8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
These are basic skill set, duty responsibility and his ability to do the assigned work. The requirement of client is also mentioned to make process proper.
Emergency Response Training has been implemented to many corporate giants and are being used by some of my counter parts. This programme involves earth quake, fire fighting, tsunami, armed intruder and bomb threat. The second version of this programme is called Workplace Emergency Preparedness Training (WEPT) soon will be launched in this Slide Share
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
Occupational Health and Safety Powerpoint PresentationJoLowe72
This is a Powerpoint Presentation I have been asked to prepare as part of my assessment for the Certificate 3 in Multimedia at Tastafe, Alanvale, Launceston.
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
These are basic skill set, duty responsibility and his ability to do the assigned work. The requirement of client is also mentioned to make process proper.
Emergency Response Training has been implemented to many corporate giants and are being used by some of my counter parts. This programme involves earth quake, fire fighting, tsunami, armed intruder and bomb threat. The second version of this programme is called Workplace Emergency Preparedness Training (WEPT) soon will be launched in this Slide Share
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
Occupational Health and Safety Powerpoint PresentationJoLowe72
This is a Powerpoint Presentation I have been asked to prepare as part of my assessment for the Certificate 3 in Multimedia at Tastafe, Alanvale, Launceston.
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Telehealth Psychology Building Trust with Clients.pptxThe Harvest Clinic
Telehealth psychology is a digital approach that offers psychological services and mental health care to clients remotely, using technologies like video conferencing, phone calls, text messaging, and mobile apps for communication.
R3 Stem Cells and Kidney Repair A New Horizon in Nephrology.pptxR3 Stem Cell
R3 Stem Cells and Kidney Repair: A New Horizon in Nephrology" explores groundbreaking advancements in the use of R3 stem cells for kidney disease treatment. This insightful piece delves into the potential of these cells to regenerate damaged kidney tissue, offering new hope for patients and reshaping the future of nephrology.
Medical Technology Tackles New Health Care Demand - Research Report - March 2...pchutichetpong
M Capital Group (“MCG”) predicts that with, against, despite, and even without the global pandemic, the medical technology (MedTech) industry shows signs of continuous healthy growth, driven by smaller, faster, and cheaper devices, growing demand for home-based applications, technological innovation, strategic acquisitions, investments, and SPAC listings. MCG predicts that this should reflects itself in annual growth of over 6%, well beyond 2028.
According to Chris Mouchabhani, Managing Partner at M Capital Group, “Despite all economic scenarios that one may consider, beyond overall economic shocks, medical technology should remain one of the most promising and robust sectors over the short to medium term and well beyond 2028.”
There is a movement towards home-based care for the elderly, next generation scanning and MRI devices, wearable technology, artificial intelligence incorporation, and online connectivity. Experts also see a focus on predictive, preventive, personalized, participatory, and precision medicine, with rising levels of integration of home care and technological innovation.
The average cost of treatment has been rising across the board, creating additional financial burdens to governments, healthcare providers and insurance companies. According to MCG, cost-per-inpatient-stay in the United States alone rose on average annually by over 13% between 2014 to 2021, leading MedTech to focus research efforts on optimized medical equipment at lower price points, whilst emphasizing portability and ease of use. Namely, 46% of the 1,008 medical technology companies in the 2021 MedTech Innovator (“MTI”) database are focusing on prevention, wellness, detection, or diagnosis, signaling a clear push for preventive care to also tackle costs.
In addition, there has also been a lasting impact on consumer and medical demand for home care, supported by the pandemic. Lockdowns, closure of care facilities, and healthcare systems subjected to capacity pressure, accelerated demand away from traditional inpatient care. Now, outpatient care solutions are driving industry production, with nearly 70% of recent diagnostics start-up companies producing products in areas such as ambulatory clinics, at-home care, and self-administered diagnostics.
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...Guillermo Rivera
This conference will delve into the intricate intersections between mental health, legal frameworks, and the prison system in Bolivia. It aims to provide a comprehensive overview of the current challenges faced by mental health professionals working within the legislative and correctional landscapes. Topics of discussion will include the prevalence and impact of mental health issues among the incarcerated population, the effectiveness of existing mental health policies and legislation, and potential reforms to enhance the mental health support system within prisons.
The dimensions of healthcare quality refer to various attributes or aspects that define the standard of healthcare services. These dimensions are used to evaluate, measure, and improve the quality of care provided to patients. A comprehensive understanding of these dimensions ensures that healthcare systems can address various aspects of patient care effectively and holistically. Dimensions of Healthcare Quality and Performance of care include the following; Appropriateness, Availability, Competence, Continuity, Effectiveness, Efficiency, Efficacy, Prevention, Respect and Care, Safety as well as Timeliness.
