This document provides an executive summary of the environmental impact assessment for a proposed 660 MW coal-fired power plant in Pakistan. Key points include:
- The plant would be located near Port Qasim, Karachi and use imported coal from Indonesia, South Africa, or Australia.
- The environmental impact assessment evaluates potential impacts on the surrounding environment from construction and operation of the plant.
- Baseline studies found the site has a mild climate and the nearby creeks and mangroves could be impacted. Water and air quality in the area currently meet standards.
- The report outlines basic design parameters for the supercritical boiler and steam turbine system and proposes mitigation measures to minimize environmental impacts during
Grid Connected Solar Photovoltaic Array with MPPT Matlab Simulationijtsrd
Now a days, due to the problem of generation of electricity and consumption required is not sufficient so, solar generation system is essential. Nowadays, with generates electricity to match the required demand. So this paper is important. Here using, 1 Soltech 1STH 215 P solar panel in SIMULINK. In this paper we are control the renewable energy based solar photovoltaic system using MATLAB. The grid connected MATLAB model is studied under solar radiation and changing weather condition. In this we generate excess amount of electricity and send to the utility grid. Here we used MPPT technique which is implemented in DC DC step up converter to permit P V module to give power at maximum power point. The output of this converter is given to the 3 level inverter and it synchronized the utility grid. Payal Ganvir | Radharaman Shaha ""Grid Connected Solar Photovoltaic Array with MPPT Matlab Simulation"" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-4 , June 2019, URL: https://www.ijtsrd.com/papers/ijtsrd23832.pdf
Paper URL: https://www.ijtsrd.com/engineering/electrical-engineering/23832/grid-connected-solar-photovoltaic-array-with-mppt-matlab-simulation/payal-ganvir
Abstract:-This paper deals with open loop study of fixed capacitor thyristor controlled reactor (FC-TCR) system simulation using Matlab/Simulink for various loading. The modelling of the FC-TCR is verified using the Matlab/Simulink. First power flow results are obtained and power profile have been studied for an uncompensated then results are compared with the results obtained after compensating using the FC-TCR.Its observed that current drawn by FC-TCR is varied by changing firing angle. In compensation without FC-TCR, load increases and power factor become less and in compensation with FC-TCR, load increases and power factor become near to the unity.Hence by providing compensation Voltage, power profile of system will be improved and system losses are reduced.
Grid Connected Solar Photovoltaic Array with MPPT Matlab Simulationijtsrd
Now a days, due to the problem of generation of electricity and consumption required is not sufficient so, solar generation system is essential. Nowadays, with generates electricity to match the required demand. So this paper is important. Here using, 1 Soltech 1STH 215 P solar panel in SIMULINK. In this paper we are control the renewable energy based solar photovoltaic system using MATLAB. The grid connected MATLAB model is studied under solar radiation and changing weather condition. In this we generate excess amount of electricity and send to the utility grid. Here we used MPPT technique which is implemented in DC DC step up converter to permit P V module to give power at maximum power point. The output of this converter is given to the 3 level inverter and it synchronized the utility grid. Payal Ganvir | Radharaman Shaha ""Grid Connected Solar Photovoltaic Array with MPPT Matlab Simulation"" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-4 , June 2019, URL: https://www.ijtsrd.com/papers/ijtsrd23832.pdf
Paper URL: https://www.ijtsrd.com/engineering/electrical-engineering/23832/grid-connected-solar-photovoltaic-array-with-mppt-matlab-simulation/payal-ganvir
Abstract:-This paper deals with open loop study of fixed capacitor thyristor controlled reactor (FC-TCR) system simulation using Matlab/Simulink for various loading. The modelling of the FC-TCR is verified using the Matlab/Simulink. First power flow results are obtained and power profile have been studied for an uncompensated then results are compared with the results obtained after compensating using the FC-TCR.Its observed that current drawn by FC-TCR is varied by changing firing angle. In compensation without FC-TCR, load increases and power factor become less and in compensation with FC-TCR, load increases and power factor become near to the unity.Hence by providing compensation Voltage, power profile of system will be improved and system losses are reduced.
Supercapacitors offer a promising alternative approach to meeting the increasing power demands of energy storage systems and electronic devices. With their high power density, ability to perform in extreme temperatures, and millions of charge-recharge cycle capabilities, supercapacitors can increase circuit performance and prolong the life of batteries. This can add value to the end-product and ultimately reduce the costs to the customer by reducing the amount of batteries needed and the frequency of the replacement of the batteries, which adds greatly to the environmental friendliness of the end-product as well.
PEMFC (proton exchange membrane)
DMFC (direct methanol)
SOCF (solid oxide)
AFC (alkaline)
PAFC (phosphoric acid)
MCFC (Molten Carbonate)
PEM Fuel Cell
A fuel cell is a battery that produces DC current and voltage
Most fuel cells use hydrogen which burns cleaner compared to hydrocarbon fuels
A fuel cell will keep producing electricity as long as fuel is supplied
The energy efficiency of fuel cells is high when compared to many other energy systems
There is great interest in fuel cells for automotive and electronic applications
There will be employment for technicians particularly in Ohio’s fuel cell industry.
This ppt explained the basic concept of Tidal energy , Components of Tidal barrage powerplant, Modes of generation of Tidal power, Tidal stream generator, single and double bassin arrangement, Horizontal & vertical axis Tidal turbine Helical Turbine, Dynamic Tidal powerplant, Environmental impacts and Site selection for tidal powerplant. Also describes the advantages and disadvantages of Tidal powerplant.
In this presentation, it proposes efficient method of storing energy by the use of piezoceramic. It is very reliable to use
piezo ceramic for generating electrical energy which can be used for powering any portable devices. The basic concept
of piezo ceramic is that the mechanical strain applied on to the ceramic such as bimorph or unimorph piezo converts it
into electrical energy. In the present day scenerio, wherein there is great demand for energy, this idea of piezoelectric
concept works well.
Supercapacitors offer a promising alternative approach to meeting the increasing power demands of energy storage systems and electronic devices. With their high power density, ability to perform in extreme temperatures, and millions of charge-recharge cycle capabilities, supercapacitors can increase circuit performance and prolong the life of batteries. This can add value to the end-product and ultimately reduce the costs to the customer by reducing the amount of batteries needed and the frequency of the replacement of the batteries, which adds greatly to the environmental friendliness of the end-product as well.
PEMFC (proton exchange membrane)
DMFC (direct methanol)
SOCF (solid oxide)
AFC (alkaline)
PAFC (phosphoric acid)
MCFC (Molten Carbonate)
PEM Fuel Cell
A fuel cell is a battery that produces DC current and voltage
Most fuel cells use hydrogen which burns cleaner compared to hydrocarbon fuels
A fuel cell will keep producing electricity as long as fuel is supplied
The energy efficiency of fuel cells is high when compared to many other energy systems
There is great interest in fuel cells for automotive and electronic applications
There will be employment for technicians particularly in Ohio’s fuel cell industry.
This ppt explained the basic concept of Tidal energy , Components of Tidal barrage powerplant, Modes of generation of Tidal power, Tidal stream generator, single and double bassin arrangement, Horizontal & vertical axis Tidal turbine Helical Turbine, Dynamic Tidal powerplant, Environmental impacts and Site selection for tidal powerplant. Also describes the advantages and disadvantages of Tidal powerplant.
In this presentation, it proposes efficient method of storing energy by the use of piezoceramic. It is very reliable to use
piezo ceramic for generating electrical energy which can be used for powering any portable devices. The basic concept
of piezo ceramic is that the mechanical strain applied on to the ceramic such as bimorph or unimorph piezo converts it
into electrical energy. In the present day scenerio, wherein there is great demand for energy, this idea of piezoelectric
concept works well.
Greetings,
Attached FYI ( NewBase Special 17 March 2016 ) , from Hawk Energy Services Dubai . Daily energy news covering the MENA area and related worldwide energy news. In todays’ issue you will find news about:-
• Mauritania: Kosmos Energy announces successful appraisal of gas discovery offshore Mauritania and Senegal
• Egypt: SDX Energy commences 3D seismic programme on South Disouq
• Saudi Dow Jubail ships the first batch of RO elements to emerging markets
• Saudi Aramco, Shell plan to break up Motiva, divide up assets
• Oman:Rex International Holding Ups Stake in Oman's Masirah
• India govt firms ink energy deals with Russia’s Rosneft
• Rosneft Sells Stake in Taas-Yuryakh Neftegasodobycha Field to Indian Investors
• India targets $40bn of untapped oil and gas
• Afghanistan: Mine Removal Process on TAPI Route Begins
• Kenya: Tullow Oil's Cheptuket-1 Block 12A encounters good oil
• Oil extends strong gains after supplier meeting agreed
• With or without Iran, oil producers to meet in April on output deal
• Saudi Arabia Said to Join Mid-April Oil Producer Meeting in Doha
we would appreciate your actions to send to all interested parties that you may wish. Also note that if you or your organization wish to include your own article or advert in our circulations, please send it to :-
khdmohd@hotmail.com or khdmohd@hawkenergy.net
Best Regards.
Khaled Al Awadi
Energy Consultant & NewBase Chairman - Senior Chief Editor
MS & BS Mechanical Engineering (HON), USA
Emarat member since 1990
ASME meme since 1995
Hawk Energy since 2010
New base energy news issue 892 dated 25 july 2016Khaled Al Awadi
NewGreetings,
Attached FYI (NewBase Special 25 July 2016 ) , from Hawk Energy Services Dubai . Daily energy news covering the MENA area and related worldwide energy news. In today’s issue you will find news about:-
• UAE: Enec and Khnp sign agreement for nuclear plant operations
• Oman:Musandam’s first gas-fired power plant to launch in Feb
• Libya oil exports threatened as NOC warns against port deal
• US:Refiners in US, stuck with lots of gasoline, switch to winter brew
• U.K. onshore Wind Farm subsidies Ban May Cost Scotland $B3.9
• Crude stays near 2-month low on oil glut worries
• Rig Gains Add to Glut Concerns, as Oil Trades Near Two-Month Low as
• Oil Bulls Headed Over Demand Cliff as B
• Making Fracking Great Again
we would appreciate your actions to send to all interested parties that you may wish. Also note that if you or your organization wish to include your own article or advert in our circulations, please send it to :-
khdmohd@hotmail.com or
khdmohd@hawkenergy.net
Best Regards.
Khaled Al Awadi
Energy Consultant & NewBase Chairman - Senior Chief Editor
MS & BS Mechanical Engineering (HON), USA
Emarat member since 1990
ASME meme since 1995
Hawk Energy since 2010
Base Special 25 July 2016
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCEzubeditufail
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE IN RESPECT OF THE
PROPOSED KHAIRAGURA OPENCAST EXPANSION COAL
MINING PROJECT NEAR KHAIRAGURA VILLAGE,
TIRIYANI MANDAL, ADILABAD DISTRICT, A.P.
