SlideShare a Scribd company logo
Originally appreared in:                                                                                                   INFORMATION
November 2007 issue, pgs 91-95.                                                                                             TECHNOLOGY
Posted with permission.




Engineering portals add significant value
to E&P project delivery capabilities
A portal approach enables information sharing among globally spread E&P
project stakeholders.
Kailash Samdani, Infosys Technologies Limited and Andy Till, BP Exploration Limited

INTRODUCTION                                      Organizations are adopting portal               hydrocarbon potential and making a
   An E&P project is a complex engi-          technology to publish project engineer-             business case for field development.
neering effort involving hundreds of          ing information. Being able to share and            Once the business case is in place, a
engineers from different organizations,       review project engineering information              basic design development and selection
working together to design, construct         leads to significant benefits. Since pub-           of Original Equipment Manufacturers
and commission an asset before handing        lished information is available instant-            (OEM), vendors and contractors is car-
it over to the owner/operator. Efficient      ly—independent of stakeholder author-               ried out in basic design. Subsequently,
project management requires that engi-        ing system constraints or geographical              detailed plans and drawings are devel-
neering information is available to all key   location—information cycle times are                oped in the detailed design phase. Fab-
stakeholders in a way that enables them       reduced. A portal system uses a single              rication, construction and commis-
to work as one integrated organization.       integrated window to access all types of            sioning activities for various systems
   There are numerous challenges in shar-     engineering content, such as 3D models,             and equipments are carried out in the
ing and viewing engineering information       intelligent drawings, data sheets and en-           construct phase, which ends in handing
from various sources, spread globally. An     gineering databases. Also, operators are            over the project to operations.
engineering information portal provides       better prepared to run the asset due to                As shown in Fig. 1, engineering infor-
a single window to view the informa-          early exposure to engineering informa-              mation volume increases as the project
tion in a secure manner. It enables easy      tion that allows them space and time to             progresses from one phase to another.
collaboration between stakeholders and        develop and validate supporting proce-              During the detailed design and construct
supports productivity gains.                  dures and processes.                                phases, the volume of engineering in-
                                                                                                  formation shared and viewed reaches
BACKGROUND                                    TYPICAL PROJECT LIFECYCLE                           peak. Engineering information, such as
    Building a new E&P facility can cost         Figure 1 provides an overview of a               hundreds of 3D models, hundreds of
$1–5 billion, taking three to five years to   typical project lifecycle. The project’s            thousands of documents and millions
complete. As facility complexity increases,   assess phase is about determining the               of engineering data attributes, are shared
the tradition of nominating a single lead
EPCM (Engineering Procurement and
Construction Management) contractor is
                                                 Project
being replaced by a consortium of EPC            lifecycle      Assess
                                                                                Basic       Detailed
                                                                                                              Construct           Operations
                                                                                design       design
contractors. As a result, the owner/op-          stages
erator is taking on more responsibility for                           Project management   Engineering project contractor   Operations
the management of interfaces between                                  contractors          • Detailed models, design        • Asset maintenance
stakeholders. Oil and gas companies are          Project              • Basic design         schematics                       and production
                                                 activities             development        • Piping and instruments           activities
developing and implementing new in-                                   • Large packages       diagrams                       • De-bottlenecking
formation management strategies to sup-                               • Contractor         • Fabrications drawings            studies
port their evolving role and improve their                             selection           • Construction and testing       • Process
                                                                                           • Testing and commissioning        re-engineering
project execution capabilities.
    Recent advances in technology are al-
                                                 Volume of
lowing organizations to take new man-            engineering
agement approaches of project informa-           content                                                               Handover
tion. First, the link between authoring
applications and publishing applications
has been broken and, as a result, docu-                              • Fewer               • Increased number of            • O&M users
ments and 3D models can be viewed                Information           stakeholders          stakeholders                   • Linking to business
                                                 characteristics     • Less information    • Large volume of information      systems
independent of the tool used to create
                                                                       volume              • Focus on details
them. Second, the advancements in por-
tal technology enable all stakeholders to      Fig. 1. Project lifecycle and information explosion.
view project information on the internet.
                                                             November 2007 World Oil
INFORMATION TECHNOLOGY

and viewed in this virtual explosion of                   these organizations to validate and share                 contradictions and potential delays affect-
engineering information.                                  the information. Traditionally, a project                 ing the project schedule.
   Hundreds of engineers and designers                    owner has little visibility of the informa-                   The logical conclusion of E&P proj-
belonging to various project stakeholders                 tion being exchanged among the external                   ects, as shown in Fig. 1, is the handover
such as owner, EPCM contractor, fabrica-                  project stakeholders on their behalf. From                of the facility to the operations team. It is
tors, vendors, etc, generate, share, review               a project perspective, this leads to multiple             crucial for operations to have a complete
and publish engineering information. Dif-                 sets of truths across organizations which,                set of cleansed and validated engineering
ferent systems and processes exist across                 if not managed appropriately, can result in               information so that they can efficiently
                                                                                                                    run and maintain the asset. Tradition-
                                                                                                                    ally, the operations teams received in-
                                                      Original equipment                                            formation in bulk toward the end of the
                                                         manufacturer           Data cleansing
                                                                               service provider                     construct phase at the time of handover.
                EDW         EDM      3D                Project
                                                                                                                    It is humanly impossible to review and
                                    models           management                                                     validate all shared information during
                                                      contractor                                                    the handover process.
                                                                               Construction and                         Several problems exist due to lack of a
                                                                                commissioning                       proper environment for sharing informa-
                    EDW       EDM        3D model                                   teams
                                         snapshots                                                                  tion. Little visibility leads to lack of con-
                                                                                                                    trol on engineering activities and prog-
                                                                                                                    ress. Project reviews can be delayed due to
        EPC 1                                        Engineering                                                    inconsistent information across multiple
                                                                                                  EPC 4
                                                       portal                                                       stakeholders. Productivity losses can oc-
                                                                                                                    cur as a result of the overheads in search-
             EDW        EDM        3D                                                                               ing and retrieving required project docu-
                                  models
                                                                                                                    mentation. Operators are ill-prepared to
                                                                                                                    run and maintain the asset because of the
                                            EPC 2                                EPC 3                              bulk of information that is shared at the
                                                                                                                    time of hand-over. Technology advances
                                                                                                                    enable project owners to adopt a portal
                      EDW         EDM       3D                     EDW       EDM      3D                            approach, which addresses a number of
                                           models                                    models                         such issues.
 Fig. 2. Project engineering information portal.
 Engineering Data Warehouse (EDW), Engineering Document Management (EDM) and
                                                                                                                    A PORTAL APPROACH
 Engineering Procurement Contractor (EPC).                                                                            A portal approach provides a single
                                                                                                                    window to all project engineering content


