SlideShare a Scribd company logo
Presented by
T Ram Kumar
Associate
 Equipment qualification is an essential step that
companies need to perform in order to ensure that
their products or services meet manufacturing and
testing requirements and international standards.
Project Initiation
master validation plan
vendor management
Equipment Qualification DQ(FAT, SAT),
IQ, OQ, PQ
Validation
◦ Establishing documented evidence that provides a
high degree of assurance that a specific process will
consistently provide a product meeting its
predetermined specifications and quality attributes.
Design Qualification
◦ The documented verification that the proposed
design of the facilities, systems and equipment is
suitable for the intended purpose or documented
verification that the system design satisfies the
requirements set forth in the URS.
Installation Qualification
◦ The installation qualification is to demonstrate that
all the critical components of the process
equipment and support installations have been
installed appropriately and are installed to the
respective manufacturer’s or supplier’s
requirements.
Operational Qualification
◦ The OQ demonstrates whether a facility, process
equipment and sub- systems are capable of
consistently operating within established limits and
tolerances by testing compliance with design
requirements in URS.
 Performance Qualification
◦ Performance qualification are a collection of test
cases used to verify that the system performs as
expected under simulated real-world conditions.
◦ The documented collection of activities necessary
to demonstrate that an instrument consistently
performs according to the specifications defined by
the user and is appropriate for the intended use. A
series of tests are drawn to check the performance
of the equipment.
 The installation is done as per design
specification URS. (IQ)
 The operation is as per the function and
design specification in the URS. (OQ)
 The performance is as per the overall
performance requirements specified in the
URS. (PQ)
 FAT or SAT may be done based on risk
assessment or criticality.
 The impact of the equipment or system shall
be assessed during risk assessment to
determine those equipment or system that
requires qualification and those equipments
which do not require qualification.
 Based on risk assessment, the equipment can
be categorized as
1. Direct impact
2. Indirect impact
3. No impact
 Having direct impact on the product quality.
E.g. Air quality, Material of construction, type
of water, autoclave, CIP systems.
 Produces data, which is used to accept /
reject in process material or product.
E.g. Electronic Batch recording system.
 For process control systems such as PLC and
SCADA or DCS.
 Indirect systems are those systems whose
parts are connected to direct impact system
or are playing an important role in direct
impact systems.
E. g. labelling machine, packing machine.
 No impact systems are those having no
impact on product quality.
E.g. conveyer belts, lifting and positioning
devices.
category Need for Qualification
activity
Qualification approach
Direct Impact system Yes URS→DQ(FAT,SAT) →
IQ→OQ→PQ
Indirect Impact system Yes URS→DQ (FAT,SAT) →
IQ & OQ, OQ& PQ (as
applicable)
No impact system No Good Engineering
practice
 User Requirement specification shall be
prepared by the user department in co-
ordination with engineering based on
previous performance and practical
experience.
 URS should contain specifications of the
system, documents required, safety design
features, Equipment/ system description.
 The URS shall be approved by QA and the
same shall be submitted.
 After approval “Uncontrolled copy” shall be
issued by QA to Engineering dept. for the
identification of vendor who meets required
specifications.
 Design Qualification is aimed to specify the
equipment, system or facility is designed in
accordance with the requirements of the user
and good manufacturing practice(GMP)
standards.
 DQ document shall be prepared, reviewed by
the manufacturer. For feasibility the same
shall be reviewed and approved by the user,
Engineering and QA department.
 Design qualification should contain
1. Equipment/system description
2. Equipment/system technical specification
3. Review/evaluation of vendor design against the URS
4. Deficiency sheet
5. Review inclusive of follow up action (if any)
6. It should cover all the necessary diagrams and layout
7. Desired material of construction
8. Location of control panel and electrical and utility
requirement and their range.
9. After sign off, any changes made which is having
direct or indirect impact can be handled through
change control.
 Factory Acceptance Test is carried out by
user, Engineering/projects and QA at the site
of the vendor or by video conferencing
through FAT document provided by the
vendor.
 The evaluation includes
◦ Physical verification of dimensions
◦ Blower specifications
◦ Valves
◦ Safety requirements
 Critical operation requirement
◦ By simulation or conventional function
◦ Verification of documents
◦ Overall review / inspection
