Presentation on six weeks internship
at
NKG Infrastructures Limited
“Construction of army residential building”
Jalandhar Cantt
Submitted by :-Md Sharique(11306175)
School Of Civil Engg.
Lovely Professional University
CONTENTS
 Learning objectives
 About project
 Lap joints
 Water Tank
 Batching plant
 Plastering(Grit wash)
 Defects
 Conclusion
2
ABOUT PROJECT
 Grade of concrete used - M25
 Lateral ties - 10 mm and 8mm
 Design life - 80 years
 Type/Class of structure - Class A
 Type of foundation - Raft
 Designed for fire resistance - 1.5 hours
3
LEARNING OBJECTIVES
 All reinforcement bars should be Thermo Mechanically treated steel
bars of Fe-500 grade
 Clear Cover to Reinforcement
1. For Footing bottom face -75mm
2. Footing side and top face - 50mm
3. Column - 40mm
4. Beam - 25mm
5. Slab - 20mm
 For faces of members likely to be in direct contact with ground clear
cover should be greater of either
Dia of Main reinforcement bar
or
Equal to 50mm
4
Grade of conc. Tension bars Compression
bars
Remarks
M-25 40.5 x D 32.5 x D D is dia. Of
reinforcement
bars
5
WATER TANK
 Capacity - 30,000 ltrs
 Material - Rcc and concrete
 Reinforcement used - 8 mm for tie bars and 10mm as
distribution bars bothway and 12 mm as main bars in
beams.
 Size of Beam - 230× 450 mm
 Grade of concrete –M25
 Tank is divided in 3 equal portions i.e 10,000 ltrs in each
portion and baffel walls are made.
 Two portions are used for drinking and other purposes
while 1 portion is used as reserved for fire and other
mishaps. 6
7
8
9
Fig showing 10 mm dia
steel Fe500 D
Machine Room
Water Tank
10
Binding wire
Hook used to tie
reinforcement with help of
binding wire
Reinforcement
12
Concreting
13
14
Concreting done with concrete pump
15
Beams & slab after concreting Slab after casting 15 cm thick
Further reinforcement Further formwork
BATCHING PLANT
16
17
Conveyor belt
Operating Unit
Cement Storage
Mixing Unit
18
PLASTERING - GRIT WASH
(EXTERNAL PLASTER)
 Plaster to be applied in two layers i.e after raking
first layer of 15 mm thick cement mortar (1:4) and
again make surface rough.
Curing to be done for atleast 7 days 19
SECOND LAYER
20
Making square boxes as per design
using thin tapered wooden batten fixed
over previous layer with nails. Battens
must be removed with great care so that
edges are not damaged.
Wash marble chipping with clean water
before application.
Wet the previous layer with water and
then apply mix.
Mix should be made with marble chipping 12mm mixed in grey 65% approx. and
white cement 35% approx.
1:0.5:2 where 1 proportion is of mixed grey and white cement, 0.5 is marble
powder and 2 represent marble chipping of 12mm size.
21
1:1/2:2
1=.65 grey
cement+.35
white cement
½=marble
powder
2=marble
chipping
Marble chipping 12mm
Mix made is applied in uniform thickness and is pressed properly
with wooden float for proper bonding with previous layer and is
finished upto true surface.
After initial setting it is watered to achieve strength.
H2SO4 mixed with water is used for washing and scrubbing
purposes. Suitable brushes are used and top layer is scrubbed
until natural colour of marble chipping is achieved.
22
DEFECTS
23Concrete not filled
properly
24
Honeycombing
CONCLUSION
 Six weeks internship was very helpful to me. I get
practical knowledge that how task is executed.
 I learnt about working of concrete pump, batching
plant, water tank, grit wash and some defects.
25
26

More Related Content

What's hot

Tutorial Staad-Pro
Tutorial Staad-ProTutorial Staad-Pro
Tutorial Staad-Pro
Nabeh Wildan
 
limit state method
limit state methodlimit state method
limit state method
illpa
 

What's hot (20)

Post tensioning company method statement | shivforce.in
Post tensioning company   method statement | shivforce.in Post tensioning company   method statement | shivforce.in
Post tensioning company method statement | shivforce.in
 
Project
ProjectProject
Project
 
Design of Concrete Structure 1
Design of Concrete Structure 1Design of Concrete Structure 1
Design of Concrete Structure 1
 
Building Construction process
Building Construction processBuilding Construction process
Building Construction process
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
Shrinkage and creep
Shrinkage and creepShrinkage and creep
Shrinkage and creep
 
Design & Construction Errors- How it Affects Repair and Rehabilitation of Str...
Design & Construction Errors- How it Affects Repair and Rehabilitation of Str...Design & Construction Errors- How it Affects Repair and Rehabilitation of Str...
Design & Construction Errors- How it Affects Repair and Rehabilitation of Str...
 
