MAHER M. ABU-MALLOUH, Ph.D., P.E.
188 Morgan Court
Romeoville, Illinois 60446
Home: (815) 293-2308
Mobile: (773) 619-8897
mallouh2005@yahoo.com
Personal Data: United States Citizen
Key Qualifications
Maher Abu-Mallouh has 32 years of engineering experience; with which 12 years as a Senior Engineering
Manager and 20 years experience in Railroad, at the two major USA Commuter rail systems (New York MTA
Transit System) and the Chicago Transit Authority (CTA)). He has worked for five years as a Deputy Program
Manager supervising the design and construction of Tunnel Stations, underground stations, On-Grade-Stations,
and Elevated stations. The Rail projects work includes the design of Railroad Right of Way, subway tunnels,
viaducts, bridges, substations, intermodal transportation, planning, and construction. M Abu-Mallouh developed
the scope for rehabilitation of stations, and devised schemes to construct temporary stations adjacent to existing
stations during closure of existing stations for rehabilitation. This procedure reduced construction time by half.
His responsibilities as a Deputy Program Manger include contract negotiation, collaboration and coordination
between design disciplines, developing design criteria, value engineering, plan preparation, inspection, contract
specification writing, cost estimation, report writing, and quality assurance/quality control (QA/QC).
He coordinated the design work of the consortium team, made up of 15 design firms, for the rehabilitation of the
CTA transit stations. The major firms include HNTB, Parsons, EarthTech, and Tang Engineers.
He developed the Scope of work for the station rehabilitation program. And then compiled and combined the final
design packages for pre-bids.
He has the ability to motivate subordinates, coordinate mentor programs for junior engineers, and work as a team
member and a team leader, working effectively in stressful environments. Delivering projects that are on time and
within budget. Served as lead negotiator for procurement contracts representing the stakeholder and change
orders.
He was the head of the technical office for the general contractor for the construction of the Grand Mosque in
Makkah at a budget of 15 billion dollars. Responsibilities extend to developing of shop drawings and details for
the design support to the artificial decorative stones that forms the major religious attractions to 20 million
visitors yearly for the city of Makkah.
He was the head of Construction office responsible for the construction of stormwater infrastructure drainage
system that has four different contracts: 1) A construction of 46Km twin-pipe 3.5 meter in diameter to cut across
the streets of City of Jeddah using open cut with protective walls and underpin adjacent structures; 2) A
construction of 37Km open channel 27 meter wide with the construction of 12 Roadway bridges over the open
channel and the construction of 24 pedestrian bridges to ease movement and the access; 3) A construction of 15
Km precast twin-box culvert 2.5mx2.5m to run under the streets and parks of the city; 4) Construction of 3
outfalls at the end of the stormwater system at the Red sea inlets; for the City of Jeddah and within Makkah
Region.
He supervised the construction of four Reservoirs to store the water temporarily to alleviate the danger to city
flooding then transfer rainwater via the channels to the Rea Sea.
He currently coordinates the design work of all disciplines and compiles them and work with client to have design
issues finalized and incorporated into the final design and the bid package.
He is proficient in the design and the construction management phases of buildings, transit structures, intermodal
facilities, and nuclear reactors projects. He is able to develop and forecast programs for strategic planning to help
the company plan for the future. In addition, some of his responsibilities include evaluation of the consultants and
the contractors, bids, RFP’s, and contract drawings, and shop drawing reviews.
He is a licensed professional engineer for more than 23 years in Illinois, Indiana, New York, New Jersey, and
Connecticut.
He is familiar with the use of various software packages for the design and analysis of structures. In addition, he
is familiar with various codes including NFPA, ICC, IBC, ADA, ADAAG, AREA, AISC, ACI, ASCE, AREMA,
ANSI, FHWA, BOCA, AASHTO, LEED, New York City Building Code, and Chicago Building Code, and
European Code and the Saudi Building Codes 301, 302, 303, and 304.
Professional Experience
Tishman Construction Group
New York, NY
9/2015 to Present Resident Engineer
Bus Command Center for New York City Transit
• Resident Engineer for the Construction of Bus Command Center for New building to oversee the Bus
operation of 7000 buses daily in and around New York city Area.
• The Facility will have State of the Art building to be LEED Certified Facility
• The Facility will house the bus operation and command monitoring Facility.
• The facility will cost 51 million dollars to construct. In addition to 20 million dollars New Radio
communication system, that will take place after the completion of the building construction.
• He is responsible for the construction project Management team representing the owner. The
Construction supervision team is a total of 13 Senior Engineers, Senior Project Engineers, Quality
Engineer, Safety Engineer, Four Superintendent project inspectors, in addition to 3 Document controllers.
Assistant Resident Engineers.
• The work in summary extends to but not limited to dealing with reviews of the design, coordination with
contractor, and review of shop drawings and facilitate responses to RFI’s and management of safe work
plan, quality plans, cost estimates, review of payments, review of material submittals. Lead and
coordinate Job Progress meetings, prepare daily progress reports and monthly progress reports and submit
them to clients for review and prepare payment percentages for work accomplished.
AECOM Arabia
Jeddah, Saudi Arabia
3/2012 to August 2015 Sr. Structural Engineering Manager
Head of the Technical Office-Field Engineering design support
• Sr. Structural Engineer Head of the Technical Office Jazan Economic City Port and Infrastructure Project
(JECPI). (October 01 2013 – August 2015).
• Prepared the design and contract drawings for the design of Baish Corniche that extends for more than 4
square kilometer of park and recreation for public use.
• Design bulkhead for waterfront retaining structures.
• Design and review of the waterfront structures to protect against flooding and water damage.
• He is responsible for the structural design team, and the electromechanical design for all the buildings
including a mosque, restaurant, and coffee shop. In addition to the maintenance and water closets, pump
rooms and irrigation tanks.
• Design, review and supervise the design of current design packages that are being let out for the design
packages associated with the Economic City projects, including review and approval of shop drawings for
the work of the JECPI, design package.
• Involved in the development of the contract for ground preparation for the construction of the Baish
Corniche Park Project.
• Developed specifications and standard drawings for the design and construction packages.