◦ Any modification from approved DQ, approved
during FAT shall be incorporated in CC and
considered during IQ.
◦ FAT document shall be filed in QA department.
 Site acceptance test shall be performed by
User, Engineering and QA at site after the
recipient of equipment/system in presence of
vendor to ensure that the equipment /
system is in good state, no components are
damaged and meeting the design as per URS.
 It involves inspection of major or sub
components in packed or unpacked
condition, alignment checks of various
components.
 SAT also verifies the supporting utilities,
pendants availability and adequacy etc at site.
 Points which are left out in FAT can be
assessed in SAT test.
 IQ document shall be prepared by
Engineering department in coordination with
user and QA.
 IQ is carried out to ensure the premises
supporting utilities and equipment have been
built and installed in compliance with their
approved design specification (DQ) and
manufacturers manual and recommendations.
 The documents used for IQ should contain
but not limited to
◦ Equipment description & identification
◦ List of reference documents & drawings
◦ Pre-requisites
◦ Checklist for inspection of Equipment on receipt
◦ List of Spares received
◦ Location suitability
◦ Verification of major components
◦ Verification of installation
◦ Identification of equipment / instrument for
calibration and preventive maintenance.
◦ Material of construction
◦ Utilities/service connection checks
◦ Cleaning & passivation
◦ Manufacturer certificates
◦ Identification of product contact surfaces
◦ Deficiency sheet
Any non compliance observed during Installation
qualification shall be recorded.
 OQ shall be performed to verify that the
equipment, instrument, utility and system,
operates in accordance with design
specification, manufacturer recommendations
and cGMP requirements.
 Operational Qualification shall be prepared by
user department in coordination with
Engineering department and Quality
assurance.
 OQ shall be prepared based on the DQ and
manufacturers manual and recommendation.
 Operational testing to be done, whenever
possible to challenge the system, to the limits
of anticipated operating conditions.
 OQ shall be done without any load, if its not
possible then loaded trials can be taken.
 It also should test the performance of the
equipments components such as motors,
blowers, sensors, functioning of interlocks,
safety features.
 The OQ document should contain but not
limited to
◦ Equipment operating principle
◦ Pre-requisites for operational qualification
◦ Methodology for operational qualification
◦ Calibration review of critical instruments like
sensor, probes, gauges, recorders, air flow rates.
◦ Directions, pressure, temperature etc and referring
to standard test instrument.
◦ Operational verification of equipment i.e
operational testing as per process and system.
◦ Verifications of Draft SOPs & training.
◦ Testing of safety features and interlocks
◦ Power failure verification
◦ Validation of PLC
◦ Training to personnel for maintenance and operation
◦ Deficiency sheet
◦ When OQ documents compiled by vendor the documents
shall be evaluated by the QA.
◦ The completion of successful OQ should allowed the
finalization of SOPs and cleaning procedures, operator
training and PM requirement.
 PQ demonstrates that how the
equipment/system will perform when
challenged under simulated or actual
production conditions.
 A series of tests are designed to demonstrate
that the equipment/system are capable to
perform consistently and meet required
specifications under routine production
operations.
 Performance qualification document shall be
prepared by QA (Validation) in coordination
with user department and Engineering
department.
 Performance qualification of the equipment
shall be prepared based on User’s
requirement and design qualification/
technical specification provided by the
manufacturer.
 PQ document should contain but not limited
to
◦ Pre-requisites for PQ
◦ Methodology for performance qualification
◦ Performance verification tests
◦ Deficiency sheet
Any significant changes it approved DQ/IQ/OQ/PQ
documents during execution should be documented
as a deviation and the same should be justified.
 Conditional approval for proceeding to next
phase of qualification can be given when
certain acceptance criteria or deviation is not
fully addressed, the same shall be addressed
through documented evidence of no
significant impact on the next activity.
 Qualification activities wherein location needs
to be identified for placement of data loggers
or sensors, the schematic layouts for sensor
location should be mentioned in validation
protocol for better clarity.
 Requalification shall be carried out in case
◦ Modification in the equipment which directly or
indirectly affects the quality of the products
processed in the equipment
◦ Relocation of the equipment
◦ Equipment up gradation
◦ Any other changes that deemed necessary for
requalification through change management
system.
 Guideline – SOP.com
 ICH, Q9 Quality risk management
EQUIPMENT QUALIFICATION.pptx

