SlideShare a Scribd company logo
1 of 24
DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE INTERSECTION OF JULIUS NYERERE AND KENETH KAUNDA IN HARARE
NAME:MARLON KACHUWA
REG #:R182902R
INTRODUCTION
 Although there has been a popularity discipline of walking, it remains as the most used mode of transport daily
 Walking inevitably involves crossing a road, where the desire line of the pedestrian conflicts with the higher speed
and lesser vulnerability of motor vehicles
 According to (Department for Transport, 2004), pedestrians still comprise around a quarter of those who die in
road collisions and statistics shows that in Great Britain in 2003 over 290,000 people were killed or injured in road
traffic collisions (36,405 were pedestrians)
 According to Traffic Safety Council of Zimbabwe (TSCZ), the rate of road crash fatality has increased from 1,836
in 2016 to an average of 2,000 deaths per year – over 5 deaths per day- from 2017 to 2019
 These problems were dealt with by introducing education programmes, physical interventions, signage, road
markings and construction of footbridges.
PROBLEM STATEMENT
 THERE IS HIGH TRAFFIC FLOW AND PEDESTRIAN FLOW AT THE INTERSECTION
WHICH RESULTS IN HIGH LEVEL OF CONGESTION AND PEDESTRIAN
COLLISIONS.
 POWERCUTS IN HARARE ALSO INCREASE CHANCES OF ACCIDENTS AND
PEDESTRIAN COLLISIONS AS TRAFFIC SIGNALS WON’T BE WORKING.
 AT THE INTERSECTION, PEDESTRIANS FACES CHALLENGE OF CROSSING THE
ROAD AS THE DRIVERS WONT BE GIVING THEM RIGHT OF WAY THIS RESULTS
IN PEDESTRIANS CROSSING THE ROAD WITHOUT PAYING ATTENTION TO
TRAFFIC SIGNALS.
 SUCH ACTIONS WILL ENDANGER THE SAFETY OF PEDESTRIANS USING THE
INTERSECTION.
PROBLEM
STATEMENT CONT
THE CAPTION
SHOWS
PEDESTRIANS
USING THE
INTERSECTION.
JUSTIFICATION
 AT THE INTERSECTION OF JULIUS NYERERE AND CHARTER, A LOT OF
PEOPLE USES THAT INTERSECTION SINCE IT IS THE MAIN ROAD THAT
LEADS TO CHITUNGWIZA WHICH IS ONE OF THE BIGGEST TOWNS IN
HARARE.
 A LARGE NUMBER OF PEOPLE IN CHITUNGWIZA WORK IN CITY OF
HARARE AND USES THIS INTERSECTION TO ACCESS OTHER PARTS OF
THE CBD, HENCE THERE IS NEED TO SEPARATE THE PEDESTRIAN AND
VEHICULAR TRAFFIC AS WELL AS TO IMPROVE THE TRAFFIC FLOW AND
SAFETY OF PEDESTRIANS, AND TO BUILD A LANDMARK STRUCTURE IN
THE CITY CENTRE BY CONSTRUCTING A FOOTBRIDGE.
OBJECTIVES
MAIN OBJECTIVE
 Design of a circular composite
footbridge so as to improve safety of
pedestrians and reduce traffic
congestion by pedestrians at the
intersection of Julius Nyerere and
Charter according to the specified
standards.
1. To carry out interviews with the
pedestrians and drivers using the
intersection.
2. To carry out a traffic, pedestrian
survey at the intersection.
3. To design and analyse the composite
footbridge manually and use of
software such as Sap2000.
LITERATURE REVIEW
