SlideShare a Scribd company logo
1 of 21
Download to read offline
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Module 8 
(Lectures 29 to 34) 
PILE FOUNDATIONS 
Topics 
29.1 INTRODUCTION 
29.2 TYPES OF PILES AND THEIR STRUCTURAL 
CHARACTERISTICS 
 Steel Piles 
 Concrete Piles 
 Cased Pile 
 Uncased Pile 
 Timber Piles 
 Composite Piles 
 Comparison of Pile Types 
29.3 ESTIMATING PILE LENGTH 
 Point Bearing Piles 
 Friction Piles 
 Compaction Piles 
29.4 INSTALLATION OF PILES 
30.1 LOAD TRANSFER MECHANISM 
30.2 EQUATIONS FOR ESTIMATING PILE CAPACITY 
 Point Bearing Capacity, 푸푸풑풑 
 Frictional Resistance, 푸푸풔풔 
30.3 MEYERHOF’S METHODS ESTIMATION OF 푸푸풑풑
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
 Sand 
 Clay (흓흓 = ퟎퟎ 퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜) 
30.4 VESIC’S METHOD-ESTIMATION OF 푸푸풑풑 
30.5 JANBU’S METHOD-ESTIMATION OF 푸푸풑풑 
30.6 COYLE AND CASTELLO’S METHOD-ESTIMATION OF 
푸푸풑풑 IN SAND 
30.7 FRICTIONAL RESISTANCE (푸푸풔풔) IN SAND 
31.1 FRICTIONAL (SKIN) RESISTANCE IN CLAY 
31.2 POINT BEARING CAPACITY OF PILES RESTING ON 
ROCK 
31.3 PILE LOAD TESTS 
32.1COMPARISON OF THEORY WITH FIELD LOAD TEST 
RESULTS 
32.2SETTLEMENT OF PILES 
32.3 PULLOUT RESISTANCE OF PILES 
 Piles in Clay 
 Piles in Sand 
32.4 LATERALLY LOADED PILES 
 Elastic Solution 
 Ultimate Load Analysis-Brom’s Method 
 Ultimate Load Analysis-Meyerhof’s Method 
 Piles in Sand 
33.1 PILE-DRIVING FORMULA
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
33.2 NEGATIVE SKIN FRICTION 
 Clay Fill over Granular Soil 
 Granular Soil Fill over Clay 
33.3 GROUP PILES 
33.4 GROUP EFFICIENCY 
34.1 ULTIMATE CAPACITY OF GROUP 
34.2 PILES IN SATURATED CLAY 
34.3 PILES IN ROCK 
34.4 CONSOLIDATION SETTLEMENT OF GROUP PILES 
34.5 ELASTIC SETTLEMENT OF GROUP PILES 
34.6 UPLIFT CAPACITY OF GROUP PILES 
PROBLEMS 
REFERENCES
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Module 8 
Lecture 29 
PILE FOUNDATIONS 
Topics 
1.2 INTRODUCTION 
1.3 TYPES OF PILES AND THEIR STRUCTURAL 
CHARACTERISTICS 
 Steel Piles 
 Concrete Piles 
 Cased Pile 
 Uncased Pile 
 Timber Piles 
 Composite Piles 
 Comparison of Pile Types 
1.4ESTIMATING PILE LENGTH 
 Point Bearing Piles 
 Friction Piles 
 Compaction Piles 
1.5 INSTALLATION OF PILES
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
INTRODUCTION 
Piles are structural members that are made of steel, concrete, and/or timber. They are 
used to build pile foundations, which are deep and which cost more than shallow 
foundations (chapters 3 and 4). Despite the cost, the use of piles often is necessary to 
ensure structural safety. The following list identifies some of the conditions that require 
pile foundations (Vesic, 1977). 
1. When the upper soil layer(s) is (are) highly compressible and too weak to support 
the load transmitted by the superstructure, piles are used to transmit the load to 
underlying bedrocks or a stronger soil layer, as shown in figure 8.1a. When 
bedrock is not encountered at a reasonable depth below the ground surface, piles 
are used to transmit the structural load to the soil gradually. The resistance to the 
applied structural load is derived mainly from the frictional resistance developed 
at the soil-pile interface (figure 8. 1b). 
Figure 8.1 Conditions for use of pile foundations
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
2. When subjected to horizontal forces (see figure 8.1c), pile foundations resist by 
bending while still supporting the vertical load transmitted by the superstructure. 
This type of situation is generally encountered in the design and construction of 
earth-retaining structures and foundations of tall structures that are subject to high 
wind and/or earthquake forces. 
3. In many cases, expansive and collapsible soils (chapter 11) may be present at the 
site of a proposed structure. These soils may extend to a great depth below the 
ground surface. Expansive soils swell and shrink as the moisture content increases 
and decreases, and the swelling pressure of such soils can be considerable. If 
shallow foundations are used in such circumstances, the structure may suffer 
considerable damage. However, pile foundations may be considered as an 
alternative when pies are extended beyond the active zone, which swells and 
shrinks (figure 8.1d). 
Soils such as loess are collapsible in nature. When the moisture content of these 
soils increases, their structures ay break down. A sudden decrease in the void ratio 
of soil induces large settlements of structures supported by shallow foundations. 
In such cases, piles foundations may be used in which piles are extended into 
stable soil layers beyond the zone of possible moisture change. 
4. Foundations of some structures, such as transmission towers, offshore platforms, 
and basement mats below the water table, are subjected to uplifting forces. Piles 
are sometimes used for these foundations to resist the uplifting force (figure 8. 
1e). 
5. Bridge abutments and piers are usually constructed over pile foundations to avoid 
the possible loss of bearing capacity that a shallow foundation might suffer 
because of soil erosion at the ground surface (figure 8.1f). 
TYPES OF PILES AND THEIR STRUCTURAL CHARACTERISTICS 
Different types of piles are used in construction work, depending on the type of load to be 
carried, the subsoil conditions, and the location of the water table. Piles can be divided 
into the following categories: (a) steel piles (b) concrete piles, (c) wooden (timber) piles, 
and (d) composite piles. 
Steel Piles 
Steel piles generally are either pile piles or rolled steel H-section piles. Pipe piles can be 
driven into the ground with their ends open or closed. Wide-flange and I-section steel 
beams can also be used as piles. However, H-section piles are usually preferred because 
their wed and flange thicknesses are equal. In wide-flange and I-section beams, the wed 
thicknesses are smaller than the thicknesses of the flange. Table D. I. (Appendix D) gives 
the dimensions of some standard H-section steel piles used in the United States. Table 
D.2 (Appendix D) shows selected pile sections frequently used for piling purposes. In 
many cases, the pile piles are filled with concrete after driving.
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
The allowable structural capacity for steel piles is 
푄푄all = 퐴퐴푠푠푓푓푠푠 [8.1] 
Where 
퐴퐴푠푠 = cross − sectional area of the steel 
푓푓푠푠 = allowable stress of steel 
Based on geotechnical considerations (once the design load for a pile is fixed) 
determining whether 푄푄(design ) is within the allowable range as defined by equation 1) is 
always advisable. 
When necessary, steel piles are spliced by welding or by riveting. Figure 8. 2a shows a 
typical condition of splicing by welding for an H-pile. A typical case of splicing by 
welding for a pipe is shown in figure 8. 2b. Figure 8. 2c shows a diagram of splicing an 
H-pile by rivets or bolts. 
Figure 8. 2 Steel piles: (a) splicing of H-pile by welding; (b) splicing of pile by welding; 
(c) splicing of H-pile rivets and bolts; (d) flat driving point of pipe pile; (e) conical 
driving point of pipe pile
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
When hard driving conditions are expected, such as driving through dense gravel, shale, 
and soft rock, steel piles can be fitted with driving points or shoes. Figure 8.2d and 8.2e 
are diagrams of two types of shoe used for pipe piles. 
Steel piles may be subject to corrosion. For example, swamps, peats, and other organic 
soils are corrosive. Soils that have a pH greater than 7 are not so corrosive. To offset the 
effect of corrosion, an additional thickness of steel (over the actual design cross-sectional 
area) is generally recommended. In many circumstances, factory-applied epoxy coatings 
on piles work satisfactorily against corrosion. These coatings are not easily damaged by 
pile driving. Concrete encasement of steel piles in most corrosive zones also protects 
against corrosion. 
Concrete Piles 
Concrete piles may be divided into two basic categories: (a) precise piles and (b) case-in-situ 
piles. Precast piles can be prepared by using ordinary reinforcement, and they can be 
square or octagonal in cross section (figure 8.3). Reinforcement is provided to enable the 
pile to resist the bending moment developed during pickup and transportation, the 
vertical load, and the bending moment caused by lateral load. The piles are cast to desired 
lengths and cured before being transported to the work sites. 