More Related Content

What's hot

SUPAC, BACPAC, Post Marketing Surveillance
SUPAC, BACPAC, Post Marketing SurveillanceSUPAC, BACPAC, Post Marketing Surveillance
SUPAC, BACPAC, Post Marketing Surveillance
MANIKANDAN V
 
Product Registration Guidlines
Product Registration GuidlinesProduct Registration Guidlines
Product Registration Guidlines
Sagar Bagul
 
IPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptxIPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptx
Dhruvi50
 
Vendor qualification
Vendor qualification Vendor qualification
Vendor qualification
KhushbooKunkulol
 
Validation of hvac system
Validation of hvac systemValidation of hvac system
Validation of hvac system
vaishali kyadari
 
Requalification
RequalificationRequalification
CHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdfCHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdf
Dr. Dinesh Mehta
 
Regulatory requirements for api registration
Regulatory requirements for api registrationRegulatory requirements for api registration
Regulatory requirements for api registration
Siddu K M
 
Qualification of Autoclave.pptx
Qualification of Autoclave.pptxQualification of Autoclave.pptx
Qualification of Autoclave.pptx
Dhruvi50
 
Validation of hvac
Validation of hvacValidation of hvac
CGMP guidelines
CGMP guidelinesCGMP guidelines
CGMP guidelines
NikitaTakale
 
Change control oos oot
Change control oos ootChange control oos oot
Change control oos oot
AMOGH DANDEKAR
 
Qualification of Dry Powder Mixture
Qualification of Dry Powder Mixture Qualification of Dry Powder Mixture
Pharmaceutical inspection convention
Pharmaceutical inspection conventionPharmaceutical inspection convention
Pharmaceutical inspection convention
RAGHAV DOGRA
 
Qualification of high performance liquid chromatography
Qualification of high performance liquid chromatographyQualification of high performance liquid chromatography
Qualification of high performance liquid chromatography
srikrupa institute of pharmaceutical analysis
 
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.
KhushbooKunkulol
 
Qualification of membrane filtration apparatus
Qualification of membrane filtration apparatusQualification of membrane filtration apparatus
Qualification of membrane filtration apparatus
PRAVADA
 
BACPAC
BACPACBACPAC
BACPAC
Dhruvi50
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
Sanathoiba Singha
 
Validation of pharaceutical water system and pure steam
Validation of pharaceutical water system and pure steamValidation of pharaceutical water system and pure steam
Validation of pharaceutical water system and pure steam
Jp Prakash
 

What's hot (20)

SUPAC, BACPAC, Post Marketing Surveillance
SUPAC, BACPAC, Post Marketing SurveillanceSUPAC, BACPAC, Post Marketing Surveillance
SUPAC, BACPAC, Post Marketing Surveillance
 
Product Registration Guidlines
Product Registration GuidlinesProduct Registration Guidlines
Product Registration Guidlines
 
IPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptxIPQC of Sterile Ointment.pptx
IPQC of Sterile Ointment.pptx
 
Vendor qualification
Vendor qualification Vendor qualification
Vendor qualification
 
Validation of hvac system
Validation of hvac systemValidation of hvac system
Validation of hvac system
 
Requalification
RequalificationRequalification
Requalification
 
CHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdfCHAPTER-1 DEFICIENCIES.pdf
CHAPTER-1 DEFICIENCIES.pdf
 
Regulatory requirements for api registration
Regulatory requirements for api registrationRegulatory requirements for api registration
Regulatory requirements for api registration
 
Qualification of Autoclave.pptx
Qualification of Autoclave.pptxQualification of Autoclave.pptx
Qualification of Autoclave.pptx
 
Validation of hvac
Validation of hvacValidation of hvac
Validation of hvac
 
CGMP guidelines
CGMP guidelinesCGMP guidelines
CGMP guidelines
 
Change control oos oot
Change control oos ootChange control oos oot
Change control oos oot
 
Qualification of Dry Powder Mixture
Qualification of Dry Powder Mixture Qualification of Dry Powder Mixture
Qualification of Dry Powder Mixture
 
Pharmaceutical inspection convention
Pharmaceutical inspection conventionPharmaceutical inspection convention
Pharmaceutical inspection convention
 
Qualification of high performance liquid chromatography
Qualification of high performance liquid chromatographyQualification of high performance liquid chromatography
Qualification of high performance liquid chromatography
 
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.
 