• Sr. Structural Engineer Head of the Construction Technical Office Jeddah Stormwater Drainage Program
(JSDP), (March 06, 2012 - October 1, 2013)
• Reviewed construction and provide review and approval of shop drawings for the work of the JSDP
program.
• Provided alternate designs needed for construction to simplify the Issue for Construction drawings (IFC).
• Writing and review and coordinate the roadway work, pavement profile, and reinstatement of roadways
and roadway surfaces.
• Value engineering review of the design projects, including lessons learned for the engineering designers
at Houston, United Kingdom offices.
• Experience in developing detailed drawings for manholes and junction boxes that will are constructed in
the roadways and reviews plans for contractor to meet the final grade profile.
• Developed detailed drawings of pier caps, abutments, roadway bridges, staircases, and other structural
drawings for the super structure.
• The JSDP project is divided into four construction packages: 1) Northern channel (Box culvert
construction) 10 kilometers long with an outlet to the Red Sea Corniche area; 2) Eastern Channel Open
trapezoidal Channel 30 km long and the construction of thirteen two and three span concrete Vehicular
bridges, 3) Southern Channel 15 km long trapezoidal channel including the construction of two new
vehicular bridges and four new pedestrian bridges, and 4) Construction of One new Ghulil Dam and a sub
channel called Wadi Ghaia 10 kilometers, and Um Hablin channel of 15 kilometers.
• Developed location plans and schematic plans to be aesthetically pleasing design for 24 pedestrian
bridges being constructed above the recently constructed Channels such as Alsamer, Um alkhiar,
Umhableen, Eastern channel, Southern channel and on the proposed new channels being new contract
Al-khumra and Wadi Quraa. (Jeddah, KSA)
• Writing technical reports for the proposed work and developing recommendation to the technical issues
that arise for the current projects and for the proposed new projects.
• Review structural details for the existing structures within the program.
• Provide structural details, coordination, and analysis for the repairs needed.
• Provide recommendation on repairs to existing structures, and develop repair details.
Saudi B. L. Group (SBG)
Jeddah, Saudi Arabia
5/2010 to 1/2012 Sr. Structural Project Manager
• Head of the Construction Technical Office for SBG-ABCD to provide reviews, cost estimating,
Construction project management, and review safety and quality procedures.
• In charge of three parts of the Project Haram Expansion, Piazza & Service Building, and Central Utility
Complex.
• The Haram Building included three floors, 64,000m2
each, a full basement, and three mezzanines for each
floor. The Project cost exceeds 60 billion Saudi Riyal.
• The Haram construction includes artificial stone with special design to commemorate the beauty of an
extraordinary structure. It has concrete precast arches to carry the decorative marble, gold plated,
ornamental steel work.
• The structure also has a raised floor design under each floor to include all the utilities and all duct work
for Haram cooling. The raised floor will be designed using stainless steel columns and beams to provide
longevity of the material.
• The Piazza and Service Building includes 15,000 precast units of concrete pods.
• There are 112 umbrellas within the piazza, 70 of which are of 25m ×25m, and while the other 42
umbrellas are with a size of 52m×52m.
• These umbrellas cover security cameras, zamzam water line and mist.
• The third section of the Project is the Central Utility Complex which includes three buildings: Generator
Building, Water Tank Building and Central Waste Building.
Sargent & Lundy LLC.
Chicago, Illinois
7/2008 to 3/2010 Project Associate
• The design of retaining walls for the South Texas Nuclear Project.
• Developed analytical process for analysis and evaluation of retaining walls.
• The analysis includes soil earth pressure at-rest condition, and analysis includes earthquake design for
various types of structures.
• Work under pressure to deliver projects on time and within budget.
• Ability to motivate subordinates and work as a team member and a team leader.
• Responsible for the structural design and analysis of portions of the RB and prepare structural design
analyses and details for the project.
• Developed static and dynamic loadings for the exterior wall of the RB.
• Reviewed and updated the Seismic Design Criteria for the entire South Texas Project.
• Prepared the Structural Design Criteria for the Reactor Building (RB).
• Developed calculations for soil design report used in the design of specific segments of the RB.
• Reviewed pipe penetration anchorage calculations for a Reinforced Concrete Containment Vessel
(RCCV) structure.
Globetrotters Engineering Group
Chicago, Illinois
10/2007 to 7/2008 Program Manager – Design/Construction Management
• Managed a portion of the Tollway Capital Program for the rebuilding of maintenance facilities –System
wide for the Tollway Infrastructure. The total budget for the project was $20.0 Million dollars.
• Supervised a team of 8 project managers and 8 design consultants to accomplish this task.
• Wrote proposals and Master plans for various types and sizes of projects.
• Developed detailed drawings of pier caps, abutments, roadway bridges, staircases, and other structural
drawings for the super structure.
• Developed layout of Drainage system in elevated Metro viaduct structures.
Worked as a Field Site-Engineer for the construction of low, medium, and high rise buildings.
• Prepared tender design, preliminary design, and final detailed design structural drawings.
• Prepared design drawings for construction methodology with alternative methods to fit different site
conditions and construction sequences for precast and cast-in-situ super structures.
• Reviewed plans and coordinated projects with consultants, prime contractors maintaining project
schedules.
• Reviewed consultant design and drawings for Quality Assurance and compliance with applicable design
guidelines.
• Developed forecasts and strategic plans to help the company plan for the future.
• Develop Value Management and Value Engineering programs to eliminate project overruns.
Exelon Nuclear
Morris, IL
10/2006 to 10/2007 Sr. Structural Engineer – Design Engineering and Construction Supervision
• Provided structural design and analysis for protection of the turbine and reactor building.
• Reviewed structural designs for owner’s acceptance.
• Provided structural analysis and support for the plant during normal operation and during outage
shutdown.
• Worked under pressure to deliver projects on time and within budget.
• Review construction procedures, shop drawings and rebar details for the construction of Protection slabs
for the Storage of the Concrete and steel canisters called (CASKS) to be stored on site until the
government finds another option to store the depleted Fusion rods.
Desman Associates
Chicago, Illinois
10/2005 to 10/2006 Sr. Structural Engineer – Design Engineering
• Designed structural elements for parking garage structures.
• Reviewed structural design as the owner’s representative.