Figure 8.3 Precast piles with ordinary reinforcement 
Precise piles can also be prestressed by the use of high-strength steel prestressing cables. 
The ultimate strength of these steel cables is about 260 ksi (≈ 1800 MN/m2). During 
casting of the piles, the cables are pretensioned to about 130 − 190 ksi (≈ 900 − 
1300 MN/m2), and concrete is poured around them. After curing, the cables are cut, thus 
producing a compressive force on the pile section. Table D3 (Appendix D) gives 
additional information about prestressed concrete piles with square and octagonal cross 
sections. 
Cast-in-situ, or cast-in-place, piles are built by making a hole in the ground and then 
filling it with concrete. Various types of cast-in-place concrete pile are currently used in 
construction, and most of them have been pat ended by their manufactures. These piles
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
may be divided into two broad categories: (a) cased and (b) uncased. Both types may 
have a pedestal at the bottom. 
Cased piles are made by driving a steel casing into the ground with the help of a mandrel 
placed inside the casing. When the pile reaches the proper depth, the mandrel is 
withdrawn and the casing is filled with concrete. Figure 8.4a, b, c, and d show some 
examples of cased piles without a pedestal. Table 1 gives additional information about 
these cased piles. Figure 8.4 shows a cased pile with a pedestal. The pedestal is an 
expanded concrete bulb that is formed by dropping a hammer on fresh concrete. 
Figure 8.4 Cast-in-place concrete piles (see table 1 for descriptions) 
Figure 8.4f and 8.4g are two types of uncased pile, one with a pedestal and the other 
without. The uncased piles are made by first driving the casing to the desired depth and 
then filling it with fresh concrete. The casing is then gradually withdrawn. 
The allowable loads fore cast-in-place concrete piles are given by the following 
equations, 
Cased Pile 
푄푄all = 퐴퐴푠푠푓푓푠푠 + 퐴퐴푐푐 푓푓푐푐 [8.2a] 
Where
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
퐴퐴푠푠 = area of cross section of steel 
퐴퐴푐푐 = area of cross section of concrete 
푓푓푠푠 = allowable stress of steel 
푓푓푐푐 = allowable stress of concrete 
Uncased Pile 
푄푄all = 퐴퐴푐푐 푓푓푐푐 [2b] 
Table 1 Description of the Cast-in-Place Piles Shown in figure 8. 4 
Part in figure 8. 
4 Name of pile Type of casing 
Maximum usual depth of pile 
(ft) (meter) 
a Raymond Step- 
Taper 
Corrugated, 
thin, cylindrical 
casing 
100 30 
b Monotube or 
Union Metal 
Thin, fluted, 
tapered steel 
casing driven 
without mandrel 
130 40 
c Western cased Thin sheet 
casing 
100-130 30-40 
d Seamless pile or 
Armco 
Straight steel 
pipe casing 
160 50 
e Franki cased 
pedestal 
Thin sheet 
casing 
100-130 30-40 
f Western 
uncased without 
pedestal 
- 50-65 15-20 
g Franki uncased 
pedestal 
- 100-130 30-40 
Timber Piles 
Timber piles are tree trunks that have had their branches and bark carefully trimmed off. 
The maximum length of most timber piles is 30-65 ft (10-20 m). To qualify for use as a 
pile, the timber should be straight, sound, and without any defects. The American Society
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
of Civil Engineers’ Manual of Practice, No. 17 (1959), divided timber piles into three 
classifications: 
1. Class A piles carry heavy loads. The minimum diameter of the butt should be 14 
in. (356 mm). 
2. Class B piles are used to carry medium loads. The minimum butt diameter should 
be 12-13 in. (305-330 mm). 
3. Class C piles are used in temporary construction work. They can be used 
permanently for structures when the entire pile is below the water table. The 
minimum butt diameter should be 12 in. (305 mm). 
In any case, a pile tip should not have a diameter less than 6 in. (150 mm). 
Timber piles cannot withstand hard driving stress; therefore, the pile capacity is generally 
limited to about 25-30 tons (220 − 270 kN). Steel shoes may be used to avoid damage at 
the pile tip (bottom). The tops of timber piles may also be damaged during the driving 
operation. The crushing of the wooden fibers caused by the impact of the hammer is 
referred to as brooming. To avoid damage to the pile top, a metal band or a cap may be 
used. 
Splicing of timber piles should he avoided, particularly when they are expected to carry 
tensile load or lateral load. However, if splicing is necessary, it can be done by using pile 
sleeves (figure 8.5a) or metal straps and bolts (figure 8. 5b). The length of the pile sleeve 
should be at least five times the diameter of the pile. The butting ends should be cut 
square so that full contact can be maintained. The spliced portions should be carefully 
trimmed so that they fit tightly to the inside of the pile sleeve. In the case of metal straps 
and bolts, the butting ends should also be cut square. Also, the sides of the spliced portion 
should be trimmed plane for putting the straps on. 
Figure 8. 8.5 Splicing of timber piles: (a) use of pipe sleeves; (b) use of metal straps and 
bolts
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Timber piles can stay undamaged indefinitely if they are surrounded by saturated soil. 
However, in a marine environment timber piles are subject to attack by various organisms 
and can be damaged extensively in a few months. When located above the water table, 
the piles are subject to attach by insects. The life of the piles may be increased by treating 
them with preservatives such as creosote. 
The allowable load-carrying capacity of wooden piles is 
푄푄all = 퐴퐴푝푝 푓푓푤푤 [8.3] 
Where 
퐴퐴푝푝 = average area of cross section of the pile 
푓푓푤푤 = allowable stress for the timber 
The following allowable stresses are for pressure-treated round timber piles made from 
Pacific Coast Douglas fir and Southern pine, when used in hydraulic structures (ASCE, 
1993). 
Allowable stress Pacific coast Douglas fir Southern pine 
Compression parallel to 
gain 
875 lb/in2 (6.04 MN/m2) 825 lb/in2 (5.7MN/m2) 
Bending 1700 lb/in2 (11.7 MN/ 
m2) 
1650 lb/in2 (11.4 MN/ 
m2) 
Horizontal shear 95 lb/in2 (0.66 MN/m2) 90 lb/in2 (0.62 MN/m2) 
Compression perpendicular 
to grain 
190 lb/in2 (1.31 MN/m2) 205 lb/in2 (1.41 MN/m2) 
Composite Piles 
The upper and lower portions of composite piles are made of different materials. For 
example, composite piles may be made of steel and concrete or timber and concrete. Steel 
and concrete piles consist of a lower portion of steel and an upper portion of cast-in-place 
concrete. This type of pile is the one used when the length of the pile required for 
adequate bearing exceeds the capacity of simple cast-in-place concrete piles. Timber and 
concrete piles usually consist of a lower portion of timber pile below the permanent water 
table and an upper portion of concrete. In any case, forming proper joints between two 
dissimilar materials is difficult, and, for that reason, composite piles are not widely used. 
Comparison of Pile Types
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Several factors affect the selection of piles for a particular structure at a specific site. 
Table 2 gives a brief comparison of the advantages and disadvantages of the various 
types of pile based on the pile material. 
Table 2 Comparison of Piles Made of Different Materials 
Pile 
type 
Usual 
length of 
piles 
Maximum 
length of 
pile 
Usual load Approximate 
maximum load 
Comments 
Steel 50-200 ft 
(15-60 m) 
Practicall 
y 
unlimited 
67 
− 270 kip (300 
− 1200 kN) 
Equation (1) Advantages 
a. Easy to 
handle with 
respect to 
cutoff and 
extension to 
the desired 
length 
b. Can stand 
high driving 
stresses 
c. Can 
penetrate 
hard layers 
such as 
dense 
gravel, soft 
rock 
d. High load-carrying 
capacity 
Disadvantages 
a. Relatively 
costly 
material 
b. High level 
of noise 
during pile 
driving 
c. Subject to 
corrosion 
d. H-piles may 
be damaged 
or deflected
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
from the 
vertical 
during 
driving 
through 
hard layers 
or past 
major 
obstructions 
Precast 
concre 
te 
Precast: 
30-50 ft 
(10-15 m) 
Prestresse 
d: 
30-150 ft 
(`10-35 
m) 
Precast: 
100 ft (30 
m) 
Prestresse 
d: 
200 ft (60 
m) 
67 
− 675 kip (300 
− 3000 kN) 
Precast: 
180 
− 200 kip (800 
− 900 kN) 
Advantages 
Prestressed: 
1700 
− 1900 kip (7500 
− 8500 kN) 
a. Can be 
subjected to 
hard driving 
b. Corrosion 
resistant 
c. Can be 
easily 
combined 
with 
concrete 
superstructu 
re 
Disadvantages 
a. Difficult to 
achieve 
proper 
cutoff 
b. Difficult to 
transport 
Cased 
cast-in-place 
