Descon Engineering, UAE recently completed ENOC Refinery Shutdown-2016 and this Case Study is being written to share the success story with industry professionals. The case study include the introduction, challenges we faced and solution for these challenges. The conclusion include the appreciation from ENOC for completing the project in time, and with highest standard of safety and quality.
Descon Engineering, UAE recently completed ENOC Refinery Shutdown-2016 and this Case Study is being written to share the success story with industry professionals. The case study include the introduction, challenges we faced and solution for these challenges. The conclusion include the appreciation from ENOC for completing the project in time, and with highest standard of safety and quality.
Study: The Future of VR, AR and Self-Driving CarsLinkedIn
We asked LinkedIn members worldwide about their levels of interest in the latest wave of technology: whether they’re using wearables, and whether they intend to buy self-driving cars and VR headsets as they become available. We asked them too about their attitudes to technology and to the growing role of Artificial Intelligence (AI) in the devices that they use. The answers were fascinating – and in many cases, surprising.
This SlideShare explores the full results of this study, including detailed market-by-market breakdowns of intention levels for each technology – and how attitudes change with age, location and seniority level. If you’re marketing a tech brand – or planning to use VR and wearables to reach a professional audience – then these are insights you won’t want to miss.
Seeking a high profile career-oriented job in a dynamic corporate environment, wherein I am accorded an opportunity to explore my skills and experience to wider horizons with a “CAN DO” attitude and proven efficiency.
Survey engineering with 10.5 years (5 years in ABROAD ) As a Surveyor of rich & extensive experience in diversified project of Construction Industries, Oil & Gas Offshore & Onshore Refineries, Ports, Power Plants, Petrochemical, Buildings, Pipe line, Marine, Rail Industry, Power Transmission & Distribution, Transportation, Infrastructure & Utilities Etc. . .Currently associated with Med Gulf Const. Company W.L.L. an ISO9001-2008, ISO14001-2004 & OHSAS 18001-2007.
Construction of Industrial building such as where houses, Pumping stations, Substations, Lifting stations, Residential & Commercial buildings.
Expertise in handling modern Surveying Instrument like GPS, TOTAL STATION, AUTO LEVEL, AUTO CAD & RADIO DETECTOR
Thanks & Regards,
AADARSH JILKA
+97470940181
+97466317564
Dear Sir ,,,Greetings!
Please find enclosed my resume for '' Sr .Surveyor ". I've more than 15 years experience an exposure in Water Reservoirs Roads Bridge,Towers, Building Groups, Crude Oil Pipeline projects, Infrastructure Civil Oil and Gas Industries.
I've made numerous contribution to my previous and present employer that have gained me professional experience at different Projects i.e. high rise Towers Crude Oil Pipeline Projects, G L Noble Denton(Third Party Inspection) and presently working with Dubai Engineering Consulting Company Jeddah Saudi Arabia.
These accomplishments are derived from my exceptional communication and interpersonal skills, unparalleled work ethic and strong attention to details. I am enthusiastic about exploring opportunities with your organization and looking forward to hear from your side.
Best Regards ,
Muhammad Amjad
Sr.Survey Inspector / Civil Engineer
Dubai Engineering Consultants Jeddah Saudi Arabia
Briman Strategic Water Reservoir Project
World’s Largest Drinking Water Storage Facility.
Contact NO = KSA ,00966580667473 // PAK , 00923007565840
Responsibilities: E&I QA/QC
Responsibilities for Field Inspection as per Inspection Testing Plan (ITP’s) Related (E&I)
Jobs.QA/QC with the help of specification, drawings.
Inspection for Material Receiving related Electrical, Instrument as per Indent, Delivery
Note.
Inspection for Cable Laying (E & I) in Cable Trays, Trenches as per cross-sectional
drawings.
Inspection for Cable Trays (E&I) Installation (Perforated, Ladder, Mesh) as per drawing.
Responsible for all Red Marks/As Built drawing as per site modification.
Inspection for Lighting Installation as per circuit diagram, Panel Installation,Transformer
installation.
Inspection for Heating Tracing cables and Testing.
Having Good Knowledge of (NEC) National Electrical Code.
American Petroleum Institute (API ) Standards
IEC- international ELECTROTECHNICAL Commission Standards.
Inspection for the Installation of MCT’s.
Inspection for Lightning Protection (Lightning Arresters).
Inspection for EARTHING Cable Laying, CAD Weld - Exothermic Weld joints,
Earth Bus Bar, EARTHING Test.
Inspection for Motor Installation, Resistance/IR test & Motor torque test.
Inspection for Cable Continuity/IR, Cable termination, EARTHING test.
Prepare the NCR, CAR, TQ, ITP, and Method Statements & RFI’S.
Complete QA/QC Documentation as per Project specification.
Inspection for calibration of PI, PDIT, PT, TT, TE, FT, LT.
Functional Test of Ultrasonic Transmitters, LSL, LSH, LSHH, AT.
Inspection for Field Instrument Installation (PT,FT, LT, Control Valves as per Hook up drawing)
Inspection for Impulse Line Leak test.
Inspection for JB’S Installation, Panels, Cabinets Installation.
