East Virtual Open House

  1. 1. Forum Forum IT’S HAPPENING, TODAY Eglinton Crosstown LRT
  2. 2. We have a strong connection with our customers, and a great understanding of who they are and where they are going. Metrolinx’s Core Business – Providing Better, Faster, Easier Service Adding More Service Today Making It Easier for Our Customers to Access Our Service Building More to Improve Service Planning for New Connections Investing in Our Future
  3. 3. MISSION: WE CONNECT COMMUNITIES VISION: GETTING YOU THERE BETTER, FASTER, EASIER
  4. 4. LAND ACKNOWLEDGEMENT Metrolinx acknowledges that it operates on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples. In particular these lands are covered by 20 Treaties, and we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a manner that is built on the foundation of trust, respect and collaboration. Metrolinx is committed to building meaningful relationships with Indigenous Peoples, and to working towards meaningful reconciliation with the original caretakers of this land.
  5. 5. Welcome Our Eastern Open House will feature the following stations and stops: • Eglinton • Mount Pleasant • Leaside • Laird • Sunnybrook Park Stop • Science Centre • Aga Khan Park & Museum and Wynford Stops • Sloane and O’Connor Stops • Pharmacy and Hakimi Lebovic Stops • Golden Mile, Birchmount, and Ionview Stops • Kennedy Station
  6. 6. 111 escalators 15.2 million job hours 273.5 km medium voltage/ direct current cable 38 two-vehicle trains 60 elevators 6000 tons of rail 208 overhead catenary system poles 5 new bridges PROJECT QUANTITIES
  7. 7. MODEL: Bombardier Flexity Freedom Overhead Catenary POWER SUPPLY: 60 KM/H on street
  8. 8. Read more about how Eglinton Crosstown will change Toronto’s cityscape here.
  9. 9. 12 Train Testing Video: Click Here
  10. 10. • The Eglinton Crosstown project is now over 80% complete. • Five stations – Mount Dennis, Keelesdale, Oakwood, Laird, and Science Centre – will reach building construction completion by the end of 2021. • 100% of track has been installed. • Vehicle testing is underway between Mount Dennis Station and Chaplin Station in the west, and between Brentcliffe Road and Ionview Road in the east. Project update Eglinton Crosstown
  11. 11. Eglinton Crosstown What to Expect: Systems and Track 2021 Progress to-date Remaining Work in 2021 • 100% of track installed. • 95% of overhead catenary system (OCS) installed. • OCS energized from Mount Dennis Station to Chaplin Station and from Laird Station to Ionview Road. • Tunnel lighting 91% complete, with work still ongoing between Avenue Station and Mount Pleasant Station. • Surface section between Sunnybrook Park Stop to Kennedy Station being used for vehicle/systems testing activities. • Static vehicle & systems testing now taking place between Caledonia Station and Chaplin Station. • Installation of track between Avenue Station and Mount Pleasant Station. • OCS installation at Cedarvale and Eglinton Stations • Fibre line installations between Cedarvale Station and Laird Station. • Installation of remaining tunnel lighting between Avenue Station and Mount Pleasant Station. • Installation of medium-voltage/direct-current (MV/DC) cables between Chaplin Station and Laird Station. • Readiness for MV/DC energization between Chaplin Station and Laird Station.