concre 
te 
15-50 ft 
(5-15 m) 
100-130 ft 
(30-40 m) 
180 kip (800 kN)Advantages 
45 115 kip (200 
− 50 kN) 
a. Relatively 
cheap 
b. Possibility 
of 
inspection 
before 
pouring 
concrete 
c. Easy to 
extend 
Disadvantages 
a. Difficult to 
splice after
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
concreting 
b. This casings 
may be 
damaged 
during 
driving 
Uncas 
ed 
cast-in-place 
concre 
te 
15-5- ft 
(5-15 m) 
100-130 ft 
(30-40 m) 
65 
− 115 kip (300 
− 500 kN) 
160 kip (700 kN)Advantages 
a. Initially 
economical 
b. Can be 
finished at 
ay elevation 
Disadvantages 
a. Voids may 
be created if 
concrete is 
placed 
rapidly 
b. Difficult to 
splice after 
concreting 
c. In soft soils, 
the sides of 
the hole 
may cave 
in, thus 
squeezing 
the concrete 
Wood 30-50 ft 
(10-15 m) 
100 ft (30 
m) 
2245 kip (100 
− 200 kN) 
60 kip (270 kN) Advantages 
a. Economical 
b. Easy to 
handle 
c. Permanentl 
y 
submerged 
piles are 
fairly 
resistant to 
decay 
Disadvantages 
a. Decay 
above water 
table
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
b. Can be 
damaged in 
hard driving 
c. Low load-bearing 
capacity 
d. Low 
resistance to 
tensile load 
when 
spliced 
ESTIMATING PILE LENGTH 
Selecting the type of pile to be used and estimating its necessary length are fairly difficult 
tasks that require good judgment. In addition to the classification given in section 2, piles 
can be divided into three major categories, depending on their lengths and the 
mechanisms of load transfer to the soil: (a) point bearing piles, (b) friction piles, and (c) 
compaction piles. 
Point Bearing Piles 
If soil-boring records establish the presence of bedrocks or rocklike material at a site 
within a reasonable depth, piles can be extended to the rock surface. (Figure 8.6a). In 
this case, the ultimate capacity of the piles depends entirely on the load bearing capacity 
of the underlying material; thus the piles are called point bearing piles. In most of these 
cases, the necessary length of the pile can be fairly well established. 
Figure 8.6 (a) and (b) Point bearing piles; (c) friction piles
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
If, instead to bedrock, a fairly compact and hard stratum of soil is encountered at a 
reasonable depth, piles can be extended a few meters into the hard stratum (figure 8. 6b). 
Piles with pedestals can be constructed on the bed of the hard stratum, and the ultimate 
pile load may be expressed as 
푄푄푢푢 + 푄푄푝푝 + 푄푄푠푠 [8.4] 
Where 
푄푄푝푝 = load carried at the pile point 
푄푄푠푠 = load carried by skin friction developed at the side of the pile (caused by 
shearing resistance between the soil and the pile) 
If 푄푄푠푠 is very small, 
푄푄푢푢 ≈ 푄푄푝푝 [8.5] 
In this case, the required pile length maybe estimated accurately if proper subsoil 
exploration records are available. 
Friction Piles 
When no layer of rock or rocklike material is present at a reasonable depth at a site, point 
bearing piles become very long and uneconomical. For this type o subsoil condition, piles 
are driven through the softer material to specified depths (figure 8. 6c). The ultimate load 
of these piles may be expressed by equation (4). However, if the value o 푄푄푝푝 is relatively 
small, 
푄푄푢푢 ≈ 푄푄푠푠 [8.6] 
These piles are called friction piles because most of the resistance is derived from skin 
friction. However, the term friction pile, although used often in the literature, is a 
misnomer: in clayey soils, the resistance to applied load is also caused by adhesion. 
The length of friction of piles depends on the shear strength of the soil, the applied load 
and the pile size. To determine the necessary lengths of these piles, an engineer needs a 
good understanding of soil-pile interaction, good judgment, and experience. Theoretical 
procedures for the calculation of load-bearing capacity of piles are presented later in this 
chapter. 
Compaction Piles 
Under certain circumstances, piles are driven in granular soils to achieve proper 
compaction of soil close to the ground surface. These piles are called compaction piles. 
The length of compaction piles depends on factors such as (a) relative density of the soil 
before compaction, (b) desired relative density of the soil after compaction, and (c) 
required depth of compaction. These piles are generally short; however, some field tests 
are necessary to determine a reasonable length.
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
INSTALLATION OF PILES 
Most piles are driven into the ground by means of hammers or vibratory drivers. In 
special circumstances, piles can also be inserted by jetting or partial augering. The types 
of hammer used for pile driving include the (a) drop hammer, (b) single acting air or 
steam hammer, (c) double-acting and differential air or steam hammer, and (d) diesel 
hammer. In the driving operation, a cap is attached to the top of the pile. A cushion may 
be used between the pile and the cap. This cushion has the effect of reducing the impact 
force and spreading it over a longer time; however, its use is optional. A hammer cushion 
is placed on the pile cap. The hammer drops on the cushion. 
Figure 8. 7 illustrated various hammers. A drop hammer (figure 8. 7a) is raised by a 
winch and allowed to drop from a certain height H. it is the oldest type of hammer used 
for pile driving. The main disadvantage of the drop hammer is the slow rate of hammer 
blows. The principle of the single-acting air or steam hammer is shown in figure 8. 7b. In 
this case, the striking part, or ram, is raised by air or steam pressure and then drops by 
gravity. Figure 8.7c shows the operation of the double-acting and differential air or steam 
hammer. For these hammers, air or steam is used both to raise the ram and to push it 
downward. This increases the impact velocity of the ram. The diesel hammer (figure 8. 
7d) essentially consists of a ram, an anvil block, and a fuel-injection system. During the 
operation, the ram is first raised and fuel is injected near the anvil. Then the ram is 
released. When the ram drops, it compresses the air fuel mixture, which ignites it. This 
action, in effect, pushes the pile downward and raises the ram. Diesel hammers work well 
under hard driving conditions. In soft sols, the downward movement of the pile is rather 
large, and the upward movement of the ram is small. This differential may not be 
sufficient to ignite the air-fuel system, so the ram may have to be lifted manually.
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Figure 8.7 Pile-driving equipment: (a) drop hammer; (b) single-acting air or seam 
hammer; (c) double-acting and differential air or steam hammer; (d) diesel hammer; (e) 
vibratory pile driver
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
Figure 8.7 (Continued) 
The principles of operation of a vibratory pile driver are shown in figure 8.7e. This driver 
essentially consists of two counter-rotating weights. The horizontal components of the 
centrifugal force generated as a result of rotating masses cancel each other. As a result, a 
sinusoidal dynamic vertical force is produced on the pile and helps drive the pile 
downward. 
Jetting is a technique sometimes used in pile driving when the pile needs to penetrate a 
thin layer of hard soil (such as sand and gravel) overlying a softer soil layer. In this
NPTEL – ADVANCED FOUNDATION ENGINEERING-I 
technique, water is discharged at the pile point by means of a pile 2-3 in. (50-75 mm) is 
diameter to wash and loosen the sand and gravel. 
Piles driven at an angle to the vertical, typically14° to 20°, are referred to as batter piles. 
Batter piles are used in group piles when higher lateral load-bearing capacity is required. 
Piles also may be advanced by partial augering, with power augers (chapter 2) being used 
to predrill holes part of the way. The piles can then be inserted into the holes and driven 
to the desired depth. 
Based on the nature of their placement, piles may be divided into two categories: 
displacement piles and nondisplacement piles. Driven piles are displacement piles 
because they move some soil laterally; hence there is a tendency for densification of soil 
surrounding them. Concrete piles and closed-ended pile piles are high-displacement piles. 
However, steel H-piles displace less soil laterally during driving, and so they are low-displacement 
piles. In contrast, bored piles are nondisplacement piles because their 
placement causes very little change in the state of stress in the soil.

