday: Metering Configurations
TESCO - The Eastern Specialty Company
 
Field Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair KitsField Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair Kits
TESCO - The Eastern Specialty Company
 
ANSI C12.1 Overview
ANSI C12.1 OverviewANSI C12.1 Overview
Hioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogueHioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogue
NIHON DENKEI SINGAPORE
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
TESCO - The Eastern Specialty Company
 
Hioki Field measuring instruments 2022 catalogue
Hioki Field measuring instruments 2022 catalogueHioki Field measuring instruments 2022 catalogue
Hioki Field measuring instruments 2022 catalogue
NIHON DENKEI SINGAPORE
 

What's hot (20)

Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 
Simulating Real World Metering Conditions
Simulating Real World Metering ConditionsSimulating Real World Metering Conditions
Simulating Real World Metering Conditions
 
Self Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter TestingSelf Contained Metering Fundamentals and Introduction to Meter Testing
Self Contained Metering Fundamentals and Introduction to Meter Testing
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Communicating to Your Meters
Communicating to Your MetersCommunicating to Your Meters
Communicating to Your Meters
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
TESCO Tuesday: Metering Configurations
TESCO Tuesday: Metering ConfigurationsTESCO Tuesday: Metering Configurations
TESCO Tuesday: Metering Configurations
 
Field Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair KitsField Test Kits and Hot Socket Repair Kits
Field Test Kits and Hot Socket Repair Kits
 
ANSI C12.1 Overview
ANSI C12.1 OverviewANSI C12.1 Overview
ANSI C12.1 Overview
 
Hioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogueHioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogue
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
 
Hioki Field measuring instruments 2022 catalogue
Hioki Field measuring instruments 2022 catalogueHioki Field measuring instruments 2022 catalogue
Hioki Field measuring instruments 2022 catalogue
 

Similar to Site Verification for Newer Employees

AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
TESCO - The Eastern Specialty Company
 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
TESCO - The Eastern Specialty Company
 
Field Testing
Field TestingField Testing
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
TESCO - The Eastern Specialty Company
 
Self-Contained Fundamentals
Self-Contained FundamentalsSelf-Contained Fundamentals
Self-Contained Fundamentals
TESCO - The Eastern Specialty Company
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
TESCO - The Eastern Specialty Company
 
Introduction to Self-Contained Metering
Introduction to Self-Contained MeteringIntroduction to Self-Contained Metering
Introduction to Self-Contained Metering
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
TESCO - The Eastern Specialty Company
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
TESCO - The Eastern Specialty Company
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
Meter Operations In a Post AMI World
Meter Operations In a Post AMI WorldMeter Operations In a Post AMI World
Meter Operations In a Post AMI World
TESCO - The Eastern Specialty Company
 
Meter Testing 101
Meter Testing 101Meter Testing 101
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
TESCO - The Eastern Specialty Company
 

Similar to Site Verification for Newer Employees (20)

AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
Field Testing
Field TestingField Testing
Field Testing
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
Self-Contained Fundamentals
Self-Contained FundamentalsSelf-Contained Fundamentals
Self-Contained Fundamentals
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
Introduction to Self-Contained Metering
Introduction to Self-Contained MeteringIntroduction to Self-Contained Metering
Introduction to Self-Contained Metering
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Operations In a Post AMI World
Meter Operations In a Post AMI WorldMeter Operations In a Post AMI World
Meter Operations In a Post AMI World
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 

Recently uploaded

Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 

Recently uploaded (20)

Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 

Site Verification for Newer Employees

  • 1. 1 10/02/2012 Slide 1 Site Verification for Newer Employees Prepared by Rob Reese, TESCO The Eastern Specialty Company For NREA – Nebraska Rural Electric Association February 9, 2021
  • 2. 2 Site Verification • Why is Site Verification Important? • More than Meter Testing • Testing and Inspecting the Entire Service • Self-Contained vs. Transformer-Rated Meter Installations • Self-Contained Meter Installation Verifications • What to Inspect and Test • Transformer-Rated Meter Installation Verifications • What to Inspect and Test • Detailed Testing Theory and Equipment • Meter Accuracy • CT Burden, Ratio, Admittance • Vectors and Harmonics • Hot Socket
  • 3. 3 What is Site Verification? Testing and inspection of more than just the meter accuracy. 99.975% Registration
  • 4. 4 Premise • Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. • This focus is now changing with the deployment of electronic AMR and AMI meters to the majority of the 155 Million connected customers in North America. • The focus has now shifted from just the accuracy of the meter to also checking other features of the meter (e.g. communication and disconnect devices), the firmware versions and settings of the meter, and the overall meter installations for both residential and C&I customers. • Incorrect or miscalculated site information or undetected problems can lead to an improperly metered customer not related to the meters accuracy and could also lead to potential safety issues.
  • 5. 5 Field Testing Common Features and Common Sources of Concern Electro Mechanical meters were subject to registration errors caused by mechanical issues with moving parts resulting in either the loss of revenue to the utility or over billing for the customer. Some of the more common problems were: • Friction wear • Gear mesh misalignment • Retarding magnet failure • Timing motors
  • 6. 6 Electronic Meters – new failure modes require new testing and inspection methods Electronic meters fail as do electromechanical meters but differently • Their overall life expectancy is not nearly the same • Failure modes include drift (unexpected) • Failure modes include catastrophic (expected) • Power supply damage due to lightning surges or other causes • LCD Display failures making a visual read impossible when required • AMR/AMI communications module failures requiring a field visit to repair or replace meter/AMI module and get a read for billing purposes • Failure modes include non-catastrophic but significant measurement error modes sometimes attributed to improper meter programming and in some cases meter firmware issues. • Failure modes can include non-measurement issues which render the meter ineffective or inaccurate for billing purposes • Clerical errors such as incorrect multipliers can do more damage than even the most catastrophic equipment failure in the field.
  • 7. 7 Best Practices • Residential vs Commercial • Self-Contained vs Transformer Rated • Follow the money and be as proactive as possible
  • 8. 8 • A meter test may not catch intermittent errors or identify errors with other equipment at the site, e.g. CT’s & PT’s • A discrepancy between what is thought to be at a given site and what is actually at that site can cause a major billing error (either over or under billed) Why Site Verifications are a Valuable Utility Tool • It is important to remember that with current systems it is not just the meter that can cause a major error in the measurement of a given service • A meter test that indicates a meter is within the required accuracy parameters does not mean your service is being measured and billed accurately
  • 9. 9 • While these numbers will vary from utility to utility the basic premise should be the same for all utilities regarding where Meter Services should focus their efforts – follow the money. Why C&I and what should we invest our limited meter service resources here? • Easy Answer: Money. • These customers represent a disproportionately large amount of the overall revenue for every utility in North America. • For some utilities the ten percent of their customers who have transformer rated metering services can represent over 70% of their overall revenue.
  • 10. 10 • Most Utilities do not have a comprehensive and complete list of every instrument transformer on their system that is involved in providing the billing for the largest 10 to 20% of any utilities revenue. • Most Utilities do not visit, document and verify these same services on any regular basis. • Best practices call for the on-site verification of a Utilities “largest” customers on a periodic basis. – There is no definition of what this verification should entail – There is no definition of what “largest” means – There is no agreement on the frequency of this “periodic” inspection What are the opportunities that can be found in this work and what are our industry’s “Best Practices” for this type of work?
  • 11. 11 • A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over a two year period). Does this mean that $10,000 per month or more defines large? Define “Largest” and what this may represent • Largest should be defined by revenue. • Lost metering revenue is no longer “recovered in the next rate case”, nor is recovered metering revenue necessarily “given back” in the next rate case. • Utility Commissions are having less tolerance for new rate cases. • Over billing of any customer has always been a public relations nightmare.
  • 12. 12 • A facility with an electric bill of $10,000 per month would pay for a meter tech in two years if an error affecting the wiring of only one transformer (estimated lost revenue $160,000 over a two year period). Does this mean that $10,000 per month or more defines large? – I would argue that this size customer is universally a “Large customer” and that from here each utility should decide how much smaller they should go in their definition of “Large”. Define “Largest” and what this may represent • Largest should be defined by revenue. • Lost metering revenue is no longer “recovered in the next rate case”, nor is recovered metering revenue necessarily “given back” in the next rate case. • Utility Commissions are having less tolerance for new rate cases. • Over billing of any customer has always been a public relations nightmare.
  • 13. 13 • If changes in usage, equipment failures in the metering service, external damage to the service, or energy diversion at a single “large” customer can pay for a single meter tech in just two or three years, and a single meter tech can handle several of these inspections in a single day, then there is ample cost justification for inspecting these services at least once every year. Define “Periodically” and how frequent this may be
  • 14. 14 Self-Contained vs. Transformer Rated Self Contained (direct) Transformer-Rated (indirect)