Qualification of membrane filtration apparatus
Qualification of membrane filtration apparatusQualification of membrane filtration apparatus
Qualification of membrane filtration apparatus
 
BACPAC
BACPACBACPAC
BACPAC
 
Qualification of analytical instruments
Qualification of analytical instrumentsQualification of analytical instruments
Qualification of analytical instruments
 
Validation of pharaceutical water system and pure steam
Validation of pharaceutical water system and pure steamValidation of pharaceutical water system and pure steam
Validation of pharaceutical water system and pure steam
 

Similar to EQUIPMENT QUALIFICATION.pptx

Qualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptxQualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptx
HemlataMore3
 
Qualification for validation
Qualification for validationQualification for validation
Qualification for validation
Institute Of Pharmacy, Nirma University
 
GMP Equipment Qualification and Maintenance System .pdf
GMP Equipment Qualification and Maintenance System .pdfGMP Equipment Qualification and Maintenance System .pdf
GMP Equipment Qualification and Maintenance System .pdf
sri krishna pharmaceuticals limited
 
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptxEQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
praaditya2020
 
Equipment Qualification.pptx
Equipment Qualification.pptxEquipment Qualification.pptx
Equipment Qualification.pptx
Neeraj Kumar Rai
 
Validation documents
Validation documentsValidation documents
Validation documents
Mruganka Jadhav
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom Qualification
Anwar Munjewar
 
Urs,dq, iq,oq,pq
Urs,dq, iq,oq,pqUrs,dq, iq,oq,pq
Urs,dq, iq,oq,pq
Māľāý Păųļ
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdf
abdo badr
 
Validation master plan
Validation master planValidation master plan
Validation master plan
Dr. Amsavel A
 
Validation Documents.ppt
Validation Documents.pptValidation Documents.ppt
Validation Documents.ppt
Mruganka Jadhav
 
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptxICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
NikitaSahu39
 
Equipment Qualification
Equipment QualificationEquipment Qualification
Equipment Qualification
CMiller669
 
An approach on pharmaceuticals qualification
An approach on pharmaceuticals qualificationAn approach on pharmaceuticals qualification
An approach on pharmaceuticals qualification
Dewan Sumsuzzman
 
validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdf
AkashChaudhary749568
 
Jatin validation
Jatin validationJatin validation
Jatin validation
jatin singla
 
Introduction to validation
Introduction to validation Introduction to validation
Introduction to validation
Ankush Sule
 

Similar to EQUIPMENT QUALIFICATION.pptx (20)

Qualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptxQualification of Laboratory Equipments.pptx
Qualification of Laboratory Equipments.pptx
 
Qualification for validation
Qualification for validationQualification for validation
Qualification for validation
 
GMP Equipment Qualification and Maintenance System .pdf
GMP Equipment Qualification and Maintenance System .pdfGMP Equipment Qualification and Maintenance System .pdf
GMP Equipment Qualification and Maintenance System .pdf
 
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptxEQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
EQUIPMENT QUALIFICATION & MAINTENANCE SYSTEM.pptx
 
Equipment Qualification.pptx
Equipment Qualification.pptxEquipment Qualification.pptx
Equipment Qualification.pptx
 
Validation documents
Validation documentsValidation documents
Validation documents
 
Cleanroom Qualification
Cleanroom QualificationCleanroom Qualification
Cleanroom Qualification
 
Urs,dq, iq,oq,pq
Urs,dq, iq,oq,pqUrs,dq, iq,oq,pq
Urs,dq, iq,oq,pq
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdf
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
Validation
ValidationValidation
Validation
 
Validation Documents.ppt
Validation Documents.pptValidation Documents.ppt
Validation Documents.ppt
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptxICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
ICH guidelines for validation Of Equipments by Nikita Sahu[1].pptx
 
Equipment Qualification
Equipment QualificationEquipment Qualification
Equipment Qualification
 
An approach on pharmaceuticals qualification
An approach on pharmaceuticals qualificationAn approach on pharmaceuticals qualification
An approach on pharmaceuticals qualification
 
validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdf
 
Jatin validation
Jatin validationJatin validation
Jatin validation
 
Introduction to validation
Introduction to validation Introduction to validation
Introduction to validation
 