More Related Content

What's hot

Retaining wall
Retaining wallRetaining wall
Retaining wall51412
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footingkamariya keyur
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.MD.MAHBUB UL ALAM
 
Settlement of soil with sand drains
Settlement of soil with sand drainsSettlement of soil with sand drains
Settlement of soil with sand drainsUmed Paliwal
 
Isolated footing design
Isolated footing designIsolated footing design
Isolated footing designsrinu_anduri
 
Aci 318 08-seismic-requirements-l e garcia
Aci 318 08-seismic-requirements-l e garciaAci 318 08-seismic-requirements-l e garcia
Aci 318 08-seismic-requirements-l e garciaAycin Mungan
 
Analyses and Ddesign of a Two Storied RC Building
Analyses and Ddesign of a Two Storied RC BuildingAnalyses and Ddesign of a Two Storied RC Building
Analyses and Ddesign of a Two Storied RC Buildingsandougah
 
how to calculate wind load on any building
how to calculate wind load on any building how to calculate wind load on any building
how to calculate wind load on any building Mahreen Zamir Abro
 
Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak Nada Zarrak
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel examplemamilli
 
Design of reinforced flat slabs to bs 8110 (ciria 110)
Design of reinforced flat slabs to bs 8110 (ciria 110)Design of reinforced flat slabs to bs 8110 (ciria 110)
Design of reinforced flat slabs to bs 8110 (ciria 110)bmxforu
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural AnalysisDavidJPCChai
 

What's hot (20)

Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footing
 
Two way slab
Two way slabTwo way slab
Two way slab
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.
 