 WHAT IS TRAFFIC CONGESTION
 CAUSES OF TRAFFIC CONGESTION
 CAUSES OF PEDESTRIAN COLLISIONS AT INTERSECTION
 PEDESTRIAN BEHAVIOUR AND ATTITUDE WHEN CROSSING
 CASE STUDIES
 DESIGN
METHODOLOGY
OBJECTIVE METHOD
To carry out interviews with the pedestrians using the
intersection to see if the structure would serve its purpose
and to assess the causes of pedestrian collisions at
intersections and how pedestrians cause traffic
congestion.
Questions were asked to pedestrians and drivers on how
they use the intersection and how they give each other
right of way.
To carry out a pedestrian survey at the intersection. Observations were done manually, observing how
pedestrians are crossing the intersection and how drivers
behave on the intersection.
To design and analyse the composite footbridge. Use of software(SAP2000)
STUDY AREA
The caption shows the map of
Harare.
LOCATION OF
PEDESTRIAN BRIDGE
The caption shows the
intersection of Julius Nyerere
and Charter.
RESULTS AND ANALYSIS
Behaviour of Drivers
(When a driver saw a pedestrian passing the road)
Vehicle Type Total Willing To Stop Don’t want to stop
(Slow down)
Overtake
Bus 100 24 53 23
Car 100 33 21 46
Motor Cycle 100 10 19 71
Mini-bus 100 8 35 67
Pick-Up 100 27 63 10
Truck 100 36 42 22
RESULTS AND ANALYSIS
 From survey it is clear that high speedy vehicle has a tendency of overtaking. On the other-hand the large vehicle
slows down when someone cross the road.
RESULTS AND ANALYSIS
Means of Crossing the Road Number of Pedestrians Crossing
Traffic Signal 31
Pass Directly 69
RESULTS AND ANALYSIS
 The survey shows that pedestrians are less interested in crossing in waiting for traffic signals to give them right of
way. Most of them pass the road directly which is risky and hamper their safety. When they were asked about why
they do not use safer means they replied that traffic signal consumes time while crossing the road directly is
quicker.
GEOTECHNICAL RESULTS FROM CITY OF HARARE
SOIL PROFILE
TRIAL HOLE NUMBER TESTED DEPTH (MM) DESCRIPTION OF MATERIAL
1 0 – 30 Spray and Chip
30 – 120 Crusher Run
120 – 330 Brown Iron Stone
330+ Light Grey Clay
SIEVE ANALYSIS TEST
SAMPLE
NUMBE
R
DESCRIPTIO
N OF
MATERIAL
TESTED
DEPTH
(MM)
BS SIEVE SIZES (MM) % PASSING
37,5 26,5 19,0 9,5 4.75 2,36 1,18 0,600 0,300 0,150 0,075
1. LIGHT
GREY
CLAY.
1 000 - - - - - 100 99 92 94 91 89
PLASTICITY INDEX
SAMPLE
NUMBER
DESCRIPTION
OF SAMPLE
TESTED
DEPTH
(mm)
WL WP IP IC IF PP
1. LIGHT GREY
CLAY.
1000 66 21,8 44,6 0 88,7 3 956
DCP TEST
SAMPLE NUMBER TESTED DEPTH
(MM)
PENETRATION
PER BLOW
(MM)
BEARING
CAPACITY
KN/M2
(KPa)
1. 1 065 65 Less than 50
1 115 50 45
1 150 35 67
1 190 40 57
1 225 35 57
1 245 20 120
1 275 30 80
1 300 25 97
1 320 20 120
1 340 20 120
1 360 20 120
CONCLUSIONS