DEPARTMENT OF ENVIRONMENT
THE SINGARENI COLLIERIES COMPANY LIMITED
(A Government Company)
KOTHAGUDEM COLLIERIES-507101 (A.P)
JANUARY 2013
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...zubeditufail
Directorate of Urban Policy & Strategic Planning, Planning & Development Department, Government of Sindh
Karachi Neighborhood Improvement Project
Environmental and Social Management Framework (ESMF)
February 2017
Guiding Principles and Recommendations for Responsible Business Operations in and around Key Biodiversity Areas (KBAs)
A collaborative project of the KBA Partnership coordinated by IUCN
Draft 2 for public consultation
2 December 2016
For any query about this document or the project, please contact Giulia Carbone, Deputy Director, Global Business and Biodiversity Programme, IUCN (Giulia.carbone@iucn.org).
A global standard_for_the_identification_of_key_biodiversity_areas_final_webzubeditufail
A Global Standard for the Identification of Key Biodiversity Areas
Version 1.0
Prepared by the IUCN Species Survival Commission and IUCN World Commission on Protected Areas in association with the IUCN Global Species Programme
23 March 2016
Artificial Reefs by Kuddle Life Foundation - May 2024punit537210
Situated in Pondicherry, India, Kuddle Life Foundation is a charitable, non-profit and non-governmental organization (NGO) dedicated to improving the living standards of coastal communities and simultaneously placing a strong emphasis on the protection of marine ecosystems.
One of the key areas we work in is Artificial Reefs. This presentation captures our journey so far and our learnings. We hope you get as excited about marine conservation and artificial reefs as we are.
Please visit our website: https://kuddlelife.org
Our Instagram channel:
@kuddlelifefoundation
Our Linkedin Page:
https://www.linkedin.com/company/kuddlelifefoundation/
and write to us if you have any questions:
info@kuddlelife.org
Prevalence of Toxoplasma gondii infection in domestic animals in District Ban...Open Access Research Paper
Toxoplasma gondii is an intracellular zoonotic protozoan parasite, infect both humans and animals population worldwide. It can also cause abortion and inborn disease in humans and livestock population. In the present study total of 313 domestic animals were screened for Toxoplasma gondii infection. Of which 45 cows, 55 buffalos, 68 goats, 60 sheep and 85 shaver chicken were tested. Among these 40 (88.88%) cows were negative and 05 (11.12%) were positive. Similarly 55 (92.72%) buffalos were negative and 04 (07.28%) were positive. In goats 68 (98.52%) were negative and 01 (01.48%) was recorded positive. In sheep and shaver chicken the infection were not recorded.
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Venturesgreendigital
Willie Nelson is a name that resonates within the world of music and entertainment. Known for his unique voice, and masterful guitar skills. and an extraordinary career spanning several decades. Nelson has become a legend in the country music scene. But, his influence extends far beyond the realm of music. with ventures in acting, writing, activism, and business. This comprehensive article delves into Willie Nelson net worth. exploring the various facets of his career that have contributed to his large fortune.
Follow us on: Pinterest
Introduction
Willie Nelson net worth is a testament to his enduring influence and success in many fields. Born on April 29, 1933, in Abbott, Texas. Nelson's journey from a humble beginning to becoming one of the most iconic figures in American music is nothing short of inspirational. His net worth, which estimated to be around $25 million as of 2024. reflects a career that is as diverse as it is prolific.
Early Life and Musical Beginnings
Humble Origins
Willie Hugh Nelson was born during the Great Depression. a time of significant economic hardship in the United States. Raised by his grandparents. Nelson found solace and inspiration in music from an early age. His grandmother taught him to play the guitar. setting the stage for what would become an illustrious career.
First Steps in Music
Nelson's initial foray into the music industry was fraught with challenges. He moved to Nashville, Tennessee, to pursue his dreams, but success did not come . Working as a songwriter, Nelson penned hits for other artists. which helped him gain a foothold in the competitive music scene. His songwriting skills contributed to his early earnings. laying the foundation for his net worth.
Rise to Stardom
Breakthrough Albums
The 1970s marked a turning point in Willie Nelson's career. His albums "Shotgun Willie" (1973), "Red Headed Stranger" (1975). and "Stardust" (1978) received critical acclaim and commercial success. These albums not only solidified his position in the country music genre. but also introduced his music to a broader audience. The success of these albums played a crucial role in boosting Willie Nelson net worth.
Iconic Songs
Willie Nelson net worth is also attributed to his extensive catalog of hit songs. Tracks like "Blue Eyes Crying in the Rain," "On the Road Again," and "Always on My Mind" have become timeless classics. These songs have not only earned Nelson large royalties but have also ensured his continued relevance in the music industry.
Acting and Film Career
Hollywood Ventures
In addition to his music career, Willie Nelson has also made a mark in Hollywood. His distinctive personality and on-screen presence have landed him roles in several films and television shows. Notable appearances include roles in "The Electric Horseman" (1979), "Honeysuckle Rose" (1980), and "Barbarosa" (1982). These acting gigs have added a significant amount to Willie Nelson net worth.
Television Appearances
Nelson's char
Climate Change All over the World .pptxsairaanwer024
Climate change refers to significant and lasting changes in the average weather patterns over periods ranging from decades to millions of years. It encompasses both global warming driven by human emissions of greenhouse gases and the resulting large-scale shifts in weather patterns. While climate change is a natural phenomenon, human activities, particularly since the Industrial Revolution, have accelerated its pace and intensity
UNDERSTANDING WHAT GREEN WASHING IS!.pdfJulietMogola
Many companies today use green washing to lure the public into thinking they are conserving the environment but in real sense they are doing more harm. There have been such several cases from very big companies here in Kenya and also globally. This ranges from various sectors from manufacturing and goes to consumer products. Educating people on greenwashing will enable people to make better choices based on their analysis and not on what they see on marketing sites.
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...MMariSelvam4
The carbon cycle is a critical component of Earth's environmental system, governing the movement and transformation of carbon through various reservoirs, including the atmosphere, oceans, soil, and living organisms. This complex cycle involves several key processes such as photosynthesis, respiration, decomposition, and carbon sequestration, each contributing to the regulation of carbon levels on the planet.
Human activities, particularly fossil fuel combustion and deforestation, have significantly altered the natural carbon cycle, leading to increased atmospheric carbon dioxide concentrations and driving climate change. Understanding the intricacies of the carbon cycle is essential for assessing the impacts of these changes and developing effective mitigation strategies.
By studying the carbon cycle, scientists can identify carbon sources and sinks, measure carbon fluxes, and predict future trends. This knowledge is crucial for crafting policies aimed at reducing carbon emissions, enhancing carbon storage, and promoting sustainable practices. The carbon cycle's interplay with climate systems, ecosystems, and human activities underscores its importance in maintaining a stable and healthy planet.
In-depth exploration of the carbon cycle reveals the delicate balance required to sustain life and the urgent need to address anthropogenic influences. Through research, education, and policy, we can work towards restoring equilibrium in the carbon cycle and ensuring a sustainable future for generations to come.
Characterization and the Kinetics of drying at the drying oven and with micro...Open Access Research Paper
The objective of this work is to contribute to valorization de Nephelium lappaceum by the characterization of kinetics of drying of seeds of Nephelium lappaceum. The seeds were dehydrated until a constant mass respectively in a drying oven and a microwawe oven. The temperatures and the powers of drying are respectively: 50, 60 and 70°C and 140, 280 and 420 W. The results show that the curves of drying of seeds of Nephelium lappaceum do not present a phase of constant kinetics. The coefficients of diffusion vary between 2.09.10-8 to 2.98. 10-8m-2/s in the interval of 50°C at 70°C and between 4.83×10-07 at 9.04×10-07 m-8/s for the powers going of 140 W with 420 W the relation between Arrhenius and a value of energy of activation of 16.49 kJ. mol-1 expressed the effect of the temperature on effective diffusivity.
WRI’s brand new “Food Service Playbook for Promoting Sustainable Food Choices” gives food service operators the very latest strategies for creating dining environments that empower consumers to choose sustainable, plant-rich dishes. This research builds off our first guide for food service, now with industry experience and insights from nearly 350 academic trials.
4. EMC Pakistan Pvt. Ltd Page i of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
EXECUTIVE SUMMARY
Pakistan faces a number of critical challenges in energy sector such as energy and power resource
deficit, power shortages, and a greater dependency on imported oil to meet the energy demand-
supplygap.Thedemandforelectricitycurrentlyoutstripssupply.Inadequategeneration,transmission,
anddistribution,aswellastheinefficientuseofelectricity,leadtoshortagesof12-20hours,particularly
at peak times. Realizing these challenges, the governments of Sindh & Pakistan are focusing on the
huge potential of developing indigenous coal resources on fast-track basis and put coal based power
asamajorportioninoverallenergymix.
The National Energy Policy 2013 requires development of strategy to i) ensure the generation of
inexpensiveandaffordableelectricityfordomestic,commercial,andindustrialusebyusingindigenous
resourcessuch ascoal(Thar coal)and hydelpower, ii)addressthe key challengesof the power sector
in order to provide much needed relief to the citizens of Pakistan, and iii) shift Pakistan’s energy mix
towardscheaperfueland conservationof gasforpower.
In order to contribute towards meeting Pakistan’s growing electricity demand, Lucky Electric Power
Company Limited (LEPCL) proposes constructing a 1 x 660 MW coal based power station near Port
Qasim Karachi. LEPCL has acquired 250 acres of land from the Sindh Board of Revenue for the
establishmentoftheproposedpowerplant.CoalforthepowerplantwillbeimportedfromIndonesia,
South Africa, and/or Australia. The preferred option for imported coal is the under-construction
Pakistan International Bulk Terminal (PIBT) at Port Qasim. The terminal is expected to be operational
by2016.
FigureEX-1:Locationof LECPPSite
ThisEnvironmentalImpactAssessment(EIA)servesasusefultoolinpredictionofpotentialimpactson
thesurroundingenvironmentduetodevelopmentalproject.Itwillhelptheprojectproponent,impact
assessment authorities, regulatory agencies and other stakeholders in understanding the project and
mitigation measures, environmental impact and establishing emission requirements and other
5. EMC Pakistan Pvt. Ltd Page ii of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
measuresearlyinthe project cycle.Thisreport describesthe project location,baseline environmental
scenario, potential impacts of the project on the environment and proposed measures for effective
environment management(EMaP &EMoP)duringtheproject cycle.
