SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
       Public Private Partnership
              Industry Workshop

                                        July 6, 2009
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



  Doyle Drive Overview
Project Purpose
Environmental Approval
Project Setting
Early Schedule
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



               Project Setting




Location Map
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
                Project Purpose and
             Environmental Approval
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



            Project Purpose

“Improve the seismic, structural, and
traffic safety of the roadway within the
setting and context of the Presidio of
San Francisco and its purpose as a
National Park.”
- Doyle Drive EIS/R
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Project Consensus


FHWA

     Doyle Drive Subcommittee
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



   Environmental Process

2000                  Initiate Environmental Process
2003                  Introduce Parkway Concept
2005                  Circulate Draft EIS/R
October 2008          Release Final EIS/R
January 2009          Record of Decision
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



 The Presidio
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Why Replace Doyle Drive?
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                Presidio Parkway




Replace deficient facility             Two new tunnels
Wide landscaped median                 New direct access to Presidio
Continuous shoulders
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Presidio Parkway
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                  Original Project Timeline

                                    Preferred Alt           Fall 2010
           Feb.                         Sept.
           2000                Dec.                                     Winter     Spring
                                        2006
  Summer                       2005               Dec                               2014
                                                                         2011
   2000                                           2008


                                                          Detailed Design
       Environmental                                        Completed               Project
                           Draft ESI/EIR                                           Complete
       Studies begin      Public Comment         Final              Construction
     ID                       Begins            EIS/EIR                Start
Alternatives
Begin Prelim
Engineering
                            Draft              Final              Start
                           EIS/EIR            EIS/EIR          Construction
                        For Comment            ROD

        = Milestones Completed
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
                             Project Status
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
    Project Description and Status
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



     Presentation Overview


Project Acceleration
Project Description
Conditions, Constraints, Limitations
Maintenance Requirements
Operations Requirements
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



        Project Acceleration

To achieve seismic safety earlier (Feb. 2011)
To reduce risk of cost growth
To meet Economic Stimulus timetable
To take advantage of the favorable market
conditions
Help create jobs and support the local and
regional economy
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                     Contracts
Pre-Construction Contracts:
Contract 1: Environmental mitigation (Built-Environmental Treatment
Plan) – Active through roadway contracts
Contract 2: Utility Plan and Relocation
Roadway Construction Contracts:
Contract 3: Southbound Presidio Interchange/High Viaduct
Contract 4: Southbound Battery Tunnel and At-Grade Detour
           P3 Contracts:
Contract 5: Girard Interchange, Low Viaduct
Contract 6: Northbound Battery Tunnel, Main Post Tunnels
Contract 7: Northbound Presidio Interchange/High Viaduct
Contract 8: Landscaping
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                   DRAFT Schedule
                                                      Seismic Safety
                                                      Achieved – Feb
                                                           2011
 Contract 1

R/W Activities

Contract 2                                                             Roadway
                                                                      Complete –
 Contract 3
                                                                       Late 2012
 Contract 4

Contract 5

Contract 6

Contract 7
                 P3
Contract 8

                 Original Project Schedule Completion – Spring 2014
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                                 Existing Site
Golden Gate Bridge Toll Plaza




                                      We are here.

          National Historic Park
          Historic Buildings
          Former Army Base
          Presidio Trust
          South Access to Golden Gate Bridge
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Contract No. 3 – SB Presidio Interchange




 Construction Capital $ 130 Million
 Begin/End Construction: Oct 2009 - Summer 2011
 Design – 100% complete
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

Contract No. 4 – Southbound Battery
 Tunnel/Temporary at-grade detour




 Construction Capital $ 110 Million
 Begin/End Construction: Dec. 2009 – Summer 2011
 Traffic Shift for Seismic Safety – February 2011
 Design – 95% complete
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
         Construction Contracts for
                   P3 Procurement
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



    Contract No. 5 – Tunnels




Construction Capital $ 233 Million
Begin/End Construction: Summer 2011- Early 2013
Design – 50% complete
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Contract No. 6 – Girard Interchange




Construction Capital $144 Million
Begin/End Construction: Summer 2011 – Early 2013
Design – 50% complete
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Contract No. 7 – NB Presidio Interchange




 Construction Capital $103 Million
 Begin/End Construction: Summer 2011 - Early 2013
 Design – 55% complete
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Contract No. 8 – Landscaping




Construction Capital $ 9 Million
Begin/End: Early 2013 – 2016
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
                 Constraints, Conditions,
                              Limitations
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



