Who I am …
Global Engineering Project Manager; PMP certified, Registered Professional Engineer
Award-winning team leader, coach, and mentor with extensive experience in every phase of Project Management from proposal preparation to project execution to project close and resolution of warranty issues. Supervised engineering teams and installation contractors. Excellent track record in project schedule, budget, risk, and scope management. Strong scope, risk and schedule manager with the ability to work well with all levels of project teams across divisional lines. Excellent verbal and written communication skills.
Awards and Recognition …
Awarded 4 ‘Golden Gobs’ for unsolicited customer praise with SmartSignal.
Closed projects under budget for 12 consecutive years with United Conveyor.
Achieved 95+ % customer satisfaction with United Conveyor.
Awarded patent #4,932,985 for new electro-mechanical device with Midwest Power.
What I do …
Manage electro-Mechanical project teams plus Controls, IT, and Software Project Managers from project conception through proposal preparation, management acceptance, design, fabrication and assembly, installation and commissioning including sub-contractor specification, selection, and work site supervision. Put my feet in the customer’s shoes and see things from their perspective. My management style is collaborative; letting team members exhibit strengths while helping them develop new abilities.
How I add value …
Perform Budgeting and CPM scheduling, controlling scope, schedule, and budget
Manage project teams
Establish Resource assignment & leveling methods
Develop and implement standard project status reporting tools
Manage product development projects
Negotiate and secure site permitting
Execute projects from $5 thousand to $32+ million
Successfully interface with Customers, contractors, and consultants in North America, Europe, and Asia
A bit about Project Management …
A wise man once said that Project Management was 80% Project Management skills developed over a long period of time and 20% engineering knowledge easily learned in a short while.
Techniques for developing a cost-effective expansion will be presented. The key is advanced planning and evaluating constructability. The limiting large equipment capacity will be determined using process heat and material balance simulations and rating of the equipment. Once bottlenecks are determined, the rest of the facility can be revamped. Heat pinch will be used in the heat exchanger trains as heat input is usually the limiting item. A crude, vacuum and delayed coker complex expansion will be provided as an example.
Attendees will be provided with a step-by-step procedure on how to get more capacity, reduce energy usage or improve product quality from a unit or complex. Process simulations, equipment rating by computer evaluations, hydraulics, cost-estimates at the fel-0 conceptual, fel-1 factored and fel-2 take-off level will be provided. A process complex featuring three different types of units will be used as an example.
Managers of complex energy projects struggle with delivering project performance even with implementing proven project management practices, including change management, risk management, and interface management. This presentation discusses a new approach that gives project teams a higher level of oversight, enabling more informed decisions and leading to improved project efficiency.
This presentation will highlight the major causes of cost overrun in megaprojects, and, with a focus on interface management as a recently adopted best practice, it will discuss:
The features and elements of interface management best practice,
Its correlation with other management practices, and
How these practices can be connected to interface management in a novel way to boost project compliance and efficiency.
Techniques for developing a cost-effective expansion will be presented. The key is advanced planning and evaluating constructability. The limiting large equipment capacity will be determined using process heat and material balance simulations and rating of the equipment. Once bottlenecks are determined, the rest of the facility can be revamped. Heat pinch will be used in the heat exchanger trains as heat input is usually the limiting item. A crude, vacuum and delayed coker complex expansion will be provided as an example.
Attendees will be provided with a step-by-step procedure on how to get more capacity, reduce energy usage or improve product quality from a unit or complex. Process simulations, equipment rating by computer evaluations, hydraulics, cost-estimates at the fel-0 conceptual, fel-1 factored and fel-2 take-off level will be provided. A process complex featuring three different types of units will be used as an example.
Managers of complex energy projects struggle with delivering project performance even with implementing proven project management practices, including change management, risk management, and interface management. This presentation discusses a new approach that gives project teams a higher level of oversight, enabling more informed decisions and leading to improved project efficiency.
This presentation will highlight the major causes of cost overrun in megaprojects, and, with a focus on interface management as a recently adopted best practice, it will discuss:
The features and elements of interface management best practice,
Its correlation with other management practices, and
How these practices can be connected to interface management in a novel way to boost project compliance and efficiency.
• With 11 years’ experience as effective project Leader more than 5 years’ experience on handling AO and SI projects successfully as Project managing while leading all phase’s delivery with diverse technologies and almost 7 years closely working with Oracle technology level while driving with functional knowledge on Finance- risk and compliance, Resources & Utilities , CMT and Retail. Rigorous working knowledge and trained on PMP, ITIL process & Strategy Management process from IIM-B.