 The soil found were light grey clay with high plasticity index. The plasticity index is 44.6. The soils are stable at
1320mm below ground level where the safe bearing capacity is 120kPa.
 Pile foundation is recommended since the structure is going to carry heavy loads .
PRELIMINARY DESIGN/SIZING
BRIDGE GEOMETRY
CLEAR SPAN 30.1M(DIAMETER)
CHS SECTIONS 60.3x3.5
CLEAR HEIGHT 5m
WIDTH OF FOOTBRIDGE 4m
COLUMN PIER SIZE 500MM
COMPOSITE SLAB DEPTH 200MM
LOADS APPLIED ON STRUCTURE
DEAD LOADS: Selfweight of concrete+selfweight of
steel+floor finishes
LIVE LOADS 5.0KNm-2 (BS 5400-2-1978 7.1.1)
PELIMINARY SIZING
PLAN VIEW OF THE
PEDESTRIAN BRIDGE
PRLIMINARY SIZING
SECTION VIEW OF THE
PEDESTRIAN BRIDGE
THANK YOU
REFERENCES
AA Foundation For Road Safety Research, 1994. Pedestrian Activity and Accident Risk, London: University of London and Steer Davies Gleave..
Binti Kadzim, H. N., 2021. Study on Effectiveness of Pedestrian Bridge Utilization.Bachelor's Thesis, Faculty of Engineering &Earth Resources University Malysia
Pahang, Malysia: s.n.
Daff, R., Cramphorn , B., Wilson , C. J. & Neylan, J., 1991. Pedestrian Behaviour near signalised crossings. Sydney, Proceedings 16th ARRB Conference Part(4).
Department for Transport, 2004. Road Casualties Great Britain, London: TSO.
Elliot, M. A., Armitage, C. J. & Baughan, C. J., 2003. The behaviour of adoloscent road users-survey of 11-16 years old, Crowthorne: TRL Report TRL 561.
Garder, P., 1989. Pedestrian safety at traffic signals:a study carried out with the help of a traffic conflicts technique. Accident Analysis and Prevention, 20(5),
pp. 435-444.
Ghee, C. E. et al., 1994. Pedestrian behaviour and exposure to risk, s.l.: Ross Silcock Limited.
Hasan, R. & Napian, M., 2017. Influential factors and improvement proposals. In: Utilization of Footbridges. s.l.:s.n., p. 43.
Moyano, D. E., 2002. Theory of planned behaviour and pedestrians' interventions to violate traffic regulations. Transportation Research Part(5), pp. 169-175.
Preston, B., 1986. The behaviour and safety of pedestrians at Pelican crossing in Greater Manchester. TEC, pp. 596-599.
Sisiopiku , V. P. & Akin, D., 2003. Pedestrian Behaviours at perceptions towards varoius pedestrian facilities: an examination based onobservation and survey
data. Transportation Research, pp. 249-274.
Transport For London, 2004. Planning and Design for Walkin and Cycling-Consultation Draft, London: Local Transport Note 1/04.
Wall, G. T., 2000. Road markings to improve pedestrain safety at crossings. Traffic Engineering and Control, pp. 136-140.
Yagil, D., 2000. Beliefs,motives and situational factors related to pedestrians' self reported behaviour at signal controlled-crossings, s.l.: Transportation
Research Part F 3.
ZIMSTAT, 2022. 2022 Population and Housing Census Preliminary Results, Harare: Zimstat.