 Table 1. Issues with portal solution and possible resolutions
  Information
  characteristic	                       Issue description	                                    Possible resolution

  Information types                     User expects to view 3D models as well as engi-       Portal should incorporate the ability to move seamlessly from 3D
                                        neering data sheets or smart P&IDs altogether.        models with associated detailed functionalities along with the abil-
                                                                                              ity to view intelligent drawings and engineering data tables.
                                                                                              The portal should be able to present information to a user either
                                                                                              through a native file format or rendition.
  Information quality                   User expects to view accurate and consistent          Portal should be able to perform quality assurance checks for
                                        information. Typically, different organizations       incoming data accuracy and consistency.
                                        follow different standards/conventions for data       Portal should be able to establish and update associations among
                                        management (e.g., different organizations may         3D models, engineering data and engineering documents, where
                                        represent the same pump by P_101 or P/101 or          necessary providing an aliasing capability.
                                        P101, etc. owing to their internal standards and
                                        procedures).
  Information volume                    The nature of project engineering information         Portal should be based on a robust technology platform that can
                                        is such that it keeps changing. The problem of        handle transactions involving high volumes over internet.
                                        managing such continuously changing informa-          Portal should be able to update the associations every time new
                                        tion gets compounded by the sheer volume of           information arrives and should posses change management func-
                                        information.                                          tionality.
  Information vulnerability             Hundreds of users from different organizations        The system should have a security model which is company, disci-
                                        need to access portal and interact according to       pline and role based.
                                        their role on the project, their job position and     Security of information should extend to the revision of individual
                                        organization they represent. Also companies may       documents and the design status.
                                        perceive risk in hosting such a portal on intranet.   The application and hosting environment should be certified by
                                                                                              an accredited Digital Security organization for use on Intranet /
                                                                                              Internet.

                                                                         November 2007 World Oil
INFORMATION TECHNOLOGY

such as 3D models, intelligent documents                 cessed over the web in a secure manner, as                        lessly between otherwise unrelated data
and datasheets. It displays two types of                 well as in remote offshore areas and high                         sets. The ability to share and view infor-
information sets: published information                  latency-low bandwidth areas. It should be                         mation with multiple stakeholders across
(e.g., a document with a specific revi-                  able to interface with source systems on                          geographies improves team collabora-
sion number which will never change but                  the internet as well as intranet.                                 tion, which results in more informed and
could be superseded) and snapshot infor-                                                                                   quicker decisions due to increased visibil-
mation (e.g., a copy of a 3D model at a                  ISSUES AND POSSIBLE                                               ity. Developing and updating hook-up
specific time). Through a cleansing and                  RESOLUTIONS                                                       and commissioning workpacks is easier
validation process, these information sets                   Good information specifications                               and saves time. Portals enable simplified
can be aggregated together into an engi-                 are needed for all projects. A portal ap-                         and progressive handover of informa-
neering portal as shown in Fig. 2.                       proach quickly highlights inconsistencies                         tion to operations, which enables them
    When the portal is accessed, users are               in the project information. The true cost                         to contribute to reviews of operation and
provided with requisite information of all               of implementing a portal approach is                              maintenance apart from developing work
types from all stakeholders. Stakeholder                 marginal when compared to the real cost                           procedures and training manuals in ad-
organizations need to have systems (e.g.,                of getting the relevant project informa-                          vance. Portals enable a population of data
engineering data warehouse, engineering                  tion. If a project aspires to use a portal                        into enterprise systems, such as mainte-
document management systems, model-                      approach, it must have a clearly defined                          nance management, document manage-
ing systems) and processes (such as data                 and published approach to information                             ment and engineering data warehouses.
cleansing and validation processes) to                   management. The requirement of shar-                              Also, since the bulk of engineering or
publish a variety of engineering informa-                ing accurate, consistent and complete in-                         vendor data is common across projects,
tion to a portal environment.                            formation must be contractually binding                           a portal system substantially reduces the
    Project organizations desire to improve              on all information suppliers. It is prefer-                       cost of information for future projects.
the availability and visibility of engineer-             able to have information validated and
ing information throughout the project                   cleansed before it is published.                                  CONCLUSION
lifecycle to optimize concurrent engineer-                   Projects adopting a portal approach                              As the size of E&P projects continue
ing, minimize information cycle time and                 to access project information can face a                          to grow, the way in which stakeholders
eliminate rework due to poor informa-                    number of issues because of the nature of                         interact needs to evolve. Larger and more
tion. Requirements from a portal solution                information being handled. The project                            complex projects need to develop more
can be categorized into three broad areas.               information can be characterized as:                              appropriate ways of project execution.
                                                             •  Information types: Multiple native                         Technology advances are being increas-
Functional requirements. A portal                        file formats exist according to the au-                           ingly used to make projects more effi-
solution should provide a single window                  thoring system (3D models, intelligent                            cient. The web-based portal approach
to different project engineering content,                drawings, engineering data, etc).                                 enables organizations to control and
such as models, engineering databases                        •  Information quality: Complete-                             share project information among global
and intelligent, as well as dumb, drawings               ness and consistency of information                               stakeholders and reduce information
and documents. It should enable easy                     coming from different organizations or                            cycle time, thus improving the speed of
navigation through various information                   systems varies.                                                   execution, leading to a successful deliv-
sets, so that users can move seamlessly                      •  Information volume: Hundreds of                            ery of the project into operation. WO
across different content types. It should                3D models, hundreds of thousands of
be independent of source systems and be                  documents, and millions of engineering
able to interface with proprietary file for-             data attributes are available to view.                            The authors
mats from multiple suppliers. It should                      •  Information vulnerability: Infor-                                                Kailash Samdani works
support quality assurance checks before                  mation accessed by large numbers of us-                                                 with Domain Competency
the information is published on the por-                 ers from different organizations gives rise                                             Group of Infosys Technolo-
                                                         to security concerns.                                                                   gies Ltd. Kailash has 15
tal. It should also manage updated con-                                                                                                          years of experience in pre-
tent from stakeholders. It should enable                     Each information characteristic gives                                               sales, consulting and busi-
role based workflow capabilities coupled                 rise to a set of unique issues. These is-                                               ness development of IT en-
with an information security model and                   sues and resolution approaches are cov-                                                 abled advanced solutions
                                                         ered in Table 1.                                                                        to hydrocarbon, chemicals
also support collaboration among all us-                                                                                                         and metal industries. He
ers spread geographically.                                                                                                 has a BS degree in chemical engineering from
                                                         BENEFITS OF PORTAL                                                Birla Institute of Technology  Science, Pilani,
User requirements. A portal solution                     APPROACH                                                          India. He can be reached at Kailash_Samdani@
                                                                                                                           infosys.com.
should provide viewing capabilities to                      A portal approach provides benefits
analyze information contained within                     in many areas. Easy access to current and                         Andy Till worked for BP
3D models and intelligent drawings                       consistent information is one of the key                          Exploration Ltd for 18 years
e.g., zoom in/out, collision detection,                  parameters to successful execution of                             in a number of roles and is
                                                                                                                           currently an IT consultant
mark-up, etc. It should provide easy, yet                large projects. A portal approach provides                        for Major Projects. Andy
advanced, search mechanisms to get to                    a single window to the published infor-                           spent his first eight years
desired information within a minimum                     mation, thus improving availability of                            as an engineer designing,
number of mouse-clicks.                                  requisite drawings and documents lead-                            constructing, installing and
                                                                                                                           commissioning both on-
                                                         ing to better preparedness for project re-                        shore and offshore facili-
Technical requirements. A portal so-                     views in less time. It enables quick access                       ties before moving to IT, where he continues to
lution should allow information to be ac-                to current information, moving seam-                              support both engineering and projects.
                                        Article copyright © 2009 by Gulf Publishing Company. All rights reserved.     Printed in U.S.A.
                      Not to be distributed in electronic or printed form, or posted on a website, without express written permission of copyright holder.