  • 15. 15 Self-Contained Metering Relatively Low Current Example: 100A Primarily Residential (1S, 2S, 12S)
  • 17. 17 Transformer-Rated Metering Relatively High Current Example: 400A Primarily Commercial/Industrial (9S, 16S)
  • 19. 19 Self-Contained Metering Verification Potential tasks to be completed: Double check the meter number, the location the test result and the meter record Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. Visually check lightning arrestors for damage. Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue.
  • 20. 20 Self-Contained Metering Verification Verify service voltage. Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data. Look for signs of excessive heat on the meter base - melted plastic or discoloration related to heat
  • 21. 21 Transformer-Rated Metering Verification Potential list of tasks to be completed: Double check the meter number, the location the test result and the meter record Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. Visually check lightning arrestors and transformers for damage or leaks. Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. Burden, Ratio, and/or Admittance test CTs and voltage check PTs.
  • 22. 22 Transformer-Rated Metering Verification Burden, Ratio, and/or Admittance test CTs and voltage check PTs. Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage. Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross wired. Be sure CTs are grounded in one location (test switch) only. Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data.
  • 23. 23 Transformer-Rated Metering Verification Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. If present test/inspect isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly. Verify meter information including meter multiplier (rework it), serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values.
  • 24. 24 Transformer-Rated Metering Verification Verify CT shunts are all opened. Look for signs of excessive heat on the meter base e.g. melted plastic or discoloration related to heat
  • 25. 25 Testing Theory and Equipment Most Important Tools You Have!
  • 26. 26 Testing Theory and Equipment Meter Accuracy Testing – A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX
  • 27. 27 Testing Theory and Equipment Meter Accuracy Testing – A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Watthour Meter - Measures Electrical Energy (kWh) Potential (V) * Current (I) = Power (W) Power Over Time = Energy (kWh)
  • 28. 28 Testing Theory and Equipment Meter Accuracy Testing – A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Energy Reference Standard - Measures Electrical Energy (kWh) - Higher Accuracy Class - Traceability to SI
  • 29. 29 Testing Theory and Equipment Meter Accuracy Testing – A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX - Apply the Same Voltage and Current to the Standard and Meter for a Defined Period of Time - Standard and Meter Should Measure the Same Energy - The Difference is the Error of the Meter
  • 30. 30 Testing Theory and Equipment Meter Accuracy Testing – A Comparison Test CURRENT SOURCE POTENTIAL SOURCE ENERGY REFERENCE STANDARD XXXXXXXXX Example: Standard Registers 100kWh / Meter Registers 101.38 Then the Error of the Meter is 1.38%
  • 32. 32 Example Application 9S Meter Installation 5A PHASE A SOURCE PHASE C PHASE B LOAD 400A 400A 400A 5A 5A
  • 35. 35 CTs Ratio For instance, a CT with a 400:5 ratio will produce 5A on the secondary, when 400A are applied to the primary.
  • 37. 37 Burden Rating The burden range, present in the secondary circuit, that the manufacturer will guarantee their CT’s will still accurately function, in regards to the ratio specification.
  • 38. 38 Ratio Testing Ratio of Primary Current to Secondary Current 5A PHASE A SOURCE LOAD 400A 400A 400A 5A 5A Calculate Ratio
  • 39. 39 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A Some burden will always be present – junctions, meter coils, test switches, cables, etc. CT’s must be able to maintain an accurate ratio with burden on the secondary.
  • 40. 40 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A Some burden will always be present – junctions, meter coils, test switches, cables, etc. CT’s must be able to maintain an accurate ratio with burden on the secondary.
  • 41. 41 Burden Testing Functionality with Burden Present on the Secondary Loop Example Burden Spec: 0.3% @ B0.1, B0.2, B0.5 or There should be less than the 0.3% change in secondary current from initial (“0” burden) reading, when up to 0.5Ohms of burden is applied
  • 42. 42 Burden Testing Functionality with Burden Present on the Secondary Loop ANSI Burden Values 0.1 Ohms 0.2 Ohms 0.5 Ohms 1 Ohms 2 Ohms 4 Ohms 8 Ohms
  • 43. 43 Burden Testing Functionality with Burden Present on the Secondary Loop PHASE A .1 Ohm
  • 44. 44 Burden Testing 0.0000 1.0000 2.0000 3.0000 4.0000 5.0000 6.0000 0 2 4 6 8 Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000 0.3% @ B0.1, B0.2, B0.5 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A – 0.015 = 4.985A
  • 45. 45 Burden Testing 4.9500 4.9600 4.9700 4.9800 4.9900 5.0000 5.0100 5.0200 5.0300 5.0400 5.0500 0 0.2 0.4 0.6 0.8 1 Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000 0.3% @ B0.1, B0.2, B0.5 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A – 0.015 = 4.985A At 0.5Ohms of Burden the secondary current is still at 4.990A – Less than 0.3% change – Good CT!
  • 46. 46 Admittance Testing • What is Admittance? • Admittance testing measures the overall “health” of the secondary loop of the CT. • Measured in units of MiliSiemens (mS) • Admittance is the inverse of impedance. • Impedance is the opposition to current. • Therefore, admittance testing measures the overall “health” of the secondary loop of the CT.
  • 47. 47 Admittance Testing • Admittance testing devices inject an audio sine wave signal into the secondary loop of the CT. • The resulting current is measured. • The voltage of the initial signal is known. • From these two parameters, the impedance, and thus the admittance can be calculated.
  • 48. 48 Admittance Testing • Admittance test results are not immediately intuitive. • Some analysis and interpretation is need. • What do all these mS values mean?
  • 49. 49 Admittance Testing Three phase process is recommended. 1.Test each CT individually 2.Test the matched sets 3.Test over time
  • 51. 51 References and Citations 1. http://www.texasmeter.com/ 2. https://home.howstuffworks.com/home-improvement/repair/how-to-do-home-electrical-repairs.htm 3. https://www.youtube.com/watch?v=SeyojxVonrk 4. https://www.tescometering.com/product/tesco-transockets/ 5. http://www.gecdurham.com/ 6. https://www.radianresearch.com/ 7. http://www.brooksutility.com/products/122
  • 52. 52 Questions and Discussion Rob Reese TESCO – The Eastern Specialty Company Bristol, PA 215-310-8809 (cell) This presentation can also be found under Meter Conferences and Schools on the TESCO website: www.tescometering.com