• Provided structural analysis for different types of concrete structures, such as steel buildings and concrete
pre-stress design using P-DATA and STAAD programs.
• Provided analysis for forensic investigation with regard to the design and construction quality.
• Motivated coworkers to work as a team member and acted as team leader.
URS Corporation
Chicago, Illinois
10/2000 to 3/2005 Deputy Program Manager – Design/Construction Management
• Managed part of the Capital Program for the rebuilding of 26 train stations for the Chicago Transit
Authority. The total budget for the project was $2.4 Billion dollars.
• Supervised the design and construction of Tunnel Stations, underground stations (cut and fill), on-grade-
stations, elevated stations.
• The Rail projects work includes: design of Railroad Right of Way, subway tunnels, viaducts, bridges,
stations, intermodal transportation, planning, and construction.
• Developed scope of work for rehabilitation of stations; devised scheme to construct temporary station
adjacent to existing station and have the existing station closed for rehabilitation which reduced
construction time by one half.
• Coordinated the design work of the consortium team made up of 15 design firms used for the
rehabilitation of the CTA transit stations. Major firms include HNTB, Parsons, EarthTech, Teng
Engineers, and Primera.
• Developed the scope of work for the station rehabilitation program. Then compiled and combined the
final design packages for bids.
• Supervise a team of 15 project managers and 10 design consultants to accomplish this task.
• Wrote proposals and Master plans for various types of projects of different sizes.
• Worked under pressure to deliver projects on time and within budget.
• Motivated subordinates and work as a team member and a team leader.
• Lead Negotiator of contracts, consultants, change orders, payments, field memos and any other contract
related issues.
• Reviewed plans, coordinate projects with consultants, prime contractors and maintaining projects
schedules.
• Reviewed of consultant design and drawings for Quality Assurance and compliance with the design
guidelines.
Haks Engineers, P.C.,
New York, NY
7/1998 to 10/2000 Sr. Structural Engineer/Construction Manager
• Inspected of Brooklyn Queens Expressway for the New York State Department of Transportation
(NYSDOT).
• Bridge Design Engineer for three New York City DOT Bridges.
• Reviewed plans, coordinated projects with consultants, prime contractor.
• Reviewed plans and coordinate with registered engineers.
• Reviewed consultant design and drawings for Quality Assurance and compliance with the design
guidelines.
• Team Leader of Bridge Inspectors for the NYCDOT and NYSDOT joint venture with Ammann &
Whitney for the inspection of Twelve bridges: 10-span concrete arch, 2 one-span bridges, and 7 two span
Steel Bridges.
• Checked design, construction procedure, and shop drawings for East Gun Hill Road Bridge.
• Supervised Drafting and Junior Engineers.
Lawless and Mangione
Yonkers, NY
6/1996 to 7/1998 Sr. Project Engineer /Construction Manager
• Investigated commercial and residential buildings, including landmark and historic, for exterior
restoration, conservation, façade renovation, plaza and roof repairs and/or replacements.
• Supervised the construction of Two Parking structures at Grand Park Avenue in New York City,
Highland Park Avenue in White Plains New York.
• Supervised the construction of Two six story prefabricated buildings in the City of Yonkers at Bruce
Avenue and down town development projects.
• Provided solutions to address various structural issues.
• Designed various structural elements; reviewed impact of demolition and construction of adjacent
buildings.
• Developed investigation reports with accurate cost estimates. Created background drawings, structural
and architectural repair details; prepared project manual.
• Assisted clients in the bidding process and prepared AIA contracts.
• Reviewed RFIs, handle submittals, change orders, shop drawings and schedules. Inspected work progress
to evaluate construction materials and methods.
• Columbia Presbyterian Hospital inspection, and rehabilitation of the structural integrity of the building
(New York City) ($20 million dollar project).
• Fordham University; renovation of the playground and access facilities. St. Ursuline Church renovation,
New York.
• Restoration of High-rise buildings of many buildings within the New York City Area.
• Design and Restoration of parking garage structures, and low-rise residential buildings.
• Forensic Investigation of a two-level parking structure collapse.
• Modeling of structural analysis using STAAD III.
• Supervised and coordinated the work of four Senior Engineers and two drafters.
• Developed Cost estimate for three major projects (estimate of $40 million).
Metropolitan Transportation Authority
Brooklyn, NY
6/1982 to 6/1996 Administrative Engineer/Structural Designer, Capital Program
Management, Cost Estimating and Project Control
• Supervised and coordinated the work of three Senior Project Engineers, two Project Coordinators, and a
Senior Project Coordinators.
• Designed numerous projects for Railroad Right of Way, subway tunnels, bridges, and stations.
• Prepared design and alignment of 42nd
street terminal station. City Hall Station Tunnel station and grand
Central Underground station rehabilitation.
• Lexington Avenue tunnel inspection and Ocean Parkway stations rehabilitation Viaduct open-cut station.
• 100 Street bus depot above ground structure Terminal and Flushing Bus depot Terminal design for 200
bus facilities operation.
• Prepared, reviewed, negotiated, and analyzed cost estimates for all trades, including structural,
architectural, mechanical, electrical, and communication.
• Accomplishments include production and development of cost estimates of major subway stations
renovations such as: Underground Times Square Terminal Complex ($181 million), Underground Grand
Central Phase II project ($47 million), Trump City at 72nd St. Station ($60 million), and Underground
Atlantic Avenue Terminal Complex ($152 million).
• Designed steel and reinforced concrete structures, retaining walls, pile foundations, slurry walls.
Professional Registrations
Professional Engineering Licenses in the States of Illinois (current), Indiana, New York (current), New Jersey,
and Connecticut.
Education
Polytechnic University
Brooklyn, NY
• Ph.D. (Civil Engineering) in Construction Management June 1999.
• Dissertation Title: Model for Station Rehabilitation Planning.
• Master of Science (Transportation & Planning), January 1993
• Engineer Degree (Structural Engineering), January 1990
• Project Title: Earthquake analysis for two dimensional bridges.
Manhattan College
Riverdale, NY
• Master of Engineering (Civil), June 1982
• Bachelor of Engineering (Civil), June 1981
Professional Affiliations
• Honor Society of Civil Engineers (CHI EPSILON), American Society of Civil Engineers (ASCE),
• American Institute of Steel construction (AISC), and American Concrete Institute (ACI), and Project
Management Institute (PMI)
Computer Software experience: RISA, Strudl, MathCAD, TEKLA, AutoCAD, RAM, MathCAD, Prokon,
SAFE, PCA Slab, PCA Column, and Microsoft.
References: Available upon request.