ThebasicdesignparametersforthesearelistedinTable EX-1:
TableEX-1:BasicDesignParametersofLECPP
Parameter Value
ThermalCycleInformation-GrossCapacity
660MW(approximately)atannualaverage
conditionswithturbinemax.continuousrating
(TMCR)
ThermalCycleInformation-NetCapacity
607.2MW(target)atannualaverageconditions
TMCR
NetPlantHeatRate 2,224kcal/kWhatannualaverageconditionsTMCR
MainSteamFlow 1,993,500kg/h,4,394,918lb/hr
MainSteamPressure 242bar,3,509psi
MainSteamTemperature 566°C,1,050°F
HotReheatFlow 1,623,420kg/h,3,597,031lb/hr
HotReheatPressure 42.63bar,618psi
HotReheatTemperature 566°C,1,050°F
ColdReheatFlow 1,623,420kg/h,3,597,031lb/hr
ColdReheatPressure 47.36bar,686.7psi
ColdReheatTemperature 325.8°C,618°F
FeedwaterPressure 291.1bar,4,221psiatpumpdischarge
CoalBurnRate 269t/hforthedesigncoal,100%load
WaterFlowto thePlant 82,000m3
/h
CirculatingWaterFlow 78,000m3
/htocondenserandclosedcooling
CirculatingWaterTemperatureRisein
Condenser
8.5°C,15.3°F
CirculatingWaterTemperatureRiseTotal
CondenserandSeawaterFGD
9°Cat34%scrubbing
SeaWaterFlowtoDesalinationSystem 600m3
/h
WasteWaterFlow 12m3
/h
PotableWaterSupplytoPlant&Colony 15m3
/h
Theboilerisasupercritical,balanceddraft,outdoor,coal-fireddesign,andLowNOxburner,pulverized
coalwithfrontorrearortiltingtangentialfiringdesignsuitableforoperationatthesuper-criticalsteam
conditions. The boiler will be equipped with regenerative type air heaters, 2x50% adjustable moving-
bladeaxial-flowPAfansforFDand2x50%adjustablestationary-bladeaxial-flowfansforID.Thedesign
oftheairheaters,fansandassociatedboilerauxiliarieswillbeprovidedwithadequatemarginstoavoid
limitingthecapabilityofthePlanttoachievefullratedoutputthroughoutthedesignlifeoftheFacility.
Steamsootblowerswillbeprovidedtosupportthecleaningoperationoftheboilertoallowcontinuous
fullloadoperationwiththeworstcasefuelcharacteristics.Thefurnacewillbeequippedwithwallsoot
blowers and long retractable soot blowers for the superheater, reheater and economizer areas. The
air heaters willhave fixed lance type soot blower units.The boiler maximum continuous ratingwillbe
designed with the inclusion of auxiliary steam flow. The boiler will have a suitable number of duty
medium speed coal mill groups which allows the firingof performance coal at BMCR conditions, with
one spare mill group acts as standby. The boiler exit flue gas will pass through an electrostatic
6. EMC Pakistan Pvt. Ltd Page iii of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
precipitator and the SWFGD plant prior to entry into the stack, but the electrostatic precipitator and
SWFGDplantwillhavebypasssysteminorderforemergencycondition.
There are currently over 400 supercritical units in operation in the United States, Europe, Korea, and
Japan and a few in the developing countries. The European, Japanese, and, recently, the Chinese
suppliers have standardized on supercritical designs for units larger than 600 MW. Due to renewed
interest in large coal-firedplantsinthe United States,the American suppliershave revived the debate
over subcritical versus supercritical steam cycles. Most recent coal plants now under design and
constructionaresupercritical.
ThecoastalmeteorologyandhydrographyofKarachiiscontrolledbytheseasonalchangeinthenorth
Arabian Sea viz. monsoon system. The data collected for a number of studies along the Karachi coast
show the influence of NE and SW monsoon winds. The meteorological conditions in the area around
Port Qasim are characterized by generally hot and relatively humid conditions especially in the
summers(ApriltoOctober)whentheprevailingwindisfromthesouthwest.Thesouthwestmonsoon
bringshumidairinfromthesea,buttherainfallisgenerallyverylowwithnearly80%ofthe265mmof
rainfallingfrom JulytoSeptember.Rainfall,whenitdoescome isoftentorrentialcausingproblemsof
drainageanderosionofthelightandsparselyvegetated land.
ThewintersareshortandmildfromDecembertomid-Februarywiththeprevailingwindcomingfrom
the northeast with very little rainfall. The most important characteristics of the prevailing
meteorological conditions are the generally high dusty conditions as a result of the aridity of the
surrounding area; dust storms occur especially during the summer as well as winter monsoons. The
higher winds during the south west monsoon tend to carry any air-borne contaminant inland during
the summermonths.In winterthe windstendtobe lighttomoderateinintensity.
TheproposedCPPsitelocatedinthecoastalzonehasarelativelymildclimate,characterizedbydry,hot
and humid conditions. There is minor seasonal intervention of a mild winter from mid-December to
mid-Februaryintoa longhot andhumid summerextendingfromAprilto mid-September.
Sea water samples collected from Lath Basti had lower SAR~65 but TDS ~38700 at 26 and 28oC, pH
7.44 and 7.58, and DO~4.0 showing dilution with wastewater discharges from the surrounding. The
samplesfromboreholesshowcharacteristicsofgroundwaterhavinghigherproportionsofsodiumand
chloride ions. The water supply samples with SAR above 1.2 show characteristics of fresh water
contaminationwithgroundwater.
Wastewater samples collected from Korangi Industrial Area which is the outfall region of Malir River,
hadSARvaluesrangingfrom2.79to5.56;TDSrangingfrom1228to4310;lowDO0.39to0.62andthe
high BOD and COD values in the samples; they are characterized as industrial wastewater mixed with
sewage.Thesewageisinhigherproportionupstreamwhileindustrialeffluentisdominantastheriver
enters its delta area. Seawater intrusion was noted at Malir River/Korangi Industrial Area during high
tide. It was noted that the sample collected from here had SAR 57.68, TDS 22300, DO 0.82 and quite
highBODandCOD,andischaracterizedasseawatercontaminatedwithsewageandindustrialeffluent.
The quality of water samples collected from the Kadiro Creek in front of the proposed site during the
currentEIAstudyispresentedinTable5.5.HereagainitisnotedthattheSeawaterTDSinbothsamples
isatleast10,000mg/Llowerthanwhatisnormalforopenseasandmuchlowerthanthatobservedat
the creeks. The BOD5 is much lower than COD values suggesting that the seawater has been
7. EMC Pakistan Pvt. Ltd Page iv of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
contaminated by chemical oxidants or industrial effluents and that the channel is least exposed to
sewageorbiologicalcontaminants.
EMC acquired the services of SUPARCO to study the pollutants concentration levels in ambient air in
themicroenvironmentofprojectsite.Theresultsshowthatambientairconcentrationofallparameters
i.e., SO2, NO2, NO, CO, PM10, PM2.5, SPM and Lead in the area meets Sindh Ambient Air quality
Standards.
The mangrove trees growing 200-300 m away from the creek (seawater) in the land ward direction
showedanoveralldeclineintheheightofthemangroveplantations.
The density of mangrove vegetation was randomly evaluated in an area of 100m2. The trees were
characterized (visualobservations)accordingtothearbitraryheightoftheplants.
Theheightofmangroveseedlingwerecharacterizedas<0.5m
Mangrove saplingheight0.5-1.0m
Shortmangrovestreeswere characterizedashaving1-2 mheight.
Mediumheightmangrovestreeshadwere characterized ashaving2-3 mheight.
Highmangrovestreeshadwerecharacterizedashavingmorethan3mheight.
The Shannon Weiner biodiversity Index was undertaken. Both the species diversity and the species
richnessisrelativelypoor.The speciesdiversityrangesfrom 0.69to 0.90 (normalrange is3.0)whereas
the species richness i.e. number of species in each of the community measured between 0.07 at
sample 3 to 0.188 at station 1 (species richness ranges from 0.01 (low) to (1.0) high. It is not unusual,
sincethecreeksare generallyadisturbedarea.
The ecology of the two UCs viz. Ibrahim Haidery and Rehri, which are the main constituencies of the
macroenvironment of the proposed project site, has completely changed by having grown from
villagesdominatedmainlybyfishermenuntilthelate1950swithhardly250hutseachscatteredalong
the coast to attain the category of towns with population estimated by the local residents to exceed
50,000. Both of them are now the headquarters for Union Council Administration. Lath Basti and
ChashmaGothhavealsogrownfromvillagestosmalltowns;theyarebothpartofRehriUnionCouncil.
Residents of Ibrahim Haidery and Rehri were traditional fishermen involved in fishing business since
thelastfewcenturies.Theyhavebeenjoinedbyscoresofmigrantsfromcoastalvillagesandtownslike
Shah Bunder and Keti Bunder on the east and west of Indus Delta respectively and also the
Bangladeshis and Burmese who appeared here as cheap labor. Lath Basti on the other hand is home
fortheJattribe,whoweretraditionallyengagedincattleandcamelfarming.TheJattribehadmigrated
from the interior of Sindh and has been residing at the present site of Lath Basti for the last seven or
eightdecades.JumaGothwithitsRailwayStationandalargeplotofland,designatedtohousetheKCR
displacedpopulation,liesbetweenCattle ColonyandPortQasimEmployeesResidentialarea.
Screeningprocesshasbeenadoptedtoidentifysignificantenvironmentalandsocialaspectsduringthe
pre-construction, construction and operation stages of proposed 1 x 660 MW CPP Project. Based on
the environmental aspects identified for the different stages and during the stakeholder meetings,
mitigation measures have been proposed. Mitigation Measures will have to be adopted in order to
reduce,minimizeorcompensateforthenegativeimpact asfaraspossible.
8. EMC Pakistan Pvt. Ltd Page v of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
The power plant building structure(s) would be reinforced concrete (recommended by UNDP for
Tsunamiaffected areas).ThisrespondstotheTsunamihazardthathasbeen identifiedrecently.
The near shore environment of the project site is characterized by long and narrow creeks, mud flats
and the mangroves forest ecosystems. However, it has been committed by LEPCL that for any
mangrove tree / plant destroyed due to Project activities, five mangrove seedlings / species will be
plantedinanotherpartofthecoast/projectsiteinpresenceofindependentobserverssuchasIUCN-P,
WWF-P and LEPCLshallberesponsibletoprovidenecessarycareuntiltheyreachmaturity.
To avoid adverse impact of the construction activities on the environment, following measures are
proposed:
The construction contractor will develop a specific Construction Management Plan (CMP) based
ontheCMPincluded intheEMP.TheCMPwillbesubmittedtothe LEPCLforapproval.
TheCMPwillclearlyidentifyallareasthatwillbeutilizedduringconstruction forvariouspurposes.