More Related Content

What's hot

Why Adopt Nearshore Agile Development?
Why Adopt Nearshore Agile Development?Why Adopt Nearshore Agile Development?
Why Adopt Nearshore Agile Development?
Ciklum Ukraine
 
UC2 International Deployment, Baltimore Society of Communications Technology ...
UC2 International Deployment, Baltimore Society of Communications Technology ...UC2 International Deployment, Baltimore Society of Communications Technology ...
UC2 International Deployment, Baltimore Society of Communications Technology ...
Agustin Argelich Casals
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
06 jerome crotteux - 3 e
06   jerome crotteux - 3 e06   jerome crotteux - 3 e
06 jerome crotteux - 3 eLinea Trovata
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazenNASAPMC
 
Intelligent Buildings
Intelligent BuildingsIntelligent Buildings
Intelligent Buildings
Sustainable Resources Management
 
Organizing Design-Driven Development Using Rational Requirements Composer
Organizing Design-Driven Development Using Rational Requirements ComposerOrganizing Design-Driven Development Using Rational Requirements Composer
Organizing Design-Driven Development Using Rational Requirements ComposerKurt Solarte
 
Conference Agenda, Topics
Conference Agenda, TopicsConference Agenda, Topics
Conference Agenda, Topics
Krishna Gorle
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project DeliveryMike Purdy
 
Bogdan Radu Resume
Bogdan Radu ResumeBogdan Radu Resume
Bogdan Radu ResumeBogdan Radu
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project Managment
Ahmed Alageed
 
Barriers To Innovation
Barriers To InnovationBarriers To Innovation
Barriers To Innovation
rdbms
 
Recent developments in BIM in geotechnics
Recent developments in BIM  in geotechnicsRecent developments in BIM  in geotechnics
Recent developments in BIM in geotechnics
Rob Madill
 
thismedia 009
thismedia 009thismedia 009
thismedia 009
thismedia
 

What's hot (19)

Siemens plm-key ox-industrial-design-cs-z5
Siemens plm-key ox-industrial-design-cs-z5Siemens plm-key ox-industrial-design-cs-z5
Siemens plm-key ox-industrial-design-cs-z5
 
Why Adopt Nearshore Agile Development?
Why Adopt Nearshore Agile Development?Why Adopt Nearshore Agile Development?
Why Adopt Nearshore Agile Development?
 