More Related Content

What's hot (20)

PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
 
Mohamed Abdelaal cv
Mohamed Abdelaal cvMohamed Abdelaal cv
Mohamed Abdelaal cv
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Hanin qreis 2018 cv
Hanin qreis 2018 cvHanin qreis 2018 cv
Hanin qreis 2018 cv
 
majdi C.V
majdi C.Vmajdi C.V
majdi C.V
 
Subhash CV Dec 2016
Subhash CV Dec 2016Subhash CV Dec 2016
Subhash CV Dec 2016
 
Salem mohamed curriculum vitae
Salem mohamed curriculum vitaeSalem mohamed curriculum vitae
Salem mohamed curriculum vitae
 
ENGLISH
ENGLISH ENGLISH
ENGLISH
 
Civil Engineer - Ashraf Gomah Mohamed 2016
Civil Engineer - Ashraf Gomah Mohamed 2016Civil Engineer - Ashraf Gomah Mohamed 2016
Civil Engineer - Ashraf Gomah Mohamed 2016
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
Resume (final cv)
Resume (final cv)Resume (final cv)
Resume (final cv)
 
160226 muhammad alhanbali cv-rev00
160226 muhammad  alhanbali cv-rev00160226 muhammad  alhanbali cv-rev00
160226 muhammad alhanbali cv-rev00
 
MAA CV 2015
MAA CV 2015MAA CV 2015
MAA CV 2015
 
Survey Engr
Survey EngrSurvey Engr
Survey Engr
 
MARWAN_FARRAG_ARCHITECT_SITE ENGINEER_CV_KSA
MARWAN_FARRAG_ARCHITECT_SITE ENGINEER_CV_KSAMARWAN_FARRAG_ARCHITECT_SITE ENGINEER_CV_KSA
MARWAN_FARRAG_ARCHITECT_SITE ENGINEER_CV_KSA
 
Vera Ho CV - 2016
Vera Ho CV - 2016Vera Ho CV - 2016
Vera Ho CV - 2016
 
Aftab Ahmad CV_Sr. CM RB (1)
Aftab Ahmad CV_Sr. CM RB (1)Aftab Ahmad CV_Sr. CM RB (1)
Aftab Ahmad CV_Sr. CM RB (1)
 
Muhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.VMuhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.V
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
Summery
SummerySummery
Summery
 

Viewers also liked

Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.
Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.
Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.Lorena Martin
 
Pradeep koneru
Pradeep koneruPradeep koneru
Pradeep koneruKrisroj h
 
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016Lorena Martin
 
ArtsSpace: Inspiration, Cultural Diversity and the Arts
ArtsSpace: Inspiration, Cultural Diversity and the Arts ArtsSpace: Inspiration, Cultural Diversity and the Arts
ArtsSpace: Inspiration, Cultural Diversity and the Arts Janice K. Jones
 
Presentación Marketing Nativo con Adnews
Presentación Marketing Nativo con AdnewsPresentación Marketing Nativo con Adnews
Presentación Marketing Nativo con AdnewsFrancisco Álvarez Cano
 
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016Stratesys
 
Writing - Factual Recount
Writing - Factual RecountWriting - Factual Recount
Writing - Factual Recountsuhailalaip
 
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...CONGRESO EGF
 
Visual Merchandising Portfolio
Visual Merchandising PortfolioVisual Merchandising Portfolio
Visual Merchandising PortfolioKannu Priya Rawat
 

Viewers also liked (13)

Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.
Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.
Stratesys - Transformacion Digital eCommerce - ECOMMERCENEWS.ES - AGO 2016.
 