Forexample,onaplotplanoftheconstructionsitethefollowingwillbeshown:
o Areasusedfor camp
o Storageareasforrawmaterialandequipment
o Waste yard
o Locationofanypotentiallyhazardousmaterialsuchasoil
o Parkingarea
o Loadingandunloadingofmaterial
o Septictanks
o Safedistancefromwaterfront
Otherkeymitigationmeasuresareasfollows:
Thenewequipment willbestoredinproperlydemarcatedandidentifiedareas;
Liftingequipment (cranes)usedfortheequipment willfollowtheprescribedsafetyspecification;
MaterialSafetyDataSheet(MSDS)forchemicals,ifany,willaccompanytheconsignment. A copy
oftheMSDS willbeavailablenearthe storage areaatalltimes;
AppropriatePPEswillbeprovidedtotheworkers and it willbeensuredthatthePPEsareused;
Thestaffwillbeprovided withtraininginuseofPPE;
Properscaffoldingplatformswillbeprovidedforallworkareaslocatedmorethan1mabovefloor
level;
First Aid facilities and fire protection devices will be placed in areas where activates will be
performed;
Earprotection willbeusedifthenoiselevelisabove85dB(A);
Allconfined spaceswillbeidentified;
Thetemperatureofthe confined spacewillbeinthehumantolerancerange;
Artificialandintrinsicallysafe lightingwillbeprovidedintheconfinedspaces;
Ifthereisariskofgasesorfumesintheconfinedspacetheprovisionsforventilationwillbemade.
9. EMC Pakistan Pvt. Ltd Page vi of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
During operation of a thermal power project, the soils within the deposition zone of pollutants may
undergophysico-chemicalchangesduetodepositionofSPM(ashparticles)andwashoutofgases(SOx
and NOx) during the rains.However, the impacts of these are likely to be marginal, as the impacts on
soil due to gaseous emissions from operation of LECPP, are likely to be negligible as the maximum
incrementalPM and SO2 levelsareintherangeof1.3and15.1µg/m3respectively.
The effluents from the plant include the boiler blow down, cooling water and waste water from the
plant.Awatertreatmentplantwillbeconstructedattheplantsitewhichwillensuretheeffluentsmeet
the SEQSlimits.
Themainmodeofairpollutionfromathermalpowerplantispointemission–emissionsfromtheboiler
and the combustion of fuel (HSFO, natural gas and coal) results in the emission of various types of
pollutantsfrom the plant stack. The main pollutantsare Particulate Matter,Oxides of Nitrogen (NOx),
and SulphurDioxide(SO2).
The modeling for the proposed LECPP Project was carried out using the US EPA ISCST3 Model. The
modeliscapableofhandlingmultiplesources,includingpoint,volume,areaandopenpitsourcetypes.
However, in the present scope the model was used for point emission (chimney) source type. The
worst incremental24 hourly average GLC value of SO2,NOx,PM10 andPM2.5 from the project at full
operating load with 200 m high stack will be 15.1 μg/m3, 40 μg/m3, 1.3 μg/m3 and 0.85 μg/m3
respectivelyinthedownwindENEdirection(at2.0kmdistance).Theworstincrementalannualaverage
GLC vale of SO2, NOx, PM10 and PM2.5 from the project at full operating load will be 3.6 μg/m3, 9.5
μg/m3,0.4 μg/m3 and 0.2 μg/m3respectivelyin the downwind ENE direction (at 1.0 km distance).The
maximum incremental GLC is superimposed over the maximum baseline ambient air level and the
resultantvaluesareshowninTableEX-2(24-houraverageinμg/m3).The200mtallstackheightswith
high momentum and buoyancy takes the plume above the highest mixing height. 99.98%. PM
emissions are controlled using ESP, SO2 by FGD and NOx by Low NOx burners. This results in lowest
ground levelconcentrationofairpollutantsinthestudyarea.
TableEX-2:IncrementalGLCduetoLECPP
Parameter IncrementalGLC(max) BackgroundLevel SuperimposedValue SindhEQS
SO2 15.1μg/m3
12.06μg/m3
27.16μg/m3
120μg/m3
NOx 40μg/m3
7.89μg/m3
47.39μg/m3
80μg/m3
PM10 1.3μg/m3
70μg/m3
71.3μg/m3
150μg/m3
PM2.5 0.9μg/m3
19.25μg/m3
19.2μg/m3
75μg/m3
Theimpactontheterrestrialecosystemduetooperationofthethermalpowerprojectmayoccurfrom
deposition and absorption of air pollutants on flora and soil surfaces. Deposition of fly ash on leaves
may interrupt gaseousexchangethrough stomatalclogging,therebyaffectingplant growth However,
the impact due to operation of the project is envisaged to be negligible, as incremental ground level
concentration ofPM10 due to emissions from the project is predicted to be 1.3 µg/m3 only. The
predictedmaximumincrementalgroundlevelconcentrationofSO2 duetooperationofprojectis15.1
µg/m3 and maximum ground level concentration of SO2 after operation of the project is predicted as
27.16µg/m3.Thisiswellwithinthe Sindh AmbientAir QualityStandards.
A100meterwidegreenbeltshallbedevelopedallaroundtheprojectandextensiveafforestationshall
be undertaken within main plant, township and ash disposal areas. Such activities would help
10. EMC Pakistan Pvt. Ltd Page vii of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
ameliorating the impact and improving the environmental quality of the surrounding area. It is
envisagedthattheplantationinand aroundtheproject site wouldactassinktopollutants.
Themarine ecologicalresourcesincludingthemangrove plants,MBI,fish,crabsand shrimpsmayalso
suffer harm from the coal dust and ash dust generated as a result of project activities. Leakage from
the prospective ash disposal site due to seepage or an accident may release toxic or hazardous
materialsintothecreekwater,negativelyimpactingmarinebiodiversity.
Goodpracticemeasureswillbeadoptedincluding:
Waste managementmeasuresoutlinedintheWasteManagementPlan.
MonitoringofliquideffluentsfromProjecttoensuretheymeettheSEQS.
Monitoringofgaseousemissionsincludingcoalandashdust
Monitoringtoensurethatthereisnoleakagefromtheashdisposalsite.
Fly ash, bottom ash,and boiler slag are other areas of concern in case of coalfired boiler. Recycling of
ash will be the preferred option for ash disposal. The quantity of ash production from the proposed
Project will depend on the quantity of coal and its ash content. For 5-10% ash content, the ash
productionisestimatedat250,000to500,000tonnes/year.
A review of the utilization of fly ash produced in the coal powered plants in India shows that on an
averagetheutilizationofflyashproducedbythecoalfiredpowerplantsisover50%,withanumberof
plantsachieving100%utilization.InChina,thenearly70%oftheflyashproducedisrecycled.
The flyash collection and disposal system willtransfer particulate collected from the boiler flue gas to
a fly storage silo for unloading into trucks for disposal (transported to lucky cement Karachi). Fly ash
entrained in the boiler flue gas will be collected using a baghouse or electrostatic precipitator. Fly ash
will also be collected throughout the flue gassystem bymeansof ash hoppersat other locationssuch
as the air heaters. The bottom ash handling system will collect, store, and transport bottom ash from
the boiler furnace,economizer hoppers and millreject hoppers.The system will include a submerged
scraperconveyor(SSC)forcollecting,coolingandtransportingthebottomash,aflightconveyorsystem
toconveyeconomizerashtotheSSC,andasluicesystemtoconveymillrejectstotheSSC.Thebottom
ash,millrejectsandeconomizerashwillbetransportedtoaconcretebunkerforremovalbytrucks.
The objectives of Environmental Management and Monitoring Plan are to provide consistent
information and guidance for implementing the management and monitoring measures which will
help achieve compliance with recommendations and conditions specified through the EIA process as
well as to ensure continuous improvement of environmental performance, reduction of negative
impactsandenhancementofpositiveeffectsduringtheconstruction,operationanddecommissioning
ofthefacility.
TheaimsofthisEMMPareto:
Ensure that all relevant legislations (including national, provincial and local) are complied with
duringallthephases;
Identify entities that will be responsible for the implementation of the measures and outlines the
functionsandresponsibilities;
11. EMC Pakistan Pvt. Ltd Page viii of viii
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
To propose mechanisms for monitoring compliance & prevent long-term or permanent
environmentaldegradation;
Ensure that the best management/ industry practices and best available techniques are
incorporated and implemented to minimize potential environmental and social impacts during
eachphase;
Ensure that the project operation does not result in undue or reasonably avoidable adverse
environmentalimpacts,andthatanypotentialenvironmentalbenefitsareenhanced;
Enforcethe companypoliciesthroughtraining,supervision,regularreviewsandconsultation;
Adheretohighstandardsofsafetyand carefortheprotectionoftheEmployeesandpublic.
Screening of potential environmental impacts at the different stages of the Project namely siting,
construction and operation of the proposed 1 x 600 MW Coal Power Plant by Lucky Electric Power
CompanyLimited(LEPCL)leadstothefollowingconclusion:
Environmental impacts of the proposed Project are localized to the microenvironment of the
activityarea and consequentlyareratedas minororinsignificant.
Severityofimpactoftheactivitiesisofsmallorder.
Implementation of recommended mitigation measures and strictly following the environmental
managementplanshallminimizetheimpactofproposedactivities.
The proposed project will create enormous potentiality of economic and social development of the
region.Thepresentelectricitycrisisandrisingelectricitydemandurgeinstallationofnewpowerplant.
It will offerlarge numberof jobopportunityduringitslife time wherethe localpeople willget priority.
The potential benefits of the project will compensate the negative impact if the prescribed EMP is
implemented with honesty. The proposed Project would, on adoption of mitigation measures, have
nosignificantimpactonthemicroenvironmentandmacroenvironmentoftheprojectarea.
This EIA Study finds that the proposed project would fulfil the requirements of sustainable
developmentbybeingsociallyequitable,andeconomicallyviableinimprovingthequalityoflifeforall
citizensofPakistan,withoutalteringthebalanceintheresourcesoftheecosystemoftheregion.
The Studytherefore recommends that the EIA report should be approved with the provision that the
suggested mitigation measures will be adopted and the Environmental Management & Monitoring
Plansshallbefollowedinletterandspirit.
