The document summarizes a large infrastructure project to reconstruct an interchange in New Haven, Connecticut. The interchange was originally built in 1958 but is now handling 50% more traffic than its original design capacity. The $357 million contract includes reconfiguring the interchange, constructing new ramps and bridges, and widening existing bridges. Temporary formwork including custom transition forms between round columns and pier caps were used to construct the 85 columns and 34 pier caps efficiently.