More Related Content

Similar to Designing a circular composite footbridge to improve pedestrian safety

Pedestrian and Bicycle facility planning for kochi city region, part 2 data ...
Pedestrian and Bicycle facility planning for kochi city region, part 2  data ...Pedestrian and Bicycle facility planning for kochi city region, part 2  data ...
Pedestrian and Bicycle facility planning for kochi city region, part 2 data ...Arun Chandra Babu
 
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...inventionjournals
 
Stirling Regional Centre Modelling
Stirling Regional Centre ModellingStirling Regional Centre Modelling
Stirling Regional Centre ModellingJumpingJaq
 
Introduction When highway planners examine ways to improve the.pdf
Introduction When highway planners examine ways to improve the.pdfIntroduction When highway planners examine ways to improve the.pdf
Introduction When highway planners examine ways to improve the.pdfsdfghj21
 
PHYS102 Introduction To Electromagnetism.docx
PHYS102 Introduction To Electromagnetism.docxPHYS102 Introduction To Electromagnetism.docx
PHYS102 Introduction To Electromagnetism.docxwrite5
 
Traffic at urban road junctions
Traffic at urban road junctionsTraffic at urban road junctions
Traffic at urban road junctionsDasun_Ransiri
 
[Transportation] 2. kulrathna(colombo)
[Transportation] 2. kulrathna(colombo)[Transportation] 2. kulrathna(colombo)
[Transportation] 2. kulrathna(colombo)shrdcinfo
 
Quality and safety assesment of pedestrians sidewalk in panipat city
Quality and safety assesment of pedestrians sidewalk in panipat cityQuality and safety assesment of pedestrians sidewalk in panipat city
Quality and safety assesment of pedestrians sidewalk in panipat citykaran verma
 
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONS
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONSMODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONS
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONSIRJET Journal
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 
Road User priorities July 2015
Road User priorities July 2015Road User priorities July 2015
Road User priorities July 2015Dr Douglas Dalziel
 
Safety assessment of pedestrian at intersection.pptx
Safety assessment of pedestrian at intersection.pptxSafety assessment of pedestrian at intersection.pptx
Safety assessment of pedestrian at intersection.pptxTanupriyaPatel
 
Effland.presentation
Effland.presentationEffland.presentation
Effland.presentationTrailnet
 
Presentation on road network 1
Presentation on road network 1 Presentation on road network 1
Presentation on road network 1 LAWAL SANI
 
MANIDEEPA BAIDYA DISSERTATION
MANIDEEPA BAIDYA DISSERTATIONMANIDEEPA BAIDYA DISSERTATION
MANIDEEPA BAIDYA DISSERTATIONMANIDEEPA BAIDYA
 
IRJET- Appraisal and Design of Foot Over Bridge
IRJET- Appraisal and Design of Foot Over BridgeIRJET- Appraisal and Design of Foot Over Bridge
IRJET- Appraisal and Design of Foot Over BridgeIRJET Journal
 
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...IRJET Journal
 

Similar to Designing a circular composite footbridge to improve pedestrian safety (20)

Pedestrian and Bicycle facility planning for kochi city region, part 2 data ...
Pedestrian and Bicycle facility planning for kochi city region, part 2  data ...Pedestrian and Bicycle facility planning for kochi city region, part 2  data ...
Pedestrian and Bicycle facility planning for kochi city region, part 2 data ...
 
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
 
Bx33454457
Bx33454457Bx33454457
Bx33454457
 
Bx33454457
Bx33454457Bx33454457
Bx33454457
 
Stirling Regional Centre Modelling
Stirling Regional Centre ModellingStirling Regional Centre Modelling
Stirling Regional Centre Modelling
 
Introduction When highway planners examine ways to improve the.pdf
Introduction When highway planners examine ways to improve the.pdfIntroduction When highway planners examine ways to improve the.pdf
Introduction When highway planners examine ways to improve the.pdf
 
PHYS102 Introduction To Electromagnetism.docx
PHYS102 Introduction To Electromagnetism.docxPHYS102 Introduction To Electromagnetism.docx
PHYS102 Introduction To Electromagnetism.docx
 
Traffic at urban road junctions
Traffic at urban road junctionsTraffic at urban road junctions
Traffic at urban road junctions
 
[Transportation] 2. kulrathna(colombo)
[Transportation] 2. kulrathna(colombo)[Transportation] 2. kulrathna(colombo)
[Transportation] 2. kulrathna(colombo)
 
Quality and safety assesment of pedestrians sidewalk in panipat city
Quality and safety assesment of pedestrians sidewalk in panipat cityQuality and safety assesment of pedestrians sidewalk in panipat city
Quality and safety assesment of pedestrians sidewalk in panipat city
 
Masters Dissertation Posters 2016
Masters Dissertation Posters 2016Masters Dissertation Posters 2016
Masters Dissertation Posters 2016
 