12. EMC Pakistan Pvt. Ltd Page 1 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
Table of Contents
1.0 INTRODUCTION........................................................................................................... 1
1.1 PROJECT PROPONENT .........................................................................................................................1
1.2 EIA CONSULTANT.................................................................................................................................3
1.3 THE PROJECT .......................................................................................................................................4
1.4 PROJECT BACKGROUND ......................................................................................................................7
1.4.1 ENERGY RESOURCES IN PAKISTAN ......................................................................................................7
1.4.2 CURRENT ENERGY MIX ........................................................................................................................7
1.4.3 TARGET ENERGY MIX...........................................................................................................................8
1.4.4 PROFILE OF CURRENT ENERGY CONSUMPTION..................................................................................8
1.4.5 CURRENT POWER SUPPLY ...................................................................................................................9
1.4.5.1 ELECTRICITY GENERATION...................................................................................................................9
1.4.5.2 K-ELECTRIC (FORMERLY KESC)...........................................................................................................10
1.4.5.3 NUCLEAR ...........................................................................................................................................10
1.4.6 GOVERNMENT OF PAKISTAN POLICY, THE REGULATORY FRAMEWORK, AND THE ENERGY SECTOR
..........................................................................................................................................................11
1.4.7 ELECTRICAL POWER SUPPLY IN PAKISTAN ........................................................................................14
1.4.7.1 FUTURE DEMAND FOR POWER.........................................................................................................14
1.4.7.2 DEMAND FORECAST..........................................................................................................................14
1.4.7.3 FUTURE SUPPLY.................................................................................................................................15
1.4.7.4 THE ROLE OF IMPORTED COAL..........................................................................................................16
1.4.7.5 NUCLEAR ENERGY..............................................................................................................................16
1.4.8 TRANSMISSION NETWORK................................................................................................................17
1.5 OBJECTIVES OF PROJECT ...................................................................................................................18
1.6 NEED FOR EIA ....................................................................................................................................19
1.7 OBJECTIVES OF EIA ............................................................................................................................19
1.8 CATEGORIZATION OF PROJECT..........................................................................................................20
1.9 METHODOLOGY.................................................................................................................................20
1.9.1 SCOPING............................................................................................................................................20
1.9.2 BASELINE DATA COLLECTION ............................................................................................................21
1.9.3 IDENTIFICATION OF ASPECTS ............................................................................................................21
1.9.4 IMPACT ASSESSMENT & EMP............................................................................................................21
1.9.5 DOCUMENTATION & REVIEW ...........................................................................................................22
1.10 STRUCTURE OF THE EIA REPORT .......................................................................................................22
2.0 POLICY, LEGAL & REGULATORY FRAMEWORK ............................................................ 23
2.1 NATIONAL POLICY FRAMEWORK.......................................................................................................23
2.1.1 NATIONAL CONSERVATION STRATEGY..............................................................................................23
2.1.2 BIODIVERSITY ACTION PLAN..............................................................................................................23
2.1.3 NATIONAL POWER POLICY 2013 .......................................................................................................23
2.1.4 NATIONAL FOREST POLICY 2010 .......................................................................................................24
2.1.5 NATIONAL ENVIRONMENTAL POLICY 2005.......................................................................................24
2.1.6 NATIONAL CLIMATE CHANGE POLICY ...............................................................................................25
2.1.7 NATIONAL STRATEGY AND ACTION PLAN FOR MANGROVES FOR THE FUTURE (2010) ...................25
2.1.8 NATIONAL DRINKING WATER POLICY................................................................................................26
2.2 THE 18TH AMENDMENT IN CONSTITUTION OF PAKISTAN ...............................................................26
2.2.1 SINDH ENVIRONMENTAL PROTECTION AGENCY...............................................................................26
2.2.2 SINDH ENVIRONMENTAL PROTECTION ACT 2014.............................................................................27
2.3 SINDH WILDLIFE PROTECTION ORDINANCE 1972 AND AMENDMENTS 2001...................................28
2.4 SINDH FISHERIES ORDINANCE 1980..................................................................................................29
2.5 SINDH FOREST ACT 1927 ...................................................................................................................29
2.6 THE FACTORIES ACT 1934..................................................................................................................29
2.7 LAND ACQUISITION ACT (LAA) 1984..................................................................................................30
2.8 PORT QASIM AUTHORITY ACT 1973 (AMENDMENTS 2002) .............................................................31
13. EMC Pakistan Pvt. Ltd Page 2 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
2.9 PAKISTAN PENAL CODE .....................................................................................................................31
2.10 SINDH ANTIQUITIES ACT 1974...........................................................................................................32
2.11 SINDH CULTURAL HERITAGE (PRESERVATION) ACT 1994 .................................................................32
2.12 THE BOILER ACT 1923........................................................................................................................32
2.13 THE MOTOR VEHICLES ORDINANCE 1965 AND RULES 1969.............................................................32
2.14 ENVIRONMENTAL REGULATIONS & GUIDELINES..............................................................................32
2.14.1 SINDH EPA REVIEW OF IEE AND EIA REGULATIONS 2014 .................................................................32
2.14.2 ENVIRONMENTAL ASSESSMENT PROCEDURES.................................................................................34
2.14.3 SINDH ENVIRONMENTAL QUALITY STANDARDS ...............................................................................37
2.14.4 SELF-MONITORING AND REPORTING BY INDUSTRY RULES 2014......................................................40
2.14.5 THE HAZARDOUS SUBSTANCES RULES 2014 .....................................................................................41
2.14.6 GUIDELINES FOR SENSITIVE AND CRITICAL AREAS............................................................................41
2.14.7 GUIDELINES FOR PUBLIC CONSULTATION.........................................................................................41
2.14.8 GUIDELINES FOR COAL FIRED THERMAL POWER PLANTS – NIAP (2014)..........................................43
2.14.9 IFC GUIDELINES FOR THERMAL POWER PLANTS...............................................................................43
2.14.10 IFC GENERAL EHS GUIDELINES ..........................................................................................................44
2.14.11 IFC PERFORMANCE STANDARDS 2012 ..............................................................................................45
2.15 INTERNATIONAL CONVENTIONS AND TREATIES ...............................................................................47
2.15.1 CONVENTION ON CONSERVATION OF MIGRATORY SPECIES, 1979..................................................48
2.15.2 CONVENTION OF INTERNATIONAL TRADE IN ENDANGERED SPECIES (CITES) 1973 .........................48
2.15.3 CONVENTION ON WETLANDS OF INTERNATIONAL IMPORTANCE; RAMSAR CONVENTION 1971....48
2.15.4 IUCN RED LIST....................................................................................................................................49
2.15.5 INTERNATIONAL CONVENTION ON BIODIVERSITY 1992...................................................................49
2.15.6 KYOTO PROTOCOL (1992) AND UNITED NATION’S CLIMATE CHANGE CONVENTION ......................49
3.0 DESCRIPTION OF PROJECT ......................................................................................... 51
3.1 THERMAL POWER GENERATION PROCESS........................................................................................51
3.2 BOILER SYSTEM .................................................................................................................................54
3.2.1 FURNACE ...........................................................................................................................................55
3.2.2 SUPERHEATERS AND REHEATERS......................................................................................................55
3.2.3 REHEAT STEAM PIPES........................................................................................................................56
3.2.4 ECONOMIZER ....................................................................................................................................56
3.2.5 STARTUP SYSTEM ..............................................................................................................................56
3.2.6 AIR PREHEATER .................................................................................................................................56
3.2.7 SOOT BLOWERS.................................................................................................................................57
3.2.8 PULVERIZER .......................................................................................................................................57
3.2.9 BURNERS ...........................................................................................................................................58
3.2.10 SYSTEM OPERATION..........................................................................................................................58
3.3 TURBINE GENERATOR .......................................................................................................................58
3.3.1 HIGH-PRESSURE TURBINE .................................................................................................................59
3.3.2 INTERMEDIATE-PRESSURE TURBINE .................................................................................................59
3.3.3 LOW-PRESSURE TURBINE ..................................................................................................................59
3.3.4 LUBRICATING OIL SYSTEM.................................................................................................................59
3.3.5 ELECTROHYDRAULIC CONTROL OIL SYSTEM .....................................................................................60
3.3.6 GENERATOR.......................................................................................................................................60
3.3.7 HYDROGEN SEAL OIL SYSTEM............................................................................................................60
3.3.8 STATIC EXCITER..................................................................................................................................60
3.3.9 CONTROL SYSTEM .............................................................................................................................60
3.3.10 SYSTEM OPERATION..........................................................................................................................60
3.4 MAIN STEAM AND REHEAT PIPING ...................................................................................................61
3.4.1 FUNCTION..........................................................................................................................................61
3.4.2 MAIN STEAM .....................................................................................................................................61
3.4.3 COLD REHEAT ....................................................................................................................................61
3.4.4 HOT REHEAT......................................................................................................................................61
3.4.5 EXTRACTION STEAM..........................................................................................................................61
3.4.6 SYSTEM OPERATION..........................................................................................................................62
3.5 CONDENSATE ....................................................................................................................................62
15. EMC Pakistan Pvt. Ltd Page 4 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
3.14.3.4 THERMAL DISCHARGE .......................................................................................................................78
3.14.3.5 NOISE.................................................................................................................................................78
3.14.3.6 ASH ....................................................................................................................................................78
3.14.3.7 AIRBORNE DUST FORM ASH STORAGE YARD....................................................................................78
3.14.3.8 WASTEWATER DISCHARGE................................................................................................................78
3.15 HVAC..................................................................................................................................................79
3.15.1 FUNCTION..........................................................................................................................................79
3.15.2 DESIGN BASIS ....................................................................................................................................79
3.15.3 AIR CONDITIONING ...........................................................................................................................79
3.15.4 BATTERY ROOM.................................................................................................................................79
3.16 COAL DUST COLLECTORS...................................................................................................................80
3.17 DRY PIPE DELUGE TYPE SPRINKLER SYSTEM......................................................................................81
3.18 DUST SUPPRESSION...........................................................................................................................82
3.18.1 SYSTEM OPERATION..........................................................................................................................82
3.18.2 WET CENTRIFUGAL DUST COLLECTOR ..............................................................................................82
3.19 COMPRESSED AIR..............................................................................................................................83
3.19.1 FUNCTION..........................................................................................................................................83
3.19.2 DESIGN BASIS ....................................................................................................................................83
3.19.3 SYSTEM OPERATION..........................................................................................................................83
3.20 FIRE PROTECTION..............................................................................................................................83
3.20.1 FUNCTION..........................................................................................................................................83
3.20.2 DESIGN BASIS ....................................................................................................................................83
3.20.3 FIRE PROTECTION MASTER PLAN......................................................................................................85
3.20.4 BUILDING AND FIRE CODES & LIFE SAFETY COMPLIANCE REVIEW ...................................................85
3.20.5 FIRE RISK EVALUATION......................................................................................................................86
3.20.6 HAZARDOUS AREA CLASSIFICATION EVALUATION............................................................................86
3.20.7 SYSTEM OPERATION..........................................................................................................................86