UC2 International Deployment, Baltimore Society of Communications Technology ...
UC2 International Deployment, Baltimore Society of Communications Technology ...UC2 International Deployment, Baltimore Society of Communications Technology ...
UC2 International Deployment, Baltimore Society of Communications Technology ...
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
06 jerome crotteux - 3 e
06   jerome crotteux - 3 e06   jerome crotteux - 3 e
06 jerome crotteux - 3 e
 
Michael.hazen
Michael.hazenMichael.hazen
Michael.hazen
 
Intelligent Buildings
Intelligent BuildingsIntelligent Buildings
Intelligent Buildings
 
Organizing Design-Driven Development Using Rational Requirements Composer
Organizing Design-Driven Development Using Rational Requirements ComposerOrganizing Design-Driven Development Using Rational Requirements Composer
Organizing Design-Driven Development Using Rational Requirements Composer
 
Conference Agenda, Topics
Conference Agenda, TopicsConference Agenda, Topics
Conference Agenda, Topics
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project Delivery
 
01_Program
01_Program01_Program
01_Program
 
Bogdan Radu Resume
Bogdan Radu ResumeBogdan Radu Resume
Bogdan Radu Resume
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project Managment
 
Barriers To Innovation
Barriers To InnovationBarriers To Innovation
Barriers To Innovation
 
Agile It 20091020
Agile It 20091020Agile It 20091020
Agile It 20091020
 
De Nigris
De Nigris De Nigris
De Nigris
 
3a2 roadmap
3a2 roadmap3a2 roadmap
3a2 roadmap
 
Recent developments in BIM in geotechnics
Recent developments in BIM  in geotechnicsRecent developments in BIM  in geotechnics
Recent developments in BIM in geotechnics
 
thismedia 009
thismedia 009thismedia 009
thismedia 009
 

Viewers also liked

Future of Work & Careers
Future of Work & CareersFuture of Work & Careers
Future of Work & Careers
Infosys
 
China and the 8 Dragons – A primer for multinational corporations seeking a f...
China and the 8 Dragons – A primer for multinational corporations seeking a f...China and the 8 Dragons – A primer for multinational corporations seeking a f...
China and the 8 Dragons – A primer for multinational corporations seeking a f...
Infosys
 
Data Source Integration
Data Source IntegrationData Source Integration
Data Source Integration
Infosys
 
Deriving Business Value from Social Networks
Deriving Business Value from Social NetworksDeriving Business Value from Social Networks
Deriving Business Value from Social Networks
Infosys
 
iEngage-Animated
iEngage-AnimatediEngage-Animated
iEngage-Animated
Infosys
 
Sustainable Tomorrow - Driving Opportunity While Discharging Responsibility
Sustainable Tomorrow - Driving Opportunity While Discharging ResponsibilitySustainable Tomorrow - Driving Opportunity While Discharging Responsibility
Sustainable Tomorrow - Driving Opportunity While Discharging Responsibility
Infosys
 
Infosys – Hi Tech Order Management Distribution Planning Solution - Case Study
Infosys – Hi Tech Order Management Distribution Planning Solution - Case StudyInfosys – Hi Tech Order Management Distribution Planning Solution - Case Study
Infosys – Hi Tech Order Management Distribution Planning Solution - Case Study
Infosys
 
Dodd-Frank Act: Impact on Business and IT
Dodd-Frank Act: Impact on Business and ITDodd-Frank Act: Impact on Business and IT
Dodd-Frank Act: Impact on Business and IT
Infosys
 
Problem Solving Essential For Stress Management
Problem Solving  Essential For Stress ManagementProblem Solving  Essential For Stress Management
Problem Solving Essential For Stress Management
kumar mahi
 

Viewers also liked (9)

Future of Work & Careers
Future of Work & CareersFuture of Work & Careers
Future of Work & Careers
 
China and the 8 Dragons – A primer for multinational corporations seeking a f...
China and the 8 Dragons – A primer for multinational corporations seeking a f...China and the 8 Dragons – A primer for multinational corporations seeking a f...
China and the 8 Dragons – A primer for multinational corporations seeking a f...
 
Data Source Integration
Data Source IntegrationData Source Integration
Data Source Integration
 
Deriving Business Value from Social Networks
Deriving Business Value from Social NetworksDeriving Business Value from Social Networks
Deriving Business Value from Social Networks
 
iEngage-Animated
iEngage-AnimatediEngage-Animated
iEngage-Animated
 
Sustainable Tomorrow - Driving Opportunity While Discharging Responsibility
Sustainable Tomorrow - Driving Opportunity While Discharging ResponsibilitySustainable Tomorrow - Driving Opportunity While Discharging Responsibility
Sustainable Tomorrow - Driving Opportunity While Discharging Responsibility
 
Infosys – Hi Tech Order Management Distribution Planning Solution - Case Study
Infosys – Hi Tech Order Management Distribution Planning Solution - Case StudyInfosys – Hi Tech Order Management Distribution Planning Solution - Case Study
Infosys – Hi Tech Order Management Distribution Planning Solution - Case Study
 
Dodd-Frank Act: Impact on Business and IT
Dodd-Frank Act: Impact on Business and ITDodd-Frank Act: Impact on Business and IT
Dodd-Frank Act: Impact on Business and IT
 
Problem Solving Essential For Stress Management
Problem Solving  Essential For Stress ManagementProblem Solving  Essential For Stress Management
Problem Solving Essential For Stress Management
 

Similar to Exploration Production Portals

C bent01
C bent01C bent01
Bryan.moser
Bryan.moserBryan.moser
Bryan.moserNASAPMC
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moserNASAPMC
 
ets rticle eng
ets rticle engets rticle eng
ets rticle eng
chetanmoore
 
Pbd for es
Pbd for esPbd for es
Pbd for es
prudhvi Krishna
 
Software Lifecycle
Software LifecycleSoftware Lifecycle
Software Lifecycle
Soumen Sarkar
 
Auto DCR building plan approval-nov2012
Auto DCR building plan approval-nov2012Auto DCR building plan approval-nov2012
Auto DCR building plan approval-nov2012SoftTech Engineers
 
Resume-Rebecca Hebda
Resume-Rebecca HebdaResume-Rebecca Hebda
Resume-Rebecca HebdaRebecca Hebda
 
Building maintenance documentation
Building maintenance documentation Building maintenance documentation
Building maintenance documentation gaitkeeper
 
GIS POV
GIS POVGIS POV
GIS POV
Sougata Mitra
 
Mike najarian resume
Mike najarian resumeMike najarian resume
Mike najarian resume
Mike Najarian Senior IT PMP PMO
 