Pradeep koneru
Pradeep koneruPradeep koneru
Pradeep koneru
 
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016
Stratesys - Transformacion Digital eCommerce - SILICON ES - AGO 2016
 
ArtsSpace: Inspiration, Cultural Diversity and the Arts
ArtsSpace: Inspiration, Cultural Diversity and the Arts ArtsSpace: Inspiration, Cultural Diversity and the Arts
ArtsSpace: Inspiration, Cultural Diversity and the Arts
 
Presentación Marketing Nativo con Adnews
Presentación Marketing Nativo con AdnewsPresentación Marketing Nativo con Adnews
Presentación Marketing Nativo con Adnews
 
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016
Stratesys - Transformacion Digital eCommerce - ITUSER - AGO 2016
 
Acoso Cibernetico y sus Implicaciones Legales
Acoso Cibernetico y sus Implicaciones LegalesAcoso Cibernetico y sus Implicaciones Legales
Acoso Cibernetico y sus Implicaciones Legales
 
MOLECULAR BIOLOGY/BIOCHEMISTRY CORE
MOLECULAR BIOLOGY/BIOCHEMISTRY COREMOLECULAR BIOLOGY/BIOCHEMISTRY CORE
MOLECULAR BIOLOGY/BIOCHEMISTRY CORE
 
Latihan 6 tk 1d_K'6
Latihan 6 tk 1d_K'6Latihan 6 tk 1d_K'6
Latihan 6 tk 1d_K'6
 
Writing the Memoir - 11th Grade English
Writing the Memoir - 11th Grade EnglishWriting the Memoir - 11th Grade English
Writing the Memoir - 11th Grade English
 
Writing - Factual Recount
Writing - Factual RecountWriting - Factual Recount
Writing - Factual Recount
 
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...
Ponencia Miguel Castro en I Congreso Empresarial e Institucional LGBT Friendl...
 
Visual Merchandising Portfolio
Visual Merchandising PortfolioVisual Merchandising Portfolio
Visual Merchandising Portfolio
 

Similar to Maher Abu-Mallouh's 32-Year Engineering Experience

Project Summary in Hyder Consulting
Project Summary in Hyder ConsultingProject Summary in Hyder Consulting
Project Summary in Hyder ConsultingMark Regalado
 
Relevance of civil engineering
Relevance of civil engineeringRelevance of civil engineering
Relevance of civil engineeringPriya Sarita Mane
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-RailwayMubasher Malik
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph Raftery
 
Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce Brown
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L NBasavaraj L N
 
Curriculum vita mohamed nabil
Curriculum vita  mohamed nabilCurriculum vita  mohamed nabil
Curriculum vita mohamed nabilMohamed Omer
 
DESTECH - COMPANY PROFILE
DESTECH - COMPANY PROFILEDESTECH - COMPANY PROFILE
DESTECH - COMPANY PROFILEBhauso Desai
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021Eduardo H. Pare
 
Erfan Farooqui CV- 17072016
Erfan Farooqui CV- 17072016Erfan Farooqui CV- 17072016
Erfan Farooqui CV- 17072016Erfan Farooqui
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cvBladina.com
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cvBladina.com
 
Hays Highways CV
Hays Highways CVHays Highways CV
Hays Highways CVSa Ga
 

Similar to Maher Abu-Mallouh's 32-Year Engineering Experience (20)

Project Summary in Hyder Consulting
Project Summary in Hyder ConsultingProject Summary in Hyder Consulting
Project Summary in Hyder Consulting
 
Relevance of civil engineering
Relevance of civil engineeringRelevance of civil engineering
Relevance of civil engineering
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-Railway
 
Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.Joseph J. Raftery - Civil Engineer, P.E.
Joseph J. Raftery - Civil Engineer, P.E.
 
Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115
 
CV Sujit pdf
CV Sujit pdfCV Sujit pdf
CV Sujit pdf
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L N
 
_Mohamad Bendary_Jan-2015
_Mohamad Bendary_Jan-2015_Mohamad Bendary_Jan-2015
_Mohamad Bendary_Jan-2015
 
Curriculum vita mohamed nabil
Curriculum vita  mohamed nabilCurriculum vita  mohamed nabil
Curriculum vita mohamed nabil
 
CV of KP Tomy
CV of KP TomyCV of KP Tomy
CV of KP Tomy
 
DESTECH - COMPANY PROFILE
DESTECH - COMPANY PROFILEDESTECH - COMPANY PROFILE
DESTECH - COMPANY PROFILE
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021
 
shishir_cv
shishir_cvshishir_cv
shishir_cv
 
Erfan Farooqui CV- 17072016
Erfan Farooqui CV- 17072016Erfan Farooqui CV- 17072016
Erfan Farooqui CV- 17072016
 
Naveed Asif C.V Updated
Naveed Asif C.V UpdatedNaveed Asif C.V Updated
Naveed Asif C.V Updated
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cv
 