3.21 FUEL OIL STORAGE AND TRANSFER...................................................................................................87
3.21.1 FUNCTION..........................................................................................................................................87
3.21.2 DESIGN BASIS ....................................................................................................................................87
3.21.3 SYSTEM OPERATION..........................................................................................................................88
3.22 COAL UNLOADING AND HANDLING SYSTEM.....................................................................................88
3.22.1 FUNCTION..........................................................................................................................................88
3.22.2 DESIGN BASIS ....................................................................................................................................88
3.22.3 DESCRIPTION .....................................................................................................................................89
3.22.4 SYSTEM OPERATION..........................................................................................................................90
3.23 ASH HANDLING AND DISPOSAL.........................................................................................................90
3.23.1 FUNCTION..........................................................................................................................................90
3.23.2 DESIGN BASIS ....................................................................................................................................90
3.23.2.1 FLY ASH HANDLING SYSTEM..............................................................................................................90
3.23.2.2 BOTTOM ASH HANDLING SYSTEM ....................................................................................................90
3.23.2.3 MILL REJECTS HANDLING SYSTEM.....................................................................................................90
3.23.2.4 ECONOMIZER ASH HANDLING SYSTEM.............................................................................................91
3.23.3 DESCRIPTION .....................................................................................................................................91
3.23.3.1 FLY ASH HANDLING SYSTEM..............................................................................................................91
3.23.3.2 BOTTOM ASH AND PYRITE HANDLING..............................................................................................91
3.23.3.3 SYSTEM OPERATION..........................................................................................................................92
3.24 ELECTRICAL........................................................................................................................................92
3.24.1 FUNCTION..........................................................................................................................................92
3.24.2 DESIGN BASES....................................................................................................................................92
3.24.3 SYSTEM CONFIGURATION .................................................................................................................93
3.24.4 SYSTEM OPERATION..........................................................................................................................93
3.25 STATION TRANSFORMER SYSTEM.....................................................................................................95
3.25.1 FUNCTION..........................................................................................................................................95
3.25.2 DESIGN BASIS ....................................................................................................................................95
3.25.3 SYSTEM CONFIGURATION .................................................................................................................95
3.25.4 SYSTEM OPERATION..........................................................................................................................95
16. EMC Pakistan Pvt. Ltd Page 5 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
3.26 11-KV UPPER MEDIUM VOLTAGE SYSTEM ........................................................................................96
3.26.1 FUNCTION..........................................................................................................................................96
3.26.2 DESIGN BASIS ....................................................................................................................................96
3.26.3 SYSTEM CONFIGURATION .................................................................................................................96
3.26.4 SYSTEM OPERATION..........................................................................................................................96
3.27 3.3-KV LOWER MEDIUM VOLTAGE SYSTEM......................................................................................96
3.27.1 FUNCTION..........................................................................................................................................96
3.27.2 DESIGN BASIS ....................................................................................................................................96
3.27.3 SYSTEM CONFIGURATION .................................................................................................................97
3.27.4 SYSTEM OPERATION..........................................................................................................................97
3.28 400-VOLT LOW-VOLTAGE AUXILIARY SYSTEM ..................................................................................97
3.28.1 FUNCTION..........................................................................................................................................97
3.28.2 DESIGN BASIS ....................................................................................................................................97
3.28.3 SYSTEM CONFIGURATION .................................................................................................................98
3.28.4 SYSTEM OPERATION..........................................................................................................................98
3.29 DC SYSTEMS.......................................................................................................................................98
3.29.1 FUNCTION..........................................................................................................................................98
3.29.2 DESIGN BASIS ....................................................................................................................................99
3.29.3 SYSTEM CONFIGURATION .................................................................................................................99
3.29.4 SYSTEM OPERATION..........................................................................................................................99
3.30 UNINTERRUPTIBLE POWER SUPPLY SYSTEM...................................................................................100
3.30.1 FUNCTION........................................................................................................................................100
3.30.2 DESIGN BASIS ..................................................................................................................................100
3.30.3 SYSTEM CONFIGURATION ...............................................................................................................100
3.30.4 SYSTEM OPERATION........................................................................................................................100
3.31 EMERGENCY DIESEL GENERATOR SYSTEM......................................................................................100
3.31.1 FUNCTION........................................................................................................................................100
3.31.2 DESIGN CRITERIA.............................................................................................................................100
3.31.3 SYSTEM CONFIGURATION ...............................................................................................................101
3.31.4 SYSTEM OPERATION........................................................................................................................101
3.32 SWITCHYARD...................................................................................................................................101
3.32.1 FUNCTION........................................................................................................................................101
3.32.2 DESIGN BASIS ..................................................................................................................................101
3.32.3 SYSTEM CONFIGURATION ...............................................................................................................101
3.32.4 SYSTEM OPERATION........................................................................................................................102
3.33 INSTRUMENTATION AND CONTROLS..............................................................................................102
3.34 DISTRIBUTED CONTROLS AND MONITORING SYSTEMS..................................................................103
3.35 OPERATOR CONSOLE.......................................................................................................................104
3.36 BOILER CONTROL SYSTEM...............................................................................................................105
3.36.1 GENERAL..........................................................................................................................................105
3.36.2 SYSTEM DESCRIPTION .....................................................................................................................105
3.37 BURNER CONTROL AND FURNACE SAFETY SYSTEM........................................................................106
3.37.1 SYSTEM DESCRIPTION .....................................................................................................................107
3.37.2 FLAME SCANNERS ...........................................................................................................................107
3.38 TURBINE CONTROL SYSTEM ............................................................................................................107
3.38.1 GENERAL..........................................................................................................................................107
3.38.2 SYSTEM DESCRIPTION .....................................................................................................................107
3.38.3 TURBINE SUPERVISORY INSTRUMENTS...........................................................................................108
3.39 VIBRATION MONITORING ...............................................................................................................108
3.40 CONTINUOUS EMISSION MONITORING SYSTEM ............................................................................109
3.41 PROPOSED COAL RECEIVAL .............................................................................................................109
4.0 SCREENING OF ALTERNATIVES................................................................................. 111
4.1 NO PROJECT ALTERNATIVE..............................................................................................................111
4.2 TECHNOLOGY SELECTION................................................................................................................112
4.2.1 THE BOILER......................................................................................................................................112
4.2.2 UNIT SIZE SELECTION.......................................................................................................................112
17. EMC Pakistan Pvt. Ltd Page 6 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
4.2.3 PARTICULATE MATTER EMISSION CONTROLS.................................................................................114
4.2.4 ASH HANDLING AND DISPOSAL.......................................................................................................115
4.3 COAL SOURCE AND PRICING ...........................................................................................................116
4.3.1 SUPPLY.............................................................................................................................................116
4.3.2 WORLD PRODUCTION: THE WORLD SEABORNE THERMAL COAL MARKET ....................................116
4.3.3 POTENTIAL COAL SUPPLY SOURCES ................................................................................................117
4.3.3.1 AUSTRALIA - NEW SOUTH WALES ...................................................................................................119
4.3.3.2 AUSTRALIA - QUEENSLAND .............................................................................................................120
4.3.3.3 INDONESIA ......................................................................................................................................120
4.3.3.4 BUMI RESOURCES............................................................................................................................122
4.3.3.5 PT ADARO INDONESIA.....................................................................................................................122
4.3.3.6 BANPU PUBLIC COMPANY LTD........................................................................................................123
4.3.3.7 PT KIDECO JAYA AGUNG..................................................................................................................123
4.3.3.8 OTHER LARGE INDONESIAN STEAM COAL PRODUCERS..................................................................123
4.3.3.9 PAKISTAN.........................................................................................................................................123
4.3.3.10 SOUTH AFRICA.................................................................................................................................124
4.3.3.11 BHP BILLITON...................................................................................................................................125
4.3.3.12 ANGLO COAL ...................................................................................................................................125
4.3.3.13 XSTRATA ..........................................................................................................................................125
4.3.3.14 OTHER MAJOR STEAM COAL EXPORTERS .......................................................................................125
4.3.3.15 MOATIZE MINE................................................................................................................................125
4.3.4 COAL QUALITIES ..............................................................................................................................126
4.3.4.1 SIZE OF SHIPS AND AVAILABILITY OF COAL CARRIERS.....................................................................128
4.3.4.2 HANDLING CAPACITY OF COAL LOADING PORTS ............................................................................128
4.3.4.3 VOYAGE DISTANCE AND FREQUENCY OF TRANSPORTATION .........................................................129
4.3.4.4 INDIGENOUS COAL ..........................................................................................................................129
4.4 COAL SHIPPING AND RECEIVAL .......................................................................................................129
4.4.1 TRANSPORTATION TECHNOLOGIES.................................................................................................129
4.5 AVAILABILITY OF APPROPRIATE ENERGY SOURCE ..........................................................................132
4.5.1 SINDH PROVINCE.............................................................................................................................132
4.5.1.1 THAR................................................................................................................................................132
4.5.1.2 LAKHRA............................................................................................................................................133
4.5.1.3 SONDA-JHERRUCK...........................................................................................................................134
4.5.2 BALOCHISTAN..................................................................................................................................135
4.5.2.1 SOR-RANGE, DEGARI, SINJIDI ..........................................................................................................135
4.5.3 PUNJAB............................................................................................................................................135
4.5.3.1 SALT RANGE.....................................................................................................................................135
4.5.3.2 MAKERWAL/GULLAKHEL.................................................................................................................135
4.5.4 COAL RESOURCES SUMMARY..........................................................................................................136
4.5.5 COAL PRODUCTION .........................................................................................................................136
4.5.6 COAL MINING AND TRANSPORTATION ...........................................................................................136
4.5.6.1 COAL MINING ..................................................................................................................................136
4.5.6.2 TRANSPORTATION...........................................................................................................................137
4.5.7 PAKISTAN COAL FOR LEPCL .............................................................................................................137
5.0 ENVIRONMENTAL & SOCIAL BASELINE..................................................................... 138