Settlement of soil with sand drains
Settlement of soil with sand drainsSettlement of soil with sand drains
Settlement of soil with sand drains
 
Lateral Earth pressure
Lateral Earth pressureLateral Earth pressure
Lateral Earth pressure
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
pile wall
pile wallpile wall
pile wall
 
Isolated footing design
Isolated footing designIsolated footing design
Isolated footing design
 
Chapter 11
Chapter 11Chapter 11
Chapter 11
 
Aci 318 08-seismic-requirements-l e garcia
Aci 318 08-seismic-requirements-l e garciaAci 318 08-seismic-requirements-l e garcia
Aci 318 08-seismic-requirements-l e garcia
 
Staircase design
Staircase designStaircase design
Staircase design
 
Analyses and Ddesign of a Two Storied RC Building
Analyses and Ddesign of a Two Storied RC BuildingAnalyses and Ddesign of a Two Storied RC Building
Analyses and Ddesign of a Two Storied RC Building
 
Ch 7 design of rcc footing
Ch 7 design of rcc footingCh 7 design of rcc footing
Ch 7 design of rcc footing
 
how to calculate wind load on any building
how to calculate wind load on any building how to calculate wind load on any building
how to calculate wind load on any building
 
Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel example
 
Design of reinforced flat slabs to bs 8110 (ciria 110)
Design of reinforced flat slabs to bs 8110 (ciria 110)Design of reinforced flat slabs to bs 8110 (ciria 110)
Design of reinforced flat slabs to bs 8110 (ciria 110)
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural Analysis
 
Chapter 08
Chapter 08Chapter 08
Chapter 08
 

Similar to Foundation analysis and design

Pile foundation project_report
Pile foundation project_reportPile foundation project_report
Pile foundation project_reportBITANROY3
 
Profiled deck composite floors
Profiled deck composite floorsProfiled deck composite floors
Profiled deck composite floorsElamathy Murugan
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentationSevar Dilkhaz
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Buildingppt_master
 
Cfst columns
Cfst columns Cfst columns
Cfst columns amits2280
 
CFST Column Report
CFST Column ReportCFST Column Report
CFST Column ReportNandhuH
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx2020CEB005POTNURUSAI
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxanik7nziza
 
manual pile, practice installation with different method
manual pile, practice installation with different methodmanual pile, practice installation with different method
manual pile, practice installation with different methodvalter gentile
 
pppppppppppppppHighway
pppppppppppppppHighwaypppppppppppppppHighway
pppppppppppppppHighwayaapawar
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundationstooty s
 
PILE FOUNDATION (basics)
PILE FOUNDATION (basics)PILE FOUNDATION (basics)
PILE FOUNDATION (basics)Gaurav Paliwal
 
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEW
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEWCONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEW
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEWIRJET Journal
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabIRJET Journal
 
Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62hlksd
 

Similar to Foundation analysis and design (20)

Chap1
Chap1Chap1
Chap1
 
Pile foundation project_report
Pile foundation project_reportPile foundation project_report
Pile foundation project_report
 
Profiled deck composite floors
Profiled deck composite floorsProfiled deck composite floors
Profiled deck composite floors
 
Pile footing.pptx
Pile footing.pptxPile footing.pptx
Pile footing.pptx
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Cfst columns
Cfst columns Cfst columns
Cfst columns
 
CFST Column Report
CFST Column ReportCFST Column Report
CFST Column Report
 
2327
23272327
2327
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptx
 
manual pile, practice installation with different method
manual pile, practice installation with different methodmanual pile, practice installation with different method
manual pile, practice installation with different method
 
pppppppppppppppHighway
pppppppppppppppHighwaypppppppppppppppHighway
pppppppppppppppHighway
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Types Of Foundation
Types Of FoundationTypes Of Foundation
Types Of Foundation
 
PILE FOUNDATION (basics)
PILE FOUNDATION (basics)PILE FOUNDATION (basics)
PILE FOUNDATION (basics)
 
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEW
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEWCONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEW
CONCRETE-ENCASED CFST BEAM-COLUMN JOINTS: A REVIEW
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