Recently uploaded

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 

Recently uploaded (20)

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 

EQUIPMENT QUALIFICATION.pptx

  • 1. Presented by T Ram Kumar Associate
  • 2.  Equipment qualification is an essential step that companies need to perform in order to ensure that their products or services meet manufacturing and testing requirements and international standards.
  • 3. Project Initiation master validation plan vendor management Equipment Qualification DQ(FAT, SAT), IQ, OQ, PQ
  • 4. Validation ◦ Establishing documented evidence that provides a high degree of assurance that a specific process will consistently provide a product meeting its predetermined specifications and quality attributes. Design Qualification ◦ The documented verification that the proposed design of the facilities, systems and equipment is suitable for the intended purpose or documented verification that the system design satisfies the requirements set forth in the URS.
  • 5. Installation Qualification ◦ The installation qualification is to demonstrate that all the critical components of the process equipment and support installations have been installed appropriately and are installed to the respective manufacturer’s or supplier’s requirements. Operational Qualification ◦ The OQ demonstrates whether a facility, process equipment and sub- systems are capable of consistently operating within established limits and tolerances by testing compliance with design requirements in URS.
  • 6.  Performance Qualification ◦ Performance qualification are a collection of test cases used to verify that the system performs as expected under simulated real-world conditions. ◦ The documented collection of activities necessary to demonstrate that an instrument consistently performs according to the specifications defined by the user and is appropriate for the intended use. A series of tests are drawn to check the performance of the equipment.
  • 7.
  • 8.  The installation is done as per design specification URS. (IQ)  The operation is as per the function and design specification in the URS. (OQ)  The performance is as per the overall performance requirements specified in the URS. (PQ)  FAT or SAT may be done based on risk assessment or criticality.
  • 9.  The impact of the equipment or system shall be assessed during risk assessment to determine those equipment or system that requires qualification and those equipments which do not require qualification.  Based on risk assessment, the equipment can be categorized as 1. Direct impact 2. Indirect impact 3. No impact
  • 10.  Having direct impact on the product quality. E.g. Air quality, Material of construction, type of water, autoclave, CIP systems.  Produces data, which is used to accept / reject in process material or product. E.g. Electronic Batch recording system.  For process control systems such as PLC and SCADA or DCS.
  • 11.  Indirect systems are those systems whose parts are connected to direct impact system or are playing an important role in direct impact systems. E. g. labelling machine, packing machine.  No impact systems are those having no impact on product quality. E.g. conveyer belts, lifting and positioning devices.
  • 12. category Need for Qualification activity Qualification approach Direct Impact system Yes URS→DQ(FAT,SAT) → IQ→OQ→PQ Indirect Impact system Yes URS→DQ (FAT,SAT) → IQ & OQ, OQ& PQ (as applicable) No impact system No Good Engineering practice
  • 13.  User Requirement specification shall be prepared by the user department in co- ordination with engineering based on previous performance and practical experience.  URS should contain specifications of the system, documents required, safety design features, Equipment/ system description.  The URS shall be approved by QA and the same shall be submitted.
  • 14.  After approval “Uncontrolled copy” shall be issued by QA to Engineering dept. for the identification of vendor who meets required specifications.
  • 15.  Design Qualification is aimed to specify the equipment, system or facility is designed in accordance with the requirements of the user and good manufacturing practice(GMP) standards.  DQ document shall be prepared, reviewed by the manufacturer. For feasibility the same shall be reviewed and approved by the user, Engineering and QA department.
  • 16.  Design qualification should contain 1. Equipment/system description 2. Equipment/system technical specification 3. Review/evaluation of vendor design against the URS 4. Deficiency sheet 5. Review inclusive of follow up action (if any) 6. It should cover all the necessary diagrams and layout 7. Desired material of construction 8. Location of control panel and electrical and utility requirement and their range. 9. After sign off, any changes made which is having direct or indirect impact can be handled through change control.
  • 17.  Factory Acceptance Test is carried out by user, Engineering/projects and QA at the site of the vendor or by video conferencing through FAT document provided by the vendor.  The evaluation includes ◦ Physical verification of dimensions ◦ Blower specifications ◦ Valves ◦ Safety requirements