5.1 METHODOLOGY OF BASELINE SURVEY ...........................................................................................138
5.2 DESCRIPTION OF MICRO AND MACRO ENVIRONMENT..................................................................138
5.3 PHYSICAL ENVIRONMENT................................................................................................................140
5.3.1 TOPOGRAPHY..................................................................................................................................140
5.3.2 GEOLOGY, GEOMORPHOLOGY & SOIL ............................................................................................140
5.3.2.1 SUB-RECENT AND RECENT DEPOSITS ..............................................................................................141
5.3.3 SEISMIC CONDITIONS......................................................................................................................143
5.3.4 TSUNAMIS .......................................................................................................................................143
5.3.5 HYDROLOGY ....................................................................................................................................144
5.3.6 WAVES.............................................................................................................................................147
5.3.7 TIDES & SURGES ..............................................................................................................................148
18. EMC Pakistan Pvt. Ltd Page 7 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
5.3.8 SEAWATER CURRENTS.....................................................................................................................149
5.3.9 CLIMATE ..........................................................................................................................................149
5.3.9.1 TEMPERATURE ................................................................................................................................150
5.3.9.2 PRECIPITATION ................................................................................................................................151
5.3.9.3 HUMIDITY........................................................................................................................................153
5.3.9.4 WIND DIRECTION AND SPEED .........................................................................................................153
5.3.10 AMBIENT AIR & NOISE QUALITY......................................................................................................154
5.3.10.1 DATA ACQUISITION CRITERIA..........................................................................................................154
5.3.10.2 AMBIENT AIR QUALITY MONITORING METHODS & AMBIENT AIR QUALITY STANDARDS..............155
5.3.10.3 RESULTS...........................................................................................................................................156
5.4 ECOLOGY .........................................................................................................................................161
5.4.1 FLORA ..............................................................................................................................................161
5.4.2 FAUNA .............................................................................................................................................163
5.4.2.1 METHODOLOGY...............................................................................................................................163
5.4.2.2 SURVEY RESULTS .............................................................................................................................164
5.5 SOCIOECONOMIC ENVIRONMENT ..................................................................................................170
5.5.1 DEMOGRAPHY.................................................................................................................................170
5.5.2 EMPLOYMENT AND LIVING CONDITIONS........................................................................................170
5.5.3 DEPENDENCE ON MANGROVES ......................................................................................................171
5.5.4 EDUCATION .....................................................................................................................................171
5.5.5 HEALTH............................................................................................................................................172
5.5.6 LANDSCAPING .................................................................................................................................172
5.5.7 ARCHAEOLOGICAL AND HISTORICAL SITES .....................................................................................172
6.0 SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND PROPOSED MITIGATION
MEASURES.............................................................................................................. 175
6.1 IMPACT ON LANDUSE......................................................................................................................175
6.2 IMPACT OF CONSTRUCTION ACTIVITIES .........................................................................................175
6.3 SOIL DISTURBANCE..........................................................................................................................178
6.4 STABILITY OF STRUCTURES..............................................................................................................178
6.5 SOIL & WATER CONTAMINATION ...................................................................................................179
6.6 IMPACT ON AIR QUALITY.................................................................................................................183
6.7 COAL DUST CONTROL......................................................................................................................198
6.8 IMPACT DUE TO NOISE....................................................................................................................198
6.9 IMPACT ON TERRESTRIAL ECOLOGY................................................................................................206
6.10 IMPACT ON AQUATIC ECOLOGY......................................................................................................206
6.11 DISPOSAL OF WASTE .......................................................................................................................207
6.12 ASH HANDLING AND UTILIZATION ..................................................................................................208
6.13 GREENBELT DEVELOPMENT ............................................................................................................209
6.14 EXPLOSION RISK AND PREVENTION ................................................................................................209
6.15 SOCIOECONOMIC IMPACT ..............................................................................................................210
6.16 SAFETY & OCCUPATIONAL HEALTH.................................................................................................210
7.0 CONSULTATION & INFORMATION DISCLOSURE........................................................ 212
7.1 OBJECTIVES......................................................................................................................................212
7.2 CONSULTATION FRAMEWORK ........................................................................................................212
7.3 CONSULTATION PROCESS................................................................................................................213
7.4 COMMUNITY ENGAGEMENT RESPONSIBILITIES .............................................................................219
7.5 TRAINING ON COMMUNITY RELATIONS .........................................................................................221
7.6 STAKEHOLDER ENGAGEMENT PLAN FRAMEWORK.........................................................................221
7.6.1 OBJECTIVES AND PRINCIPLES ..........................................................................................................221
7.6.2 PRINCIPLES OF STAKEHOLDER ENGAGEMENT ................................................................................222
7.6.3 IMPLEMENTATION PLAN.................................................................................................................222
7.6.4 GRIEVANCE MANAGEMENT ............................................................................................................223
7.6.5 COMMITMENT REGISTER ................................................................................................................224
7.6.6 ROLES AND RESPONSIBILITIES.........................................................................................................224
7.6.7 COMMUNITY DEVELOPMENT..........................................................................................................225
19. EMC Pakistan Pvt. Ltd Page 8 of 8
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
7.6.8 MONITORING AND EVALUATION ....................................................................................................225
7.6.9 PERFORMANCE INDICATORS...........................................................................................................226
8.0 ENVIRONMENTAL MANAGEMENT & MONITORING PLAN......................................... 227
8.1 INTRODUCTION ...............................................................................................................................227
8.2 SCOPE OF EMMP .............................................................................................................................227
8.3 OBJECTIVES OF EMMP.....................................................................................................................228
8.3.1 PROJECT...........................................................................................................................................228
8.4 EMMP PROCESS...............................................................................................................................228
8.5 PRE-CONSTRUCTION (DESIGN) PHASE ............................................................................................229
8.5.1 RESPONSIBILITIES OF LEPCL.............................................................................................................229
8.5.2 RESPONSIBILITIES OF EPC CONTRACTOR ........................................................................................230
8.5.3 CONSTRUCTION PHASE ...................................................................................................................230
8.5.4 ROLES AND RESPONSIBILITIES DURING CONSTRUCTION................................................................231
8.6 OPERATIONS PHASE ........................................................................................................................235
8.6.1 EXPECTED HSE ORGANIZATIONAL STRUCTURE...............................................................................235
8.6.2 ROLES AND RESPONSIBILITIES DURING OPERATIONS PHASE .........................................................236
8.7 CLOSURE AND DECOMMISSIONING PHASE ....................................................................................238
8.8 MITIGATION PLAN...........................................................................................................................238
8.9 MONITORING PLAN.........................................................................................................................256
8.9.1 OBJECTIVES OF MONITORING PLAN................................................................................................256
8.10 WASTE MANAGEMENT PLAN..........................................................................................................260
8.11 SPILL MANAGEMENT.......................................................................................................................261
8.11.1 AVOIDING SPILLS .............................................................................................................................261
8.11.2 SPILL KITS.........................................................................................................................................262
8.11.3 RESPONDING TO SPILLS...................................................................................................................262
8.12 COAL DUST MANAGEMENT PLAN ...................................................................................................262
8.13 TRAINING PROGRAM.......................................................................................................................263
8.14 CONSTRUCTION MANAGEMENT PLAN............................................................................................264
8.15 CHANGE MANAGEMENT .................................................................................................................270
8.15.1 FIRST-ORDER CHANGE.....................................................................................................................270
8.15.2 SECOND-ORDER CHANGE................................................................................................................270
8.15.3 THIRD-ORDER CHANGE ...................................................................................................................271
8.15.4 CHANGES TO THE EMMP.................................................................................................................272
8.16 EMERGENCY RESPONSE PLAN............................................................................................... 272
9.0 CONCLUSION........................................................................................................... 275
ANNEXURES
Annex–I : SindhEnvironmentalProtectionAct2014
Annex–II : SindhEPA(Reviewof IEEandEIA)Regulations2014
Annex–III : NationalEnvironmentalQualityStandards(NEQS)
20. EMC Pakistan Pvt. Ltd Page 1 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
1.0 INTRODUCTION
Pakistan faces a number of critical challenges in energy sector such as energy and power resource
deficit, power shortages, and a greater dependency on imported oil to meet the energy demand-
supplygap.Thedemandforelectricitycurrentlyoutstripssupply.Inadequategeneration,transmission,
anddistribution,aswellastheinefficientuseofelectricity,leadtoshortagesof12-18hours,particularly
at peak times. Realizing these challenges, the governments of Sindh & Pakistan are focusing on the
huge potential of developing indigenous coal resources on fast-track basis and put coal based power
asamajorportioninoverallenergymix.
The National Energy Policy 2013 requires development of strategy to i) ensure the generation of
inexpensiveandaffordableelectricityfordomestic,commercial,andindustrialusebyusingindigenous
resourcessuch ascoal(Thar coal)and hydelpower, ii)addressthe key challengesof the power sector
in order to provide much needed relief to the citizens of Pakistan, and iii) shift Pakistan’s energy mix
towardscheaperfueland conservationof gasforpower.
In order to contribute towards meeting Pakistan’s growing electricity demand, Lucky Electric Power
Company Limited (LEPCL) proposes constructing a 1 x 660 MW coal based power station near Port
Qasim Karachi. LEPCL has acquired 250 acres of land from the Sindh Board of Revenue for the
establishmentoftheproposedpowerplant.CoalforthepowerplantwillbeimportedfromIndonesia,
South Africa, and/or Australia. The preferred option for imported coal is the under-construction
Pakistan International Bulk Terminal (PIBT) at Port Qasim. The terminal is expected to be operational
by2016.
ThisEnvironmentalImpactAssessment(EIA)servesasusefultoolinpredictionofpotentialimpactson
thesurroundingenvironmentduetodevelopmentalproject.Itwillhelptheprojectproponent,impact
assessment authorities, regulatory agencies and other stakeholders in understanding the project and
mitigation measures, environmental impact and establishing emission requirements and other
measuresearlyinthe project cycle.Thisreport describes the project location,baseline environmental
scenario, potential impacts of the project on the environment and proposed measures for effective
environment management(EMaP &EMoP)duringtheproject cycle.
1.1 PROJECT PROPONENT
TheprojectcompanyLuckyElectricPowerCompanyLimited(LEPCL)iswhollyowned
subsidiaryorLuckyHoldingsLimited(LHL),whichisalsoanindirectsubsidiaryofLucky
CementLimited.
LuckyCementLimitedwasfoundedin1996byTabbaMemons.Thecompanyinitially
started with factories in the Pezu district of the North West Frontier Province (N.W.F.P). It now, also,
owns a factory in Karachi. Lucky Cement Limited has been sponsored by one of the largest business
groupsinPakistan,theYunusBrothersGroupbasedinKarachi.Overtheyears,theCompanyhasgrown
substantiallyand isexpandingitsbusinessoperationswithproductionfacilitiesatstrategiclocationsin
KarachitocatertotheSouthernregionsandPezu,KhyberPakhtunkhwatofurnishtheNorthernareas
ofthecountry.LuckyCementhasanetworkofover200dealerswhichenablesittodominatethelocal
market and is Pakistan’s first company to export sizeable quantities of loose cement and is the only
cementmanufacturertohave itsownloadingandstorageterminalat KarachiPort.
21. EMC Pakistan Pvt. Ltd Page 2 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
In 2013, LCL imported 1 million ton of thermalcoal.In the thermalcoalmarket in Japan,LCLhasbeen
the largest coal importer for many years. The stable supply of coal from many countries, including
Australia,Canada,China,Indonesia,and Russia,supportsconsistentpowersupplyin Japan.
Thecompanyisproducingenoughelectricitytonotonlyfulfilitsownrequirementsbuthasalsostarted
supplying electricity to Hyderabad Electric Supply Corporation and is now in the process of providing
electricity to Peshawar Electric Supply Corporation which is a noteworthy achievement in the area of
energygeneration.
ItalsohasLargest,lowestcostandmostefficientcementmanufacturerinPakistanwithcaptivepower
generation capacity of 200 MW. Similarly it produces 7.75 million tons of cement per annum
production capacity with production lines at different strategic locations from coverage perspective
within Pakistan. The 2013 Turnover of USD 375 million with USD 127 million exports to Africa, GCC
countries,India,Iraq,SriLankaandAfghanistan.ItisalsotheLargestexportedofcementfromPakistan.
The group has around 29,000 employees. Yunus brother group is also a proud sponsor of 9 different
firms including Lucky Cement Limited. The firms include textile mills, building materials and others.