Foundation analysis and design

  • 1. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Module 8 (Lectures 29 to 34) PILE FOUNDATIONS Topics 29.1 INTRODUCTION 29.2 TYPES OF PILES AND THEIR STRUCTURAL CHARACTERISTICS  Steel Piles  Concrete Piles  Cased Pile  Uncased Pile  Timber Piles  Composite Piles  Comparison of Pile Types 29.3 ESTIMATING PILE LENGTH  Point Bearing Piles  Friction Piles  Compaction Piles 29.4 INSTALLATION OF PILES 30.1 LOAD TRANSFER MECHANISM 30.2 EQUATIONS FOR ESTIMATING PILE CAPACITY  Point Bearing Capacity, 푸푸풑풑  Frictional Resistance, 푸푸풔풔 30.3 MEYERHOF’S METHODS ESTIMATION OF 푸푸풑풑
  • 2. NPTEL – ADVANCED FOUNDATION ENGINEERING-I  Sand  Clay (흓흓 = ퟎퟎ 퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜퐜) 30.4 VESIC’S METHOD-ESTIMATION OF 푸푸풑풑 30.5 JANBU’S METHOD-ESTIMATION OF 푸푸풑풑 30.6 COYLE AND CASTELLO’S METHOD-ESTIMATION OF 푸푸풑풑 IN SAND 30.7 FRICTIONAL RESISTANCE (푸푸풔풔) IN SAND 31.1 FRICTIONAL (SKIN) RESISTANCE IN CLAY 31.2 POINT BEARING CAPACITY OF PILES RESTING ON ROCK 31.3 PILE LOAD TESTS 32.1COMPARISON OF THEORY WITH FIELD LOAD TEST RESULTS 32.2SETTLEMENT OF PILES 32.3 PULLOUT RESISTANCE OF PILES  Piles in Clay  Piles in Sand 32.4 LATERALLY LOADED PILES  Elastic Solution  Ultimate Load Analysis-Brom’s Method  Ultimate Load Analysis-Meyerhof’s Method  Piles in Sand 33.1 PILE-DRIVING FORMULA
  • 3. NPTEL – ADVANCED FOUNDATION ENGINEERING-I 33.2 NEGATIVE SKIN FRICTION  Clay Fill over Granular Soil  Granular Soil Fill over Clay 33.3 GROUP PILES 33.4 GROUP EFFICIENCY 34.1 ULTIMATE CAPACITY OF GROUP 34.2 PILES IN SATURATED CLAY 34.3 PILES IN ROCK 34.4 CONSOLIDATION SETTLEMENT OF GROUP PILES 34.5 ELASTIC SETTLEMENT OF GROUP PILES 34.6 UPLIFT CAPACITY OF GROUP PILES PROBLEMS REFERENCES
  • 4. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Module 8 Lecture 29 PILE FOUNDATIONS Topics 1.2 INTRODUCTION 1.3 TYPES OF PILES AND THEIR STRUCTURAL CHARACTERISTICS  Steel Piles  Concrete Piles  Cased Pile  Uncased Pile  Timber Piles  Composite Piles  Comparison of Pile Types 1.4ESTIMATING PILE LENGTH  Point Bearing Piles  Friction Piles  Compaction Piles 1.5 INSTALLATION OF PILES
  • 5. NPTEL – ADVANCED FOUNDATION ENGINEERING-I INTRODUCTION Piles are structural members that are made of steel, concrete, and/or timber. They are used to build pile foundations, which are deep and which cost more than shallow foundations (chapters 3 and 4). Despite the cost, the use of piles often is necessary to ensure structural safety. The following list identifies some of the conditions that require pile foundations (Vesic, 1977). 1. When the upper soil layer(s) is (are) highly compressible and too weak to support the load transmitted by the superstructure, piles are used to transmit the load to underlying bedrocks or a stronger soil layer, as shown in figure 8.1a. When bedrock is not encountered at a reasonable depth below the ground surface, piles are used to transmit the structural load to the soil gradually. The resistance to the applied structural load is derived mainly from the frictional resistance developed at the soil-pile interface (figure 8. 1b). Figure 8.1 Conditions for use of pile foundations
  • 6. NPTEL – ADVANCED FOUNDATION ENGINEERING-I 2. When subjected to horizontal forces (see figure 8.1c), pile foundations resist by bending while still supporting the vertical load transmitted by the superstructure. This type of situation is generally encountered in the design and construction of earth-retaining structures and foundations of tall structures that are subject to high wind and/or earthquake forces. 3. In many cases, expansive and collapsible soils (chapter 11) may be present at the site of a proposed structure. These soils may extend to a great depth below the ground surface. Expansive soils swell and shrink as the moisture content increases and decreases, and the swelling pressure of such soils can be considerable. If shallow foundations are used in such circumstances, the structure may suffer considerable damage. However, pile foundations may be considered as an alternative when pies are extended beyond the active zone, which swells and shrinks (figure 8.1d). Soils such as loess are collapsible in nature. When the moisture content of these soils increases, their structures ay break down. A sudden decrease in the void ratio of soil induces large settlements of structures supported by shallow foundations. In such cases, piles foundations may be used in which piles are extended into stable soil layers beyond the zone of possible moisture change. 4. Foundations of some structures, such as transmission towers, offshore platforms, and basement mats below the water table, are subjected to uplifting forces. Piles are sometimes used for these foundations to resist the uplifting force (figure 8. 1e). 5. Bridge abutments and piers are usually constructed over pile foundations to avoid the possible loss of bearing capacity that a shallow foundation might suffer because of soil erosion at the ground surface (figure 8.1f). TYPES OF PILES AND THEIR STRUCTURAL CHARACTERISTICS Different types of piles are used in construction work, depending on the type of load to be carried, the subsoil conditions, and the location of the water table. Piles can be divided into the following categories: (a) steel piles (b) concrete piles, (c) wooden (timber) piles, and (d) composite piles. Steel Piles Steel piles generally are either pile piles or rolled steel H-section piles. Pipe piles can be driven into the ground with their ends open or closed. Wide-flange and I-section steel beams can also be used as piles. However, H-section piles are usually preferred because their wed and flange thicknesses are equal. In wide-flange and I-section beams, the wed thicknesses are smaller than the thicknesses of the flange. Table D. I. (Appendix D) gives the dimensions of some standard H-section steel piles used in the United States. Table D.2 (Appendix D) shows selected pile sections frequently used for piling purposes. In many cases, the pile piles are filled with concrete after driving.
  • 7. NPTEL – ADVANCED FOUNDATION ENGINEERING-I The allowable structural capacity for steel piles is 푄푄all = 퐴퐴푠푠푓푓푠푠 [8.1] Where 퐴퐴푠푠 = cross − sectional area of the steel 푓푓푠푠 = allowable stress of steel Based on geotechnical considerations (once the design load for a pile is fixed) determining whether 푄푄(design ) is within the allowable range as defined by equation 1) is always advisable. When necessary, steel piles are spliced by welding or by riveting. Figure 8. 2a shows a typical condition of splicing by welding for an H-pile. A typical case of splicing by welding for a pipe is shown in figure 8. 2b. Figure 8. 2c shows a diagram of splicing an H-pile by rivets or bolts. Figure 8. 2 Steel piles: (a) splicing of H-pile by welding; (b) splicing of pile by welding; (c) splicing of H-pile rivets and bolts; (d) flat driving point of pipe pile; (e) conical driving point of pipe pile
  • 8. NPTEL – ADVANCED FOUNDATION ENGINEERING-I When hard driving conditions are expected, such as driving through dense gravel, shale, and soft rock, steel piles can be fitted with driving points or shoes. Figure 8.2d and 8.2e are diagrams of two types of shoe used for pipe piles. Steel piles may be subject to corrosion. For example, swamps, peats, and other organic soils are corrosive. Soils that have a pH greater than 7 are not so corrosive. To offset the effect of corrosion, an additional thickness of steel (over the actual design cross-sectional area) is generally recommended. In many circumstances, factory-applied epoxy coatings on piles work satisfactorily against corrosion. These coatings are not easily damaged by pile driving. Concrete encasement of steel piles in most corrosive zones also protects against corrosion. Concrete Piles Concrete piles may be divided into two basic categories: (a) precise piles and (b) case-in-situ piles. Precast piles can be prepared by using ordinary reinforcement, and they can be square or octagonal in cross section (figure 8.3). Reinforcement is provided to enable the pile to resist the bending moment developed during pickup and transportation, the vertical load, and the bending moment caused by lateral load. The piles are cast to desired lengths and cured before being transported to the work sites. Figure 8.3 Precast piles with ordinary reinforcement Precise piles can also be prestressed by the use of high-strength steel prestressing cables. The ultimate strength of these steel cables is about 260 ksi (≈ 1800 MN/m2). During casting of the piles, the cables are pretensioned to about 130 − 190 ksi (≈ 900 − 1300 MN/m2), and concrete is poured around them. After curing, the cables are cut, thus producing a compressive force on the pile section. Table D3 (Appendix D) gives additional information about prestressed concrete piles with square and octagonal cross sections. Cast-in-situ, or cast-in-place, piles are built by making a hole in the ground and then filling it with concrete. Various types of cast-in-place concrete pile are currently used in construction, and most of them have been pat ended by their manufactures. These piles