Detailed project schedule
Detailed project scheduleDetailed project schedule
Detailed project schedulePeica Ionela
 
The Impacts.pptx
The Impacts.pptxThe Impacts.pptx
The Impacts.pptx
KvmRaju
 
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
IRJET Journal
 
Integrating Essential Components of Digital Twin for Energy Industry
Integrating Essential Components of Digital Twin for Energy IndustryIntegrating Essential Components of Digital Twin for Energy Industry
Integrating Essential Components of Digital Twin for Energy Industry
IRJET Journal
 
Using Evolutionary Prototypes To Formalize Product Requirements
Using Evolutionary Prototypes To Formalize Product RequirementsUsing Evolutionary Prototypes To Formalize Product Requirements
Using Evolutionary Prototypes To Formalize Product Requirements
Arnold Rudorfer
 
Connected construction on virtual land - The Metaverse.pdf
Connected construction on virtual land - The Metaverse.pdfConnected construction on virtual land - The Metaverse.pdf
Connected construction on virtual land - The Metaverse.pdf
BIMEngus1
 
Resume.20110926
Resume.20110926Resume.20110926
Resume.20110926RobertMars
 

Similar to Exploration Production Portals (20)

C bent01
C bent01C bent01
C bent01
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moser
 
Bryan.moser
Bryan.moserBryan.moser
Bryan.moser
 
ets rticle eng
ets rticle engets rticle eng
ets rticle eng
 
CPI Article
CPI ArticleCPI Article
CPI Article
 
Pbd for es
Pbd for esPbd for es
Pbd for es
 
Software Lifecycle
Software LifecycleSoftware Lifecycle
Software Lifecycle
 
Auto DCR building plan approval-nov2012
Auto DCR building plan approval-nov2012Auto DCR building plan approval-nov2012
Auto DCR building plan approval-nov2012
 
Resume-Rebecca Hebda
Resume-Rebecca HebdaResume-Rebecca Hebda
Resume-Rebecca Hebda
 
MCS1_SJUSD_Resume
MCS1_SJUSD_ResumeMCS1_SJUSD_Resume
MCS1_SJUSD_Resume
 
Building maintenance documentation
Building maintenance documentation Building maintenance documentation
Building maintenance documentation
 
GIS POV
GIS POVGIS POV
GIS POV
 
Mike najarian resume
Mike najarian resumeMike najarian resume
Mike najarian resume
 
Detailed project schedule
Detailed project scheduleDetailed project schedule
Detailed project schedule
 
The Impacts.pptx
The Impacts.pptxThe Impacts.pptx
The Impacts.pptx
 
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
IRJET-To Implement Cloud Computing by using Agile Methodology in Indian E-Gov...
 
Integrating Essential Components of Digital Twin for Energy Industry
Integrating Essential Components of Digital Twin for Energy IndustryIntegrating Essential Components of Digital Twin for Energy Industry
Integrating Essential Components of Digital Twin for Energy Industry
 
Using Evolutionary Prototypes To Formalize Product Requirements
Using Evolutionary Prototypes To Formalize Product RequirementsUsing Evolutionary Prototypes To Formalize Product Requirements
Using Evolutionary Prototypes To Formalize Product Requirements
 
Connected construction on virtual land - The Metaverse.pdf
Connected construction on virtual land - The Metaverse.pdfConnected construction on virtual land - The Metaverse.pdf
Connected construction on virtual land - The Metaverse.pdf
 
Resume.20110926
Resume.20110926Resume.20110926
Resume.20110926
 

More from Infosys

Demystifying Machine Learning for Manufacturing: Data Science for all
Demystifying Machine Learning for Manufacturing: Data Science for allDemystifying Machine Learning for Manufacturing: Data Science for all
Demystifying Machine Learning for Manufacturing: Data Science for all
Infosys
 
Digital Outlook: Healthcare Industry
Digital Outlook: Healthcare IndustryDigital Outlook: Healthcare Industry
Digital Outlook: Healthcare Industry
Infosys
 
5 tips to make your mainframe as fit as you
5 tips to make your mainframe as fit as you5 tips to make your mainframe as fit as you
5 tips to make your mainframe as fit as you
Infosys
 
Mainframe modernization powered by AI
Mainframe modernization powered by AIMainframe modernization powered by AI
Mainframe modernization powered by AI
Infosys
 
Human Amplification In The Enterprise - Resources and Utilities
Human Amplification In The Enterprise - Resources and UtilitiesHuman Amplification In The Enterprise - Resources and Utilities
Human Amplification In The Enterprise - Resources and Utilities
Infosys
 
Human Amplification In The Enterprise - Telecom and Communication
Human Amplification In The Enterprise - Telecom and CommunicationHuman Amplification In The Enterprise - Telecom and Communication
Human Amplification In The Enterprise - Telecom and Communication
Infosys
 
Human Amplification In The Enterprise - Retail and CPG
Human Amplification In The Enterprise - Retail and CPGHuman Amplification In The Enterprise - Retail and CPG
Human Amplification In The Enterprise - Retail and CPG
Infosys
 
Human Amplification In The Enterprise - Manufacturing and High-tech
Human Amplification In The Enterprise - Manufacturing and High-techHuman Amplification In The Enterprise - Manufacturing and High-tech
Human Amplification In The Enterprise - Manufacturing and High-tech
Infosys
 
Human amplification in the enterprise - Automation. Innovation. Learning.
Human amplification in the enterprise - Automation. Innovation. Learning.Human amplification in the enterprise - Automation. Innovation. Learning.
Human amplification in the enterprise - Automation. Innovation. Learning.
Infosys
 
Human Amplification In The Enterprise - Healthcare and Life Sciences
Human Amplification In The Enterprise - Healthcare and Life SciencesHuman Amplification In The Enterprise - Healthcare and Life Sciences
Human Amplification In The Enterprise - Healthcare and Life Sciences
Infosys
 