Almostallgeneratetheirownelectricity.Followingarethecompaniesgeneratingtheirownelectricity:
LuckyCementLimited(Pezu)-75MW
LuckyCementLimited(Karachi)-80MW
LuckyCementLimited–WHRPezu–20MW
LuckyCementLimited–WHRKarachi–25MW
ICIPakistan Limited–37MW
GadoonTextileMillsLimited–50MW
YunusTextileMillsLimited– 14MW
LuckyEnergy(Pvt)Limited– 16.52MW
Al-MabrookaCement(Iraq)–8MW
YunusEnergyLimited–50MW(2015-E)
TotalIn-housepower capacity–375.52MW
Somekeystrengthsofthe groupare:
7.75 million tons per annum state of the art cement manufacturing plant in Pakistan which
continuestobea Cash cowforthe group
300,000 spindles with 1,050 weaving looms along with significant processing, stitching and
finishingcapacitywithinthetextilesectorinPakistan
Captive power generation of 316 MW to support industrial units and under construction 50 MW
wind power generation plant and 10 MW through waste heat recovery from Lucky Cement
operations
Recent acquisition of ICI Pakistan Limited which is(i)a renowned brand in the local market, (ii) 2nd
largest Polyester Staple Fibre producer and (iii) market leader in Soda Ash production and Life
Sciencesbusiness
22. EMC Pakistan Pvt. Ltd Page 3 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
TheuseofexpertisegainedviaLuckyCementLimitedintheCementManufacturingsectorevident
fromthenewplannedinvestmentsinAfricaandIraq.
A special purpose company (LEPCL) has been established by Lucky Cement, bringing together a team
of highly professional people in all areas like, technical, commercial, and legal specialists with the
capabilitytoconstruct,develop,operate,financeandmaintaintheProject.Followingfigureshowsthe
project companyorganizationwhich isguidedbya BoardofDirectors.
Figure1.1— Project CompanyOrganization
Allapplicable nationalandprovincial regulationswillbe followed bythe LEPCL(Project Company)and
it will be organized and managed under an agreement that outlines reporting and budgeting
requirements and the limits of authority for its various members. The Project Company will own
finance, construct, design, and operate the facility. Development of a world class facility in terms of
safety, customer satisfaction, employee development, regulatory relations, environmental
compliance,andcosteffectivenessistheproject company’sgoverningphilosophy.
The management component of the Project Company will comprised of individuals with direct
experience in development of power projects in developing countries, leading the Project through
eachphaseofdevelopmentwillbetheirresponsibility.Therewillbeadate-certain,lump-sum,turnkey
basis EPC Contract. It is envisioned at this time that a single EPC Contractor will be responsible for the
powerplantfacilities,colony,andanyotherfacilitiesnecessaryforthegenerationofpower.
An Operation &Maintenance (O&M)organization willbe established bythe Project Companyfor the
efficient operation and maintenance of the Project upon commissioning. The Project Company may
formthisO&Morganizationorassignedtoathird-partycompany.Operationsincludingcomplianceto
thePPA,fueldelivery,permit,&environmentallawswillbetheresponsibilitiesof O&Morganization.
1.2 EIA CONSULTANT
LEPCL appointed EMC Pakistan Private Limited for conducting the Environmental Impact
Assessment(EIA)studyoftheProposedProjecttoassessthelikelyenvironmentalandsocial
impactsthatmayresultfromProjectactivitiesandtoidentifymeasurestomitigatenegative
impacts,if any.
23. EMC Pakistan Pvt. Ltd Page 4 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
EMCformulatedthefollowingteamofofficialsandexpertsforconductingtheEIAstudyandpreparing
thereport:
Table1.1:ListofEIATeam
S. No. Name PositioninProject
1 SyedNadeemArif ProjectDirector
2 SaquibEjazHussain ESIASpecialist/ExpertonEnvironmentalModeling
3 Dr.MirzaArshadAliBeg SeniorEnvironmentalist/TeamLeader
4 Dr.ShahidAmjad MarineBiologist
5 Dr.SyedAliGhalib ExpertonFauna
6 Mr.KhurramShamsKhan SocialDevelopmentSpecialist
7 Ms.ZulekhaSoorma Health&SafetySpecialist
8 AsharH.Lodi TransportationSpecialist
9 Mr.S.M.Zaman Geologist
1.3 THE PROJECT
Theproposed[1 x660MW] LuckyElectricCoalPowerProject(LECPP] willbeestablishedoveranarea
of250acresoflandacquiredfromSindh BoRinDehGhangiaro,Bin QasimTown,Karachi.
Ontheeast,the LECPP sitefacesPakistan InternationalBulkTerminal[PIBT]inPQAwhichisbeingset-
up for handling Coal, Cement and Clinker. On the South, the Kadiro Creek flows into Arabian Sea. The
Lath Bastiislocatedinthewest whilethe BhainsColonyislocatedatabout1km intheNorth.
Figure1.2(a)showsthelocationoftheproposedpowerplantsiteandFigure1.2(b)showstheviewof
theproject site.
The boiler technology shall be based on super critical boiler parameters having higher thermal
efficiency as compared to conventionalpulverized coal fired units. The increase in efficiency results in
lowercoalconsumptionaswellaslowergeneration ofashandgaseousemissions.Coalforthepower
plantwillbemadeavailablethrough Indonesia,SouthAfricaor Australia.
Themaincomponentsoftheproposedproject include:
CoalHandlingSystemincludingDustExtractionandSuppressionSystem
Steam Generator,TurbineGeneratorand AuxiliaryUnits
Coolingwater system
Water &EffluentTreatment System
FireProtectionSystem
Air Conditioning&VentilationSystem
ElectrostaticPrecipitators,LowNoxBurners,FGD
A 200metershighstack
AshHandlingSystemwithDryAshExtraction&TemporaryStorageFacilities.
ElectricalSystems:Generator BusDuct,Transformers,Switchgears,SwitchYardetc.
24. EMC Pakistan Pvt. Ltd Page 5 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
Figure 1.2 (a) — Map showing LECPP Site
LECPP
Site
Lath basti
Bhains
Colony
Landhi
Ind. Area
Bin
Qasim
PIBT
Port
Qasim
25. EMC Pakistan Pvt. Ltd Page 6 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
Figure 1.2 (b) — Pictorial view of Project Site
26. EMC Pakistan Pvt. Ltd Page 7 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
1.4 PROJECT BACKGROUND
1.4.1 ENERGY RESOURCES IN PAKISTAN
The economy has taken a turnaround on account of following serious economic agenda and striving
sincerely to implement it. Early positive results, particularly stabilizing foreign exchange reserves,
appreciation of exchange rate, stability in prices despite heavy adjustments, remarkable industrial
growth on account of improved energy supply, considering the strong correlation between economic
growthandenergydemandgrowth,thereisanimperativeneedforsustainedincreasesinenergysupply
not only to sustain the growth momentum but to protect the economy from disruptions caused by
energydeficitsreflectedindemandmanagement,popularlyknownasloadshedding.
WiththecommissioningofprivatesectorIndependentPowerProjects(IPPs)thedemandandsupplyof
electricitywasbalancedin1997,IPPswereestablishedunderthePrivatePowerPolicy,1994.Generation
capacity has increased since 1997, and it was expected that demand and supply would remain in
equilibrium through 2014.However,demand of electricity has been increasingdue to faster economic
activity, rising disposable income, higher availability of consumer finance, double-digit growth of large-
scale manufacturing, and higher agricultural production. Therefore, the government has encouraged
theprivate sectortomeetthisadditionaldemand.
1.4.2 CURRENT ENERGY MIX
Pakistan is producing around 36 percent from oil, 29 percent each from gas and hydroelectric and five
percent from nuclear to meet its requirements. Unlike the global practice of producing electricity
through cheapest energy sources, Pakistan is fulfilling its energy needs through expensive oil and gas-
basedpowerplants.
The world is producing approximately 41 percent of electricity through coal, whereas Pakistan is
producing approximately seven percent electricity through coal. We produce 36 percent electricity
through the most expensive source of energy, which is oil, adding that 29 percent of electricity is
producedthroughgaswhile 29percentisproducedthroughhydroelectricsources.
Figure 1.3 – Primary Energy Supply by Source
27. EMC Pakistan Pvt. Ltd Page 8 of 275
Environmental Impact Assessment for 660 MW Coal Power Project (Final Report)
1.4.3 TARGET ENERGY MIX
Government of Pakistan aims to achieve power generation mix through development of indigenous
energy resources particularly hydel and coal. The government is committed to arrange timely finances
fortheseprojectsandmonitortheirdevelopmentregularlyinordertocompletethemasperschedule.
It is expected that 16, 564 MW power generation will be added in the nation al grid system through
various resources by completing the new projects which will reduce/eliminate load shedding during
nextfouryears.Thedetailoftheprojectisgivenbelow:
Table 1.1 — Power Generation Plan
Year NameofProject Capacity Agency Fuel
2014
GUDDU-1 (243MW) GENCOs Gas
NandipurPowerProject (425MW) GENCOs Oil
Guddu-2 (243MW) GENCOs Gas
Quaid-e-AzamSolarPark(Phase-I) (100MW) PPDB Solar
Quaid-e-AzamSolarPark(Phase-II) (300MW) PPDB Solar
GudduSteam(3) (261MW) GENCOs Gas
2015
Quaid-e-AzamSolarPark(Phase-III) (600MW) PPDB Solar
NeelumJhelumHydel (969MW) WAPDA Hydel
2016
GolenGol (106MW) WAPDA Hydel
Patrind HPP (147MW) PPDB Hydel
2017
Terbela4th
Extension (1410MW) WAPDA Hydel
CoalPlantatSahiwal (1200MW) PPDB COAL
2018
CoalPlantatJamshoro (1320MW) GENCOs COAL
TharCoalPlant (1320MW) GENCOs COAL
GaddaniPowerPark (6600MW) Public+Pvt COAL
Upto2018TotalGenerationAddition 16564MW
Source:PakistanElectricPowerCompanyLtd
1.4.4 PROFILE OF CURRENT ENERGY CONSUMPTION
The 6-year summary presented in Figure 1.4 reveals that there has been a decline in the use of coal
concurrent with an increase in gas, electricity and petroleum product. This structural change in the
energyconsumptionpatternisalsoassistedbythegovernmentadministeredpricedifferentialbetween
petroleum products and gas. The apparent reversal, recently, wherever there is an increase in
petroleumproductsusage,ismostprobablybecauseoflackofalternativefuel,loadsheddingofgasetc,
andhigherconsumptionofoilinagriculturesector.Theiscoalconsumption inPakistan alsobecauseof
itshigherusageinbrickkilns,afunctionofgrowingdemandinthehousingandotherinfrastructureand
conversion of about 80% of the cement industry from heavyoilto coal, but as far as power generation
isconcernedithasnotbeenusedproperlyuptilnow.