Economy and Energy Security for Pakistan -
What lies ahead
COMSATS Institute of Information Technology
12 October 2013
• The Economic Survey of Pakistan recognizes that during 2012
around 2 percent of gross domestic product (GDP) was lost
due to the power sector outages.
• The petroleum crude and products contributed to a third of
total imports of Pakistan during 2012
• The transmission and distribution (T&D) losses were valued at
PKR 140 billion in 2012
• Issues being currently faced can be categorised into policy,
governance, technical and cost issues
2
Background
• Short-term situation analysis
• Limiting analysis to power sector
• Assumptions:
– It will be difficult to attract investment
– It will be difficult to bring legislative changes
– Will be difficult to change governance structures at generation and
distribution companies
• What lies ahead?
3
Sequence of Discussion
Circular Debt in Power Sector
111
145 161
236
366
538
872
0
100
200
300
400
500
600
700
800
900
1000
2006 2007 2008 2009 2010 2011 2012
PKRBillions
Source: Planning Commission 2013
Integrated Energy
Policy
Consolidate
fragmented energy
governance
Build capacity of
regulators
Deregulate energy
sector further
Reforms for
attracting
investment in
energy sector
Make generation
efficient
Reduce
transmission losses
Hydro, Coal and
other sources
Steps that were promised
These may be symptoms but are not causes of crisis
Unwillingess to
pay the price of
energy
Political
stubbornness
to maintain
subsidies
Administrative
and line losses
7
3 key causes
• Willingness and ability to pay for power
• Recoveries of some very large power distribution companies
have deteriorated over time
– In Hyderabad, for example, only 60% of the power supplied in 2012
was paid for – in a city of over 6.5 million people
• DISCOs are unable to adopt the normal commercial practices
in other countries of disconnecting customers for non-
payment because of unclear legislation and political pressure.
8
1. Unwillingness to pay for power
9
Source: SDPI Survey Unit 2013
No , 82%
Don't
Know, 6%
Yes,
12%
Will households pay if power cuts are
eliminated and tariff is increased by 10%
• The fundamental rationale for subsidising electricity tariffs is
to augment the paying capacity of the poorest of poor
• However once subsidies are provided across the board,
people start to demand them as their right and politicians feel
compelled to maintain this distortive fiscal burden to win
popularity.
• Do poor really get power subsidies in Pakistan
– Domestic lifeline consumers (1-100 units) only get 0.3% subsidy
10
2. Political stubbornness to maintain subsidies
Subsidybythegovernmentonpowerconsumption(Rs/kW)
LESCO GEPCO FESCO MEPCO HESCO SEPCO QESCO PESCO
1.Residential,<700units 0.4 1.4 1.4 2.9 3.9 3.9 1.4 4.4
2.Industrial,(66.132KV&above)-
TOU(Peak) 2.1 2.1 2.1 3.1 6.6 6.6 4.0 7.1
3.Agricultural,5KW&above-TOU
(Peak) 1.5 1.5 1.5 2.5 6.0 6.0 3.5 6.5
Source: Economic Survey of Pakistan, 2013
Electricity Shortfall & Subsidies
12
0
50
100
150
200
250
300
350
400
450
500
0
1000
2000
3000
4000
5000
6000
7000
2005 2006 2007 2008 2009 2010 2011 2012 2013
Subsidy(PKRBillion)
Deficit(MW)
Electricity Shortfall (MW) Subsidy to Power Sector
Source: NEPRA and Planning Commission 2013
• In August 2013, the Secretary of Water and Power
Ministry informed the Senate Standing Committee that
– Pakistan loses annually PKR 150 billion (USD 1.7 billion) in
line losses and power theft.
– Until August 23770 cases of theft were registered and
under trial
– But only 3 cases were punished. Moreover, the fine
imposed was under PKR 5000 in each case.
• Lacunae in the accountability mechanism. This requires
amendments in Pakistan Penal Code so that there is
certainty of effective punishment in cases of power
theft
13
3. Administrative & Line Losses (Theft)
14
Power T & D Losses (% of output)
0
5
10
15
20
25
30
35
40
1971
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
Percentage
Pakistan Bangladesh
15
35%
59%
6%
Yes No Don't Know
Do you know of power theft in your area?