Mohamed sanoussi cv
Mohamed sanoussi cvMohamed sanoussi cv
Mohamed sanoussi cv
 
Hays Highways CV
Hays Highways CVHays Highways CV
Hays Highways CV
 
JDG CV_160413
JDG CV_160413JDG CV_160413
JDG CV_160413
 

Maher Abu-Mallouh's 32-Year Engineering Experience

  • 1. MAHER M. ABU-MALLOUH, Ph.D., P.E. 188 Morgan Court Romeoville, Illinois 60446 Home: (815) 293-2308 Mobile: (773) 619-8897 mallouh2005@yahoo.com Personal Data: United States Citizen Key Qualifications Maher Abu-Mallouh has 32 years of engineering experience; with which 12 years as a Senior Engineering Manager and 20 years experience in Railroad, at the two major USA Commuter rail systems (New York MTA Transit System) and the Chicago Transit Authority (CTA)). He has worked for five years as a Deputy Program Manager supervising the design and construction of Tunnel Stations, underground stations, On-Grade-Stations, and Elevated stations. The Rail projects work includes the design of Railroad Right of Way, subway tunnels, viaducts, bridges, substations, intermodal transportation, planning, and construction. M Abu-Mallouh developed the scope for rehabilitation of stations, and devised schemes to construct temporary stations adjacent to existing stations during closure of existing stations for rehabilitation. This procedure reduced construction time by half. His responsibilities as a Deputy Program Manger include contract negotiation, collaboration and coordination between design disciplines, developing design criteria, value engineering, plan preparation, inspection, contract specification writing, cost estimation, report writing, and quality assurance/quality control (QA/QC). He coordinated the design work of the consortium team, made up of 15 design firms, for the rehabilitation of the CTA transit stations. The major firms include HNTB, Parsons, EarthTech, and Tang Engineers. He developed the Scope of work for the station rehabilitation program. And then compiled and combined the final design packages for pre-bids. He has the ability to motivate subordinates, coordinate mentor programs for junior engineers, and work as a team member and a team leader, working effectively in stressful environments. Delivering projects that are on time and within budget. Served as lead negotiator for procurement contracts representing the stakeholder and change orders. He was the head of the technical office for the general contractor for the construction of the Grand Mosque in Makkah at a budget of 15 billion dollars. Responsibilities extend to developing of shop drawings and details for the design support to the artificial decorative stones that forms the major religious attractions to 20 million visitors yearly for the city of Makkah. He was the head of Construction office responsible for the construction of stormwater infrastructure drainage system that has four different contracts: 1) A construction of 46Km twin-pipe 3.5 meter in diameter to cut across the streets of City of Jeddah using open cut with protective walls and underpin adjacent structures; 2) A construction of 37Km open channel 27 meter wide with the construction of 12 Roadway bridges over the open channel and the construction of 24 pedestrian bridges to ease movement and the access; 3) A construction of 15 Km precast twin-box culvert 2.5mx2.5m to run under the streets and parks of the city; 4) Construction of 3 outfalls at the end of the stormwater system at the Red sea inlets; for the City of Jeddah and within Makkah Region. He supervised the construction of four Reservoirs to store the water temporarily to alleviate the danger to city flooding then transfer rainwater via the channels to the Rea Sea. He currently coordinates the design work of all disciplines and compiles them and work with client to have design issues finalized and incorporated into the final design and the bid package. He is proficient in the design and the construction management phases of buildings, transit structures, intermodal facilities, and nuclear reactors projects. He is able to develop and forecast programs for strategic planning to help
  • 2. the company plan for the future. In addition, some of his responsibilities include evaluation of the consultants and the contractors, bids, RFP’s, and contract drawings, and shop drawing reviews. He is a licensed professional engineer for more than 23 years in Illinois, Indiana, New York, New Jersey, and Connecticut. He is familiar with the use of various software packages for the design and analysis of structures. In addition, he is familiar with various codes including NFPA, ICC, IBC, ADA, ADAAG, AREA, AISC, ACI, ASCE, AREMA, ANSI, FHWA, BOCA, AASHTO, LEED, New York City Building Code, and Chicago Building Code, and European Code and the Saudi Building Codes 301, 302, 303, and 304. Professional Experience Tishman Construction Group New York, NY 9/2015 to Present Resident Engineer Bus Command Center for New York City Transit • Resident Engineer for the Construction of Bus Command Center for New building to oversee the Bus operation of 7000 buses daily in and around New York city Area. • The Facility will have State of the Art building to be LEED Certified Facility • The Facility will house the bus operation and command monitoring Facility. • The facility will cost 51 million dollars to construct. In addition to 20 million dollars New Radio communication system, that will take place after the completion of the building construction. • He is responsible for the construction project Management team representing the owner. The Construction supervision team is a total of 13 Senior Engineers, Senior Project Engineers, Quality Engineer, Safety Engineer, Four Superintendent project inspectors, in addition to 3 Document controllers. Assistant Resident Engineers. • The work in summary extends to but not limited to dealing with reviews of the design, coordination with contractor, and review of shop drawings and facilitate responses to RFI’s and management of safe work plan, quality plans, cost estimates, review of payments, review of material submittals. Lead and coordinate Job Progress meetings, prepare daily progress reports and monthly progress reports and submit them to clients for review and prepare payment percentages for work accomplished. AECOM Arabia Jeddah, Saudi Arabia 3/2012 to August 2015 Sr. Structural Engineering Manager Head of the Technical Office-Field Engineering design support • Sr. Structural Engineer Head of the Technical Office Jazan Economic City Port and Infrastructure Project (JECPI). (October 01 2013 – August 2015). • Prepared the design and contract drawings for the design of Baish Corniche that extends for more than 4 square kilometer of park and recreation for public use. • Design bulkhead for waterfront retaining structures. • Design and review of the waterfront structures to protect against flooding and water damage. • He is responsible for the structural design team, and the electromechanical design for all the buildings including a mosque, restaurant, and coffee shop. In addition to the maintenance and water closets, pump rooms and irrigation tanks. • Design, review and supervise the design of current design packages that are being let out for the design packages associated with the Economic City projects, including review and approval of shop drawings for the work of the JECPI, design package.