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONS
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONSMODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONS
MODELLING OF PEDESTRIAN GAP ACCEPTANCE BEHAVIOUR AT UNCONTROLLED INTERSECTIONS
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
Road User priorities July 2015
Road User priorities July 2015Road User priorities July 2015
Road User priorities July 2015
 
Safety assessment of pedestrian at intersection.pptx
Safety assessment of pedestrian at intersection.pptxSafety assessment of pedestrian at intersection.pptx
Safety assessment of pedestrian at intersection.pptx
 
Effland.presentation
Effland.presentationEffland.presentation
Effland.presentation
 
Presentation on road network 1
Presentation on road network 1 Presentation on road network 1
Presentation on road network 1
 
MANIDEEPA BAIDYA DISSERTATION
MANIDEEPA BAIDYA DISSERTATIONMANIDEEPA BAIDYA DISSERTATION
MANIDEEPA BAIDYA DISSERTATION
 
IRJET- Appraisal and Design of Foot Over Bridge
IRJET- Appraisal and Design of Foot Over BridgeIRJET- Appraisal and Design of Foot Over Bridge
IRJET- Appraisal and Design of Foot Over Bridge
 
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...
IRJET- A Review Paper on Automatic Traffic Control System to Reduce Accidents...
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Designing a circular composite footbridge to improve pedestrian safety