  • 9. NPTEL – ADVANCED FOUNDATION ENGINEERING-I may be divided into two broad categories: (a) cased and (b) uncased. Both types may have a pedestal at the bottom. Cased piles are made by driving a steel casing into the ground with the help of a mandrel placed inside the casing. When the pile reaches the proper depth, the mandrel is withdrawn and the casing is filled with concrete. Figure 8.4a, b, c, and d show some examples of cased piles without a pedestal. Table 1 gives additional information about these cased piles. Figure 8.4 shows a cased pile with a pedestal. The pedestal is an expanded concrete bulb that is formed by dropping a hammer on fresh concrete. Figure 8.4 Cast-in-place concrete piles (see table 1 for descriptions) Figure 8.4f and 8.4g are two types of uncased pile, one with a pedestal and the other without. The uncased piles are made by first driving the casing to the desired depth and then filling it with fresh concrete. The casing is then gradually withdrawn. The allowable loads fore cast-in-place concrete piles are given by the following equations, Cased Pile 푄푄all = 퐴퐴푠푠푓푓푠푠 + 퐴퐴푐푐 푓푓푐푐 [8.2a] Where
  • 10. NPTEL – ADVANCED FOUNDATION ENGINEERING-I 퐴퐴푠푠 = area of cross section of steel 퐴퐴푐푐 = area of cross section of concrete 푓푓푠푠 = allowable stress of steel 푓푓푐푐 = allowable stress of concrete Uncased Pile 푄푄all = 퐴퐴푐푐 푓푓푐푐 [2b] Table 1 Description of the Cast-in-Place Piles Shown in figure 8. 4 Part in figure 8. 4 Name of pile Type of casing Maximum usual depth of pile (ft) (meter) a Raymond Step- Taper Corrugated, thin, cylindrical casing 100 30 b Monotube or Union Metal Thin, fluted, tapered steel casing driven without mandrel 130 40 c Western cased Thin sheet casing 100-130 30-40 d Seamless pile or Armco Straight steel pipe casing 160 50 e Franki cased pedestal Thin sheet casing 100-130 30-40 f Western uncased without pedestal - 50-65 15-20 g Franki uncased pedestal - 100-130 30-40 Timber Piles Timber piles are tree trunks that have had their branches and bark carefully trimmed off. The maximum length of most timber piles is 30-65 ft (10-20 m). To qualify for use as a pile, the timber should be straight, sound, and without any defects. The American Society
  • 11. NPTEL – ADVANCED FOUNDATION ENGINEERING-I of Civil Engineers’ Manual of Practice, No. 17 (1959), divided timber piles into three classifications: 1. Class A piles carry heavy loads. The minimum diameter of the butt should be 14 in. (356 mm). 2. Class B piles are used to carry medium loads. The minimum butt diameter should be 12-13 in. (305-330 mm). 3. Class C piles are used in temporary construction work. They can be used permanently for structures when the entire pile is below the water table. The minimum butt diameter should be 12 in. (305 mm). In any case, a pile tip should not have a diameter less than 6 in. (150 mm). Timber piles cannot withstand hard driving stress; therefore, the pile capacity is generally limited to about 25-30 tons (220 − 270 kN). Steel shoes may be used to avoid damage at the pile tip (bottom). The tops of timber piles may also be damaged during the driving operation. The crushing of the wooden fibers caused by the impact of the hammer is referred to as brooming. To avoid damage to the pile top, a metal band or a cap may be used. Splicing of timber piles should he avoided, particularly when they are expected to carry tensile load or lateral load. However, if splicing is necessary, it can be done by using pile sleeves (figure 8.5a) or metal straps and bolts (figure 8. 5b). The length of the pile sleeve should be at least five times the diameter of the pile. The butting ends should be cut square so that full contact can be maintained. The spliced portions should be carefully trimmed so that they fit tightly to the inside of the pile sleeve. In the case of metal straps and bolts, the butting ends should also be cut square. Also, the sides of the spliced portion should be trimmed plane for putting the straps on. Figure 8. 8.5 Splicing of timber piles: (a) use of pipe sleeves; (b) use of metal straps and bolts
  • 12. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Timber piles can stay undamaged indefinitely if they are surrounded by saturated soil. However, in a marine environment timber piles are subject to attack by various organisms and can be damaged extensively in a few months. When located above the water table, the piles are subject to attach by insects. The life of the piles may be increased by treating them with preservatives such as creosote. The allowable load-carrying capacity of wooden piles is 푄푄all = 퐴퐴푝푝 푓푓푤푤 [8.3] Where 퐴퐴푝푝 = average area of cross section of the pile 푓푓푤푤 = allowable stress for the timber The following allowable stresses are for pressure-treated round timber piles made from Pacific Coast Douglas fir and Southern pine, when used in hydraulic structures (ASCE, 1993). Allowable stress Pacific coast Douglas fir Southern pine Compression parallel to gain 875 lb/in2 (6.04 MN/m2) 825 lb/in2 (5.7MN/m2) Bending 1700 lb/in2 (11.7 MN/ m2) 1650 lb/in2 (11.4 MN/ m2) Horizontal shear 95 lb/in2 (0.66 MN/m2) 90 lb/in2 (0.62 MN/m2) Compression perpendicular to grain 190 lb/in2 (1.31 MN/m2) 205 lb/in2 (1.41 MN/m2) Composite Piles The upper and lower portions of composite piles are made of different materials. For example, composite piles may be made of steel and concrete or timber and concrete. Steel and concrete piles consist of a lower portion of steel and an upper portion of cast-in-place concrete. This type of pile is the one used when the length of the pile required for adequate bearing exceeds the capacity of simple cast-in-place concrete piles. Timber and concrete piles usually consist of a lower portion of timber pile below the permanent water table and an upper portion of concrete. In any case, forming proper joints between two dissimilar materials is difficult, and, for that reason, composite piles are not widely used. Comparison of Pile Types
  • 13. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Several factors affect the selection of piles for a particular structure at a specific site. Table 2 gives a brief comparison of the advantages and disadvantages of the various types of pile based on the pile material. Table 2 Comparison of Piles Made of Different Materials Pile type Usual length of piles Maximum length of pile Usual load Approximate maximum load Comments Steel 50-200 ft (15-60 m) Practicall y unlimited 67 − 270 kip (300 − 1200 kN) Equation (1) Advantages a. Easy to handle with respect to cutoff and extension to the desired length b. Can stand high driving stresses c. Can penetrate hard layers such as dense gravel, soft rock d. High load-carrying capacity Disadvantages a. Relatively costly material b. High level of noise during pile driving c. Subject to corrosion d. H-piles may be damaged or deflected
  • 14. NPTEL – ADVANCED FOUNDATION ENGINEERING-I from the vertical during driving through hard layers or past major obstructions Precast concre te Precast: 30-50 ft (10-15 m) Prestresse d: 30-150 ft (`10-35 m) Precast: 100 ft (30 m) Prestresse d: 200 ft (60 m) 67 − 675 kip (300 − 3000 kN) Precast: 180 − 200 kip (800 − 900 kN) Advantages Prestressed: 1700 − 1900 kip (7500 − 8500 kN) a. Can be subjected to hard driving b. Corrosion resistant c. Can be easily combined with concrete superstructu re Disadvantages a. Difficult to achieve proper cutoff b. Difficult to transport Cased cast-in-place concre te 15-50 ft (5-15 m) 100-130 ft (30-40 m) 180 kip (800 kN)Advantages 45 115 kip (200 − 50 kN) a. Relatively cheap b. Possibility of inspection before pouring concrete c. Easy to extend Disadvantages a. Difficult to splice after