Preparing the complete Loop Folders like(DI,DO,AI,AO,RTD for Loop Checking Pre-
Commissioning with the attachments of Instrument loop package index, Functional loop test CR,
Material Receiving Calibration CR, Instrument Installation CR Instrument index, instrument Loop
Diagram & P& ID’S.
Responsible for clear the Punch Points.
Prepare the Final Dossier as per client HOS and Hand over to Mechanical Completion
Department (MC)
Final Walk Down of Hand over System (HOS) with Client.
23. CTCI Major Reference in Vietnam : On-going Project PV – Phu My Go Dau Pipeline PV – Condensate Processing Plant PV – Dung Quat Refinery Building PV & ZNSM – Vietross Refinery Package II & III Na Doung – Power Plant Phu My – Power Plant III Ca Mau – Power Plant I & II PHI – Hai Duong Phase 1 & 2 (Building EPC) 3 4 1 7 Hochiminh 2 6 Hanoi 5 8 1 2 3 4 5 6 7 8 -- --
24. BUILDINGS -- -- King Faisal University, Al-Hassa, KSA Prince Faisal Stadium, Riyadh
26. AIRPORTS King Abdulaziz International Airport, Jeddah Aramco Airport Runway, Shaybah, KSA -- --
27. Major Achievements of PI-Consult Client: ROYAL COMMISSION FOR JUBAIL AND YANBU Project Location: JUBAIL Description: Front End Engineering & Design (FEED) include the following: Staged site development and drainage of entire site Roads and utilities crossing at the KRT (3.0 KM Wide) High Ways, Main roads and high ways rail road system. Sea water cooling supply and distribution. Potable water supply distribution. Industrial Wastewater collection and treatment system. Sanitary wastewater collection and treatment system. Material Handling, pipe and utility corridors. Feedstock supply and fuel gas system supply and distribution. Electrical Power and telecommunication transmission. Value Engineering and Optimization. Value in SAR: 35 Million (For FEED) Project Title: FEED FOR THE NEW INDUSTRIAL PARK WEST /JUBIAL 2 CONTRACT NO. 202-TO3 Design Duration: 2003-2008 Client: SAUDI ARAMCO Project Location: K.S.A Project Title: INSTALL & UPGRADE IDAS SYSTEM AT 18 COMPANY FACILITIES Description: Provide Conceptual / project Proposal for the Following: All IDAS field devices will be located within respective perimeter site fences. The IDAS system equipment which will be located at respective Control Center with relevant communications transport for each site. Also, the system shall provide local monitoring for the gate of each. Value in SAR: 7,232,963 Design Duration: 2007-2008 -- --
28. Client: SAUDI ARAMCO Project Location: KHURSANIA Description: Provide detail engineering of crude oil upstream facilities at Abu-Hadriyah and Fadhili fields consisting of Drill-sites development including the connecting pipelines from wellheads to interface manifolds. Each Drill-sites, consisting of single-well to multi-wells system, is equipped with multi-phase flow-meters and testing facility, corrosion inhibitor chemical injection system, corrosion monitoring system, remote terminal unit, switch- rack, signal muti-plexing unit (mux). Value in SAR: 5,000,000 Project Title: DETAILED ENGINEERING FOR ABU HADRIYAH / FADHILI NEW OIL DRILL SITES & DETAILED ENGINEERING FOR ABU HADRIYAH / FADHILI T/L, INTERFACE MANIFOLDS & UPGRADING EXISTING WELLS Design Duration: 2005-2006 Client: PUBLIC HOUSING EST. DAMASCUS, SYRIA Project Location: DAMASCUS, SYRIA Project Title: DIPLOMATIC QUARTERS PROJECT - DAMASCUS Description: The project is located in the suburbs of Damascus city with a total area of 600 Hectare. The project includes diplomatic area (225 Hect), General Services Area (125 Hect), open uncovered area (50 Hect.), Landscaped Area (150 Hect), Roads and Access passage and walk ways (50 Hect). Pi-Consult consortium grouped with Arch Center Riyadh, and SPC Damascus were awarded the design on Jan 19, 2006. Design Duration: 2006-2007 Value in SAR: 5 Million Major Achievements of PI-Consult -- --
29. Client: NESMA TRADING COMPANY LTD . Project Location: VARIOUS Description: The project shall provide a detail engineering design package for IDAS at 18 Company facilitates with a dedicated Alarm Management System (AMS) per site to monitor, detect, assess, trace and video record potential intrusion for 18 Company facilities. And to provide Long Range Detection and Assessment System (LRDAS) with the required infrastructure at twenty five (25) company’s vital sites as specified henceforth in this document. Value in SAR: 5,000,000 Project Title: IDAS, LR DAS INFRASTRUCTURE PROJECT Design Duration: 2009-2010 On going Major Achievements of PI-Consult -- --
31. Our Vision – Partnership with Clients -- -- Core Team from CTCI Group Full Spectrum Coach / Self-Dependent Stage Time High Value / Localization Setting Up Operation Mechanism / Implant Stage 2009 Comprehensive Training 2014 Leading EPC Company in KSA, Patnership with Mr. Clients Recruit KSA Engineers Common 3D Work Platform Advanced On-Line Support Stretch Local Capablity ISO 9001 Certificate Intergration Capability / Esteem Stage -- -- On-Line Support Introduce Corporate Social Responsibility Create Value in KSA