  • 18.  Critical operation requirement ◦ By simulation or conventional function ◦ Verification of documents ◦ Overall review / inspection ◦ Any modification from approved DQ, approved during FAT shall be incorporated in CC and considered during IQ. ◦ FAT document shall be filed in QA department.
  • 19.  Site acceptance test shall be performed by User, Engineering and QA at site after the recipient of equipment/system in presence of vendor to ensure that the equipment / system is in good state, no components are damaged and meeting the design as per URS.  It involves inspection of major or sub components in packed or unpacked condition, alignment checks of various components.
  • 20.  SAT also verifies the supporting utilities, pendants availability and adequacy etc at site.  Points which are left out in FAT can be assessed in SAT test.
  • 21.  IQ document shall be prepared by Engineering department in coordination with user and QA.  IQ is carried out to ensure the premises supporting utilities and equipment have been built and installed in compliance with their approved design specification (DQ) and manufacturers manual and recommendations.
  • 22.  The documents used for IQ should contain but not limited to ◦ Equipment description & identification ◦ List of reference documents & drawings ◦ Pre-requisites ◦ Checklist for inspection of Equipment on receipt ◦ List of Spares received ◦ Location suitability ◦ Verification of major components ◦ Verification of installation ◦ Identification of equipment / instrument for calibration and preventive maintenance.
  • 23. ◦ Material of construction ◦ Utilities/service connection checks ◦ Cleaning & passivation ◦ Manufacturer certificates ◦ Identification of product contact surfaces ◦ Deficiency sheet Any non compliance observed during Installation qualification shall be recorded.
  • 24.  OQ shall be performed to verify that the equipment, instrument, utility and system, operates in accordance with design specification, manufacturer recommendations and cGMP requirements.  Operational Qualification shall be prepared by user department in coordination with Engineering department and Quality assurance.
  • 25.  OQ shall be prepared based on the DQ and manufacturers manual and recommendation.  Operational testing to be done, whenever possible to challenge the system, to the limits of anticipated operating conditions.  OQ shall be done without any load, if its not possible then loaded trials can be taken.  It also should test the performance of the equipments components such as motors, blowers, sensors, functioning of interlocks, safety features.
  • 26.  The OQ document should contain but not limited to ◦ Equipment operating principle ◦ Pre-requisites for operational qualification ◦ Methodology for operational qualification ◦ Calibration review of critical instruments like sensor, probes, gauges, recorders, air flow rates. ◦ Directions, pressure, temperature etc and referring to standard test instrument. ◦ Operational verification of equipment i.e operational testing as per process and system.
  • 27. ◦ Verifications of Draft SOPs & training. ◦ Testing of safety features and interlocks ◦ Power failure verification ◦ Validation of PLC ◦ Training to personnel for maintenance and operation ◦ Deficiency sheet ◦ When OQ documents compiled by vendor the documents shall be evaluated by the QA. ◦ The completion of successful OQ should allowed the finalization of SOPs and cleaning procedures, operator training and PM requirement.
  • 28.  PQ demonstrates that how the equipment/system will perform when challenged under simulated or actual production conditions.  A series of tests are designed to demonstrate that the equipment/system are capable to perform consistently and meet required specifications under routine production operations.
  • 29.  Performance qualification document shall be prepared by QA (Validation) in coordination with user department and Engineering department.  Performance qualification of the equipment shall be prepared based on User’s requirement and design qualification/ technical specification provided by the manufacturer.
  • 30.  PQ document should contain but not limited to ◦ Pre-requisites for PQ ◦ Methodology for performance qualification ◦ Performance verification tests ◦ Deficiency sheet Any significant changes it approved DQ/IQ/OQ/PQ documents during execution should be documented as a deviation and the same should be justified.
  • 31.  Conditional approval for proceeding to next phase of qualification can be given when certain acceptance criteria or deviation is not fully addressed, the same shall be addressed through documented evidence of no significant impact on the next activity.  Qualification activities wherein location needs to be identified for placement of data loggers or sensors, the schematic layouts for sensor location should be mentioned in validation protocol for better clarity.
  • 32.  Requalification shall be carried out in case ◦ Modification in the equipment which directly or indirectly affects the quality of the products processed in the equipment ◦ Relocation of the equipment ◦ Equipment up gradation ◦ Any other changes that deemed necessary for requalification through change management system.
  • 33.  Guideline – SOP.com  ICH, Q9 Quality risk management