• With 11 years’ experience as effective project Leader more than 5 years’ experience on handling AO and SI projects successfully as Project managing while leading all phase’s delivery with diverse technologies and almost 7 years closely working with Oracle technology level while driving with functional knowledge on Finance- risk and compliance, Resources & Utilities , CMT and Retail. Rigorous working knowledge and trained on PMP, ITIL process & Strategy Management process from IIM-B.
• With 11 years’ experience as effective project Leader more than 5 years’ experience on handling AO and SI projects successfully as Project managing while leading all phase’s delivery with diverse technologies and almost 7 years closely working with Oracle technology level while driving with functional knowledge on Finance- risk and compliance, Resources & Utilities , CMT and Retail. Rigorous working knowledge and trained on PMP, ITIL process & Strategy Management process from IIM-B.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
1. 1
Dave Parta, P. E., PMP
Naperville, IL 60540
http://www.linkedin.com/in/daveparta
+1-630-297-2899
DLParta@UMich.edu
Senior International Project Manager
CAREER SUMMARY
Award-winning team leader, coach, and mentor with extensive experience in every phase of Project
Management from proposal preparation to project execution to project close and resolution of warranty issues.
Supervised engineering teams and installation contractors. Excellent track record in project schedule, budget,
risk, and scope management. Strong scope, risk and schedule manager with the ability to work well with all
levels of project teams across divisional lines. Excellent verbal and written communication skills.
SKILLS
Ensuring complete communication at all levels is the prime objective of the best project managers.
Team leader, coach, and mentor in every phase of Project Engineering and Management from proposal
preparation to project design, procurement, fabrication, installation, and commissioning to project close
and resolution of warranty issues.
Project schedule, budget, risk, and scope management and control
Works well with all levels of project teams across divisional lines and internationally
Verbal and written communication skills
Client relationship building
Engineering problem solver and strategic innovative thinker
Cross cultural interaction
Multiple concurrent projects
AWARDS & RECOGNITION
Awarded 4 ‘Golden Gobs’ for unsolicited customer praise with SmartSignal
Closed contracts under budget for 12 consecutive years with United Conveyor
Achieved 95+ % customer satisfaction with United Conveyor
Awarded patent for new device with Midwest Power
WORK EXPERIENCE
WestSpring International, Naperville, IL Ongoing
Principal / Managing Director
General Project Manager on consulting assignments in the Project arena.
Perform Budgeting and CPM scheduling, controlling scope, schedule, and budget
Manage project teams
Establish Resource assignment & leveling
Develop and implement standard project status reporting tools
Owner’s Engineer of Record
Negotiate and secure site permitting
Perform Project Engineering
Execute projects from $5 thousand to $32+ million
Successfully interface with Customers, contractors, and consultants in North America and Asia
2. 2
TGW Systems, Inc., Grand Rapids, MI 2015 to 2016
Senior Project Manager in the System Integration Group for this Global Automated Storage and Retrieval
Systems firm.
General Project Manager for a $25 million automated storage and retrieval Distribution Center.
Primary interface with customers.
Managed project budget and spending.
Facilitated communication at all levels.
Coordinated craft labor efforts, managed contract changes, facilitated permit issuance.
Defined and managed scope, schedule, and quality.
Monitored and documented project status.
Fortna, Inc., Reading, PA 2013 to 2014
Project Director in the Material Handling Services Group for this Global Distribution Logistics firm.
Negotiated separation of building permit from equipment permit with local authorities.
Managed scope, schedule, and quality.
Oversaw general contractors.
Crunched installation schedules to meet early completion deadlines.
Obtained competitive vendor pricing.
Commissioning Agents, Inc., Indianapolis, IN 2012 to 2013
Commissioning Engineer/Project Manager for this global provider of engineering, automation, technical
and consulting services that support manufacturing operations and capital project delivery primarily in the
Pharmaceutical and biotech industries.
Managed team of contractors in overall re-certification efforts; scheduled workload and tracked
progress.
Interfaced with Client firms and with Client construction subcontractors.
Managed overall project effort expenditures.
Work with facility personnel to maintain safety protocol and operation and maintenance
procedures.
Commissioned new pharmaceutical equipment.
GE / SmartSignal Corporation, Lisle, IL (SmartSignal purchased by GE in 2011) 2008 to 2012
Senior International Project Manager for this predictive analytics firm. Subject Matter Expert for Power
Industry electro-mechanical devices and Project Management techniques and practices. Implemented the
first application of our products in the wind turbine industry. Implemented the second through tenth nuclear
power applications in the company’s history resulting in reduced maintenance costs. Extensive experience
in implementing fleet wide software applications in Europe, North America, and Asia.
Brought formalized project management techniques to the firm utilizing Microsoft Project software
and PMI best practices resulting in streamlined operations and lower overall resource hours per
project.