  • 15. NPTEL – ADVANCED FOUNDATION ENGINEERING-I concreting b. This casings may be damaged during driving Uncas ed cast-in-place concre te 15-5- ft (5-15 m) 100-130 ft (30-40 m) 65 − 115 kip (300 − 500 kN) 160 kip (700 kN)Advantages a. Initially economical b. Can be finished at ay elevation Disadvantages a. Voids may be created if concrete is placed rapidly b. Difficult to splice after concreting c. In soft soils, the sides of the hole may cave in, thus squeezing the concrete Wood 30-50 ft (10-15 m) 100 ft (30 m) 2245 kip (100 − 200 kN) 60 kip (270 kN) Advantages a. Economical b. Easy to handle c. Permanentl y submerged piles are fairly resistant to decay Disadvantages a. Decay above water table
  • 16. NPTEL – ADVANCED FOUNDATION ENGINEERING-I b. Can be damaged in hard driving c. Low load-bearing capacity d. Low resistance to tensile load when spliced ESTIMATING PILE LENGTH Selecting the type of pile to be used and estimating its necessary length are fairly difficult tasks that require good judgment. In addition to the classification given in section 2, piles can be divided into three major categories, depending on their lengths and the mechanisms of load transfer to the soil: (a) point bearing piles, (b) friction piles, and (c) compaction piles. Point Bearing Piles If soil-boring records establish the presence of bedrocks or rocklike material at a site within a reasonable depth, piles can be extended to the rock surface. (Figure 8.6a). In this case, the ultimate capacity of the piles depends entirely on the load bearing capacity of the underlying material; thus the piles are called point bearing piles. In most of these cases, the necessary length of the pile can be fairly well established. Figure 8.6 (a) and (b) Point bearing piles; (c) friction piles
  • 17. NPTEL – ADVANCED FOUNDATION ENGINEERING-I If, instead to bedrock, a fairly compact and hard stratum of soil is encountered at a reasonable depth, piles can be extended a few meters into the hard stratum (figure 8. 6b). Piles with pedestals can be constructed on the bed of the hard stratum, and the ultimate pile load may be expressed as 푄푄푢푢 + 푄푄푝푝 + 푄푄푠푠 [8.4] Where 푄푄푝푝 = load carried at the pile point 푄푄푠푠 = load carried by skin friction developed at the side of the pile (caused by shearing resistance between the soil and the pile) If 푄푄푠푠 is very small, 푄푄푢푢 ≈ 푄푄푝푝 [8.5] In this case, the required pile length maybe estimated accurately if proper subsoil exploration records are available. Friction Piles When no layer of rock or rocklike material is present at a reasonable depth at a site, point bearing piles become very long and uneconomical. For this type o subsoil condition, piles are driven through the softer material to specified depths (figure 8. 6c). The ultimate load of these piles may be expressed by equation (4). However, if the value o 푄푄푝푝 is relatively small, 푄푄푢푢 ≈ 푄푄푠푠 [8.6] These piles are called friction piles because most of the resistance is derived from skin friction. However, the term friction pile, although used often in the literature, is a misnomer: in clayey soils, the resistance to applied load is also caused by adhesion. The length of friction of piles depends on the shear strength of the soil, the applied load and the pile size. To determine the necessary lengths of these piles, an engineer needs a good understanding of soil-pile interaction, good judgment, and experience. Theoretical procedures for the calculation of load-bearing capacity of piles are presented later in this chapter. Compaction Piles Under certain circumstances, piles are driven in granular soils to achieve proper compaction of soil close to the ground surface. These piles are called compaction piles. The length of compaction piles depends on factors such as (a) relative density of the soil before compaction, (b) desired relative density of the soil after compaction, and (c) required depth of compaction. These piles are generally short; however, some field tests are necessary to determine a reasonable length.
  • 18. NPTEL – ADVANCED FOUNDATION ENGINEERING-I INSTALLATION OF PILES Most piles are driven into the ground by means of hammers or vibratory drivers. In special circumstances, piles can also be inserted by jetting or partial augering. The types of hammer used for pile driving include the (a) drop hammer, (b) single acting air or steam hammer, (c) double-acting and differential air or steam hammer, and (d) diesel hammer. In the driving operation, a cap is attached to the top of the pile. A cushion may be used between the pile and the cap. This cushion has the effect of reducing the impact force and spreading it over a longer time; however, its use is optional. A hammer cushion is placed on the pile cap. The hammer drops on the cushion. Figure 8. 7 illustrated various hammers. A drop hammer (figure 8. 7a) is raised by a winch and allowed to drop from a certain height H. it is the oldest type of hammer used for pile driving. The main disadvantage of the drop hammer is the slow rate of hammer blows. The principle of the single-acting air or steam hammer is shown in figure 8. 7b. In this case, the striking part, or ram, is raised by air or steam pressure and then drops by gravity. Figure 8.7c shows the operation of the double-acting and differential air or steam hammer. For these hammers, air or steam is used both to raise the ram and to push it downward. This increases the impact velocity of the ram. The diesel hammer (figure 8. 7d) essentially consists of a ram, an anvil block, and a fuel-injection system. During the operation, the ram is first raised and fuel is injected near the anvil. Then the ram is released. When the ram drops, it compresses the air fuel mixture, which ignites it. This action, in effect, pushes the pile downward and raises the ram. Diesel hammers work well under hard driving conditions. In soft sols, the downward movement of the pile is rather large, and the upward movement of the ram is small. This differential may not be sufficient to ignite the air-fuel system, so the ram may have to be lifted manually.
  • 19. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Figure 8.7 Pile-driving equipment: (a) drop hammer; (b) single-acting air or seam hammer; (c) double-acting and differential air or steam hammer; (d) diesel hammer; (e) vibratory pile driver
  • 20. NPTEL – ADVANCED FOUNDATION ENGINEERING-I Figure 8.7 (Continued) The principles of operation of a vibratory pile driver are shown in figure 8.7e. This driver essentially consists of two counter-rotating weights. The horizontal components of the centrifugal force generated as a result of rotating masses cancel each other. As a result, a sinusoidal dynamic vertical force is produced on the pile and helps drive the pile downward. Jetting is a technique sometimes used in pile driving when the pile needs to penetrate a thin layer of hard soil (such as sand and gravel) overlying a softer soil layer. In this
  • 21. NPTEL – ADVANCED FOUNDATION ENGINEERING-I technique, water is discharged at the pile point by means of a pile 2-3 in. (50-75 mm) is diameter to wash and loosen the sand and gravel. Piles driven at an angle to the vertical, typically14° to 20°, are referred to as batter piles. Batter piles are used in group piles when higher lateral load-bearing capacity is required. Piles also may be advanced by partial augering, with power augers (chapter 2) being used to predrill holes part of the way. The piles can then be inserted into the holes and driven to the desired depth. Based on the nature of their placement, piles may be divided into two categories: displacement piles and nondisplacement piles. Driven piles are displacement piles because they move some soil laterally; hence there is a tendency for densification of soil surrounding them. Concrete piles and closed-ended pile piles are high-displacement piles. However, steel H-piles displace less soil laterally during driving, and so they are low-displacement piles. In contrast, bored piles are nondisplacement piles because their placement causes very little change in the state of stress in the soil.