EAC Update Process
Madrid, April 2013
Roberto Hernantes Cantero
robertohernantes@hotmail.com
roberto.hernantes.linkedin@gmail.com
Assumptions
Earned Value not included within study
Continous over-cost
Estimated values in italics shaded letter, actual values in ‘usual’ letter
Notation
Focus in cost, not in duration
Economic deviation analysis, not duration deviations
Two periods under study
Initial project cost estimation
t = t0
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
BAC = EAC Q1
Q1 finish. Thus, we do know
actual incurred values of the
period
t = end of Q1
ITD Q1
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
BAC = EAC Q1
ETC Q2
Arithmetical
ITD Q1
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
BAC = EAC Q1
ETC Q2 arithmetical = BAC - ITD Q1
Remaining work re-estimation
t = end of Q1
ETC Q2
Arithmetical
ITD Q1
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
ETC Q2 -> New Estimation
ETC Q2 Arit. = BAC - ITD Q1
BAC = EAC Q1
ETC Q2
Arithmetical
ITD Q1
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
EAC Q2
BAC = EAC Q1
ETC Q2 Arit. = BAC - ITD Q1
ETC Q2 -> New Estimation
ETC Q2
EAC Q2 = ITD Q1 + ETC Q2
ETC Q2
Arithmetical
ITD Q1
€
tQ1 Q2 Q3 Q4
BAC = EAC Q1
EAC Q2
ETC Q2
EAC Q2 = ITD Q1 + ETC Q2
Dev. EAC Q2 = EAC Q2 – BAC
BAC = EAC Q1
ETC Q2 Arit. = BAC - ITD Q1
ETC Q2 -> New Estimation
= Dev. Actual Q1 + Dev. Estimated Q2
t = end of Q2
Q2 finish. Thus, we do know
actual incurred values of the
period
EAC Q2
ITD Q2
Q1 Q2 Q3 Q4
BAC = EAC Q1
€
t
EAC Q2 ETC Q3
Arithmetical
ITD Q2
Q1 Q2 Q3 Q4
BAC = EAC Q1
€
t
ETC Q3 Arithmetical = EAC Q2 - ITD Q2
t = end of Q2
Remaining work re-estimation
EAC Q2 ETC Q3
Arithmetical
ITD Q2
Q1 Q2 Q3 Q4
BAC = EAC Q1
€
t
ETC Q3 Arit. = EAC Q2 - ITD Q2
ETC Q3 -> New Estimation
EAC Q2
EAC Q3
ETC Q3
Arithmetical
ETC Q3
ITD Q2
Q1 Q2 Q3 Q4
BAC = EAC Q1
€
t
EAC Q3 = ITD Q2 + ETC Q3
ETC Q3 Arit. = EAC Q2 - ITD Q2
ETC Q3 -> New Estimation
EAC Q2
EAC Q3
ETC Q3
Arithmetical
ETC Q3
ITD Q2
Q1 Q2 Q3 Q4
BAC = EAC Q1
€
t
ETC Q3 Arit. = EAC Q2 - ITD Q2
ETC Q3 -> New Estimation
EAC Q3 = ITD Q2 + ETC Q3
Dev. EAC Q3 = EAC Q3 – EAC Q2
= Dev. Actual Q2 + Dev. Estimated Q3
This process each period until
the end of the project
Thank you very much for your
attention
robertohernantes@hotmail.com
roberto.hernantes.linkedin@gmail.com

EAC update process

  • 1.
    EAC Update Process Madrid,April 2013 Roberto Hernantes Cantero robertohernantes@hotmail.com roberto.hernantes.linkedin@gmail.com
  • 2.
    Assumptions Earned Value notincluded within study Continous over-cost Estimated values in italics shaded letter, actual values in ‘usual’ letter Notation Focus in cost, not in duration Economic deviation analysis, not duration deviations Two periods under study
  • 3.
    Initial project costestimation t = t0
  • 4.
    € tQ1 Q2 Q3Q4 BAC = EAC Q1 BAC = EAC Q1
  • 5.
    Q1 finish. Thus,we do know actual incurred values of the period t = end of Q1
  • 6.
    ITD Q1 € tQ1 Q2Q3 Q4 BAC = EAC Q1 BAC = EAC Q1
  • 7.
    ETC Q2 Arithmetical ITD Q1 € tQ1Q2 Q3 Q4 BAC = EAC Q1 BAC = EAC Q1 ETC Q2 arithmetical = BAC - ITD Q1
  • 8.
  • 9.
    ETC Q2 Arithmetical ITD Q1 € tQ1Q2 Q3 Q4 BAC = EAC Q1 ETC Q2 -> New Estimation ETC Q2 Arit. = BAC - ITD Q1 BAC = EAC Q1
  • 10.
    ETC Q2 Arithmetical ITD Q1 € tQ1Q2 Q3 Q4 BAC = EAC Q1 EAC Q2 BAC = EAC Q1 ETC Q2 Arit. = BAC - ITD Q1 ETC Q2 -> New Estimation ETC Q2 EAC Q2 = ITD Q1 + ETC Q2
  • 11.
    ETC Q2 Arithmetical ITD Q1 € tQ1Q2 Q3 Q4 BAC = EAC Q1 EAC Q2 ETC Q2 EAC Q2 = ITD Q1 + ETC Q2 Dev. EAC Q2 = EAC Q2 – BAC BAC = EAC Q1 ETC Q2 Arit. = BAC - ITD Q1 ETC Q2 -> New Estimation = Dev. Actual Q1 + Dev. Estimated Q2
  • 12.
    t = endof Q2 Q2 finish. Thus, we do know actual incurred values of the period
  • 13.
    EAC Q2 ITD Q2 Q1Q2 Q3 Q4 BAC = EAC Q1 € t
  • 14.
    EAC Q2 ETCQ3 Arithmetical ITD Q2 Q1 Q2 Q3 Q4 BAC = EAC Q1 € t ETC Q3 Arithmetical = EAC Q2 - ITD Q2
  • 15.
    t = endof Q2 Remaining work re-estimation
  • 16.
    EAC Q2 ETCQ3 Arithmetical ITD Q2 Q1 Q2 Q3 Q4 BAC = EAC Q1 € t ETC Q3 Arit. = EAC Q2 - ITD Q2 ETC Q3 -> New Estimation
  • 17.
    EAC Q2 EAC Q3 ETCQ3 Arithmetical ETC Q3 ITD Q2 Q1 Q2 Q3 Q4 BAC = EAC Q1 € t EAC Q3 = ITD Q2 + ETC Q3 ETC Q3 Arit. = EAC Q2 - ITD Q2 ETC Q3 -> New Estimation
  • 18.
    EAC Q2 EAC Q3 ETCQ3 Arithmetical ETC Q3 ITD Q2 Q1 Q2 Q3 Q4 BAC = EAC Q1 € t ETC Q3 Arit. = EAC Q2 - ITD Q2 ETC Q3 -> New Estimation EAC Q3 = ITD Q2 + ETC Q3 Dev. EAC Q3 = EAC Q3 – EAC Q2 = Dev. Actual Q2 + Dev. Estimated Q3
  • 19.
    This process eachperiod until the end of the project
  • 20.
    Thank you verymuch for your attention robertohernantes@hotmail.com roberto.hernantes.linkedin@gmail.com