Trained and mentored Chinese partners in project management techniques resulting in successful
partnerships.
Instituted cost reduction measures across standard processes within the firm resulting in increased
efficiency.
Was awarded the first ‘Golden Gob’ for unsolicited client praise for building relationships; won four
such awards in three years.
3. 3
Hamilton Sundstrand Space Systems International, Rockford, IL 2004 to 2008
Schedule & Risk Manager in the PMO for one of the largest global suppliers of advanced aerospace and
defense products. Member of cross-divisional Project Management Office. Secret security clearance.
Maintained program schedule status and performed variance analysis to determine overall impact to the
programs and the organization. Recommended alternative corrective courses of action. Performed ongoing
critical path and earned value analysis on several large defense programs. Managed risk through formal
processes. •Analyzed project Scope Change request impacts and identified management options. Monitored
product development lifecycles and recommended corrective actions in light of schedule and cost variances.
Successfully developed and implemented a process for creating and maintaining Integrated Master
Schedules for large multi-site programs, integrating with Earned Value Management Systems [EVM].
Co-authored the standard on how programs will be managed within the organization with specific
emphasis on planning, executing, reporting and controlling, risk management, time management, and
scope management.
Created and presented Microsoft Office Project software training within the firm. Mentored less
experienced associates.
Developed and documented standard project management processes in support of CMMI Level 3
certification.
Developed and implemented standard Work Breakdown Structure applied across the entire business.
International Management Consultant, Naperville, IL 2003 to 2004
Various consulting assignments in power generation, material handling, fundraising, and business organization.
Consultant to CEC Power, an agency of the Chinese government. Associate with retail and commercial tool
rental operation affiliated with The Home Depot.
United Conveyor Corporation, Waukegan, IL 1990 to 2003
Senior International Project Manager for this world leader in coal solids material handling process systems
and equipment. Over a 13 year span, achieved a positive budget variance on closed contracts every year due
largely to effective scope control and schedule management. Successfully interfaced with all levels within our
organization and customer organizations.
Developed proposal scope of work, budget, cost estimate, equipment specification, installation procedures
and drawings, commissioning procedures.
Ensured compliance with applicable codes.
Performed Budgeting and CPM scheduling
Established Resource assignment & leveling methods.
Developed and implemented standard project status reporting tool for senior management.
PM of choice for furnish & erect projects.
Successfully interfaced with Customers,
contractors, and consultants in North America and Asia.
Completed projects on time and 4+% under budget annually over a 13-year period.
Achieved 95+ % customer satisfaction.
$1,200,000 project performance savings.
4. 4
Other experience
Midwest Power Corporation, Rolling Meadows, IL
Wore multiple hats for a firm specializing in rebuilding and upgrading electrostatic precipitators, a clean air
technology.
Project Manager – Managed and scheduled all field projects where we supplied craft labor. Planned
resource usage and availability. Interfaced with site customers. Negotiated with construction trade unions.
Product Development Engineer / Manager – designed and developed patented products with AutoCAD.
Quality Control Engineer / Manager – developed and implemented statistical analysis methodology
resulting in higher quality products.
Uniroyal Chemical Company, Joliet, IL
Project Engineer for this chemical manufacturing firm. Developed plant-wide energy efficiency protocol.
Revised new process line siting to meet flood plain restrictions.
Commonwealth Edison Company, Chicago, IL
Had multiple assignments for this firm specializing in generating fossil electric power.
Project Engineer – Developed and managed $13 million electrostatic precipitator furnish and erect
contract. Interfaced with corporate budget committee.
Project Engineer – Managed switchyard improvement projects in live yard.
Construction Manager – Completion, close-out and claim settlement for a $1 Billion fossil-fueled power
plant.
Construction Engineer – Restored fire protection systems contract from 1 year behind to on-time
completion of the contract. Completed systems verification, start-up, and commissioning. Trained
operators in equipment use.
EDUCATION Masters Degree in Project Management – Keller Graduate School of Management
Masters Degree in Business Administration – Loyola University of Chicago
Bachelor of Science in Mechanical Engineering – The University of Michigan
Dale Carnegie Course – Presentation Skills graduate
Lean Six Sigma trained – Chicago Deming Association
REGISTRATION Project Management Professional
Registered Professional Engineer
Licensed Private Instrument Pilot
Licensed Amateur Radio Operator
Secret Security Clearance (inactive)
MEMBERSHIPS Project Management Institute – Director Emeritus – member – committee member
Naperville Flying Club - President Emeritus – member
American Society of Mechanical Engineers – member
The Alberta Professional Engineers, Geologists & Geophysicists Association – past member
SOFTWARE PROFICIENCY Microsoft Project, MS Office Suite, Excel, Word, PowerPoint, Visio, Outlook.