    Fixed Design Elements
Horizontal and vertical alignments
 Cross-sections (lane and shoulder widths,
horizontal clearances)
Design Exceptions
Tunnel limits and portal shape
 High Viaduct: Aesthetic, span
lengths/column location and structure type.
Fire Life Safety requirements for Tunnel
Contract 3 and 4 completed facility tie-ins.
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



     Fixed Design Elements
ST-10 Barrier
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



Environmental/Regulatory Requirements

  Final Environmental Impact Report/Statement (FEIR/S)
  Record of Decision
   Programmatic Agreement / Section 106
   Water Quality Certification (RWQCB)
   Nationwide Permit (USACOE)
   Wetland Mitigation Monitoring Program
   General Biological Monitoring Program
  Migratory Bird Act
  Bay Conservation and Development Commission (BCDC)
  requirements
  National Pollution Discharge Elimination System (NPDES)
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
                             Maintenance
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



   Maintenance - Roadway

Highway Signs and Traffic Control Devices
Pavement Striping and Delineation
Sweeping
Removal of all Debris and Objects
Drainage
Pavement
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



   Maintenance - Roadside

Landscape
Guard Rail, Safety Devices, Bridge Rail
Maintenance
Tunnels
Pumping Plants
Electric and Mechanical Substations
Lighting
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



    Maintenance - Facility

Structures
Substructures and superstructures
Graffiti Removal
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




DOYLE DRIVE
                                  Operations
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



             Operations
Day-To-Day Coordination:

Caltrans/CHP Transportation Management Center
(24/7/365 )
Bay Area 511 Traveler Information
City/County of San Francisco:
   Signals & roadway maintenance
Golden Gate Bridge & Highway District:
   Incident management & roadway maintenance
CHP: Homeland Security
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



                Operations
Traffic Control:
Roadway/Lane Closure Charts
Seven days advance request
Approval process
Late pick-up penalties

Incident Management:
Tow Service:
  Project Limits + Approaches on Park Presidio (Hwy 1), Lombard
  Street, Marina Boulevard
  TBD in coordination with:
   • Golden Gate Bridge
   • Bay Area Freeway Service Freeway Service Program
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE



            Operations
Other Coordination Required for:


Encroachment Permits: Utilities, Filming,
Special Events


Transportation Permits: Extra-Legal Loads
& Commercial Vehicles


Safety & Operational Investigations
SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE




       Questions?