Human Amplification In The Enterprise - Banking and Insurance
Human Amplification In The Enterprise - Banking and InsuranceHuman Amplification In The Enterprise - Banking and Insurance
Human Amplification In The Enterprise - Banking and Insurance
Infosys
 
Mainframe modernization powered by AI
Mainframe modernization powered by AIMainframe modernization powered by AI
Mainframe modernization powered by AI
Infosys
 
Reimagining the future of IT Infrastructure
Reimagining the future of IT InfrastructureReimagining the future of IT Infrastructure
Reimagining the future of IT Infrastructure
Infosys
 
Infosys Amplifying Human Potential
Infosys Amplifying Human PotentialInfosys Amplifying Human Potential
Infosys Amplifying Human Potential
Infosys
 
Snapshots from Infosys Confluence 2016
Snapshots from Infosys Confluence 2016Snapshots from Infosys Confluence 2016
Snapshots from Infosys Confluence 2016
Infosys
 
Be Digital. Be More.
Be Digital. Be More.Be Digital. Be More.
Be Digital. Be More.
Infosys
 
Being Digital
Being DigitalBeing Digital
Being Digital
Infosys
 
Disruptive forces in digital payments
Disruptive forces in digital paymentsDisruptive forces in digital payments
Disruptive forces in digital payments
Infosys
 
Infosys 'Go Green' Initiative
Infosys 'Go Green' InitiativeInfosys 'Go Green' Initiative
Infosys 'Go Green' Initiative
Infosys
 
Serving the perfect Information Cocktail
Serving the perfect Information CocktailServing the perfect Information Cocktail
Serving the perfect Information Cocktail
Infosys
 

More from Infosys (20)

Demystifying Machine Learning for Manufacturing: Data Science for all
Demystifying Machine Learning for Manufacturing: Data Science for allDemystifying Machine Learning for Manufacturing: Data Science for all
Demystifying Machine Learning for Manufacturing: Data Science for all
 
Digital Outlook: Healthcare Industry
Digital Outlook: Healthcare IndustryDigital Outlook: Healthcare Industry
Digital Outlook: Healthcare Industry
 
5 tips to make your mainframe as fit as you
5 tips to make your mainframe as fit as you5 tips to make your mainframe as fit as you
5 tips to make your mainframe as fit as you
 
Mainframe modernization powered by AI
Mainframe modernization powered by AIMainframe modernization powered by AI
Mainframe modernization powered by AI
 
Human Amplification In The Enterprise - Resources and Utilities
Human Amplification In The Enterprise - Resources and UtilitiesHuman Amplification In The Enterprise - Resources and Utilities
Human Amplification In The Enterprise - Resources and Utilities
 
Human Amplification In The Enterprise - Telecom and Communication
Human Amplification In The Enterprise - Telecom and CommunicationHuman Amplification In The Enterprise - Telecom and Communication
Human Amplification In The Enterprise - Telecom and Communication
 
Human Amplification In The Enterprise - Retail and CPG
Human Amplification In The Enterprise - Retail and CPGHuman Amplification In The Enterprise - Retail and CPG
Human Amplification In The Enterprise - Retail and CPG
 
Human Amplification In The Enterprise - Manufacturing and High-tech
Human Amplification In The Enterprise - Manufacturing and High-techHuman Amplification In The Enterprise - Manufacturing and High-tech
Human Amplification In The Enterprise - Manufacturing and High-tech
 
Human amplification in the enterprise - Automation. Innovation. Learning.
Human amplification in the enterprise - Automation. Innovation. Learning.Human amplification in the enterprise - Automation. Innovation. Learning.
Human amplification in the enterprise - Automation. Innovation. Learning.
 
Human Amplification In The Enterprise - Healthcare and Life Sciences
Human Amplification In The Enterprise - Healthcare and Life SciencesHuman Amplification In The Enterprise - Healthcare and Life Sciences
Human Amplification In The Enterprise - Healthcare and Life Sciences
 
Human Amplification In The Enterprise - Banking and Insurance
Human Amplification In The Enterprise - Banking and InsuranceHuman Amplification In The Enterprise - Banking and Insurance
Human Amplification In The Enterprise - Banking and Insurance
 
Mainframe modernization powered by AI
Mainframe modernization powered by AIMainframe modernization powered by AI
Mainframe modernization powered by AI
 
Reimagining the future of IT Infrastructure
Reimagining the future of IT InfrastructureReimagining the future of IT Infrastructure
Reimagining the future of IT Infrastructure
 
Infosys Amplifying Human Potential
Infosys Amplifying Human PotentialInfosys Amplifying Human Potential
Infosys Amplifying Human Potential
 
Snapshots from Infosys Confluence 2016
Snapshots from Infosys Confluence 2016Snapshots from Infosys Confluence 2016
Snapshots from Infosys Confluence 2016
 
Be Digital. Be More.
Be Digital. Be More.Be Digital. Be More.
Be Digital. Be More.
 
Being Digital
Being DigitalBeing Digital
Being Digital
 
Disruptive forces in digital payments
Disruptive forces in digital paymentsDisruptive forces in digital payments
Disruptive forces in digital payments
 
Infosys 'Go Green' Initiative
Infosys 'Go Green' InitiativeInfosys 'Go Green' Initiative
Infosys 'Go Green' Initiative
 
Serving the perfect Information Cocktail
Serving the perfect Information CocktailServing the perfect Information Cocktail
Serving the perfect Information Cocktail
 

Recently uploaded

Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
Fwdays
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 

Recently uploaded (20)

Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 

Exploration Production Portals

  • 1. Originally appreared in: INFORMATION November 2007 issue, pgs 91-95. TECHNOLOGY Posted with permission. Engineering portals add significant value to E&P project delivery capabilities A portal approach enables information sharing among globally spread E&P project stakeholders. Kailash Samdani, Infosys Technologies Limited and Andy Till, BP Exploration Limited INTRODUCTION Organizations are adopting portal hydrocarbon potential and making a An E&P project is a complex engi- technology to publish project engineer- business case for field development. neering effort involving hundreds of ing information. Being able to share and Once the business case is in place, a engineers from different organizations, review project engineering information basic design development and selection working together to design, construct leads to significant benefits. Since pub- of Original Equipment Manufacturers and commission an asset before handing lished information is available instant- (OEM), vendors and contractors is car- it over to the owner/operator. Efficient ly—independent of stakeholder author- ried out in basic design. Subsequently, project management requires that engi- ing system constraints or geographical detailed plans and drawings are devel- neering information is available to all key location—information cycle times are oped in the detailed design phase. Fab- stakeholders in a way that enables them reduced. A portal system uses a single rication, construction and commis- to work as one integrated organization. integrated window to access all types of sioning activities for various systems There are numerous challenges in shar- engineering content, such as 3D models, and equipments are carried out in the ing and viewing engineering information intelligent drawings, data sheets and en- construct phase, which ends in handing from various sources, spread globally. An gineering databases. Also, operators are over the project to operations. engineering information portal provides better prepared to run the asset due to As shown in Fig. 1, engineering infor- a single window to view the informa- early exposure to engineering informa- mation volume increases as the project tion in a secure manner. It enables easy tion that allows them space and time to progresses from one phase to another. collaboration between stakeholders and develop and validate supporting proce- During the detailed design and construct supports productivity gains. dures and processes. phases, the volume of engineering in- formation shared and viewed reaches BACKGROUND TYPICAL PROJECT LIFECYCLE peak. Engineering information, such as Building a new E&P facility can cost Figure 1 provides an overview of a hundreds of 3D models, hundreds of $1–5 billion, taking three to five years to typical project lifecycle. The project’s thousands of documents and millions complete. As facility complexity increases, assess phase is about determining the of engineering data attributes, are shared the tradition of nominating a single lead EPCM (Engineering Procurement and Construction Management) contractor is Project being replaced by a consortium of EPC lifecycle Assess Basic Detailed Construct Operations design design contractors. As a result, the owner/op- stages erator is taking on more responsibility for Project management Engineering project contractor Operations the management of interfaces between contractors • Detailed models, design • Asset maintenance stakeholders. Oil and gas companies are Project • Basic design schematics and production activities development • Piping and instruments activities developing and implementing new in- • Large packages diagrams • De-bottlenecking formation management strategies to sup- • Contractor • Fabrications drawings studies port their evolving role and improve their selection • Construction and testing • Process • Testing and commissioning re-engineering project execution capabilities. Recent advances in technology are al- Volume of lowing organizations to take new man- engineering agement approaches of project informa- content Handover tion. First, the link between authoring applications and publishing applications has been broken and, as a result, docu- • Fewer • Increased number of • O&M users ments and 3D models can be viewed Information stakeholders stakeholders • Linking to business characteristics • Less information • Large volume of information systems independent of the tool used to create volume • Focus on details them. Second, the advancements in por- tal technology enable all stakeholders to Fig. 1. Project lifecycle and information explosion. view project information on the internet. November 2007 World Oil
  • 2. INFORMATION TECHNOLOGY and viewed in this virtual explosion of these organizations to validate and share contradictions and potential delays affect- engineering information. the information. Traditionally, a project ing the project schedule. Hundreds of engineers and designers owner has little visibility of the informa- The logical conclusion of E&P proj- belonging to various project stakeholders tion being exchanged among the external ects, as shown in Fig. 1, is the handover such as owner, EPCM contractor, fabrica- project stakeholders on their behalf. From of the facility to the operations team. It is tors, vendors, etc, generate, share, review a project perspective, this leads to multiple crucial for operations to have a complete and publish engineering information. Dif- sets of truths across organizations which, set of cleansed and validated engineering ferent systems and processes exist across if not managed appropriately, can result in information so that they can efficiently run and maintain the asset. Tradition- ally, the operations teams received in- Original equipment formation in bulk toward the end of the manufacturer Data cleansing service provider construct phase at the time of handover. EDW EDM 3D Project It is humanly impossible to review and models management validate all shared information during contractor the handover process. Construction and Several problems exist due to lack of a commissioning proper environment for sharing informa- EDW EDM 3D model teams snapshots tion. Little visibility leads to lack of con- trol on engineering activities and prog- ress. Project reviews can be delayed due to EPC 1 Engineering inconsistent information across multiple EPC 4 portal stakeholders. Productivity losses can oc- cur as a result of the overheads in search- EDW EDM 3D ing and retrieving required project docu- models mentation. Operators are ill-prepared to run and maintain the asset because of the EPC 2 EPC 3 bulk of information that is shared at the time of hand-over. Technology advances enable project owners to adopt a portal EDW EDM 3D EDW EDM 3D approach, which addresses a number of models models such issues. Fig. 2. Project engineering information portal. Engineering Data Warehouse (EDW), Engineering Document Management (EDM) and A PORTAL APPROACH Engineering Procurement Contractor (EPC). A portal approach provides a single window to all project engineering content Table 1. Issues with portal solution and possible resolutions Information characteristic Issue description Possible resolution Information types User expects to view 3D models as well as engi- Portal should incorporate the ability to move seamlessly from 3D neering data sheets or smart P&IDs altogether. models with associated detailed functionalities along with the abil- ity to view intelligent drawings and engineering data tables. The portal should be able to present information to a user either through a native file format or rendition. Information quality User expects to view accurate and consistent Portal should be able to perform quality assurance checks for information. Typically, different organizations incoming data accuracy and consistency. follow different standards/conventions for data Portal should be able to establish and update associations among management (e.g., different organizations may 3D models, engineering data and engineering documents, where represent the same pump by P_101 or P/101 or necessary providing an aliasing capability. P101, etc. owing to their internal standards and procedures). Information volume The nature of project engineering information Portal should be based on a robust technology platform that can is such that it keeps changing. The problem of handle transactions involving high volumes over internet. managing such continuously changing informa- Portal should be able to update the associations every time new tion gets compounded by the sheer volume of information arrives and should posses change management func- information. tionality. Information vulnerability Hundreds of users from different organizations The system should have a security model which is company, disci- need to access portal and interact according to pline and role based. their role on the project, their job position and Security of information should extend to the revision of individual organization they represent. Also companies may documents and the design status. perceive risk in hosting such a portal on intranet. The application and hosting environment should be certified by an accredited Digital Security organization for use on Intranet / Internet. November 2007 World Oil