6. fibre reinforced concrete
6. fibre reinforced concrete6. fibre reinforced concrete
6. fibre reinforced concrete
 
Safe pt design
Safe pt designSafe pt design
Safe pt design
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Multistorey residential building construction training report
Multistorey residential building construction training  reportMultistorey residential building construction training  report
Multistorey residential building construction training report
 
Tutorial Staad-Pro
Tutorial Staad-ProTutorial Staad-Pro
Tutorial Staad-Pro
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil Engineering
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
limit state method
limit state methodlimit state method
limit state method
 
Posttension vs flat slab
Posttension vs flat slabPosttension vs flat slab
Posttension vs flat slab
 
special types of concrete
special types of concretespecial types of concrete
special types of concrete
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Repair and strengthening of reinforced concrete beam column joints
Repair and strengthening of reinforced concrete beam column jointsRepair and strengthening of reinforced concrete beam column joints
Repair and strengthening of reinforced concrete beam column joints
 

Viewers also liked

AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
Abhishek Singh
 
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Yogesh Gunasekaran
 
Ppt of mini project.
Ppt of mini project.Ppt of mini project.
Ppt of mini project.
saikiran_gone
 
Intern Sud
Intern SudIntern Sud
Intern Sud
Sudesh K
 

Viewers also liked (16)

AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Internhsip powerpoint
Internhsip powerpointInternhsip powerpoint
Internhsip powerpoint
 
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
 
design verification of residential building
design verification of residential buildingdesign verification of residential building
design verification of residential building
 
Functional planning of a residential building
Functional planning of a residential buildingFunctional planning of a residential building
Functional planning of a residential building
 
National Institute Of Fashion Technology(NIFT)-Delhi,Mumbai,Chennai
National Institute Of Fashion Technology(NIFT)-Delhi,Mumbai,ChennaiNational Institute Of Fashion Technology(NIFT)-Delhi,Mumbai,Chennai
National Institute Of Fashion Technology(NIFT)-Delhi,Mumbai,Chennai
 
Ppt of mini project.
Ppt of mini project.Ppt of mini project.
Ppt of mini project.
 
Multi storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingMulti storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial building
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Intern Sud
Intern SudIntern Sud
Intern Sud
 
Building construction
Building constructionBuilding construction
Building construction
 
TYPES OF FOUNDATION(PPT)
TYPES OF FOUNDATION(PPT)TYPES OF FOUNDATION(PPT)
TYPES OF FOUNDATION(PPT)
 
Project proposal
Project proposalProject proposal
Project proposal
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 

Similar to Construction of residential building By Sharique

Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)
Waqas Aslam
 
Nbs specification (updated for contract)
Nbs specification (updated for contract)Nbs specification (updated for contract)
Nbs specification (updated for contract)
Noel Hickey
 
project on multistoried infrastructure
project on multistoried infrastructureproject on multistoried infrastructure
project on multistoried infrastructure
Rohan chansoriya
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
Edel Fox
 

Similar to Construction of residential building By Sharique (20)

Work methodology of roof waterproof treatment work with crown izonil 3
Work methodology of roof waterproof treatment work with crown izonil  3Work methodology of roof waterproof treatment work with crown izonil  3
Work methodology of roof waterproof treatment work with crown izonil 3
 
Building Materials & Construction Module - 5
Building Materials & Construction Module - 5Building Materials & Construction Module - 5
Building Materials & Construction Module - 5
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)
 
Nbs specification (updated for contract)
Nbs specification (updated for contract)Nbs specification (updated for contract)
Nbs specification (updated for contract)
 
Is 456 codal provisions
Is 456 codal provisionsIs 456 codal provisions
Is 456 codal provisions
 
project on multistoried infrastructure
project on multistoried infrastructureproject on multistoried infrastructure
project on multistoried infrastructure
 
Phase2 final.pptx
Phase2  final.pptxPhase2  final.pptx
Phase2 final.pptx
 
Specifications
SpecificationsSpecifications
Specifications
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1
 
Cement & their application ( Including concrete technology ) Types of custom...
Cement &  their application ( Including concrete technology ) Types of custom...Cement &  their application ( Including concrete technology ) Types of custom...
Cement & their application ( Including concrete technology ) Types of custom...
 