  12. 12. LRT Program Name EGLINTON STATION
  13. 13. Eglinton Crosstown What to Expect: Eglinton Station • Completed North Tunnel Ventilation Shaft concrete works • Completed all platform and concourse slab pours • Completed track installations • Completed roof construction at the Berwick Portal 2021 Progress to-date Remaining work in 2021 • Construction of the Main Entrance • Completion of concrete works within the main station box • Completion of the north platform escalator and stair construction joining TTC and ECLRT stations • Equipment installations at the Berwick Portal • Completion of utility reinstatement works • Completion of Berwick Portal construction • Architectural works within the station box and entrances • Road reinstatement and landscaping Remaining work in 2022
  14. 14. LRT Program Name MOUNT PLEASANT
  15. 15. Eglinton Crosstown What to Expect: Mount Pleasant • Station Box and Secondary Entrance structurally complete • Track and Overhead Catenary System (OCS) installations completed • Commenced testing and commissioning activities within technical rooms • Started tiling at the platform level 2021 Progress to-date Remaining work in 2021 • Completion of concrete works at the Main Entrance • Initiate train (LRV) testing • Continue utility upgrades • Architectural works within the Station Box and Entrances • Completion of architectural works • Road restoration and landscaping • Restoration of heritage façade at the Main Entrance • Completion of station construction Remaining work in 2022
  16. 16. LRT Program Name LEASIDE STATION
  17. 17. Eglinton Crosstown What to Expect: Leaside Station • Station Box and Main Entrance structurally complete • Completed track and Overhead Catenary System (OCS) installations • Completed structural steel at the Secondary Entrance • Technical rooms largely complete 2021 Progress to-date Remaining work in 2021 • Completion of concrete works at the Secondary Entrance • Initiate train (LRV) testing • Architectural works within the Station Box and Entrances • Completion of architectural works • Road restoration and landscaping • Completion of station construction • Final utility reinstatement works and road restoration Remaining work in 2022
  18. 18. LRT Program Name LAIRD STATION
  19. 19. Eglinton Crosstown What to Expect: Laird Station • Completed structural works at the Station Entrances • Completed major masonry works • Completed track and Overhead Catenary System (OCS) installation • Initiated train (LRV) testing 2021 Progress to-date Remaining work in 2021 • Completion of concrete works • Continue architectural works within the station • Continue mechanical and electrical works within the station • Continue escalator and elevator installations • Completion of architectural works • Completion of road and sidewalk restoration works • Completion of landscaping works • Completion of station construction Remaining work in 2022
  20. 20. SUNNYBROOK PARK STOP
  21. 21. Eglinton Crosstown What to Expect: Sunnybrook Park Stop 2021 Progress to-date Remaining Work in 2021 • Retaining wall landscaping • Second Brentcliffe retaining wall construction • Greentrack installation • Electrical finishes • Brentcliffe retaining wall construction completed • Second Brentcliffe retaining wall construction began • Sunnybrook Park Stop multi-use path backfill completed. Landscaping began. • West Don River Bridge waterproofing • Began dynamic testing of light rail vehicles in the east • Planters, curbs, handrails completed at Sunnybrook Stop • Track and Overhead Catenary System (OCS) completed Spring 2021 • Electrical installation work largely completed • Traffic lights installed Remaining Work in 2022 • Final Paving of Eglinton Avenue • Sunnybrook Park Stop multi-use path final restoration • North sidewalk restoration • Landscaping works • Brentcliffe soil nail wall removal
  22. 22. SCIENCE CENTRE STATION
  23. 23. Eglinton Crosstown What to Expect: Science Centre Station • Artwork installation completed • Began dynamic testing of light rail vehicles in the east • Watermain connection to city water supply completed • Removal of temporary power • Landscaping began • Installation of station signage began 2021 Progress to-date Remaining Work in 2021 Remaining Work in 2022 • Construction completion • Final paving of Eglinton Avenue • Platform signage • Tiling works • Glazing works • Completion of landscaping • Station signage installation • Electrical finishes • Architectural finishes
  24. 24. WYNFORD STOP