  • 3. INFORMATION TECHNOLOGY such as 3D models, intelligent documents cessed over the web in a secure manner, as lessly between otherwise unrelated data and datasheets. It displays two types of well as in remote offshore areas and high sets. The ability to share and view infor- information sets: published information latency-low bandwidth areas. It should be mation with multiple stakeholders across (e.g., a document with a specific revi- able to interface with source systems on geographies improves team collabora- sion number which will never change but the internet as well as intranet. tion, which results in more informed and could be superseded) and snapshot infor- quicker decisions due to increased visibil- mation (e.g., a copy of a 3D model at a ISSUES AND POSSIBLE ity. Developing and updating hook-up specific time). Through a cleansing and RESOLUTIONS and commissioning workpacks is easier validation process, these information sets Good information specifications and saves time. Portals enable simplified can be aggregated together into an engi- are needed for all projects. A portal ap- and progressive handover of informa- neering portal as shown in Fig. 2. proach quickly highlights inconsistencies tion to operations, which enables them When the portal is accessed, users are in the project information. The true cost to contribute to reviews of operation and provided with requisite information of all of implementing a portal approach is maintenance apart from developing work types from all stakeholders. Stakeholder marginal when compared to the real cost procedures and training manuals in ad- organizations need to have systems (e.g., of getting the relevant project informa- vance. Portals enable a population of data engineering data warehouse, engineering tion. If a project aspires to use a portal into enterprise systems, such as mainte- document management systems, model- approach, it must have a clearly defined nance management, document manage- ing systems) and processes (such as data and published approach to information ment and engineering data warehouses. cleansing and validation processes) to management. The requirement of shar- Also, since the bulk of engineering or publish a variety of engineering informa- ing accurate, consistent and complete in- vendor data is common across projects, tion to a portal environment. formation must be contractually binding a portal system substantially reduces the Project organizations desire to improve on all information suppliers. It is prefer- cost of information for future projects. the availability and visibility of engineer- able to have information validated and ing information throughout the project cleansed before it is published. CONCLUSION lifecycle to optimize concurrent engineer- Projects adopting a portal approach As the size of E&P projects continue ing, minimize information cycle time and to access project information can face a to grow, the way in which stakeholders eliminate rework due to poor informa- number of issues because of the nature of interact needs to evolve. Larger and more tion. Requirements from a portal solution information being handled. The project complex projects need to develop more can be categorized into three broad areas. information can be characterized as: appropriate ways of project execution. •  Information types: Multiple native Technology advances are being increas- Functional requirements. A portal file formats exist according to the au- ingly used to make projects more effi- solution should provide a single window thoring system (3D models, intelligent cient. The web-based portal approach to different project engineering content, drawings, engineering data, etc). enables organizations to control and such as models, engineering databases •  Information quality: Complete- share project information among global and intelligent, as well as dumb, drawings ness and consistency of information stakeholders and reduce information and documents. It should enable easy coming from different organizations or cycle time, thus improving the speed of navigation through various information systems varies. execution, leading to a successful deliv- sets, so that users can move seamlessly •  Information volume: Hundreds of ery of the project into operation. WO across different content types. It should 3D models, hundreds of thousands of be independent of source systems and be documents, and millions of engineering able to interface with proprietary file for- data attributes are available to view. The authors mats from multiple suppliers. It should •  Information vulnerability: Infor- Kailash Samdani works support quality assurance checks before mation accessed by large numbers of us- with Domain Competency the information is published on the por- ers from different organizations gives rise Group of Infosys Technolo- to security concerns. gies Ltd. Kailash has 15 tal. It should also manage updated con- years of experience in pre- tent from stakeholders. It should enable Each information characteristic gives sales, consulting and busi- role based workflow capabilities coupled rise to a set of unique issues. These is- ness development of IT en- with an information security model and sues and resolution approaches are cov- abled advanced solutions ered in Table 1. to hydrocarbon, chemicals also support collaboration among all us- and metal industries. He ers spread geographically. has a BS degree in chemical engineering from BENEFITS OF PORTAL Birla Institute of Technology Science, Pilani, User requirements. A portal solution APPROACH India. He can be reached at Kailash_Samdani@ infosys.com. should provide viewing capabilities to A portal approach provides benefits analyze information contained within in many areas. Easy access to current and Andy Till worked for BP 3D models and intelligent drawings consistent information is one of the key Exploration Ltd for 18 years e.g., zoom in/out, collision detection, parameters to successful execution of in a number of roles and is currently an IT consultant mark-up, etc. It should provide easy, yet large projects. A portal approach provides for Major Projects. Andy advanced, search mechanisms to get to a single window to the published infor- spent his first eight years desired information within a minimum mation, thus improving availability of as an engineer designing, number of mouse-clicks. requisite drawings and documents lead- constructing, installing and commissioning both on- ing to better preparedness for project re- shore and offshore facili- Technical requirements. A portal so- views in less time. It enables quick access ties before moving to IT, where he continues to lution should allow information to be ac- to current information, moving seam- support both engineering and projects. Article copyright © 2009 by Gulf Publishing Company. All rights reserved. Printed in U.S.A. Not to be distributed in electronic or printed form, or posted on a website, without express written permission of copyright holder.