Source: SDPI Survey Unit 2013
Tariffs and
Subsidies
Curbing
Theft
Creating
Competition
in power
sector
16
Hopes from National Power Policy
All subsidies (including hidden and cross subsidies) - except
a 100 unit lifeline block - should be phased out over the
next 24 months.
17
1. Tariffs and Subsidies
• Unaccounted-for-gas controls should be enforced and the saved
gas diverted to the power sector. The power ministry notes that
just a 10 percent diversion can produce an extra 2000MW.
• Performance contracts for grid stations under National
Transmission and Dispatch Company.
• Performance contracts should also be introduced for DISCOs.
Such a contract should have specific clauses on reduction in
distribution losses and full collection of receivables from
consumers.
• Accountability at XEN-level
• Role of provinces
• Social accountability tools
18
2. Curbing Loses
• Creating competition on distribution side is important but a
medium to longer term option
• What about creating competition in generation sector?
• The allocation of fuel to generation companies (GENCOs) should be
linked with their efficiency levels
• If the Independent Power Producers (IPPs) are better performing in
efficiency terms then fuel allocation may be in favour of IPPs
• According to Ministry of Water and Power’s own estimates a
4000mtoe shift from GENCOs to IPPs will save PKR 77 billion annually
• The current generation comparison reveals that PKR 13 billion per
month for GENCOs allows production of 650 MW and only PKR 10
million per month in case of IPPs produces 1150 MW.
19
3. Creating competition in power sector
20
Can I get cheaper power?
21
Who will do it?
• Who runs regulatory institutions?
• How is transmission optimized at power ministry?
• What about planners at Planning Commission?
• Reform of power generation and distribution companies
• Energy sector and civil service reforms
• Define limits of government in power sector
22
Who will do it?
www.sdpi.org, www.sdpi.tv 23
Thank You

Energy comsats 12_oct13_2

  • 1.
    Economy and EnergySecurity for Pakistan - What lies ahead COMSATS Institute of Information Technology 12 October 2013
  • 2.
    • The EconomicSurvey of Pakistan recognizes that during 2012 around 2 percent of gross domestic product (GDP) was lost due to the power sector outages. • The petroleum crude and products contributed to a third of total imports of Pakistan during 2012 • The transmission and distribution (T&D) losses were valued at PKR 140 billion in 2012 • Issues being currently faced can be categorised into policy, governance, technical and cost issues 2 Background
  • 3.
    • Short-term situationanalysis • Limiting analysis to power sector • Assumptions: – It will be difficult to attract investment – It will be difficult to bring legislative changes – Will be difficult to change governance structures at generation and distribution companies • What lies ahead? 3 Sequence of Discussion
  • 4.
    Circular Debt inPower Sector 111 145 161 236 366 538 872 0 100 200 300 400 500 600 700 800 900 1000 2006 2007 2008 2009 2010 2011 2012 PKRBillions Source: Planning Commission 2013
  • 5.
    Integrated Energy Policy Consolidate fragmented energy governance Buildcapacity of regulators Deregulate energy sector further Reforms for attracting investment in energy sector Make generation efficient Reduce transmission losses Hydro, Coal and other sources Steps that were promised
  • 6.
    These may besymptoms but are not causes of crisis
  • 7.
    Unwillingess to pay theprice of energy Political stubbornness to maintain subsidies Administrative and line losses 7 3 key causes
  • 8.
    • Willingness andability to pay for power • Recoveries of some very large power distribution companies have deteriorated over time – In Hyderabad, for example, only 60% of the power supplied in 2012 was paid for – in a city of over 6.5 million people • DISCOs are unable to adopt the normal commercial practices in other countries of disconnecting customers for non- payment because of unclear legislation and political pressure. 8 1. Unwillingness to pay for power
  • 9.
    9 Source: SDPI SurveyUnit 2013 No , 82% Don't Know, 6% Yes, 12% Will households pay if power cuts are eliminated and tariff is increased by 10%
  • 10.