  • 3. • Involved in the development of the contract for ground preparation for the construction of the Baish Corniche Park Project. • Developed specifications and standard drawings for the design and construction packages. • Sr. Structural Engineer Head of the Construction Technical Office Jeddah Stormwater Drainage Program (JSDP), (March 06, 2012 - October 1, 2013) • Reviewed construction and provide review and approval of shop drawings for the work of the JSDP program. • Provided alternate designs needed for construction to simplify the Issue for Construction drawings (IFC). • Writing and review and coordinate the roadway work, pavement profile, and reinstatement of roadways and roadway surfaces. • Value engineering review of the design projects, including lessons learned for the engineering designers at Houston, United Kingdom offices. • Experience in developing detailed drawings for manholes and junction boxes that will are constructed in the roadways and reviews plans for contractor to meet the final grade profile. • Developed detailed drawings of pier caps, abutments, roadway bridges, staircases, and other structural drawings for the super structure. • The JSDP project is divided into four construction packages: 1) Northern channel (Box culvert construction) 10 kilometers long with an outlet to the Red Sea Corniche area; 2) Eastern Channel Open trapezoidal Channel 30 km long and the construction of thirteen two and three span concrete Vehicular bridges, 3) Southern Channel 15 km long trapezoidal channel including the construction of two new vehicular bridges and four new pedestrian bridges, and 4) Construction of One new Ghulil Dam and a sub channel called Wadi Ghaia 10 kilometers, and Um Hablin channel of 15 kilometers. • Developed location plans and schematic plans to be aesthetically pleasing design for 24 pedestrian bridges being constructed above the recently constructed Channels such as Alsamer, Um alkhiar, Umhableen, Eastern channel, Southern channel and on the proposed new channels being new contract Al-khumra and Wadi Quraa. (Jeddah, KSA) • Writing technical reports for the proposed work and developing recommendation to the technical issues that arise for the current projects and for the proposed new projects. • Review structural details for the existing structures within the program. • Provide structural details, coordination, and analysis for the repairs needed. • Provide recommendation on repairs to existing structures, and develop repair details. Saudi B. L. Group (SBG) Jeddah, Saudi Arabia 5/2010 to 1/2012 Sr. Structural Project Manager • Head of the Construction Technical Office for SBG-ABCD to provide reviews, cost estimating, Construction project management, and review safety and quality procedures. • In charge of three parts of the Project Haram Expansion, Piazza & Service Building, and Central Utility Complex. • The Haram Building included three floors, 64,000m2 each, a full basement, and three mezzanines for each floor. The Project cost exceeds 60 billion Saudi Riyal. • The Haram construction includes artificial stone with special design to commemorate the beauty of an extraordinary structure. It has concrete precast arches to carry the decorative marble, gold plated, ornamental steel work. • The structure also has a raised floor design under each floor to include all the utilities and all duct work for Haram cooling. The raised floor will be designed using stainless steel columns and beams to provide longevity of the material. • The Piazza and Service Building includes 15,000 precast units of concrete pods. • There are 112 umbrellas within the piazza, 70 of which are of 25m ×25m, and while the other 42 umbrellas are with a size of 52m×52m. • These umbrellas cover security cameras, zamzam water line and mist.
  • 4. • The third section of the Project is the Central Utility Complex which includes three buildings: Generator Building, Water Tank Building and Central Waste Building. Sargent & Lundy LLC. Chicago, Illinois 7/2008 to 3/2010 Project Associate • The design of retaining walls for the South Texas Nuclear Project. • Developed analytical process for analysis and evaluation of retaining walls. • The analysis includes soil earth pressure at-rest condition, and analysis includes earthquake design for various types of structures. • Work under pressure to deliver projects on time and within budget. • Ability to motivate subordinates and work as a team member and a team leader. • Responsible for the structural design and analysis of portions of the RB and prepare structural design analyses and details for the project. • Developed static and dynamic loadings for the exterior wall of the RB. • Reviewed and updated the Seismic Design Criteria for the entire South Texas Project. • Prepared the Structural Design Criteria for the Reactor Building (RB). • Developed calculations for soil design report used in the design of specific segments of the RB. • Reviewed pipe penetration anchorage calculations for a Reinforced Concrete Containment Vessel (RCCV) structure. Globetrotters Engineering Group Chicago, Illinois 10/2007 to 7/2008 Program Manager – Design/Construction Management • Managed a portion of the Tollway Capital Program for the rebuilding of maintenance facilities –System wide for the Tollway Infrastructure. The total budget for the project was $20.0 Million dollars. • Supervised a team of 8 project managers and 8 design consultants to accomplish this task. • Wrote proposals and Master plans for various types and sizes of projects. • Developed detailed drawings of pier caps, abutments, roadway bridges, staircases, and other structural drawings for the super structure. • Developed layout of Drainage system in elevated Metro viaduct structures. Worked as a Field Site-Engineer for the construction of low, medium, and high rise buildings. • Prepared tender design, preliminary design, and final detailed design structural drawings. • Prepared design drawings for construction methodology with alternative methods to fit different site conditions and construction sequences for precast and cast-in-situ super structures. • Reviewed plans and coordinated projects with consultants, prime contractors maintaining project schedules. • Reviewed consultant design and drawings for Quality Assurance and compliance with applicable design guidelines. • Developed forecasts and strategic plans to help the company plan for the future. • Develop Value Management and Value Engineering programs to eliminate project overruns. Exelon Nuclear Morris, IL 10/2006 to 10/2007 Sr. Structural Engineer – Design Engineering and Construction Supervision • Provided structural design and analysis for protection of the turbine and reactor building. • Reviewed structural designs for owner’s acceptance. • Provided structural analysis and support for the plant during normal operation and during outage
