1. CurriculumVitae
MUKHTAR AHMAD (BSc ElectronicsEngineer 4 Year)
OBJECTIVE
To work and grow in an environment where performance is rewarded with new responsibilities and
challenges. Prove myself to be an asset to the organization and the team by making maximum of the
resources available. Network/IT and Management domain, to work in a challenging and hardworking
environment in order to achieve excellence and to prove my abilities.
1BPROFESSIONAL EXPERIENCE
Career Profile:
Over Three years of extensive experience as an Electrical & Instrumentation Engineer in the field of
construction, hook-up, pre-commissioning and commissioning of various construction sites, power
plants, and production facilities.
Projects:
Jazan Refinery & Terminal Project(Aramco) Duration 2 Year
Descon Uch≠2 Power Project Duration 1 Year
Kot Addu Power Company Duration 1 Year
JOB EXPERIENCE:
I&C Jazan Refinery & Terminal Project
Jazan KSA.
I&C Engineer UCH≠2 POWER PROJECT
UCH 2 Power Plant, Pakistan.
I&C ELECTRONICS TRAINEE ENGINEER
Kot Addu Power Company, Pakistan.
Responsibilities & Tasks:
I&C ENGINEER:
Follow The Standards of (Aremco) for Installation of Instruments.
SABIC Engineering Standards (SES) & API Standards.
ISA & ASME Standards.
Follow These Standards in All Measured Variable's Pressure, Temprature, Level&Flow.
Reading of Electrical circuit drawings.
UDate of BirthU: : 15-Mar-1990
Iqama: Transferable
Religion: Islam
LLanguage: English, Urdu,Arabic(Basic)
Address: Al-Riyadh(Saudi Arabia)
UMobileNoU: : : 0599826740
EEmail : engr.mukhtar08@gmail.com
2. CurriculumVitae
Instrument installation following all kinds of instrument drawings, P&IDs, loop drawings,
interlock drawing Loop testing & troubleshooting of all process parameters.
Participate in functional tests. Testing and commissioning of field instruments such as
electronic transmitters, gauges, control valves, Relief valves, shutdown valves, water injection
systems.
Execute instrumentation installation supervision, and start-up support activities.
Inspection of instrument tubing pressure testing and ensuring ferrule connection and manifold
valve has no leaks.
Created punch list clearance which included fixing of a jumper on cable trays, installation of JBs,
tagging of power and control cables.
Execute other engineering activities specific to the control system technical area such as P&ID
review, instrument loop drawings, instrumentation location plan, hook up drawings
,Connection drawing, design index, engineering index, data sheet
Experience in project inspections activities like instruments calibration, installation, loop
checking, troubleshooting etc.
Study & analyses the routine activities and faults in order to improve performance of plant.
Gas Turbine of Siemens Frame SGT6 5000F.
Installation of Cable tray, Duct Bank, Cable Glanding & Conduit Installation as per drawing and
adjustment according to site requirements.
Installation of LV & MV Switchgears and make sure those installations are being done
according to Vendor recommendations
Direct Buried Cable, trench for Power Cables and Communication Cables.
Gas Turbine of Siemens Frame SGT6 5000F.
Siemens STG&HRSG.
Gasification Combine Cycle.
Ensure the Safety Measurement during The Project.
I&C ENGINEER:
UCH#2 power project 400 MW.
Gas Turbine of GE_Frame#9 & One Steam Turbine Fuji Electric 133 MW.
Combine & Simple Cycle, Understand of BOP.
Operations of Gas and Steam Turbine, Start up & Shut Down Procedure.
Accessories & Components of Gas Turbine & Steam Turbine.
Work in MCC Familiar with MARK VI.
Supervision of Termination in MCC.
Two None Fired Water Tube Boiler HRSG, Operation & Working of HRSG.
Instrument installation following all kinds of instrument drawings, P&ID.
Participate in functional tests. Testing and commissioning of field instruments such as electronic
transmitters, gauges, control valves, Relief valves, shutdown valves, water injection systems.
Monitored commissioning activities.
Execute other engineering activities specific to the control system technical area such as P&ID
review, instrument loop drawings, instrumentation location plan, hook up drawings ,Connection
drawing, design index, engineering index, data sheet.
Execute instrumentation installation supervision, and start-up support activities.
Created punch list clearance which included fixing of a jumper on cable trays, installation of JBs,
tagging of power and control cables.
Reviewing P&IDs, loop drawings, wiring drawings and as built drawings
Installation of Instruments with E&I Team.
Prepared daily report and strictly followed the weekly construction plan given by the project
manager
Kill & Supervision of Punch Lists. Fault Identification.
3. CurriculumVitae
Supervised installation of cable trays, laying of cables as per drawings, testing, commissioning &
troubleshooting etc
Installation of Lighting, Distribution Boards for Lighting as per client requirements. Installation of
LV & MV Switchgears and make sure those installations are being done according to Vendor
recommendations.
HV, MV, LV Cable Laying, Termination & Jointing, installation of lighting poles, transformer etc
DCS made by YOKOGAWA, cintum3000
Use proper trackers & strictly follow the schedule as per demand.
Ensure the Safety Measurement during The Project.
I&C Trainee Engineer:
Kot Addu Power Plant has a capacity of 1600 MW.
Four GE Frame#9 Gas Turbine 150 MW of each.
Familiar with SPEEDTRONIC MARK IV.
Awareness of Plant Control Software.
Understand of Gas & Steam Turbine Process.
Familiar with P&ID &IWD Diagram.
Start up & Shut Down of Gas Turbine and Steam Turbine.
The operation of None Fired Boiler (HRSG).
Understand Plant BOP.
Process and Operation of HRSG.
The process of Steam Turbine.
Operations of Cooling Tower System
Ensure the Safety Measurement during implementation of Project
EDUCATION
BSc Electrical (Electronics) Engineering 2012 74 % Islamia UniversityofBahawalpur
FSC (Pre-Engineering) 2008 68 % BISE DG Khan Board
SSC (Science School) 2005 61 % BISE Multan Board
TECHNICAL SKILLS
Jet Stream v 5.4 for Plant 3 D
TEMS Investigationv16.2
AnalyzerPower Blazer_500
MATLAB Programming
Microsoftoffice / Excel / PowerPoint
Map info Professional
Boson_Netsim_7.
Lab View.
Electronicsworkbench.
4. CurriculumVitae
AWARDS & ACHIEVEMENTS
Seminar on FPGA based system design in IUB.
Microcontroller course held in UCET, IUB.
7BPROFESSIONAL SKILLS
Management
Administration
Supervision
CustomerServices
Electrical & Electronics
8ACADMIC PROJECT
Energy Saving & OverLoad Protection(Digital Energy Meter)
7BREFERENC
On Demand