    • The fundamentalrationale for subsidising electricity tariffs is to augment the paying capacity of the poorest of poor • However once subsidies are provided across the board, people start to demand them as their right and politicians feel compelled to maintain this distortive fiscal burden to win popularity. • Do poor really get power subsidies in Pakistan – Domestic lifeline consumers (1-100 units) only get 0.3% subsidy 10 2. Political stubbornness to maintain subsidies
  • 11.
    Subsidybythegovernmentonpowerconsumption(Rs/kW) LESCO GEPCO FESCOMEPCO HESCO SEPCO QESCO PESCO 1.Residential,<700units 0.4 1.4 1.4 2.9 3.9 3.9 1.4 4.4 2.Industrial,(66.132KV&above)- TOU(Peak) 2.1 2.1 2.1 3.1 6.6 6.6 4.0 7.1 3.Agricultural,5KW&above-TOU (Peak) 1.5 1.5 1.5 2.5 6.0 6.0 3.5 6.5 Source: Economic Survey of Pakistan, 2013
  • 12.
    Electricity Shortfall &Subsidies 12 0 50 100 150 200 250 300 350 400 450 500 0 1000 2000 3000 4000 5000 6000 7000 2005 2006 2007 2008 2009 2010 2011 2012 2013 Subsidy(PKRBillion) Deficit(MW) Electricity Shortfall (MW) Subsidy to Power Sector Source: NEPRA and Planning Commission 2013
  • 13.
    • In August2013, the Secretary of Water and Power Ministry informed the Senate Standing Committee that – Pakistan loses annually PKR 150 billion (USD 1.7 billion) in line losses and power theft. – Until August 23770 cases of theft were registered and under trial – But only 3 cases were punished. Moreover, the fine imposed was under PKR 5000 in each case. • Lacunae in the accountability mechanism. This requires amendments in Pakistan Penal Code so that there is certainty of effective punishment in cases of power theft 13 3. Administrative & Line Losses (Theft)
  • 14.
    14 Power T &D Losses (% of output) 0 5 10 15 20 25 30 35 40 1971 1974 1977 1980 1983 1986 1989 1992 1995 1998 2001 2004 2007 2010 Percentage Pakistan Bangladesh
  • 15.
    15 35% 59% 6% Yes No Don'tKnow Do you know of power theft in your area? Source: SDPI Survey Unit 2013
  • 16.
  • 17.
    All subsidies (includinghidden and cross subsidies) - except a 100 unit lifeline block - should be phased out over the next 24 months. 17 1. Tariffs and Subsidies
  • 18.
    • Unaccounted-for-gas controlsshould be enforced and the saved gas diverted to the power sector. The power ministry notes that just a 10 percent diversion can produce an extra 2000MW. • Performance contracts for grid stations under National Transmission and Dispatch Company. • Performance contracts should also be introduced for DISCOs. Such a contract should have specific clauses on reduction in distribution losses and full collection of receivables from consumers. • Accountability at XEN-level • Role of provinces • Social accountability tools 18 2. Curbing Loses
  • 19.
    • Creating competitionon distribution side is important but a medium to longer term option • What about creating competition in generation sector? • The allocation of fuel to generation companies (GENCOs) should be linked with their efficiency levels • If the Independent Power Producers (IPPs) are better performing in efficiency terms then fuel allocation may be in favour of IPPs • According to Ministry of Water and Power’s own estimates a 4000mtoe shift from GENCOs to IPPs will save PKR 77 billion annually • The current generation comparison reveals that PKR 13 billion per month for GENCOs allows production of 650 MW and only PKR 10 million per month in case of IPPs produces 1150 MW. 19 3. Creating competition in power sector
  • 20.
    20 Can I getcheaper power?
  • 21.
  • 22.
    • Who runsregulatory institutions? • How is transmission optimized at power ministry? • What about planners at Planning Commission? • Reform of power generation and distribution companies • Energy sector and civil service reforms • Define limits of government in power sector 22 Who will do it?
  • 23.

Editor's Notes

  • #2 You have the paper
  • #4 So privatization is not an option in the short term.
  • #17 They didn’t have time to write a legal draft…so the document of policy is a power point document
  • #18 The policy wishes to keep it to 200 units. It also wants 3 years to phase out. Subsidizing a commodity much more distortive than giving cash…like BISP