  • 5. shutdown. • Worked under pressure to deliver projects on time and within budget. • Review construction procedures, shop drawings and rebar details for the construction of Protection slabs for the Storage of the Concrete and steel canisters called (CASKS) to be stored on site until the government finds another option to store the depleted Fusion rods. Desman Associates Chicago, Illinois 10/2005 to 10/2006 Sr. Structural Engineer – Design Engineering • Designed structural elements for parking garage structures. • Reviewed structural design as the owner’s representative. • Provided structural analysis for different types of concrete structures, such as steel buildings and concrete pre-stress design using P-DATA and STAAD programs. • Provided analysis for forensic investigation with regard to the design and construction quality. • Motivated coworkers to work as a team member and acted as team leader. URS Corporation Chicago, Illinois 10/2000 to 3/2005 Deputy Program Manager – Design/Construction Management • Managed part of the Capital Program for the rebuilding of 26 train stations for the Chicago Transit Authority. The total budget for the project was $2.4 Billion dollars. • Supervised the design and construction of Tunnel Stations, underground stations (cut and fill), on-grade- stations, elevated stations. • The Rail projects work includes: design of Railroad Right of Way, subway tunnels, viaducts, bridges, stations, intermodal transportation, planning, and construction. • Developed scope of work for rehabilitation of stations; devised scheme to construct temporary station adjacent to existing station and have the existing station closed for rehabilitation which reduced construction time by one half. • Coordinated the design work of the consortium team made up of 15 design firms used for the rehabilitation of the CTA transit stations. Major firms include HNTB, Parsons, EarthTech, Teng Engineers, and Primera. • Developed the scope of work for the station rehabilitation program. Then compiled and combined the final design packages for bids. • Supervise a team of 15 project managers and 10 design consultants to accomplish this task. • Wrote proposals and Master plans for various types of projects of different sizes. • Worked under pressure to deliver projects on time and within budget. • Motivated subordinates and work as a team member and a team leader. • Lead Negotiator of contracts, consultants, change orders, payments, field memos and any other contract related issues. • Reviewed plans, coordinate projects with consultants, prime contractors and maintaining projects schedules. • Reviewed of consultant design and drawings for Quality Assurance and compliance with the design guidelines. Haks Engineers, P.C., New York, NY 7/1998 to 10/2000 Sr. Structural Engineer/Construction Manager • Inspected of Brooklyn Queens Expressway for the New York State Department of Transportation (NYSDOT). • Bridge Design Engineer for three New York City DOT Bridges.
  • 6. • Reviewed plans, coordinated projects with consultants, prime contractor. • Reviewed plans and coordinate with registered engineers. • Reviewed consultant design and drawings for Quality Assurance and compliance with the design guidelines. • Team Leader of Bridge Inspectors for the NYCDOT and NYSDOT joint venture with Ammann & Whitney for the inspection of Twelve bridges: 10-span concrete arch, 2 one-span bridges, and 7 two span Steel Bridges. • Checked design, construction procedure, and shop drawings for East Gun Hill Road Bridge. • Supervised Drafting and Junior Engineers. Lawless and Mangione Yonkers, NY 6/1996 to 7/1998 Sr. Project Engineer /Construction Manager • Investigated commercial and residential buildings, including landmark and historic, for exterior restoration, conservation, façade renovation, plaza and roof repairs and/or replacements. • Supervised the construction of Two Parking structures at Grand Park Avenue in New York City, Highland Park Avenue in White Plains New York. • Supervised the construction of Two six story prefabricated buildings in the City of Yonkers at Bruce Avenue and down town development projects. • Provided solutions to address various structural issues. • Designed various structural elements; reviewed impact of demolition and construction of adjacent buildings. • Developed investigation reports with accurate cost estimates. Created background drawings, structural and architectural repair details; prepared project manual. • Assisted clients in the bidding process and prepared AIA contracts. • Reviewed RFIs, handle submittals, change orders, shop drawings and schedules. Inspected work progress to evaluate construction materials and methods. • Columbia Presbyterian Hospital inspection, and rehabilitation of the structural integrity of the building (New York City) ($20 million dollar project). • Fordham University; renovation of the playground and access facilities. St. Ursuline Church renovation, New York. • Restoration of High-rise buildings of many buildings within the New York City Area. • Design and Restoration of parking garage structures, and low-rise residential buildings. • Forensic Investigation of a two-level parking structure collapse. • Modeling of structural analysis using STAAD III. • Supervised and coordinated the work of four Senior Engineers and two drafters. • Developed Cost estimate for three major projects (estimate of $40 million). Metropolitan Transportation Authority Brooklyn, NY 6/1982 to 6/1996 Administrative Engineer/Structural Designer, Capital Program Management, Cost Estimating and Project Control • Supervised and coordinated the work of three Senior Project Engineers, two Project Coordinators, and a Senior Project Coordinators. • Designed numerous projects for Railroad Right of Way, subway tunnels, bridges, and stations. • Prepared design and alignment of 42nd street terminal station. City Hall Station Tunnel station and grand Central Underground station rehabilitation. • Lexington Avenue tunnel inspection and Ocean Parkway stations rehabilitation Viaduct open-cut station. • 100 Street bus depot above ground structure Terminal and Flushing Bus depot Terminal design for 200 bus facilities operation. • Prepared, reviewed, negotiated, and analyzed cost estimates for all trades, including structural,
  • 7. architectural, mechanical, electrical, and communication. • Accomplishments include production and development of cost estimates of major subway stations renovations such as: Underground Times Square Terminal Complex ($181 million), Underground Grand Central Phase II project ($47 million), Trump City at 72nd St. Station ($60 million), and Underground Atlantic Avenue Terminal Complex ($152 million). • Designed steel and reinforced concrete structures, retaining walls, pile foundations, slurry walls. Professional Registrations Professional Engineering Licenses in the States of Illinois (current), Indiana, New York (current), New Jersey, and Connecticut. Education Polytechnic University Brooklyn, NY • Ph.D. (Civil Engineering) in Construction Management June 1999. • Dissertation Title: Model for Station Rehabilitation Planning. • Master of Science (Transportation & Planning), January 1993 • Engineer Degree (Structural Engineering), January 1990 • Project Title: Earthquake analysis for two dimensional bridges. Manhattan College Riverdale, NY • Master of Engineering (Civil), June 1982 • Bachelor of Engineering (Civil), June 1981 Professional Affiliations • Honor Society of Civil Engineers (CHI EPSILON), American Society of Civil Engineers (ASCE), • American Institute of Steel construction (AISC), and American Concrete Institute (ACI), and Project Management Institute (PMI) Computer Software experience: RISA, Strudl, MathCAD, TEKLA, AutoCAD, RAM, MathCAD, Prokon, SAFE, PCA Slab, PCA Column, and Microsoft. References: Available upon request.