  • 1. DESIGN OF A CIRCULAR COMPOSITE FOOTBRIDGE AT THE INTERSECTION OF JULIUS NYERERE AND KENETH KAUNDA IN HARARE NAME:MARLON KACHUWA REG #:R182902R
  • 2. INTRODUCTION  Although there has been a popularity discipline of walking, it remains as the most used mode of transport daily  Walking inevitably involves crossing a road, where the desire line of the pedestrian conflicts with the higher speed and lesser vulnerability of motor vehicles  According to (Department for Transport, 2004), pedestrians still comprise around a quarter of those who die in road collisions and statistics shows that in Great Britain in 2003 over 290,000 people were killed or injured in road traffic collisions (36,405 were pedestrians)  According to Traffic Safety Council of Zimbabwe (TSCZ), the rate of road crash fatality has increased from 1,836 in 2016 to an average of 2,000 deaths per year – over 5 deaths per day- from 2017 to 2019  These problems were dealt with by introducing education programmes, physical interventions, signage, road markings and construction of footbridges.
  • 3. PROBLEM STATEMENT  THERE IS HIGH TRAFFIC FLOW AND PEDESTRIAN FLOW AT THE INTERSECTION WHICH RESULTS IN HIGH LEVEL OF CONGESTION AND PEDESTRIAN COLLISIONS.  POWERCUTS IN HARARE ALSO INCREASE CHANCES OF ACCIDENTS AND PEDESTRIAN COLLISIONS AS TRAFFIC SIGNALS WON’T BE WORKING.  AT THE INTERSECTION, PEDESTRIANS FACES CHALLENGE OF CROSSING THE ROAD AS THE DRIVERS WONT BE GIVING THEM RIGHT OF WAY THIS RESULTS IN PEDESTRIANS CROSSING THE ROAD WITHOUT PAYING ATTENTION TO TRAFFIC SIGNALS.  SUCH ACTIONS WILL ENDANGER THE SAFETY OF PEDESTRIANS USING THE INTERSECTION.
  • 5. JUSTIFICATION  AT THE INTERSECTION OF JULIUS NYERERE AND CHARTER, A LOT OF PEOPLE USES THAT INTERSECTION SINCE IT IS THE MAIN ROAD THAT LEADS TO CHITUNGWIZA WHICH IS ONE OF THE BIGGEST TOWNS IN HARARE.  A LARGE NUMBER OF PEOPLE IN CHITUNGWIZA WORK IN CITY OF HARARE AND USES THIS INTERSECTION TO ACCESS OTHER PARTS OF THE CBD, HENCE THERE IS NEED TO SEPARATE THE PEDESTRIAN AND VEHICULAR TRAFFIC AS WELL AS TO IMPROVE THE TRAFFIC FLOW AND SAFETY OF PEDESTRIANS, AND TO BUILD A LANDMARK STRUCTURE IN THE CITY CENTRE BY CONSTRUCTING A FOOTBRIDGE.
  • 6. OBJECTIVES MAIN OBJECTIVE  Design of a circular composite footbridge so as to improve safety of pedestrians and reduce traffic congestion by pedestrians at the intersection of Julius Nyerere and Charter according to the specified standards. 1. To carry out interviews with the pedestrians and drivers using the intersection. 2. To carry out a traffic, pedestrian survey at the intersection. 3. To design and analyse the composite footbridge manually and use of software such as Sap2000.
  • 7. LITERATURE REVIEW  WHAT IS TRAFFIC CONGESTION  CAUSES OF TRAFFIC CONGESTION  CAUSES OF PEDESTRIAN COLLISIONS AT INTERSECTION  PEDESTRIAN BEHAVIOUR AND ATTITUDE WHEN CROSSING  CASE STUDIES  DESIGN
  • 8. METHODOLOGY OBJECTIVE METHOD To carry out interviews with the pedestrians using the intersection to see if the structure would serve its purpose and to assess the causes of pedestrian collisions at intersections and how pedestrians cause traffic congestion. Questions were asked to pedestrians and drivers on how they use the intersection and how they give each other right of way. To carry out a pedestrian survey at the intersection. Observations were done manually, observing how pedestrians are crossing the intersection and how drivers behave on the intersection. To design and analyse the composite footbridge. Use of software(SAP2000)
  • 9. STUDY AREA The caption shows the map of Harare.
  • 10. LOCATION OF PEDESTRIAN BRIDGE The caption shows the intersection of Julius Nyerere and Charter.
  • 11. RESULTS AND ANALYSIS Behaviour of Drivers (When a driver saw a pedestrian passing the road) Vehicle Type Total Willing To Stop Don’t want to stop (Slow down) Overtake Bus 100 24 53 23 Car 100 33 21 46 Motor Cycle 100 10 19 71 Mini-bus 100 8 35 67 Pick-Up 100 27 63 10 Truck 100 36 42 22
  • 12. RESULTS AND ANALYSIS  From survey it is clear that high speedy vehicle has a tendency of overtaking. On the other-hand the large vehicle slows down when someone cross the road.