  25. 25. Eglinton Crosstown What to Expect: Aga Khan Park & Museum and Wynford Stops • Final Paving of Eglinton Avenue • Waterproofing of East Don River Bridge and Wynford Bridge • General landscaping • Began dynamic testing of light rail vehicles in the east • Planters, curbs, handrails completed at Aga Khan Park & Museum and Wynford Stops • Track and Overhead Catenary System (OCS) completed Spring 2021 • Electrical installation work largely completed • Traffic lights installed at Wynford Stop 2021 Progress to-date Remaining Work in 2021 • Final Paving of Eglinton Avenue • Landscaping works • Installation of greentrack • Traffic lights • North sidewalk restoration works • Electrical finishes
  26. 26. O’CONNOR STOP
  27. 27. Eglinton Crosstown What to Expect: Sloane and O’Connor Stop 2021 Progress to-date • Final Paving of Eglinton Avenue • Greentrack installed • Began dynamic testing of light rail vehicles in the east • Planters, curbs, handrails completed at Sloane and O’Connor Stops • Track and Overhead Catenary System (OCS) completed Spring 2021 • Electrical installation work largely completed • Traffic lights installed at Sloane and O’Connor Stops Remaining Work in 2021 • Watermain connection work at Credit Union Drive • Edge tile installation at O’Connor Stop • Landscaping Works • Electrical finishes • Sidewalk restoration work
  28. 28. HAKIMI LEBOVIC STOP
  29. 29. Eglinton Crosstown What to Expect: Pharmacy and Hakimi Lebovic Stops 2021 Progress to-date • Landscaping works • Final Paving of Eglinton Avenue • Began dynamic testing of light rail vehicles in the east • Planters, curbs, handrails completed at Pharmacy and Hakimi Lebovic Stops • Track and Overhead Catenary System (OCS) completed Spring 2021 • Electrical installation work largely completed • Traffic lights installed at Pharmacy and Hakimi Lebovic Stops Remaining Work in 2021 Remaining Work in 2022 • Final Paving of Eglinton Avenue – Eglinton Square • Pharmacy retaining wall removal • South sidewalk restoration • Greentrack • Electrical finishes
  30. 30. IONVIEW STOP
  31. 31. Eglinton Crosstown What to Expect: Golden Mile, Birchmount, and Ionview Stops • Final Paving of Eglinton Avenue • Greentrack installation • Massey creek backfilling and landscaping completed • Began dynamic testing of light rail vehicles in the east • Planters, curbs, handrails completed at Golden Mile, Birchmount, and Ionview Stops • Track & OCS completed Spring 2021 • Electrical installation work largely completed • Traffic lights installed at Golden Mile, Birchmount, and Ionview Stops 2021 Progress to-date Remaining Work in 2021 Remaining Work in 2022 • Final Paving of Eglinton Avenue – Birchmount – Rosemount • Edge tile installation at Ionview Stop • Sidewalk restoration work • Electrical finishes • Final Paving of Eglinton Avenue – Rosemount - Ionview • Landscaping works
  32. 32. KENNEDY STATION
  33. 33. Eglinton Crosstown What to Expect: Kennedy Station 2021 Progress to-date Remaining Work in 2021 Remaining Work in 2022 • Concrete works completed • OCS and Track installed inside station • Structural steel for Main and GO entrances installed • TVS fans installed at entrances • Jet fans inside tunnel installed • All escalators installed • All elevators inside station installed • Substantial Completion • Completion of GO platform works • Underground street lighting cable installation • Traffic lights • Elevator installation at GO platform • GO structural steel • Backfilling of GO Platforms • Decking over structural steel at GO • Transfer loads of SRT ductbanks to stationbox
  34. 34. Eglinton Crosstown • The Eglinton Crosstown LRT Project contractually requires the constructor, Crosslinx Transit Solutions Constructors (CTSC), to embed community benefits in their work, including ensuring that local communities and historically disadvantaged groups benefit directly from the province’s $5.7 billion investment • We are committed to making the pathway to Professional, Administrative and Technical (PAT) roles in the construction industry more accessible to people facing barriers to employment • CTS has hired 227 people in PAT roles to date, as well as 212 apprentices and journey persons from historically disadvantage and equity seeking groups • We are committed to supporting small and medium sized businesses along the Eglinton corridor, businesses impacted by our construction, and social enterprises that create employment and training opportunities for people who face systemic barriers to employment • CTS has spent more than $800,000 on social enterprises and more than $6 million at local businesses` Community Benefits

×