Explore our infographic on 'Essential Metrics for Palliative Care Management' which highlights key performance indicators crucial for enhancing the quality and efficiency of palliative care services.
This visual guide breaks down important metrics across four categories: Patient-Centered Metrics, Care Efficiency Metrics, Quality of Life Metrics, and Staff Metrics. Each section is designed to help healthcare professionals monitor and improve care delivery for patients facing serious illnesses. Understand how to implement these metrics in your palliative care practices for better outcomes and higher satisfaction levels.
Global launch of the Healthy Ageing and Prevention Index 2nd wave – alongside...ILC- UK
The Healthy Ageing and Prevention Index is an online tool created by ILC that ranks countries on six metrics including, life span, health span, work span, income, environmental performance, and happiness. The Index helps us understand how well countries have adapted to longevity and inform decision makers on what must be done to maximise the economic benefits that comes with living well for longer.
Alongside the 77th World Health Assembly in Geneva on 28 May 2024, we launched the second version of our Index, allowing us to track progress and give new insights into what needs to be done to keep populations healthier for longer.
The speakers included:
Professor Orazio Schillaci, Minister of Health, Italy
Dr Hans Groth, Chairman of the Board, World Demographic & Ageing Forum
Professor Ilona Kickbusch, Founder and Chair, Global Health Centre, Geneva Graduate Institute and co-chair, World Health Summit Council
Dr Natasha Azzopardi Muscat, Director, Country Health Policies and Systems Division, World Health Organisation EURO
Dr Marta Lomazzi, Executive Manager, World Federation of Public Health Associations
Dr Shyam Bishen, Head, Centre for Health and Healthcare and Member of the Executive Committee, World Economic Forum
Dr Karin Tegmark Wisell, Director General, Public Health Agency of Sweden
Empowering ACOs: Leveraging Quality Management Tools for MIPS and BeyondHealth Catalyst
Join us as we delve into the crucial realm of quality reporting for MSSP (Medicare Shared Savings Program) Accountable Care Organizations (ACOs).
In this session, we will explore how a robust quality management solution can empower your organization to meet regulatory requirements and improve processes for MIPS reporting and internal quality programs. Learn how our MeasureAble application enables compliance and fosters continuous improvement.
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...The Lifesciences Magazine
Deep Leg Vein Thrombosis occurs when a blood clot forms in one or more of the deep veins in the legs. These clots can impede blood flow, leading to severe complications.
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
fire drill check list - FEPR.pdf
1. Plant name
Time Drill initiated
Elapsed Time
Roll call completed time
Drill monitors 1 Name
2 position
Remarks
Yes No
Satisfactory Unsatisfactory
Satisfactory Unsatisfactory
Yes No
Yes No
COMMUNICATION
Method of Drill Activation
PA System
Remarks
Satisfactory Unsatisfactory
Date
ORANGE KALBE FIRE DRILL EVACUATION CHECKLIST
am/pm
Time all occupants evacuated
am/pm
……………………………………………………………………….am/pm
Brief details
In-House Word of Mouth Other: ………………………………………………………
Fire Alarm
Alarm Activation
Description Yes No
Drill Preannounced
Emergency Response Team present for the drill
Security Notified Prior to Drill
Public Address system clearly heard in all areas
All Employees participated and Evacuated
Evacuation was orderly
Electrical Power was turned off
Emergency Power was available
Fire extinguishers taken to Location of fire
Fire Hose Reel Used (Mock test)
Evacuation Performed according to Plan
Emergency Response Team respond according to plan
Rest room were checked for occupants
Missing Persons Identified by roll call
Details of Missing persons communicated to ERT
Visitors Escorted and Accounted for
Special needs persons accomodated
overall response of occupants
Fire alarm clearly heard in all area
Fire zone correctly identified by ERT/ Security gurads
Alarm monitoring Station received alarm
Number of Employees Evacuated Visitors
Employees
Others
Emergency Response Co-ordinator
Name: ……………………………………………………………………………………………. Signature: ……………………………………………………………………………………………..
Plant Manager
Name: ……………………………………………………………………………………………. Signature: ……………………………………………………………………………………………..
HSE Head
Name: ……………………………………………………………………………………………. Signature: ……………………………………………………………………………………………..
Exit Doors operating Properly
Assembly point unobstructed
Exits are clearly Marked
Illumination for assembly point & Exit path
Hydrant pump work condition
PREDRILL ASSESSMENT
Form No: F/OKL/FDC/003:00