Specifications for rcc
Specifications for rcc Specifications for rcc
Specifications for rcc
 
Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020
 
INTERNSHIP 1.pptx
INTERNSHIP 1.pptxINTERNSHIP 1.pptx
INTERNSHIP 1.pptx
 
Advance concrete technology.pdf
Advance concrete technology.pdfAdvance concrete technology.pdf
Advance concrete technology.pdf
 
rcc.pptx
rcc.pptxrcc.pptx
rcc.pptx
 
Plum concrete
Plum concretePlum concrete
Plum concrete
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
GFRG PANELS
GFRG PANELSGFRG PANELS
GFRG PANELS
 

Recently uploaded

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Recently uploaded (20)

(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Construction of residential building By Sharique

  • 1. 1 Presentation on six weeks internship at NKG Infrastructures Limited “Construction of army residential building” Jalandhar Cantt Submitted by :-Md Sharique(11306175) School Of Civil Engg. Lovely Professional University
  • 2. CONTENTS  Learning objectives  About project  Lap joints  Water Tank  Batching plant  Plastering(Grit wash)  Defects  Conclusion 2
  • 3. ABOUT PROJECT  Grade of concrete used - M25  Lateral ties - 10 mm and 8mm  Design life - 80 years  Type/Class of structure - Class A  Type of foundation - Raft  Designed for fire resistance - 1.5 hours 3
  • 4. LEARNING OBJECTIVES  All reinforcement bars should be Thermo Mechanically treated steel bars of Fe-500 grade  Clear Cover to Reinforcement 1. For Footing bottom face -75mm 2. Footing side and top face - 50mm 3. Column - 40mm 4. Beam - 25mm 5. Slab - 20mm  For faces of members likely to be in direct contact with ground clear cover should be greater of either Dia of Main reinforcement bar or Equal to 50mm 4
  • 5. Grade of conc. Tension bars Compression bars Remarks M-25 40.5 x D 32.5 x D D is dia. Of reinforcement bars 5
  • 6. WATER TANK  Capacity - 30,000 ltrs  Material - Rcc and concrete  Reinforcement used - 8 mm for tie bars and 10mm as distribution bars bothway and 12 mm as main bars in beams.  Size of Beam - 230× 450 mm  Grade of concrete –M25  Tank is divided in 3 equal portions i.e 10,000 ltrs in each portion and baffel walls are made.  Two portions are used for drinking and other purposes while 1 portion is used as reserved for fire and other mishaps. 6
  • 7. 7
  • 8. 8
  • 9. 9 Fig showing 10 mm dia steel Fe500 D
  • 10. Machine Room Water Tank 10 Binding wire Hook used to tie reinforcement with help of binding wire
  • 13. 14 Concreting done with concrete pump
  • 14. 15 Beams & slab after concreting Slab after casting 15 cm thick Further reinforcement Further formwork
  • 16. 17
  • 17. Conveyor belt Operating Unit Cement Storage Mixing Unit 18
  • 18. PLASTERING - GRIT WASH (EXTERNAL PLASTER)  Plaster to be applied in two layers i.e after raking first layer of 15 mm thick cement mortar (1:4) and again make surface rough. Curing to be done for atleast 7 days 19
  • 19. SECOND LAYER 20 Making square boxes as per design using thin tapered wooden batten fixed over previous layer with nails. Battens must be removed with great care so that edges are not damaged. Wash marble chipping with clean water before application. Wet the previous layer with water and then apply mix. Mix should be made with marble chipping 12mm mixed in grey 65% approx. and white cement 35% approx. 1:0.5:2 where 1 proportion is of mixed grey and white cement, 0.5 is marble powder and 2 represent marble chipping of 12mm size.
  • 21. Mix made is applied in uniform thickness and is pressed properly with wooden float for proper bonding with previous layer and is finished upto true surface. After initial setting it is watered to achieve strength. H2SO4 mixed with water is used for washing and scrubbing purposes. Suitable brushes are used and top layer is scrubbed until natural colour of marble chipping is achieved. 22
  • 24. CONCLUSION  Six weeks internship was very helpful to me. I get practical knowledge that how task is executed.  I learnt about working of concrete pump, batching plant, water tank, grit wash and some defects. 25