Dd P3 Wkshp Project Overview 0709

  • 1.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE
  • 2.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Public Private Partnership Industry Workshop July 6, 2009
  • 3.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Doyle Drive Overview Project Purpose Environmental Approval Project Setting Early Schedule
  • 4.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Project Setting Location Map
  • 5.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Project Purpose and Environmental Approval
  • 6.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Project Purpose “Improve the seismic, structural, and traffic safety of the roadway within the setting and context of the Presidio of San Francisco and its purpose as a National Park.” - Doyle Drive EIS/R
  • 7.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Project Consensus FHWA Doyle Drive Subcommittee
  • 8.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Environmental Process 2000 Initiate Environmental Process 2003 Introduce Parkway Concept 2005 Circulate Draft EIS/R October 2008 Release Final EIS/R January 2009 Record of Decision
  • 9.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE The Presidio
  • 10.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Why Replace Doyle Drive?
  • 11.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Presidio Parkway Replace deficient facility Two new tunnels Wide landscaped median New direct access to Presidio Continuous shoulders
  • 12.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Presidio Parkway
  • 13.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Original Project Timeline Preferred Alt Fall 2010 Feb. Sept. 2000 Dec. Winter Spring 2006 Summer 2005 Dec 2014 2011 2000 2008 Detailed Design Environmental Completed Project Draft ESI/EIR Complete Studies begin Public Comment Final Construction ID Begins EIS/EIR Start Alternatives Begin Prelim Engineering Draft Final Start EIS/EIR EIS/EIR Construction For Comment ROD = Milestones Completed
  • 14.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Project Status
  • 15.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Project Description and Status
  • 16.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Presentation Overview Project Acceleration Project Description Conditions, Constraints, Limitations Maintenance Requirements Operations Requirements
  • 17.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Project Acceleration To achieve seismic safety earlier (Feb. 2011) To reduce risk of cost growth To meet Economic Stimulus timetable To take advantage of the favorable market conditions Help create jobs and support the local and regional economy
  • 18.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contracts Pre-Construction Contracts: Contract 1: Environmental mitigation (Built-Environmental Treatment Plan) – Active through roadway contracts Contract 2: Utility Plan and Relocation Roadway Construction Contracts: Contract 3: Southbound Presidio Interchange/High Viaduct Contract 4: Southbound Battery Tunnel and At-Grade Detour P3 Contracts: Contract 5: Girard Interchange, Low Viaduct Contract 6: Northbound Battery Tunnel, Main Post Tunnels Contract 7: Northbound Presidio Interchange/High Viaduct Contract 8: Landscaping
  • 19.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DRAFT Schedule Seismic Safety Achieved – Feb 2011 Contract 1 R/W Activities Contract 2 Roadway Complete – Contract 3 Late 2012 Contract 4 Contract 5 Contract 6 Contract 7 P3 Contract 8 Original Project Schedule Completion – Spring 2014
  • 20.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Existing Site Golden Gate Bridge Toll Plaza We are here. National Historic Park Historic Buildings Former Army Base Presidio Trust South Access to Golden Gate Bridge
  • 21.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 3 – SB Presidio Interchange Construction Capital $ 130 Million Begin/End Construction: Oct 2009 - Summer 2011 Design – 100% complete
  • 22.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 4 – Southbound Battery Tunnel/Temporary at-grade detour Construction Capital $ 110 Million Begin/End Construction: Dec. 2009 – Summer 2011 Traffic Shift for Seismic Safety – February 2011 Design – 95% complete
  • 23.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Construction Contracts for P3 Procurement
  • 24.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 5 – Tunnels Construction Capital $ 233 Million Begin/End Construction: Summer 2011- Early 2013 Design – 50% complete
  • 25.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 6 – Girard Interchange Construction Capital $144 Million Begin/End Construction: Summer 2011 – Early 2013 Design – 50% complete
  • 26.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 7 – NB Presidio Interchange Construction Capital $103 Million Begin/End Construction: Summer 2011 - Early 2013 Design – 55% complete
  • 27.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Contract No. 8 – Landscaping Construction Capital $ 9 Million Begin/End: Early 2013 – 2016
  • 28.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Constraints, Conditions, Limitations
  • 29.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Fixed Design Elements Horizontal and vertical alignments Cross-sections (lane and shoulder widths, horizontal clearances) Design Exceptions Tunnel limits and portal shape High Viaduct: Aesthetic, span lengths/column location and structure type. Fire Life Safety requirements for Tunnel Contract 3 and 4 completed facility tie-ins.
  • 30.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Fixed Design Elements ST-10 Barrier
  • 31.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Environmental/Regulatory Requirements Final Environmental Impact Report/Statement (FEIR/S) Record of Decision Programmatic Agreement / Section 106 Water Quality Certification (RWQCB) Nationwide Permit (USACOE) Wetland Mitigation Monitoring Program General Biological Monitoring Program Migratory Bird Act Bay Conservation and Development Commission (BCDC) requirements National Pollution Discharge Elimination System (NPDES)
  • 32.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Maintenance
  • 33.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Maintenance - Roadway Highway Signs and Traffic Control Devices Pavement Striping and Delineation Sweeping Removal of all Debris and Objects Drainage Pavement
  • 34.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Maintenance - Roadside Landscape Guard Rail, Safety Devices, Bridge Rail Maintenance Tunnels Pumping Plants Electric and Mechanical Substations Lighting
  • 35.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Maintenance - Facility Structures Substructures and superstructures Graffiti Removal
  • 36.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE DOYLE DRIVE Operations
  • 37.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Operations Day-To-Day Coordination: Caltrans/CHP Transportation Management Center (24/7/365 ) Bay Area 511 Traveler Information City/County of San Francisco: Signals & roadway maintenance Golden Gate Bridge & Highway District: Incident management & roadway maintenance CHP: Homeland Security
  • 38.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Operations Traffic Control: Roadway/Lane Closure Charts Seven days advance request Approval process Late pick-up penalties Incident Management: Tow Service: Project Limits + Approaches on Park Presidio (Hwy 1), Lombard Street, Marina Boulevard TBD in coordination with: • Golden Gate Bridge • Bay Area Freeway Service Freeway Service Program
  • 39.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Operations Other Coordination Required for: Encroachment Permits: Utilities, Filming, Special Events Transportation Permits: Extra-Legal Loads & Commercial Vehicles Safety & Operational Investigations
  • 40.
    SOUTH ACCESS TOTHE GOLDEN GATE BRIDGE – DOYLE DRIVE Questions?