  • 13. RESULTS AND ANALYSIS Means of Crossing the Road Number of Pedestrians Crossing Traffic Signal 31 Pass Directly 69
  • 14. RESULTS AND ANALYSIS  The survey shows that pedestrians are less interested in crossing in waiting for traffic signals to give them right of way. Most of them pass the road directly which is risky and hamper their safety. When they were asked about why they do not use safer means they replied that traffic signal consumes time while crossing the road directly is quicker.
  • 15. GEOTECHNICAL RESULTS FROM CITY OF HARARE SOIL PROFILE TRIAL HOLE NUMBER TESTED DEPTH (MM) DESCRIPTION OF MATERIAL 1 0 – 30 Spray and Chip 30 – 120 Crusher Run 120 – 330 Brown Iron Stone 330+ Light Grey Clay
  • 16. SIEVE ANALYSIS TEST SAMPLE NUMBE R DESCRIPTIO N OF MATERIAL TESTED DEPTH (MM) BS SIEVE SIZES (MM) % PASSING 37,5 26,5 19,0 9,5 4.75 2,36 1,18 0,600 0,300 0,150 0,075 1. LIGHT GREY CLAY. 1 000 - - - - - 100 99 92 94 91 89
  • 17. PLASTICITY INDEX SAMPLE NUMBER DESCRIPTION OF SAMPLE TESTED DEPTH (mm) WL WP IP IC IF PP 1. LIGHT GREY CLAY. 1000 66 21,8 44,6 0 88,7 3 956
  • 18. DCP TEST SAMPLE NUMBER TESTED DEPTH (MM) PENETRATION PER BLOW (MM) BEARING CAPACITY KN/M2 (KPa) 1. 1 065 65 Less than 50 1 115 50 45 1 150 35 67 1 190 40 57 1 225 35 57 1 245 20 120 1 275 30 80 1 300 25 97 1 320 20 120 1 340 20 120 1 360 20 120
  • 19. CONCLUSIONS  The soil found were light grey clay with high plasticity index. The plasticity index is 44.6. The soils are stable at 1320mm below ground level where the safe bearing capacity is 120kPa.  Pile foundation is recommended since the structure is going to carry heavy loads .
  • 20. PRELIMINARY DESIGN/SIZING BRIDGE GEOMETRY CLEAR SPAN 30.1M(DIAMETER) CHS SECTIONS 60.3x3.5 CLEAR HEIGHT 5m WIDTH OF FOOTBRIDGE 4m COLUMN PIER SIZE 500MM COMPOSITE SLAB DEPTH 200MM LOADS APPLIED ON STRUCTURE DEAD LOADS: Selfweight of concrete+selfweight of steel+floor finishes LIVE LOADS 5.0KNm-2 (BS 5400-2-1978 7.1.1)
  • 21. PELIMINARY SIZING PLAN VIEW OF THE PEDESTRIAN BRIDGE
  • 22. PRLIMINARY SIZING SECTION VIEW OF THE PEDESTRIAN BRIDGE
  • 24. REFERENCES AA Foundation For Road Safety Research, 1994. Pedestrian Activity and Accident Risk, London: University of London and Steer Davies Gleave.. Binti Kadzim, H. N., 2021. Study on Effectiveness of Pedestrian Bridge Utilization.Bachelor's Thesis, Faculty of Engineering &Earth Resources University Malysia Pahang, Malysia: s.n. Daff, R., Cramphorn , B., Wilson , C. J. & Neylan, J., 1991. Pedestrian Behaviour near signalised crossings. Sydney, Proceedings 16th ARRB Conference Part(4). Department for Transport, 2004. Road Casualties Great Britain, London: TSO. Elliot, M. A., Armitage, C. J. & Baughan, C. J., 2003. The behaviour of adoloscent road users-survey of 11-16 years old, Crowthorne: TRL Report TRL 561. Garder, P., 1989. Pedestrian safety at traffic signals:a study carried out with the help of a traffic conflicts technique. Accident Analysis and Prevention, 20(5), pp. 435-444. Ghee, C. E. et al., 1994. Pedestrian behaviour and exposure to risk, s.l.: Ross Silcock Limited. Hasan, R. & Napian, M., 2017. Influential factors and improvement proposals. In: Utilization of Footbridges. s.l.:s.n., p. 43. Moyano, D. E., 2002. Theory of planned behaviour and pedestrians' interventions to violate traffic regulations. Transportation Research Part(5), pp. 169-175. Preston, B., 1986. The behaviour and safety of pedestrians at Pelican crossing in Greater Manchester. TEC, pp. 596-599. Sisiopiku , V. P. & Akin, D., 2003. Pedestrian Behaviours at perceptions towards varoius pedestrian facilities: an examination based onobservation and survey data. Transportation Research, pp. 249-274. Transport For London, 2004. Planning and Design for Walkin and Cycling-Consultation Draft, London: Local Transport Note 1/04. Wall, G. T., 2000. Road markings to improve pedestrain safety at crossings. Traffic Engineering and Control, pp. 136-140. Yagil, D., 2000. Beliefs,motives and situational factors related to pedestrians' self reported behaviour at signal controlled-crossings, s.l.: Transportation Research Part F 3. ZIMSTAT, 2022. 2022 Population and Housing Census Preliminary Results, Harare: Zimstat.